TxDOT contract A00183308 bid tabulation
Interstate Designation, US 281 (7.4 Miles North of SH 186 to 3.9 Miles North of SH 186). Let by Texas DOT on May 7, 2026, Hidalgo, Pharr District. 5 bids received; low bid $62,131,044 by Ioc Company LLC, -16% against the engineer's estimate of $73,884,137.
- Owner
- Texas DOT
- Letting
- 07 MAY 2026
- Pay items
- 185
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ioc Company LLC | $62,131,044 | Low | -16% |
| 2 | Foremost Paving, Inc. | $63,645,399 | +2.0% | -14% |
| 3 | CK Newberry, LLC | $65,998,974 | +6.0% | -11% |
| 4 | Posillico Civil, Inc. | $66,250,000 | +7.0% | -10% |
| 5 | James Construction Group, LLC | $86,174,194 | +39% | +17% |
Engineer's estimate: $73,884,137.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Ioc Company LLC | 2. Foremost Paving, Inc. | 3. CK Newberry, LLC | 4. Posillico Civil, Inc. | 5. James Construction Group, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 184 | $3,000.00 | $19,350 | $1,500.00 | $5,000.00 | $10,000 | $32,515 |
| 2 | Removing concrete (riprap) (104-7006) | SY | 160 | $20.00 | $25.00 | $29.17 | $25.00 | $15.00 | $27.37 |
| 3 | Removing concrete (driveways) (104-7011) | SY | 113 | $45.00 | $25.00 | $34.81 | $35.00 | $15.00 | $38.81 |
| 4 | Remove (12") TRT/untrt base & asphalt pavement (105-7091) | CY | 5,924.40 | $20.00 | $8.00 | $12.18 | $10.00 | $5.00 | $23.27 |
| 5 | Excavation (roadway) (110-7001) | CY | 158,843 | $9.00 | $4.00 | $4.85 | $7.50 | $5.00 | $7.12 |
| 6 | Embankment (final)(DC)(type C) (132-7006) | CY | 606,858 | $10.00 | $7.25 | $8.36 | $9.00 | $10.00 | $24.47 |
| 7 | Road grader work (ord comp) (152-7001) | STA | 562 | $150.00 | $10.00 | $31.75 | $100.00 | $25.00 | $356.22 |
| 8 | Furn & place topsoil (4") (160-7002) | SY | 645,302 | $1.50 | $0.40 | $0.22 | $1.00 | $0.50 | $1.15 |
| 9 | Drill seed (permanent_rural_clay) (164-7010) | SY | 645,302 | $0.50 | $0.36 | $0.46 | $0.15 | $0.35 | $0.16 |
| 10 | Drill seed (temporary_warm_cool) (164-7015) | SY | 645,302 | $0.50 | $0.23 | $0.36 | $0.14 | $0.25 | $0.14 |
| 11 | Vegetative watering (168-7001) | TGL | 19,359 | $60.00 | $15.00 | $29.40 | $16.00 | $15.00 | $37.61 |
| 12 | Soil ret BLKT (OPT1) (169-7041) | SY | 30,371 | $3.25 | $0.55 | $2.53 | $1.00 | $2.50 | $0.81 |
| 13 | Trans plant material (type I) (192-7072) | EACH | 63 | $500.00 | $1,452.00 | $808.00 | $800.00 | $1,000.00 | $800.00 |
| 14 | FL BS (roadway del)(type E GR 4)(final pos) (247-7277) | CY | 123,323 | $50.00 | $20.00 | $27.04 | $32.00 | $35.00 | $39.83 |
| 15 | Geogrid base reinforcement (type 2) (250-7002) | SY | 29,881 | $1.25 | $1.50 | $1.51 | $2.00 | $1.75 | $1.33 |
| 16 | Rework BS metal (type B)(10")(density control) (251-7030) | SY | 167,408 | $3.15 | $2.50 | $1.85 | $3.00 | $2.00 | $6.07 |
| 17 | Rework BS metal (type B)(18")(density control) (251-7084) | SY | 6,565 | $5.75 | $1.50 | $2.91 | $6.00 | $2.50 | $11.06 |
| 18 | Cement (275-7001) | TON | 12,246.82 | $225.00 | $183.25 | $195.41 | $200.00 | $185.00 | $214.24 |
| 19 | Cement TRT (existing material & new base)(12") (275-7009) | SY | 89,942 | $2.75 | $2.00 | $2.27 | $1.50 | $1.75 | $3.29 |
| 20 | Cement TRT (new base)(12") (275-7013) | SY | 86,221 | $2.50 | $2.00 | $2.25 | $1.60 | $1.75 | $3.32 |
| 21 | Cement TRT (subgrade)(12") (275-7015) | SY | 436,462 | $2.45 | $2.00 | $2.08 | $1.50 | $1.50 | $3.24 |
| 22 | Cement treat (MX exst metal & NW BS)(17") (275-7021) | SY | 255,550 | $2.75 | $2.00 | $3.19 | $2.00 | $1.50 | $4.61 |
| 23 | Salvage,haul & stockpile reclaimed asphalt PV (2") (305-7018) | SY | 3,425 | $4.00 | $4.00 | $2.46 | $2.50 | $3.50 | $1.89 |
| 24 | Salvage, haul & stockpile reclaimed asphalt PV (4") (305-7022) | SY | 6,565 | $3.00 | $4.00 | $3.74 | $2.75 | $4.00 | $2.56 |
| 25 | Salvage, haul & stockpile reclaimed ash PV (12") (305-7030) | SY | 163,983 | $8.00 | $8.50 | $9.93 | $6.00 | $7.00 | $7.25 |
| 26 | Prime coat (MC-30) (310-7004) | GAL | 81,641 | $4.50 | $5.00 | $6.45 | $5.00 | $6.00 | $4.50 |
| 27 | SP mixes SP-B sac-B PG64-22 (344-7002) | TON | 64,164.17 | $110.00 | $110.00 | $104.76 | $110.00 | $110.00 | $120.00 |
| 28 | SP mixes SP-B sac-B PG76-22 (344-7008) | TON | 30,395.88 | $120.00 | $115.00 | $111.90 | $115.00 | $120.00 | $126.00 |
| 29 | SP mixes SP-D sac-A PG76-22 (344-7064) | TON | 29,635.98 | $117.00 | $120.00 | $111.52 | $125.00 | $135.00 | $135.00 |
| 30 | SP mixes SP-D sac-B PG76-22 (344-7065) | TON | 25,702.22 | $124.00 | $115.00 | $117.29 | $120.00 | $135.00 | $130.00 |
| 31 | Stone-MTRX-asphalt SMA-D sac-A PG76-22 (346-7009) | TON | 25,610.42 | $130.00 | $142.00 | $129.24 | $150.00 | $140.00 | $160.00 |
| 32 | Plane concrete pavement(0" to 1.5") (354-7065) | SY | 84 | $12.40 | $25.00 | $74.54 | $10.00 | $2.50 | $7.42 |
| 33 | Cut & restoring pavement (400-7006) | SY | 663 | $100.00 | $100.00 | $202.00 | $125.00 | $50.00 | $119.09 |
| 34 | Cem stabil BKFL (400-7010) | CY | 901 | $125.00 | $70.00 | $111.09 | $75.00 | $115.00 | $173.69 |
| 35 | Trench excavation protection (402-7001) | LF | 958 | $6.00 | $1.00 | $1.01 | $4.00 | $10.00 | $2.24 |
| 36 | Drilled shaft (36 in) (416-7006) | LF | 828 | $300.00 | $185.00 | $353.50 | $500.00 | $300.00 | $223.95 |
| 37 | Drilled shaft (54 in) (416-7009) | LF | 300 | $700.00 | $308.00 | $656.50 | $550.00 | $500.00 | $543.77 |
| 38 | Drilled shaft (sign mounts) (12 in) (416-7027) | LF | 28 | $125.00 | $106.81 | $90.90 | $95.00 | $100.00 | $160.00 |
| 39 | Drilled shaft (sign mounts) (24 in) (416-7028) | LF | 26 | $200.00 | $183.96 | $156.55 | $160.00 | $165.00 | $290.00 |
| 40 | Drilled shaft (sign mounts) (54 in) (416-7033) | LF | 56 | $750.00 | $780.40 | $898.90 | $950.00 | $950.00 | $780.40 |
| 41 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 104 | $300.00 | $277.00 | $247.45 | $250.00 | $270.00 | $277.00 |
| 42 | Drilled shaft (traffic signal pole) (36 in) (416-7044) | LF | 56 | $310.00 | $499.40 | $292.90 | $300.00 | $320.00 | $499.40 |
| 43 | Class C concrete (abutment) (420-7012) | CY | 113.60 | $1,400.00 | $1,350.00 | $1,616.00 | $1,700.00 | $1,000.00 | $1,094.40 |
| 44 | Class C concrete (cap) (420-7022) | CY | 249.60 | $2,250.00 | $1,350.00 | $1,515.00 | $1,300.00 | $1,200.00 | $1,212.00 |
| 45 | Class C concrete (column) (420-7038) | CY | 127.20 | $2,000.00 | $2,500.00 | $2,626.00 | $1,400.00 | $1,300.00 | $2,525.20 |
| 46 | Reinforced concrete slab (422-7001) | SF | 29,194 | $30.00 | $19.50 | $25.15 | $26.00 | $22.00 | $24.13 |
| 47 | Retaining wall (MSE) (ashlar stone fin) (423-7002) | SF | 91,039 | $80.00 | $78.00 | $107.04 | $82.00 | $77.00 | $47.50 |
| 48 | Prestressed concrete girder (TX40) (425-7003) | LF | 3,416.14 | $350.00 | $200.00 | $224.22 | $225.00 | $215.00 | $230.37 |
| 49 | Riprap (concrete)(4 in) (432-7001) | CY | 752.55 | $500.00 | $485.00 | $802.95 | $425.00 | $400.00 | $372.80 |
| 50 | Riprap (concrete)(CL B) (432-7005) | CY | 7 | $1,000.00 | $2,000.00 | $2,828.00 | $425.00 | $400.00 | $1,639.57 |
| 51 | Riprap (concrete)(flume) (432-7012) | CY | 8 | $1,000.00 | $1,800.00 | $2,020.00 | $425.00 | $400.00 | $788.06 |
| 52 | Riprap (mow strip)(4 in) (432-7013) | CY | 308 | $700.00 | $590.00 | $813.05 | $425.00 | $400.00 | $670.76 |
| 53 | Riprap (stone protection)(12 in) (432-7041) | CY | 548 | $200.00 | $250.00 | $222.20 | $200.00 | $200.00 | $344.67 |
| 54 | Rail (type SSTR) (450-7024) | LF | 5,199 | $100.00 | $45.00 | $59.60 | $50.00 | $55.00 | $54.86 |
| 55 | Sealed expansion joint (4 in) (SEJ - M) (454-7004) | LF | 228 | $250.00 | $180.00 | $252.50 | $200.00 | $190.00 | $186.95 |
| 56 | Concrete box culvert (5 FT X 2 FT) (462-7006) | LF | 332 | $600.00 | $550.00 | $656.50 | $750.05 | $520.00 | $501.47 |
| 57 | Concrete box culvert (8 FT X 3 FT) (462-7020) | LF | 900 | $800.00 | $675.00 | $792.85 | $800.00 | $830.00 | $854.06 |
| 58 | RC pipe (CL III)(12 in) (464-7001) | LF | 28 | $75.00 | $140.00 | $126.25 | $80.00 | $100.00 | $80.15 |
| 59 | RC pipe (CL III)(18 in) (464-7003) | LF | 46 | $85.00 | $125.00 | $95.95 | $100.00 | $150.00 | $104.06 |
| 60 | RC pipe (CL III)(24 in) (464-7005) | LF | 1,992 | $125.00 | $75.00 | $181.80 | $90.00 | $100.00 | $95.29 |
| 61 | RC pipe (CL III)(30 in) (464-7007) | LF | 538 | $135.00 | $125.00 | $121.20 | $115.00 | $100.00 | $107.43 |
| 62 | Manh (complete)(PRM)(60IN) (465-7003) | EACH | 1 | $10,000 | $5,000.00 | $5,757.00 | $10,000 | $5,000.00 | $6,667.84 |
| 63 | Junction box(complete)(PJB)(3FTX3FT) (465-7005) | EACH | 2 | $3,750.00 | $4,000.00 | $4,949.00 | $7,000.00 | $3,000.00 | $6,039.56 |
| 64 | Inlet (complete)(pco)(3FT)(none) (465-7013) | EACH | 3 | $6,000.00 | $4,500.00 | $5,555.00 | $7,000.00 | $4,000.00 | $7,230.59 |
| 65 | Inlet (complete)(pco)(3FT)(both) (465-7016) | EACH | 1 | $6,500.00 | $5,500.00 | $7,878.00 | $8,500.00 | $5,000.00 | $8,656.55 |
| 66 | Inlet (complete) (type MSE2) (465-7352) | EACH | 24 | $11,000 | $7,500.00 | $20,301 | $10,500 | $15,000 | $13,834 |
| 67 | Headwall (CH - PW - 0) (diameter= 24 in) (466-7101) | EACH | 5 | $8,500.00 | $12,500 | $7,878.00 | $10,000 | $10,000 | $10,435 |
| 68 | Headwall (CH - PW - 0) (diameter= 30 in) (466-7103) | EACH | 1 | $9,300.00 | $14,000 | $8,080.00 | $18,000 | $7,000.00 | $10,435 |
| 69 | Wingwall (PW - 1) (HW=4 FT) (466-7174) | EACH | 2 | $13,000 | $15,500 | $24,644 | $18,000 | $15,000 | $12,833 |
| 70 | Wingwall (PW - 1) (HW=5 FT) (466-7175) | EACH | 3 | $25,000 | $21,750 | $24,745 | $20,000 | $20,000 | $14,517 |
| 71 | Wingwall (PW - 1) (HW=6 FT) (466-7176) | EACH | 6 | $20,000 | $22,750 | $30,704 | $25,000 | $20,000 | $34,450 |
| 72 | Set (type I)(S= 8 FT)(HW= 5 FT)(3:1)(C) (467-7183) | EACH | 3 | $18,000 | $16,250 | $12,120 | $10,000 | $20,000 | $12,505 |
| 73 | Set (type II) (18 in) (RCP) (6: 1) (C) (467-7307) | EACH | 2 | $2,000.00 | $1,500.00 | $1,313.00 | $1,700.00 | $1,500.00 | $2,433.10 |
| 74 | Set (type II) (24 in) (RCP) (3: 1) (C) (467-7325) | EACH | 2 | $2,500.00 | $1,750.00 | $1,616.00 | $1,600.00 | $1,500.00 | $2,523.28 |
| 75 | Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326) | EACH | 8 | $2,500.00 | $1,850.00 | $1,616.00 | $1,600.00 | $1,500.00 | $2,728.12 |
| 76 | Set (type II) (24 in) (RCP) (6: 1) (C) (467-7327) | EACH | 6 | $2,500.00 | $1,900.00 | $2,121.00 | $1,600.00 | $2,000.00 | $3,421.99 |
| 77 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 22 | $2,000.00 | $1,500.00 | $2,121.00 | $1,700.00 | $2,000.00 | $3,421.99 |
| 78 | Set (type II) (30 in) (CMP) (4: 1) (C) (467-7342) | EACH | 1 | $2,500.00 | $3,000.00 | $2,222.00 | $6,000.00 | $2,500.00 | $4,028.45 |
| 79 | Set (type II) (30 in) (CMP) (6: 1) (P) (467-7344) | EACH | 4 | $2,200.00 | $3,250.00 | $2,828.00 | $7,000.00 | $2,500.00 | $5,077.42 |
| 80 | Removing structure (set) (496-7004) | EACH | 12 | $600.00 | $200.00 | $505.00 | $500.00 | $365.00 | $561.70 |
| 81 | Removing structure (wingwall) (496-7005) | EACH | 4 | $3,250.00 | $1,000.00 | $909.00 | $2,500.00 | $1,000.00 | $3,908.41 |
| 82 | Removing structure (pipe) (496-7007) | LF | 1,155 | $15.00 | $10.00 | $20.20 | $10.00 | $10.00 | $34.37 |
| 83 | Mobilization (500-7001) | LS | 1 | $6,718,704 | $6,200,000 | $3,300,000 | $6,000,000 | $5,834,816 | $8,500,000 |
| 84 | Barricades, signs and traffic handling (502-7001) | MO | 38 | $6,000.00 | $1,000.00 | $5,718.10 | $10,000 | $3,000.00 | $7,807.46 |
| 85 | Portable changeable message sign (503-7002) | EACH | 3 | $12,000 | $100.00 | $7,165.17 | $40,000 | $15,000 | $8,741.56 |
| 86 | TMA (stationary) (505-7001) | DAY | 480 | $250.00 | $1.00 | $52.43 | $250.00 | $75.00 | $192.64 |
| 87 | TMA (mobile operation) (505-7003) | DAY | 480 | $100.00 | $0.10 | $0.01 | $25.00 | $250.00 | $363.22 |
| 88 | Rock filter dams (install) (type 2) (506-7002) | LF | 1,172 | $50.00 | $34.00 | $65.65 | $55.00 | $65.00 | $89.08 |
| 89 | Rock filter dams (remove) (506-7011) | LF | 1,172 | $15.00 | $18.00 | $40.40 | $16.00 | $40.00 | $22.40 |
| 90 | Construction exits (install) (type 1) (506-7020) | SY | 2,553 | $22.00 | $20.00 | $19.66 | $25.00 | $12.00 | $56.61 |
| 91 | Construction exits (remove) (506-7024) | SY | 2,553 | $10.00 | $1.00 | $12.98 | $10.00 | $1.00 | $13.01 |
| 92 | Temporary sediment control fence (install) (506-7039) | LF | 317 | $6.00 | $10.00 | $6.82 | $10.00 | $6.75 | $8.03 |
| 93 | Temporary sediment control fence (remove) (506-7041) | LF | 317 | $2.50 | $3.00 | $1.92 | $5.00 | $1.90 | $2.32 |
| 94 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 1,280 | $8.00 | $3.00 | $5.96 | $10.00 | $5.90 | $8.63 |
| 95 | Biodegradable erosion control logs (remove) (506-7046) | LF | 1,280 | $2.00 | $0.50 | $1.27 | $5.00 | $1.25 | $2.32 |
| 96 | Constructing detours (508-7001) | SY | 6,519 | $94.50 | $55.00 | $59.64 | $70.00 | $48.00 | $73.07 |
| 97 | PCTB (fur&inst)(F-shape or SNGL SLP)type 1 (512-7089) | LF | 21,866 | $40.00 | $10.00 | $12.12 | $38.00 | $35.00 | $32.97 |
| 98 | PCTB (move)(F-shape or SNGL SLP)type 1 (512-7090) | LF | 60,331 | $10.00 | $1.00 | $4.73 | $6.00 | $10.00 | $4.68 |
| 99 | PCTB (remove)(F-shape or SNGL SLP)type 1 (512-7092) | LF | 20,400 | $15.00 | $1.00 | $6.51 | $8.00 | $7.00 | $7.04 |
| 100 | Permanent CTB (single slope) (type 1) (42 ) (514-7001) | LF | 18,402 | $70.00 | $55.00 | $77.59 | $60.00 | $55.00 | $75.68 |
| 101 | Landscape pavers (528-7001) | SY | 521 | $60.00 | $110.00 | $95.06 | $100.00 | $60.00 | $137.21 |
| 102 | Concrete curb (type II) (529-7002) | LF | 783 | $20.00 | $20.00 | $25.66 | $20.00 | $20.00 | $22.21 |
| 103 | Concrete curb & gutter (type II) (529-7009) | LF | 1,132 | $35.00 | $20.00 | $10.80 | $20.00 | $20.00 | $48.48 |
| 104 | Driveways (concrete) (530-7006) | SY | 93 | $120.00 | $200.00 | $102.10 | $100.00 | $60.00 | $83.74 |
| 105 | Driveways (ACP) (530-7010) | SY | 1,336 | $45.00 | $50.00 | $47.45 | $45.00 | $50.00 | $76.85 |
| 106 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 71,180 | $0.25 | $0.15 | $0.32 | $0.20 | $0.15 | $0.15 |
| 107 | Metal W-beam guard fence (timber post) (540-7001) | LF | 2,625 | $30.00 | $28.44 | $30.20 | $30.00 | $30.00 | $30.77 |
| 108 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 2 | $2,800.00 | $1,812.00 | $2,090.70 | $2,200.00 | $1,900.00 | $2,130.09 |
| 109 | Downstream anchor terminal section (540-7015) | EACH | 6 | $1,800.00 | $1,480.00 | $1,035.25 | $1,500.00 | $1,500.00 | $1,054.75 |
| 110 | Guardrail end treatment (install) (544-7001) | EACH | 8 | $3,800.00 | $3,328.00 | $3,312.80 | $3,750.00 | $3,500.00 | $3,375.21 |
| 111 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 36 | $2,500.00 | $750.00 | $1,530.15 | $1,200.00 | $1,500.00 | $1,558.98 |
| 112 | Crash cushion attenuator (remove) (545-7004) | EACH | 12 | $1,000.00 | $500.00 | $818.10 | $800.00 | $1,200.00 | $833.51 |
| 113 | Crash cushion attenuator (install)(L)(N)(TL3) (545-7006) | EACH | 2 | $11,000 | $30,000 | $31,078 | $28,000 | $38,000 | $31,663 |
| 114 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 12 | $8,700.00 | $6,500.00 | $8,726.40 | $10,000 | $8,500.00 | $8,890.80 |
| 115 | In RD IL (U/P) (type 1) (150W EQ) LED (610-7014) | EACH | 8 | $1,800.00 | $1,047.50 | $1,444.30 | $1,500.00 | $1,520.00 | $1,047.50 |
| 116 | In RD IL (type SA) 40B-12 (250W EQ) LED (610-7112) | EACH | 7 | $7,000.00 | $4,327.00 | $4,676.30 | $5,000.00 | $5,000.00 | $4,327.00 |
| 117 | In RD IL (type SA) 40T-12 (250W EQ) LED (610-7128) | EACH | 13 | $7,500.00 | $5,271.00 | $5,454.00 | $5,500.00 | $5,750.00 | $5,271.00 |
| 118 | Temporary RD IL setup and remove (617-7001) | EACH | 4 | $21,000 | $10,000 | $10,656 | $11,000 | $11,300 | $6,100.00 |
| 119 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 6,061 | $10.00 | $16.85 | $10.10 | $10.00 | $11.00 | $16.85 |
| 120 | Conduit (PVC) (schedule 40) (4") (618-7040) | LF | 16,679 | $15.00 | $21.95 | $25.25 | $25.00 | $27.00 | $21.95 |
| 121 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 175 | $30.00 | $23.80 | $30.30 | $30.00 | $32.00 | $23.80 |
| 122 | Conduit (PVC) (schedule 80) (4") (618-7064) | LF | 283 | $28.00 | $27.00 | $25.25 | $25.00 | $27.00 | $27.00 |
| 123 | Conduit (PVC) (schedule 80) (4") (bore) (618-7065) | LF | 1,230 | $40.00 | $39.90 | $38.38 | $40.00 | $41.00 | $39.90 |
| 124 | Fiber optic cable road marker (619-7013) | LF | 38 | $40.00 | $216.00 | $353.50 | $375.00 | $372.00 | $216.00 |
| 125 | Electrical conductor (no.14) insulated (620-7002) | LF | 18,099 | $1.00 | $1.00 | $0.71 | $0.75 | $0.75 | $1.00 |
| 126 | Electrical conductor (no.10) bare (620-7005) | LF | 40 | $5.00 | $1.40 | $1.01 | $1.00 | $1.00 | $1.40 |
| 127 | Electrical conductor (no.10) insulated (620-7006) | LF | 80 | $10.00 | $1.60 | $1.01 | $1.00 | $1.00 | $1.60 |
| 128 | Electrical conductor (no.8) bare (620-7007) | LF | 6,196 | $2.00 | $1.80 | $1.32 | $1.50 | $1.50 | $1.80 |
| 129 | Electrical conductor (no.8) insulated (620-7008) | LF | 12,392 | $2.00 | $1.85 | $1.37 | $1.50 | $1.50 | $1.85 |
| 130 | Electrical conductor (no.6) bare (620-7009) | LF | 318 | $2.00 | $2.10 | $1.62 | $1.70 | $1.75 | $2.10 |
| 131 | Electrical conductor (no.6) insulated (620-7010) | LF | 35 | $6.00 | $2.35 | $1.72 | $1.70 | $1.80 | $2.35 |
| 132 | Tray cable (4 conductor) (12 AWG) (621-7006) | LF | 1,451 | $3.50 | $2.85 | $1.82 | $1.80 | $1.90 | $2.85 |
| 133 | ITS GND box(pcast) type 1 (243648)W/aprn (623-7004) | EACH | 35 | $3,000.00 | $4,507.00 | $7,221.50 | $7,200.00 | $7,750.00 | $4,507.00 |
| 134 | ITS GND box(pcast) type 2 (366048)W/aprn (623-7010) | EACH | 3 | $3,000.00 | $6,480.00 | $9,595.00 | $10,000 | $10,500 | $6,480.00 |
| 135 | Ground box type A (122311)W/apron (624-7002) | EACH | 19 | $1,300.00 | $1,098.00 | $1,060.50 | $1,100.00 | $1,150.00 | $1,098.00 |
| 136 | Zinc-coat steel wire strand (3/8") (625-7004) | LF | 171 | $3.25 | $3.50 | $2.53 | $2.75 | $2.75 | $3.50 |
| 137 | Elc SRV type A 240/480 060(NS)SS(T)TP(O) (628-7053) | EACH | 4 | $8,500.00 | $8,277.00 | $6,413.50 | $6,500.00 | $7,000.00 | $8,277.00 |
| 138 | Elc SRV type T 120/240 000(NS)GS(L)TS(O) (628-7322) | EACH | 1 | $3,000.00 | $4,220.00 | $2,272.50 | $2,500.00 | $2,500.00 | $4,220.00 |
| 139 | Aluminum signs (type G) (636-7002) | SF | 309 | $35.00 | $28.48 | $24.24 | $25.00 | $25.50 | $41.00 |
| 140 | Aluminum signs (type O) (636-7003) | SF | 202 | $35.00 | $33.23 | $28.28 | $30.00 | $30.00 | $28.50 |
| 141 | Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025) | EACH | 8 | $1,200.00 | $975.00 | $883.75 | $1,000.00 | $790.00 | $801.00 |
| 142 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 48 | $1,000.00 | $1,125.00 | $984.75 | $1,200.00 | $900.00 | $911.49 |
| 143 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 4 | $1,200.00 | $1,300.00 | $1,616.00 | $1,400.00 | $1,000.00 | $1,021.97 |
| 144 | Install small roadside sign support and assembly TYS80(1)SA(U-WC) (644-7035) | EACH | 1 | $3,200.00 | $1,600.00 | $252.50 | $1,750.00 | $1,300.00 | $1,325.80 |
| 145 | In bridge MNT clearance sign assembly(type N) (644-7061) | EACH | 4 | $3,800.00 | $2,750.00 | $11,494 | $2,750.00 | $3,000.00 | $2,600.00 |
| 146 | Remove SM RD SN sup&AM (644-7073) | EACH | 49 | $120.00 | $65.00 | $111.10 | $70.00 | $5.45 | $82.86 |
| 147 | Install LRSS (struct steel) (647-7001) | LB | 2,272 | $12.00 | $6.53 | $5.56 | $6.00 | $5.85 | $7.60 |
| 148 | Install overhead sign support(35 FT cant) (650-7038) | EACH | 2 | $55,000 | $53,676 | $65,650 | $70,000 | $75,000 | $53,676 |
| 149 | Install delineator assembly (D-SW)SZ 1(BRF)GF1 (658-7015) | EACH | 57 | $33.00 | $55.00 | $25.25 | $21.00 | $60.00 | $138.10 |
| 150 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (BI) (658-7032) | EACH | 181 | $25.00 | $35.00 | $15.15 | $21.00 | $38.00 | $5.52 |
| 151 | Install object marker assembly (OM-2Y)(WC)GND (658-7056) | EACH | 42 | $75.00 | $95.00 | $151.50 | $100.00 | $92.50 | $125.00 |
| 152 | Remove delin & object marker assms (658-7078) | EACH | 2 | $30.00 | $50.00 | $151.50 | $20.00 | $100.00 | $25.00 |
| 153 | Work zone pavement marking removing (reflectorized) type II-C-R (662-7053) | EACH | 4,326 | $5.00 | $3.00 | $3.03 | $3.00 | $3.00 | $3.00 |
| 154 | Work zone pavement marking removing (W)6"(broken) (662-7065) | LF | 43,060 | $1.00 | $0.72 | $0.73 | $0.75 | $0.75 | $0.72 |
| 155 | Work zone pavement marking removing (W)6"(DOT) (662-7066) | LF | 812 | $1.00 | $2.00 | $2.02 | $2.00 | $2.00 | $2.00 |
| 156 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 99,206 | $0.50 | $0.32 | $0.33 | $0.35 | $0.35 | $0.32 |
| 157 | Work zone pavement marking removing (W)8"(solid) (662-7072) | LF | 12,049 | $0.48 | $0.58 | $0.59 | $0.60 | $0.60 | $0.58 |
| 158 | Work zone pavement marking removing (W)12"(solid) (662-7075) | LF | 987 | $1.00 | $2.50 | $2.53 | $2.50 | $2.50 | $2.50 |
| 159 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 129,851 | $0.50 | $0.32 | $0.33 | $0.35 | $0.35 | $0.32 |
| 160 | Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018) | LF | 94 | $3.50 | $10.00 | $10.10 | $10.00 | $10.00 | $10.00 |
| 161 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 7,791 | $1.80 | $1.20 | $1.22 | $1.25 | $1.25 | $1.20 |
| 162 | Reflectorized pavement marking type I (W)12"(lane drop)(100MIL) (666-7027) | LF | 684 | $5.00 | $4.00 | $4.04 | $4.00 | $4.00 | $4.00 |
| 163 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 1,770 | $4.50 | $2.25 | $2.28 | $2.25 | $2.25 | $2.25 |
| 164 | Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266) | LF | 84,450 | $1.00 | $0.84 | $0.85 | $0.85 | $0.85 | $0.84 |
| 165 | Reflectorized profile pavement marking type I(Y)6"(solid)(100MIL) (666-7270) | LF | 83,168 | $1.50 | $0.84 | $0.85 | $0.90 | $0.85 | $0.84 |
| 166 | Type I high perf PM (W)6"(broken)(100MIL) (666-7290) | LF | 19,310 | $1.50 | $0.72 | $0.73 | $0.75 | $0.75 | $0.72 |
| 167 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 116 | $30.00 | $24.00 | $24.24 | $25.00 | $25.00 | $24.00 |
| 168 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 2 | $115.00 | $215.00 | $217.15 | $215.00 | $215.00 | $215.00 |
| 169 | Prefabricated PM type C (W)(uturn arrow) (668-7096) | EACH | 2 | $350.00 | $355.00 | $358.55 | $355.00 | $355.00 | $355.00 |
| 170 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 5 | $175.00 | $265.00 | $267.65 | $365.00 | $265.00 | $265.00 |
| 171 | Prefabricated PM type C (W)(36")(yld tri) (668-7111) | EACH | 8 | $50.00 | $30.00 | $30.30 | $30.00 | $30.00 | $30.00 |
| 172 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 1,519 | $7.00 | $7.50 | $7.58 | $7.50 | $7.50 | $7.50 |
| 173 | Eliminating existing PM & markers (4") (677-7001) | LF | 33,415 | $1.00 | $0.45 | $0.46 | $0.50 | $0.45 | $0.45 |
| 174 | Install highway traffic signal (flash beacon) (680-7001) | EACH | 1 | $5,000.00 | $19,275 | $2,525.00 | $2,750.00 | $2,750.00 | $19,275 |
| 175 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 10 | $290.00 | $293.00 | $297.95 | $300.00 | $320.00 | $293.00 |
| 176 | Traffic signal CBL (type A)(12 AWG)(5 conductor) (684-7010) | LF | 2,333 | $4.00 | $3.20 | $2.23 | $2.25 | $2.35 | $3.20 |
| 177 | Ins traffic signal PL AM (S)STR(type B)lum (686-7008) | EACH | 4 | $11,500 | $7,715.00 | $9,292.00 | $10,000 | $10,000 | $7,715.00 |
| 178 | Full - width mowing (730-7019) | CYC | 5 | $5,000.00 | $1,500.00 | $7,721.65 | $1,750.00 | $8,000.00 | $4,052.95 |
| 179 | Litter removal (734-7002) | CYC | 5 | $2,500.00 | $2,500.00 | $2,670.24 | $3,000.00 | $4,500.00 | $1,627.34 |
| 180 | Post and cable fence (removal) (772-7001) | LF | 6,671 | $3.00 | $4.91 | $2.26 | $1.00 | $5.00 | $5.00 |
| 181 | Bonding course (3007-7001) | GAL | 71,597 | $3.25 | $3.00 | $2.84 | $4.00 | $3.00 | $4.00 |
| 182 | Amphibian/reptile exclusion fence inst (5003-7001) | LF | 34,935 | $6.00 | $5.00 | $3.99 | $4.00 | $3.95 | $4.48 |
| 183 | Amphibian/reptile exclusion fence rem (5003-7002) | LF | 34,935 | $2.00 | $1.00 | $1.27 | $1.25 | $1.25 | $1.16 |
| 184 | Bird exclusion method (5029-7001) | SF | 38,058 | $10.00 | $1.50 | $2.98 | $3.00 | $2.95 | $2.95 |
| 185 | FO splice enclosure (type 1) (6027-7009) | EACH | 3 | $2,900.00 | $1,788.00 | $2,474.50 | $2,500.00 | $2,750.00 | $596.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of May 7, 2026. Compiled by Mirage Metrics.