TxDOT contract A00194081 bid tabulation
Bridge Replacement, CR 314 (AT DRAW to .). Let by Texas DOT on October 9, 2025, Nolan, Abilene District. 8 bids received; low bid $918,429 by Delgado'S Contractors, LLC, -26% against the engineer's estimate of $1,233,119.
- Owner
- Texas DOT
- Letting
- 09 OCT 2025
- Pay items
- 32
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Delgado'S Contractors, LLC | $918,429 | Low | -26% |
| 2 | Skyline Bridge LLC | $929,935 | +1.0% | -25% |
| 3 | C & W Southern LLC | $944,491 | +3.0% | -23% |
| 4 | Coppell Construction Co., Inc. | $1,044,657 | +14% | -15% |
| 5 | STX Civil | $1,117,845 | +22% | -9.0% |
| 6 | Hodges and Son Construction Company, Inc. | $1,158,615 | +26% | -6.0% |
| 7 | C. E. Barker, LTD. | $1,229,982 | +34% | 0.0% |
| 8 | Texas Steel Industrial Placing, LLC | $1,314,520 | +43% | +7.0% |
Engineer's estimate: $1,233,119.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Delgado'S Contractors, LLC | 2. Skyline Bridge LLC | 3. C & W Southern LLC | 4. Coppell Construction Co., Inc. | 5. STX Civil | 6. Hodges and Son Construction Company, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 7 | $5,000.00 | $750.00 | $2,500.00 | $5,000.00 | $8,000.00 | $2,800.00 | $6,000.00 |
| 2 | Excavation (roadway) (110-7001) | CY | 304 | $35.00 | $40.00 | $17.00 | $20.00 | $40.00 | $30.00 | $30.00 |
| 3 | Excavation (channel) (110-7002) | CY | 163 | $40.00 | $40.00 | $20.00 | $40.00 | $42.00 | $35.00 | $50.00 |
| 4 | Embankment (final)(DC)(type C) (132-7006) | CY | 112 | $34.00 | $25.00 | $60.00 | $20.00 | $49.00 | $40.00 | $100.00 |
| 5 | Drill seed (permanent_rural_sand) (164-7009) | SY | 1,166 | $0.20 | $1.00 | $4.00 | $3.70 | $4.00 | $1.25 | $5.00 |
| 6 | Vegetative watering (168-7001) | TGL | 22.80 | $37.00 | $50.00 | $1.00 | $1.00 | $50.00 | $50.00 | $1.00 |
| 7 | FL BS (compacted in place)(type A or B GR 4)(6") (247-7064) | SY | 1,721 | $40.00 | $35.00 | $55.00 | $50.00 | $25.00 | $115.00 | $50.00 |
| 8 | Cem stabil BKFL (400-7010) | CY | 98 | $300.00 | $280.00 | $300.00 | $350.00 | $335.00 | $235.00 | $350.00 |
| 9 | Drilled shaft (24 in) (416-7004) | LF | 360 | $320.00 | $255.00 | $275.00 | $252.00 | $290.00 | $315.00 | $305.00 |
| 10 | Class C concrete (abutment) (420-7012) | CY | 44 | $2,500.00 | $1,800.00 | $1,350.00 | $1,200.00 | $1,500.00 | $1,300.00 | $2,500.00 |
| 11 | Class C concrete (miscellaneous) (420-7067) | CY | 14.90 | $2,500.00 | $1,500.00 | $1,250.00 | $1,000.00 | $1,900.00 | $1,500.00 | $2,000.00 |
| 12 | Reinforced concrete slab (slab beam) (422-7007) | SF | 2,600 | $30.00 | $30.00 | $28.00 | $35.00 | $32.50 | $35.00 | $40.00 |
| 13 | Prestressed concrete slab beam (5SB15) (425-7019) | LF | 495 | $267.00 | $315.00 | $325.00 | $380.00 | $235.00 | $285.00 | $350.00 |
| 14 | Riprap (stone protection)(12 in) (432-7041) | CY | 236 | $362.00 | $225.00 | $165.00 | $250.00 | $240.00 | $220.00 | $225.00 |
| 15 | Rail (type T223) (450-7008) | LF | 252 | $235.00 | $180.00 | $180.00 | $200.00 | $160.00 | $220.00 | $220.00 |
| 16 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 2 | $50,000 | $35,000 | $15,000 | $10,000 | $30,000 | $38,000 | $30,000 |
| 17 | Mobilization (500-7001) | LS | 1 | $99,830 | $80,250 | $80,000 | $120,000 | $100,000 | $100,000 | $100,000 |
| 18 | Barricades, signs and traffic handling (502-7001) | MO | 9 | $15,000 | $1,250.00 | $3,000.00 | $1,160.00 | $10,000 | $2,800.00 | $8,600.00 |
| 19 | Rock filter dams (install) (type 1) (506-7001) | LF | 80 | $47.00 | $75.00 | $55.00 | $10.00 | $100.00 | $30.00 | $1.00 |
| 20 | Rock filter dams (remove) (506-7011) | LF | 80 | $16.00 | $15.00 | $10.00 | $1.00 | $25.00 | $20.00 | $1.00 |
| 21 | Temporary sediment control fence (install) (506-7039) | LF | 1,150 | $5.00 | $7.00 | $3.90 | $2.00 | $10.00 | $6.00 | $1.00 |
| 22 | Temporary sediment control fence (remove) (506-7041) | LF | 1,150 | $2.00 | $1.00 | $1.00 | $1.00 | $2.00 | $1.00 | $1.00 |
| 23 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 245 | $12.00 | $10.00 | $12.00 | $4.00 | $10.00 | $8.00 | $1.00 |
| 24 | Biodegradable erosion control logs (remove) (506-7046) | LF | 245 | $2.50 | $1.00 | $6.00 | $1.00 | $5.00 | $2.00 | $1.00 |
| 25 | Metal W-beam guard fence (timber post) (540-7001) | LF | 187.50 | $32.00 | $33.00 | $32.00 | $24.00 | $24.00 | $35.00 | $25.00 |
| 26 | Metal beam guard fence trans (TL2) (540-7006) | EACH | 8 | $2,400.00 | $1,500.00 | $1,500.00 | $1,200.00 | $1,200.00 | $1,800.00 | $1,400.00 |
| 27 | Guardrail end treatment (install) (544-7001) | EACH | 8 | $3,250.00 | $3,500.00 | $3,600.00 | $3,125.00 | $3,125.00 | $3,700.00 | $3,300.00 |
| 28 | Wire fence (type C) (552-7003) | LF | 610 | $25.00 | $25.00 | $10.00 | $32.00 | $30.00 | $20.00 | |
| 29 | Wire fence (type D) (552-7004) | LF | 852 | $30.00 | $25.00 | $25.00 | $12.00 | $32.00 | $30.00 | $25.00 |
| 30 | Wire fence (water gap) (552-7010) | LF | 229 | $55.00 | $50.00 | $150.00 | $45.00 | $90.00 | $50.00 | $35.00 |
| 31 | Wire fence (remove) (552-7011) | LF | 240 | $2.50 | $2.00 | $10.00 | $1.00 | $4.00 | $1.00 | $5.00 |
| 32 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 24 | $35.00 | $30.00 | $50.00 | $45.00 | $45.00 | $50.00 | $50.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of October 9, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.