TxDOT contract A00045441 bid tabulation
Widen Road - Add Lanes, FM 549 (SH 205 to SH 276). Let by Texas DOT on February 4, 2026, Rockwall, Dallas District. 12 bids received; low bid $29,812,034 by Urban Infraconstruction LLC, -14% against the engineer's estimate of $34,640,755.
- Owner
- Texas DOT
- Letting
- 04 FEB 2026
- Pay items
- 223
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Urban Infraconstruction LLC | $29,812,034 | Low | -14% |
| 2 | Webber, LLC | $31,956,749 | +7.0% | -8.0% |
| 3 | Highway 19 Construction LLC | $32,124,988 | +8.0% | -7.0% |
| 4 | Ed Bell Construction Company | $33,345,707 | +12% | -4.0% |
| 5 | Harper Brothers Construction LLC | $33,779,105 | +13% | -2.0% |
| 6 | Grey Sky Construction LLC | $34,455,613 | +16% | -1.0% |
| 7 | Granite Construction Company | $35,089,835 | +18% | +1.0% |
| 8 | Mario Sinacola & Sons Excavating, Inc. | $35,321,967 | +18% | +2.0% |
| 9 | McMahon Contracting and Construction, LLC | $37,441,521 | +26% | +8.0% |
| 10 | Ragle Construction, Inc. | $38,105,737 | +28% | +10% |
| 11 | Indus Road & Bridge, Inc. | $42,320,780 | +42% | +22% |
| 12 | Copasa Inc | $44,776,051 | +50% | +29% |
Engineer's estimate: $34,640,755.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Urban Infraconstruction LLC | 2. Webber, LLC | 3. Highway 19 Construction LLC | 4. Ed Bell Construction Company | 5. Harper Brothers Construction LLC | 6. Grey Sky Construction LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 109.70 | $18,569 | $5,000.00 | $28,259 | $575.00 | $4,200.00 | $10,000 | $26,000 |
| 2 | Removing concrete (riprap) (104-7006) | SY | 90 | $25.00 | $12.00 | $24.50 | $25.00 | $25.00 | $50.00 | $50.00 |
| 3 | Removing concrete (driveways) (104-7011) | SY | 2,717 | $25.00 | $10.00 | $18.50 | $25.00 | $21.00 | $15.00 | $20.00 |
| 4 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 444 | $30.00 | $12.00 | $21.90 | $25.00 | $21.00 | $15.00 | $20.00 |
| 5 | Removing concrete (curb) (104-7016) | LF | 318 | $20.00 | $3.00 | $6.85 | $10.00 | $10.00 | $5.00 | $20.00 |
| 6 | Excavation (roadway) (110-7001) | CY | 76,938 | $20.00 | $13.65 | $12.30 | $10.00 | $25.00 | $20.00 | $10.00 |
| 7 | Embankment (final)(DC)(type C1) (132-7008) | CY | 24,172 | $15.00 | $21.28 | $16.70 | $22.00 | $15.00 | $35.00 | $30.00 |
| 8 | Embankment (final)(DC)(type C2) (132-7010) | CY | 2,346 | $30.00 | $50.85 | $32.25 | $22.00 | $100.00 | $35.00 | $40.00 |
| 9 | Compost manuf topsoil (4") (161-7002) | SY | 52,337 | $3.00 | $1.64 | $2.20 | $0.93 | $1.00 | $0.94 | $3.00 |
| 10 | Block sodding (162-7002) | SY | 52,337 | $6.00 | $3.49 | $3.50 | $3.50 | $3.72 | $3.49 | $5.00 |
| 11 | Drill seed (temporary_warm_cool) (164-7015) | SY | 49,787 | $0.60 | $0.13 | $0.10 | $0.13 | $0.14 | $0.13 | $0.35 |
| 12 | Vegetative watering (168-7001) | TGL | 15,192 | $25.00 | $33.02 | $7.00 | $10.00 | $1.00 | $5.00 | $1.00 |
| 13 | FL BS (compacted in place)(type D GR 1-2) (12") (247-7125) | SY | 5,561 | $30.00 | $35.95 | $29.30 | $29.21 | $45.00 | $45.00 | $30.00 |
| 14 | Lime (com or QK)(slurry) (260-7005) | TON | 3,832 | $330.00 | $292.00 | $297.00 | $320.00 | $315.00 | $325.00 | $350.00 |
| 15 | Lime TRT (existing material)(12") (260-7009) | SY | 96,272 | $7.00 | $10.00 | $6.25 | $7.00 | $8.00 | $8.00 | $7.00 |
| 16 | Salvage, haul & stockpile reclaimed asphalt PV(2"-15.6") (305-7042) | SY | 40,936 | $4.00 | $8.00 | $8.50 | $7.00 | $9.13 | $8.50 | $5.00 |
| 17 | Prime coat(MC-30 or AE-P) (310-7013) | GAL | 1,671 | $5.00 | $6.90 | $6.70 | $9.00 | $7.21 | $6.70 | $6.00 |
| 18 | Asphalt (CRS-2P) (316-7012) | GAL | 484 | $11.00 | $10.30 | $10.00 | $10.00 | $10.76 | $10.00 | $6.00 |
| 19 | Asphalt (AC-15P, AC-20-5TR or AC-20XP) (316-7071) | GAL | 484 | $8.00 | $26.40 | $25.70 | $10.00 | $27.60 | $25.65 | $6.00 |
| 20 | Aggregate (type-B or L, GR-3)(sac-B) (316-7244) | CY | 23 | $200.00 | $689.85 | $670.00 | $250.00 | $720.63 | $669.75 | $500.00 |
| 21 | SP mixes SP-B PG64-22 (344-7001) | TON | 19,854 | $105.00 | $112.90 | $110.00 | $126.00 | $117.93 | $109.60 | $125.00 |
| 22 | SP mixes SP-C sac-B PG64-22 (344-7011) | TON | 1,207 | $140.00 | $161.35 | $157.00 | $143.00 | $168.55 | $156.65 | $145.00 |
| 23 | Tack coat (344-7077) | GAL | 330 | $5.00 | $7.45 | $7.25 | $10.00 | $7.80 | $7.25 | $6.00 |
| 24 | Concrete pavement (CRCP) (8") (360-7002) | SY | 82,836 | $80.00 | $75.00 | $69.25 | $102.00 | $80.00 | $100.00 | $55.00 |
| 25 | Concrete pavement (CRCP)(hes) (8") (360-7047) | SY | 1,584 | $150.00 | $120.00 | $125.00 | $110.00 | $120.00 | $125.00 | $105.00 |
| 26 | Cem stabil BKFL (400-7010) | CY | 520 | $220.00 | $190.00 | $203.00 | $180.00 | $300.00 | $225.00 | $350.00 |
| 27 | Flowable backfill (401-7001) | CY | 27 | $400.00 | $300.00 | $198.00 | $350.00 | $600.00 | $225.00 | $350.00 |
| 28 | Trench excavation protection (402-7001) | LF | 8,934 | $10.00 | $2.00 | $4.55 | $5.00 | $2.00 | $3.75 | $2.00 |
| 29 | Temporary special shoring (403-7001) | SF | 10,798 | $32.00 | $25.00 | $16.90 | $45.00 | $40.00 | $10.00 | $50.00 |
| 30 | Drilled shaft (18 in) (416-7002) | LF | 110 | $240.00 | $97.00 | $107.00 | $180.00 | $150.00 | $150.00 | $150.00 |
| 31 | Drilled shaft (36 in) (416-7006) | LF | 997 | $300.00 | $158.00 | $179.00 | $250.00 | $200.00 | $300.00 | $220.00 |
| 32 | Class C concrete (abutment)(HPC) (420-7013) | CY | 119.60 | $1,400.00 | $1,000.00 | $1,270.00 | $1,179.00 | $1,500.00 | $1,800.00 | $1,250.00 |
| 33 | Class C concrete (cap)(HPC) (420-7023) | CY | 102 | $1,600.00 | $1,200.00 | $1,280.00 | $1,222.00 | $1,500.00 | $2,000.00 | $1,250.00 |
| 34 | Class C concrete (column)(HPC) (420-7039) | CY | 18.90 | $1,600.00 | $2,000.00 | $2,090.00 | $1,100.00 | $2,500.00 | $2,750.00 | $1,250.00 |
| 35 | Reinforced concrete slab (HPC) (422-7002) | SF | 19,067 | $30.00 | $20.00 | $25.20 | $25.00 | $25.00 | $30.00 | $25.00 |
| 36 | Approach slab (HPC) (422-7014) | CY | 377 | $720.00 | $600.00 | $571.00 | $750.00 | $750.00 | $775.00 | $1,250.00 |
| 37 | Bridge median (HPC) (422-7021) | SF | 3,940 | $30.00 | $13.50 | $13.20 | $17.00 | $13.00 | $20.00 | $85.00 |
| 38 | Bridge sidewalk(HPC) (422-7022) | SF | 6,645 | $30.00 | $14.00 | $13.60 | $14.00 | $14.00 | $20.00 | $85.00 |
| 39 | Retaining wall (spread footing) (423-7015) | SF | 2,520 | $120.00 | $150.00 | $89.00 | $91.00 | $100.00 | $140.00 | $85.00 |
| 40 | Prestressed concrete girder (TX40) (425-7003) | LF | 2,578.42 | $200.00 | $200.00 | $212.00 | $234.00 | $250.00 | $300.00 | $250.00 |
| 41 | Riprap (concrete)(4 in) (432-7001) | CY | 256 | $625.00 | $400.00 | $525.00 | $650.00 | $700.00 | $550.00 | $550.00 |
| 42 | Riprap (concrete)(5 in) (432-7002) | CY | 118 | $800.00 | $550.00 | $577.00 | $650.00 | $1,225.00 | $600.00 | $650.00 |
| 43 | Riprap (mow strip)(4 in) (432-7013) | CY | 61 | $700.00 | $600.00 | $615.00 | $550.00 | $800.00 | $675.00 | $550.00 |
| 44 | Riprap (stone common)(dry)(12 in) (432-7031) | CY | 1,196 | $190.00 | $140.00 | $266.00 | $150.00 | $245.00 | $275.00 | $150.00 |
| 45 | Riprap (stone protection)(12 in) (432-7041) | CY | 2,242 | $220.00 | $120.00 | $186.00 | $150.00 | $225.00 | $325.00 | $185.00 |
| 46 | STR steel (miscellaneous non-bridge) (442-7007) | LB | 1,008 | $32.00 | $11.83 | $22.00 | $17.00 | $20.00 | $30.00 | $20.00 |
| 47 | Rail (type C221)(HPC) (450-7033) | LF | 472 | $160.00 | $175.02 | $154.00 | $200.00 | $200.00 | $250.00 | $200.00 |
| 48 | Rail (handrail)(type F) (450-7063) | LF | 2,042 | $155.00 | $121.10 | $126.00 | $150.00 | $150.00 | $175.00 | $185.00 |
| 49 | Sealed expansion joint (4 in) (SEJ - M) (454-7004) | LF | 218 | $245.00 | $180.00 | $212.00 | $180.00 | $250.00 | $250.00 | $100.00 |
| 50 | Concrete box culvert (3 FT X 2 FT) (462-7001) | LF | 312 | $350.00 | $350.00 | $220.00 | $235.00 | $263.82 | $260.00 | $550.00 |
| 51 | Concrete box culvert (4 FT X 2 FT) (462-7003) | LF | 1,318 | $360.00 | $400.00 | $247.00 | $279.00 | $315.72 | $315.00 | $650.00 |
| 52 | Concrete box culvert (4 FT X 4 FT) (462-7005) | LF | 169 | $450.00 | $500.00 | $303.00 | $350.00 | $364.37 | $450.00 | $680.00 |
| 53 | Concrete box culvert (5 FT X 2 FT) (462-7006) | LF | 1,199 | $450.00 | $450.00 | $304.00 | $345.00 | $374.10 | $360.00 | $575.00 |
| 54 | Concrete box culvert (5 FT X 4 FT) (462-7008) | LF | 109 | $800.00 | $550.00 | $434.00 | $450.00 | $431.41 | $415.00 | $690.00 |
| 55 | Concrete box culvert (6 FT X 2 FT) (462-7010) | LF | 98 | $800.00 | $600.00 | $457.00 | $450.00 | $416.27 | $420.00 | $625.00 |
| 56 | Concrete box culvert (6 FT X 3 FT) (462-7011) | LF | 272 | $600.00 | $600.00 | $431.00 | $535.00 | $495.20 | $450.00 | $650.00 |
| 57 | Concrete box culvert (8 FT X 4 FT) (462-7021) | LF | 221 | $750.00 | $850.00 | $514.00 | $633.00 | $673.60 | $630.00 | $1,350.00 |
| 58 | Concrete box culvert (4 FT X 4 FT)(extend) (462-7060) | LF | 36 | $880.00 | $550.00 | $698.00 | $500.00 | $1,036.89 | $630.00 | $650.00 |
| 59 | RC pipe (CL III)(18 in) (464-7003) | LF | 1,551 | $100.00 | $210.00 | $80.25 | $51.00 | $87.58 | $105.00 | $75.00 |
| 60 | RC pipe (CL III)(24 in) (464-7005) | LF | 8,613 | $100.00 | $125.00 | $89.50 | $65.00 | $104.88 | $130.00 | $95.00 |
| 61 | RC pipe (CL III)(30 in) (464-7007) | LF | 543 | $130.00 | $150.00 | $115.00 | $90.00 | $131.91 | $165.00 | $110.00 |
| 62 | RC pipe (CL III)(36 in) (464-7009) | LF | 311 | $180.00 | $200.00 | $199.00 | $160.00 | $168.67 | $180.00 | $135.00 |
| 63 | RC pipe (CL III)(42 in) (464-7010) | LF | 237 | $250.00 | $250.00 | $199.00 | $208.00 | $219.49 | $225.00 | $185.00 |
| 64 | Manh (complete)(PRM)(48IN) (465-7002) | EACH | 1 | $9,000.00 | $8,000.00 | $9,370.00 | $4,600.00 | $9,244.41 | $14,750 | $12,500 |
| 65 | Manh (complete)(PRM)(60IN) (465-7003) | EACH | 2 | $10,000 | $12,000 | $10,480 | $5,775.00 | $9,893.15 | $11,050 | $15,000 |
| 66 | Manh (complete)(PRM)(72IN) (465-7004) | EACH | 2 | $13,500 | $15,000 | $14,030 | $9,175.00 | $14,705 | $18,150 | $20,000 |
| 67 | Junction box(complete)(PJB)(6FTX6FT) (465-7011) | EACH | 1 | $13,000 | $17,000 | $10,250 | $7,500.00 | $9,406.60 | $20,200 | $25,000 |
| 68 | Junction box(complete)(PJB)(8FTX8FT) (465-7012) | EACH | 2 | $25,000 | $27,000 | $14,780 | $13,500 | $15,786 | $24,000 | $45,000 |
| 69 | Inlet (complete)(pcu)(3FT)(none) (465-7029) | EACH | 18 | $9,000.00 | $7,000.00 | $7,990.00 | $6,500.00 | $7,784.77 | $9,500.00 | $12,500 |
| 70 | Inlet (complete)(pcu)(3FT)(left) (465-7030) | EACH | 34 | $8,000.00 | $7,000.00 | $8,570.00 | $7,277.00 | $8,487.56 | $10,500 | $12,500 |
| 71 | Inlet (complete)(pcu)(3FT)(right) (465-7031) | EACH | 35 | $8,000.00 | $7,000.00 | $8,710.00 | $7,275.00 | $8,649.75 | $10,350 | $12,500 |
| 72 | Inlet (complete)(pcu)(4FT)(left) (465-7034) | EACH | 10 | $7,500.00 | $8,500.00 | $9,480.00 | $7,675.00 | $9,730.97 | $11,975 | $13,500 |
| 73 | Inlet (complete)(pcu)(5FT)(none) (465-7037) | EACH | 3 | $10,000 | $9,000.00 | $8,740.00 | $6,850.00 | $8,649.75 | $11,530 | $15,500 |
| 74 | Inlet (complete)(pcu)(5FT)(left) (465-7038) | EACH | 5 | $11,000 | $9,000.00 | $8,910.00 | $8,525.00 | $8,920.05 | $12,200 | $16,000 |
| 75 | Inlet (complete)(pcu)(5FT)(right) (465-7039) | EACH | 6 | $11,000 | $9,000.00 | $8,890.00 | $8,900.00 | $8,920.05 | $11,400 | $16,500 |
| 76 | Inlet (complete)(pcu)(6FT)(left) (465-7042) | EACH | 7 | $12,000 | $10,000 | $10,990 | $8,900.00 | $11,785 | $15,200 | $17,500 |
| 77 | Inlet (complete)(PSL)(FG)(3FTX3FT-3FTX3FT) (465-7126) | EACH | 6 | $7,200.00 | $5,500.00 | $7,950.00 | $5,125.00 | $6,811.68 | $8,500.00 | $12,500 |
| 78 | Inlet (complete)(PSL)(FG)(3FTX5FT-3FTX5FT) (465-7130) | EACH | 1 | $8,000.00 | $7,000.00 | $9,550.00 | $6,100.00 | $7,676.65 | $13,325 | $15,000 |
| 79 | Headwall (CH - PW - 0) (diameter= 18 in) (466-7099) | EACH | 2 | $10,000 | $5,000.00 | $5,910.00 | $1,800.00 | $7,568.53 | $16,500 | $1,500.00 |
| 80 | Headwall (CH - PW - 0) (diameter= 24 in) (466-7101) | EACH | 2 | $8,000.00 | $10,000 | $7,220.00 | $3,600.00 | $9,730.97 | $17,500 | $2,500.00 |
| 81 | Wingwall (PW - 1) (HW=5 FT) (466-7175) | EACH | 1 | $20,000 | $18,000 | $13,050 | $13,200 | $19,246 | $17,900 | $12,500 |
| 82 | Wingwall (PW - 1) (HW=6 FT) (466-7176) | EACH | 8 | $24,000 | $25,000 | $20,690 | $15,500 | $23,787 | $22,650 | $13,500 |
| 83 | Wingwall (PW - 1) (HW=7 FT) (466-7177) | EACH | 2 | $40,000 | $27,000 | $22,470 | $20,000 | $29,734 | $37,650 | $15,000 |
| 84 | Wingwall (PW - 1) (HW=8 FT) (466-7178) | EACH | 1 | $50,000 | $30,000 | $25,420 | $24,000 | $35,680 | $61,200 | $17,000 |
| 85 | Wingwall (PW - 2) (HW=6 FT) (466-7190) | EACH | 1 | $23,000 | $25,000 | $12,720 | $18,000 | $13,515 | $50,800 | $16,500 |
| 86 | Wingwall (PW - 2) (HW=8 FT) (466-7192) | EACH | 1 | $35,000 | $28,000 | $26,960 | $24,000 | $31,896 | $65,950 | $20,000 |
| 87 | Set (type I)(S= 8 FT)(HW= 5 FT)(6:1)(P) (467-7186) | EACH | 2 | $2,000.00 | $25,000 | $21,780 | $18,000 | $13,515 | $20,600 | $25,000 |
| 88 | Set(type II)(24 in)(RCP)(3:1)(P) (467-7469) | EACH | 2 | $2,000.00 | $4,000.00 | $2,160.00 | $1,100.00 | $4,865.49 | $6,100.00 | $2,500.00 |
| 89 | Cast-in-place trench drain (474-7021) | LF | 125 | $650.00 | $400.00 | $602.00 | $500.00 | $750.00 | $650.00 | $500.00 |
| 90 | Clean existing culverts (480-7001) | EACH | 2 | $6,000.00 | $3,000.00 | $3,970.00 | $5,000.00 | $8,109.14 | $9,950.00 | $5,000.00 |
| 91 | Removing structure (inlet) (496-7002) | EACH | 3 | $1,600.00 | $1,200.00 | $1,390.00 | $1,000.00 | $2,378.68 | $2,700.00 | $2,500.00 |
| 92 | Removing structure (set) (496-7004) | EACH | 66 | $600.00 | $700.00 | $500.00 | $500.00 | $1,621.83 | $950.00 | $500.00 |
| 93 | Removing structure (wingwall) (496-7005) | EACH | 6 | $2,000.00 | $1,800.00 | $2,380.00 | $1,000.00 | $4,216.75 | $3,900.00 | $2,500.00 |
| 94 | Removing structure (headwall) (496-7006) | EACH | 8 | $2,000.00 | $2,800.00 | $1,750.00 | $500.00 | $4,324.87 | $2,700.00 | $2,500.00 |
| 95 | Removing structure (pipe) (496-7007) | LF | 2,532 | $30.00 | $40.00 | $22.10 | $50.00 | $48.65 | $30.00 | $50.00 |
| 96 | Removing structure (box culvert) (496-7008) | LF | 291 | $100.00 | $65.00 | $65.75 | $50.00 | $114.61 | $65.00 | $100.00 |
| 97 | Removing structure (junction box) (496-7044) | EACH | 2 | $1,000.00 | $1,300.00 | $2,030.00 | $1,000.00 | $3,784.27 | $2,450.00 | $2,500.00 |
| 98 | Mobilization (500-7001) | LS | 1 | $3,150,580 | $2,368,401 | $3,190,000 | $3,400,000 | $2,919,000 | $775,000 | $3,500,000 |
| 99 | Barricades, signs and traffic handling (502-7001) | MO | 32 | $15,000 | $6,000.00 | $26,951 | $10,000 | $21,000 | $15,000 | $12,500 |
| 100 | Portable changeable message sign (503-7002) | EACH | 2 | $20,000 | $15,000 | $24,780 | $15,000 | $22,000 | $37,500 | $20,000 |
| 101 | TMA (stationary) (505-7001) | DAY | 410 | $500.00 | $183.33 | $230.00 | $200.00 | $200.00 | $350.00 | $250.00 |
| 102 | TMA (mobile operation) (505-7003) | DAY | 18 | $400.00 | $875.00 | $230.00 | $1,000.00 | $1,000.00 | $900.00 | $550.00 |
| 103 | Rock filter dams (install) (type 2) (506-7002) | LF | 800 | $50.00 | $39.56 | $39.50 | $38.00 | $60.00 | $36.87 | $30.00 |
| 104 | Rock filter dams (install) (type 3) (506-7003) | LF | 200 | $98.00 | $89.70 | $89.75 | $85.00 | $135.00 | $42.14 | $40.00 |
| 105 | Rock filter dams (remove) (506-7011) | LF | 1,000 | $17.00 | $15.76 | $15.80 | $10.00 | $25.00 | $16.85 | $20.00 |
| 106 | Construction exits (install) (type 1) (506-7020) | SY | 429 | $31.00 | $38.47 | $25.00 | $25.00 | $40.00 | $17.82 | $50.00 |
| 107 | Construction exits (remove) (506-7024) | SY | 429 | $12.00 | $12.48 | $10.00 | $10.00 | $10.00 | $26.44 | $20.00 |
| 108 | Temporary sediment control fence (install) (506-7039) | LF | 11,567 | $4.00 | $3.31 | $4.00 | $4.00 | $4.00 | $2.05 | $4.00 |
| 109 | Temporary sediment control fence (remove) (506-7041) | LF | 11,567 | $1.50 | $0.93 | $0.90 | $1.00 | $1.00 | $1.11 | $2.00 |
| 110 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 2,030 | $10.00 | $6.01 | $4.00 | $5.00 | $5.00 | $3.27 | $12.00 |
| 111 | Biodegradable erosion control logs (remove) (506-7046) | LF | 2,030 | $3.00 | $0.93 | $1.00 | $1.00 | $1.00 | $0.68 | $5.00 |
| 112 | Constructing detours (508-7001) | SY | 9,570 | $85.00 | $113.73 | $122.00 | $141.00 | $125.00 | $115.00 | $50.00 |
| 113 | Portable concrete traffic barrier (furnish and install)(F-shape)(type 1) (512-7005) | LF | 600 | $65.00 | $42.00 | $27.50 | $25.00 | $20.00 | $80.00 | $100.00 |
| 114 | Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009) | LF | 7,660 | $55.00 | $40.00 | $21.70 | $65.00 | $35.00 | $80.00 | $100.00 |
| 115 | Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010) | LF | 800 | $70.00 | $45.00 | $100.00 | $65.00 | $140.00 | $80.00 | $100.00 |
| 116 | Portable concrete traffic barrier (move)(F-shape)(type 1) (512-7029) | LF | 300 | $12.00 | $10.00 | $16.00 | $25.00 | $18.00 | $40.00 | $20.00 |
| 117 | Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033) | LF | 5,960 | $10.00 | $5.00 | $11.20 | $10.00 | $11.00 | $15.00 | $20.00 |
| 118 | Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034) | LF | 240 | $25.00 | $7.00 | $19.70 | $10.00 | $42.00 | $15.00 | $20.00 |
| 119 | Portable concrete traffic barrier (remove)(F-shape)(type 1) (512-7053) | LF | 600 | $15.00 | $15.00 | $12.80 | $25.00 | $12.00 | $20.00 | $20.00 |
| 120 | Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057) | LF | 7,660 | $15.00 | $12.00 | $15.80 | $20.00 | $13.00 | $20.00 | $20.00 |
| 121 | Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058) | LF | 800 | $20.00 | $12.00 | $29.70 | $20.00 | $35.00 | $25.76 | $20.00 |
| 122 | Portable concrete traffic barrier (pinning) (512-7071) | EACH | 120 | $108.00 | $40.00 | $51.25 | $30.00 | $120.00 | $100.00 | $500.00 |
| 123 | Colored textured concrete (4") (527-7001) | SY | 153 | $190.00 | $125.00 | $81.25 | $180.00 | $110.00 | $85.00 | $95.00 |
| 124 | Concrete curb (mono) (type II) (529-7007) | LF | 22,527 | $8.00 | $2.50 | $4.50 | $15.00 | $5.00 | $2.00 | $6.00 |
| 125 | Concrete curb (doweled) (529-7012) | LF | 369 | $50.00 | $40.00 | $20.00 | $35.00 | $40.00 | $15.00 | $65.00 |
| 126 | Driveways (concrete) (hes) (530-7007) | SY | 2,404 | $130.00 | $120.00 | $136.00 | $110.00 | $150.00 | $105.00 | $105.00 |
| 127 | Driveways (ACP) (530-7010) | SY | 289 | $80.00 | $110.00 | $76.00 | $75.00 | $215.00 | $95.00 | $45.00 |
| 128 | Concrete sidewalks (4") (531-7001) | SY | 22,060 | $70.00 | $50.00 | $62.75 | $57.00 | $70.00 | $55.00 | $40.00 |
| 129 | Curb ramps (type 1) (531-7005) | EACH | 4 | $4,000.00 | $2,500.00 | $2,970.00 | $1,500.00 | $33,000 | $2,500.00 | $2,850.00 |
| 130 | Curb ramps (type 3) (531-7007) | EACH | 6 | $6,000.00 | $2,500.00 | $2,970.00 | $1,800.00 | $3,000.00 | $2,500.00 | $2,850.00 |
| 131 | Curb ramps (type 10) (531-7011) | EACH | 6 | $6,000.00 | $3,000.00 | $2,970.00 | $1,500.00 | $3,000.00 | $2,500.00 | $2,850.00 |
| 132 | Right of way markers (538-7001) | EACH | 102 | $210.00 | $75.00 | $405.00 | $50.00 | $431.33 | $300.00 | $100.00 |
| 133 | Metal W-beam guard fence (steel post) (540-7002) | LF | 450 | $30.00 | $28.50 | $25.30 | $29.00 | $26.92 | $25.28 | $35.00 |
| 134 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 4 | $3,200.00 | $2,200.00 | $2,270.00 | $2,200.00 | $2,416.49 | $2,269.00 | $1,850.00 |
| 135 | Downstream anchor terminal section (540-7015) | EACH | 3 | $2,100.00 | $1,200.00 | $1,280.00 | $1,200.00 | $1,363.20 | $1,280.00 | $1,850.00 |
| 136 | Metal beam guard fence (long span system) (540-7027) | EACH | 1 | $2,100.00 | $1,425.00 | $1,180.00 | $1,450.00 | $1,251.38 | $1,175.00 | $2,500.00 |
| 137 | Remove metal beam guard fence (542-7001) | LF | 300 | $5.00 | $3.00 | $2.00 | $3.00 | $2.13 | $2.00 | $3.00 |
| 138 | Guardrail end treatment (install) (544-7001) | EACH | 7 | $3,200.00 | $2,950.00 | $3,060.00 | $3,000.00 | $3,253.58 | $3,055.00 | $4,250.00 |
| 139 | Guardrail end treatment (remove) (544-7003) | EACH | 4 | $300.00 | $250.00 | $200.00 | $250.00 | $213.00 | $200.00 | $1,500.00 |
| 140 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 2 | $2,600.00 | $2,000.00 | $1,090.00 | $1,500.00 | $2,000.00 | $2,750.00 | $6,500.00 |
| 141 | Crash cushion attenuator (remove) (545-7004) | EACH | 5 | $1,600.00 | $1,200.00 | $720.00 | $1,000.00 | $1,000.00 | $1,200.00 | $2,500.00 |
| 142 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 5 | $14,000 | $8,000.00 | $7,290.00 | $6,500.00 | $8,000.00 | $12,000 | $21,000 |
| 143 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 20 | $330.00 | $275.00 | $275.00 | $350.00 | $748.89 | $275.00 | $1,150.00 |
| 144 | Mailbox install-D (TWW-post) type 4 (560-7009) | EACH | 2 | $300.00 | $315.00 | $315.00 | $350.00 | $791.49 | $315.00 | $1,150.00 |
| 145 | Mailbox install-M (TWW-post) type 4 (560-7010) | EACH | 1 | $600.00 | $775.00 | $775.00 | $1,000.00 | $1,281.40 | $775.00 | $1,150.00 |
| 146 | Remove RD IL asm (shoe-base) (610-7007) | EACH | 2 | $1,400.00 | $850.00 | $1,300.00 | $750.00 | $3,727.50 | $1,300.00 | $1,500.00 |
| 147 | Conduit (RM) (2") (618-7078) | LF | 20 | $60.00 | $49.00 | $66.50 | $35.00 | $40.47 | $66.50 | $100.00 |
| 148 | Electrical conductor (no.8) insulated (620-7008) | LF | 1,240 | $3.00 | $2.80 | $3.15 | $4.00 | $2.35 | $3.15 | $3.00 |
| 149 | Electrical conductor (no.6) bare (620-7009) | LF | 10 | $3.00 | $2.70 | $3.30 | $4.00 | $3.20 | $3.30 | $3.00 |
| 150 | Electrical conductor (no.6) insulated (620-7010) | LF | 30 | $3.50 | $2.90 | $3.50 | $4.00 | $3.20 | $3.50 | $3.00 |
| 151 | Zinc-coat steel wire strand (1/4") (625-7002) | LF | 640 | $6.00 | $5.10 | $8.75 | $5.00 | $3.99 | $8.75 | $3.00 |
| 152 | Zinc-coat steel wire strand (3/8") (625-7004) | LF | 1,920 | $7.00 | $5.50 | $8.75 | $5.00 | $3.49 | $8.75 | $3.00 |
| 153 | Timber pole (CL 2) 40 FT (627-7003) | EACH | 2 | $3,000.00 | $5,583.00 | $2,420.00 | $4,000.00 | $3,328.13 | $2,415.00 | $5,000.00 |
| 154 | Aluminum signs (type A) (636-7001) | SF | 75 | $60.00 | $33.35 | $35.50 | $46.00 | $75.00 | $75.25 | $30.00 |
| 155 | Replace existing aluminum signs(type A) (636-7004) | SF | 21 | $60.00 | $33.35 | $35.50 | $50.00 | $100.00 | $100.00 | $30.00 |
| 156 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 29 | $800.00 | $610.00 | $648.00 | $1,000.00 | $649.65 | $610.00 | $1,150.00 |
| 157 | Install small roadside sign support and assembly type 10BWG(1)SA(P-BM) (644-7002) | EACH | 5 | $800.00 | $730.00 | $776.00 | $1,000.00 | $777.45 | $730.00 | $1,150.00 |
| 158 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 3 | $900.00 | $720.00 | $765.00 | $1,000.00 | $766.80 | $720.00 | $1,150.00 |
| 159 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 6 | $1,300.00 | $110.00 | $1,180.00 | $1,350.00 | $1,182.15 | $1,110.00 | $1,150.00 |
| 160 | Install small roadside sign support and assembly TYS80(1)SA(U-1EXT) (644-7032) | EACH | 1 | $1,300.00 | $1,345.00 | $1,430.00 | $1,300.00 | $1,432.43 | $1,345.00 | $1,150.00 |
| 161 | Install small roadside sign support and assembly TYS80(1)SA(U-BM) (644-7034) | EACH | 4 | $1,300.00 | $1,495.00 | $1,590.00 | $1,320.00 | $1,592.18 | $1,495.00 | $1,150.00 |
| 162 | Install small roadside sign support and assembly TYS80(1)SA(U-WC) (644-7035) | EACH | 1 | $1,300.00 | $1,390.00 | $1,480.00 | $1,700.00 | $1,480.35 | $1,390.00 | $1,150.00 |
| 163 | Install small roadside sign support and assembly (rail mount) (644-7063) | EACH | 1 | $5,000.00 | $5,990.00 | $6,360.00 | $6,500.00 | $6,379.35 | $5,990.00 | $1,150.00 |
| 164 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012) | EACH | 6 | $25.00 | $15.00 | $15.00 | $20.00 | $15.98 | $15.00 | $100.00 |
| 165 | Install delineator assembly (D-SW)SZ 1(BRF)GF1 (BI) (658-7016) | EACH | 9 | $25.00 | $25.00 | $25.00 | $20.00 | $26.63 | $25.00 | $100.00 |
| 166 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 4 | $50.00 | $25.00 | $25.00 | $25.00 | $26.63 | $25.00 | $100.00 |
| 167 | Install object marker assembly (OM-2Z)(WFLX)GNDHH (658-7249) | EACH | 26 | $70.00 | $245.00 | $245.00 | $155.00 | $260.93 | $245.00 | $100.00 |
| 168 | Work zone pavement marking non-removing (W)6"(DOT) (662-7006) | LF | 75 | $2.00 | $0.90 | $0.50 | $2.00 | $0.53 | $0.98 | $2.00 |
| 169 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 18,435 | $0.80 | $0.49 | $0.45 | $0.50 | $0.48 | $0.53 | $1.00 |
| 170 | Work zone pavement marking non-removing (W)8"(solid) (662-7012) | LF | 626 | $2.00 | $0.75 | $0.75 | $1.00 | $0.80 | $0.81 | $5.00 |
| 171 | Work zone pavement marking non-removing (W)24"(solid) (662-7017) | LF | 57 | $4.00 | $6.00 | $4.00 | $6.00 | $4.26 | $6.51 | $20.00 |
| 172 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 20,299 | $0.80 | $0.49 | $0.45 | $0.50 | $0.48 | $0.53 | $1.00 |
| 173 | Work zone pavement marking removing (W)6"(broken) (662-7065) | LF | 4,260 | $1.00 | $0.55 | $0.95 | $1.50 | $1.01 | $0.60 | $1.00 |
| 174 | Work zone pavement marking removing (W)6"(DOT) (662-7066) | LF | 228 | $1.50 | $2.00 | $0.95 | $2.00 | $1.01 | $2.17 | $1.00 |
| 175 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 46,936 | $1.30 | $1.25 | $0.85 | $1.20 | $0.91 | $1.36 | $1.00 |
| 176 | Work zone pavement marking removing (W)8"(solid) (662-7072) | LF | 4,351 | $2.30 | $1.75 | $1.95 | $2.00 | $2.08 | $1.90 | $3.00 |
| 177 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 185 | $8.00 | $7.25 | $3.00 | $10.00 | $3.20 | $7.86 | $20.00 |
| 178 | Work zone pavement marking removing (Y)6"(broken) (662-7098) | LF | 3,710 | $2.00 | $1.50 | $0.95 | $1.50 | $1.01 | $1.63 | $1.00 |
| 179 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 47,630 | $1.30 | $1.25 | $0.85 | $1.20 | $0.91 | $1.36 | $1.00 |
| 180 | Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018) | LF | 227 | $3.00 | $2.50 | $1.20 | $1.50 | $1.28 | $2.71 | $5.00 |
| 181 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 2,755 | $2.00 | $1.75 | $0.95 | $1.25 | $1.01 | $1.90 | $5.00 |
| 182 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 340 | $10.00 | $6.75 | $12.00 | $6.00 | $12.78 | $7.32 | $20.00 |
| 183 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 52 | $190.00 | $189.00 | $160.00 | $145.00 | $170.40 | $204.93 | $250.00 |
| 184 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 22 | $220.00 | $215.00 | $175.00 | $165.00 | $186.38 | $233.12 | $250.00 |
| 185 | Pavement sler 6" (666-7347) | LF | 58,962 | $0.60 | $0.20 | $0.30 | $0.20 | $0.32 | $0.22 | $1.00 |
| 186 | Pavement sler 8" (666-7348) | LF | 2,982 | $0.90 | $0.35 | $0.60 | $0.30 | $0.64 | $0.38 | $3.00 |
| 187 | Pavement sler 24" (666-7352) | LF | 340 | $4.00 | $0.90 | $2.50 | $2.50 | $2.66 | $0.98 | $20.00 |
| 188 | Pavement sler (arrow) (666-7353) | EACH | 52 | $60.00 | $25.00 | $50.00 | $75.00 | $53.25 | $27.11 | $250.00 |
| 189 | Pavement sler (word) (666-7354) | EACH | 22 | $60.00 | $25.00 | $65.00 | $75.00 | $69.23 | $27.11 | $250.00 |
| 190 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 7,287 | $2.00 | $0.65 | $0.60 | $0.80 | $0.64 | $0.70 | $1.00 |
| 191 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 23,963 | $1.00 | $0.55 | $0.55 | $0.70 | $0.59 | $0.60 | $1.00 |
| 192 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 3,712 | $2.00 | $0.65 | $0.60 | $0.80 | $0.64 | $0.70 | $1.00 |
| 193 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 24,000 | $1.50 | $0.55 | $0.55 | $0.70 | $0.59 | $0.60 | $1.00 |
| 194 | Reflectorized pavement marker type I-C (672-7002) | EACH | 429 | $8.00 | $3.75 | $5.25 | $5.50 | $5.59 | $4.07 | $6.00 |
| 195 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 577 | $8.00 | $3.95 | $5.25 | $5.50 | $5.59 | $4.28 | $6.00 |
| 196 | Eliminating existing PM & markers (4") (677-7001) | LF | 2,950 | $1.00 | $0.65 | $0.65 | $0.65 | $0.69 | $0.70 | $1.00 |
| 197 | Eliminating existing PM & markers (8") (677-7004) | LF | 500 | $2.00 | $0.65 | $1.35 | $1.00 | $1.44 | $0.70 | $3.00 |
| 198 | Eliminating existing PM & markers (24") (677-7008) | LF | 25 | $8.00 | $4.00 | $3.00 | $3.00 | $3.20 | $4.34 | $20.00 |
| 199 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 3 | $90.00 | $65.00 | $45.00 | $100.00 | $47.93 | $70.48 | $250.00 |
| 200 | Eliminating existing PM & markers (word) (677-7015) | EACH | 3 | $75.00 | $65.00 | $50.00 | $100.00 | $53.25 | $70.48 | $250.00 |
| 201 | Pavement surface preparation for marking (6") (678-7002) | LF | 58,962 | $0.40 | $0.06 | $0.15 | $0.10 | $0.16 | $0.07 | $1.00 |
| 202 | Pavement surface preparation for marking (8") (678-7004) | LF | 2,982 | $0.80 | $0.06 | $0.30 | $0.10 | $0.32 | $0.07 | $3.00 |
| 203 | Pavement surface preparation for marking (24") (678-7008) | LF | 340 | $3.00 | $0.18 | $2.00 | $1.00 | $2.13 | $0.20 | $20.00 |
| 204 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 52 | $40.00 | $10.00 | $35.00 | $50.00 | $37.28 | $10.84 | $250.00 |
| 205 | Pavement surface preparation for marking (word) (678-7016) | EACH | 22 | $50.00 | $10.00 | $40.00 | $50.00 | $42.60 | $10.84 | $250.00 |
| 206 | Removing traffic signals (680-7004) | EACH | 1 | $10,000 | $18,127 | $5,510.00 | $7,000.00 | $10,991 | $5,510.00 | $12,500 |
| 207 | Install highway traffic signal (upgrade) (680-7011) | EACH | 1 | $45,000 | $26,336 | $12,700 | $20,000 | $19,511 | $12,700 | $50,000 |
| 208 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 8 | $500.00 | $365.00 | $380.00 | $375.00 | $413.22 | $380.00 | $350.00 |
| 209 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 4 | $500.00 | $365.00 | $390.00 | $375.00 | $420.68 | $390.00 | $350.00 |
| 210 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 8 | $500.00 | $365.00 | $380.00 | $375.00 | $413.22 | $380.00 | $350.00 |
| 211 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 8 | $500.00 | $365.00 | $390.00 | $375.00 | $420.68 | $390.00 | $350.00 |
| 212 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 8 | $500.00 | $365.00 | $380.00 | $375.00 | $413.22 | $380.00 | $350.00 |
| 213 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 8 | $500.00 | $365.00 | $390.00 | $375.00 | $420.68 | $390.00 | $350.00 |
| 214 | Backplate W/ref border(3 sec)(vent)aluminum (682-7042) | EACH | 8 | $210.00 | $242.00 | $183.00 | $375.00 | $197.03 | $182.50 | $200.00 |
| 215 | Backplate W/ref border(5 sec)(vent)aluminum (682-7044) | EACH | 4 | $280.00 | $285.00 | $272.00 | $280.00 | $239.63 | $272.00 | $250.00 |
| 216 | Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031) | LF | 725 | $5.00 | $3.50 | $3.25 | $4.00 | $3.72 | $3.25 | $3.00 |
| 217 | Traffic signal CBL (type A)(14 AWG)(7 conductor) (684-7033) | LF | 695 | $5.00 | $3.90 | $3.55 | $5.00 | $4.02 | $3.55 | $3.00 |
| 218 | Full - width mowing (730-7019) | CYC | 8 | $5,000.00 | $8,384.96 | $7,000.00 | $500.00 | $5,000.00 | $4,970.28 | $3,000.00 |
| 219 | VIVDS prosr sys (6006-7001) | EACH | 1 | $22,000 | $14,319 | $12,500 | $14,000 | $10,810 | $12,500 | $20,000 |
| 220 | VIVDS cam assy FXD LNS (6006-7002) | EACH | 4 | $7,500.00 | $4,131.00 | $3,000.00 | $5,000.00 | $3,354.75 | $3,000.00 | $8,500.00 |
| 221 | VIVDS CNTRL software (6006-7005) | EACH | 1 | $12,000 | $448.00 | $1,070.00 | $1,000.00 | $532.50 | $1,074.00 | $8,500.00 |
| 222 | VIVDS cabling (6006-7007) | LF | 710 | $4.00 | $3.90 | $4.00 | $5.00 | $3.20 | $4.00 | $3.00 |
| 223 | RVDS (advance detection only) (6008-7002) | EACH | 4 | $12,000 | $10,763 | $7,550.00 | $17,000 | $8,466.75 | $7,551.00 | $10,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of February 4, 2026. Compiled by Mirage Metrics.