TxDOT contract A00045441 bid tabulation

Widen Road - Add Lanes, FM 549 (SH 205 to SH 276). Let by Texas DOT on February 4, 2026, Rockwall, Dallas District. 12 bids received; low bid $29,812,034 by Urban Infraconstruction LLC, -14% against the engineer's estimate of $34,640,755.

Owner
Texas DOT
Letting
04 FEB 2026
Pay items
223
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Urban Infraconstruction LLC$29,812,034Low-14%
2Webber, LLC$31,956,749+7.0%-8.0%
3Highway 19 Construction LLC$32,124,988+8.0%-7.0%
4Ed Bell Construction Company$33,345,707+12%-4.0%
5Harper Brothers Construction LLC$33,779,105+13%-2.0%
6Grey Sky Construction LLC$34,455,613+16%-1.0%
7Granite Construction Company$35,089,835+18%+1.0%
8Mario Sinacola & Sons Excavating, Inc.$35,321,967+18%+2.0%
9McMahon Contracting and Construction, LLC$37,441,521+26%+8.0%
10Ragle Construction, Inc.$38,105,737+28%+10%
11Indus Road & Bridge, Inc.$42,320,780+42%+22%
12Copasa Inc$44,776,051+50%+29%
TxDOT contract A00045441: bids by rank

Engineer's estimate: $34,640,755.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Urban Infraconstruction LLC2. Webber, LLC3. Highway 19 Construction LLC4. Ed Bell Construction Company5. Harper Brothers Construction LLC6. Grey Sky Construction LLC
1Preparing row (100-7002)STA109.70$18,569$5,000.00$28,259$575.00$4,200.00$10,000$26,000
2Removing concrete (riprap) (104-7006)SY90$25.00$12.00$24.50$25.00$25.00$50.00$50.00
3Removing concrete (driveways) (104-7011)SY2,717$25.00$10.00$18.50$25.00$21.00$15.00$20.00
4Removing concrete (sidewalk, ramp or shared use path) (104-7013)SY444$30.00$12.00$21.90$25.00$21.00$15.00$20.00
5Removing concrete (curb) (104-7016)LF318$20.00$3.00$6.85$10.00$10.00$5.00$20.00
6Excavation (roadway) (110-7001)CY76,938$20.00$13.65$12.30$10.00$25.00$20.00$10.00
7Embankment (final)(DC)(type C1) (132-7008)CY24,172$15.00$21.28$16.70$22.00$15.00$35.00$30.00
8Embankment (final)(DC)(type C2) (132-7010)CY2,346$30.00$50.85$32.25$22.00$100.00$35.00$40.00
9Compost manuf topsoil (4") (161-7002)SY52,337$3.00$1.64$2.20$0.93$1.00$0.94$3.00
10Block sodding (162-7002)SY52,337$6.00$3.49$3.50$3.50$3.72$3.49$5.00
11Drill seed (temporary_warm_cool) (164-7015)SY49,787$0.60$0.13$0.10$0.13$0.14$0.13$0.35
12Vegetative watering (168-7001)TGL15,192$25.00$33.02$7.00$10.00$1.00$5.00$1.00
13FL BS (compacted in place)(type D GR 1-2) (12") (247-7125)SY5,561$30.00$35.95$29.30$29.21$45.00$45.00$30.00
14Lime (com or QK)(slurry) (260-7005)TON3,832$330.00$292.00$297.00$320.00$315.00$325.00$350.00
15Lime TRT (existing material)(12") (260-7009)SY96,272$7.00$10.00$6.25$7.00$8.00$8.00$7.00
16Salvage, haul & stockpile reclaimed asphalt PV(2"-15.6") (305-7042)SY40,936$4.00$8.00$8.50$7.00$9.13$8.50$5.00
17Prime coat(MC-30 or AE-P) (310-7013)GAL1,671$5.00$6.90$6.70$9.00$7.21$6.70$6.00
18Asphalt (CRS-2P) (316-7012)GAL484$11.00$10.30$10.00$10.00$10.76$10.00$6.00
19Asphalt (AC-15P, AC-20-5TR or AC-20XP) (316-7071)GAL484$8.00$26.40$25.70$10.00$27.60$25.65$6.00
20Aggregate (type-B or L, GR-3)(sac-B) (316-7244)CY23$200.00$689.85$670.00$250.00$720.63$669.75$500.00
21SP mixes SP-B PG64-22 (344-7001)TON19,854$105.00$112.90$110.00$126.00$117.93$109.60$125.00
22SP mixes SP-C sac-B PG64-22 (344-7011)TON1,207$140.00$161.35$157.00$143.00$168.55$156.65$145.00
23Tack coat (344-7077)GAL330$5.00$7.45$7.25$10.00$7.80$7.25$6.00
24Concrete pavement (CRCP) (8") (360-7002)SY82,836$80.00$75.00$69.25$102.00$80.00$100.00$55.00
25Concrete pavement (CRCP)(hes) (8") (360-7047)SY1,584$150.00$120.00$125.00$110.00$120.00$125.00$105.00
26Cem stabil BKFL (400-7010)CY520$220.00$190.00$203.00$180.00$300.00$225.00$350.00
27Flowable backfill (401-7001)CY27$400.00$300.00$198.00$350.00$600.00$225.00$350.00
28Trench excavation protection (402-7001)LF8,934$10.00$2.00$4.55$5.00$2.00$3.75$2.00
29Temporary special shoring (403-7001)SF10,798$32.00$25.00$16.90$45.00$40.00$10.00$50.00
30Drilled shaft (18 in) (416-7002)LF110$240.00$97.00$107.00$180.00$150.00$150.00$150.00
31Drilled shaft (36 in) (416-7006)LF997$300.00$158.00$179.00$250.00$200.00$300.00$220.00
32Class C concrete (abutment)(HPC) (420-7013)CY119.60$1,400.00$1,000.00$1,270.00$1,179.00$1,500.00$1,800.00$1,250.00
33Class C concrete (cap)(HPC) (420-7023)CY102$1,600.00$1,200.00$1,280.00$1,222.00$1,500.00$2,000.00$1,250.00
34Class C concrete (column)(HPC) (420-7039)CY18.90$1,600.00$2,000.00$2,090.00$1,100.00$2,500.00$2,750.00$1,250.00
35Reinforced concrete slab (HPC) (422-7002)SF19,067$30.00$20.00$25.20$25.00$25.00$30.00$25.00
36Approach slab (HPC) (422-7014)CY377$720.00$600.00$571.00$750.00$750.00$775.00$1,250.00
37Bridge median (HPC) (422-7021)SF3,940$30.00$13.50$13.20$17.00$13.00$20.00$85.00
38Bridge sidewalk(HPC) (422-7022)SF6,645$30.00$14.00$13.60$14.00$14.00$20.00$85.00
39Retaining wall (spread footing) (423-7015)SF2,520$120.00$150.00$89.00$91.00$100.00$140.00$85.00
40Prestressed concrete girder (TX40) (425-7003)LF2,578.42$200.00$200.00$212.00$234.00$250.00$300.00$250.00
41Riprap (concrete)(4 in) (432-7001)CY256$625.00$400.00$525.00$650.00$700.00$550.00$550.00
42Riprap (concrete)(5 in) (432-7002)CY118$800.00$550.00$577.00$650.00$1,225.00$600.00$650.00
43Riprap (mow strip)(4 in) (432-7013)CY61$700.00$600.00$615.00$550.00$800.00$675.00$550.00
44Riprap (stone common)(dry)(12 in) (432-7031)CY1,196$190.00$140.00$266.00$150.00$245.00$275.00$150.00
45Riprap (stone protection)(12 in) (432-7041)CY2,242$220.00$120.00$186.00$150.00$225.00$325.00$185.00
46STR steel (miscellaneous non-bridge) (442-7007)LB1,008$32.00$11.83$22.00$17.00$20.00$30.00$20.00
47Rail (type C221)(HPC) (450-7033)LF472$160.00$175.02$154.00$200.00$200.00$250.00$200.00
48Rail (handrail)(type F) (450-7063)LF2,042$155.00$121.10$126.00$150.00$150.00$175.00$185.00
49Sealed expansion joint (4 in) (SEJ - M) (454-7004)LF218$245.00$180.00$212.00$180.00$250.00$250.00$100.00
50Concrete box culvert (3 FT X 2 FT) (462-7001)LF312$350.00$350.00$220.00$235.00$263.82$260.00$550.00
51Concrete box culvert (4 FT X 2 FT) (462-7003)LF1,318$360.00$400.00$247.00$279.00$315.72$315.00$650.00
52Concrete box culvert (4 FT X 4 FT) (462-7005)LF169$450.00$500.00$303.00$350.00$364.37$450.00$680.00
53Concrete box culvert (5 FT X 2 FT) (462-7006)LF1,199$450.00$450.00$304.00$345.00$374.10$360.00$575.00
54Concrete box culvert (5 FT X 4 FT) (462-7008)LF109$800.00$550.00$434.00$450.00$431.41$415.00$690.00
55Concrete box culvert (6 FT X 2 FT) (462-7010)LF98$800.00$600.00$457.00$450.00$416.27$420.00$625.00
56Concrete box culvert (6 FT X 3 FT) (462-7011)LF272$600.00$600.00$431.00$535.00$495.20$450.00$650.00
57Concrete box culvert (8 FT X 4 FT) (462-7021)LF221$750.00$850.00$514.00$633.00$673.60$630.00$1,350.00
58Concrete box culvert (4 FT X 4 FT)(extend) (462-7060)LF36$880.00$550.00$698.00$500.00$1,036.89$630.00$650.00
59RC pipe (CL III)(18 in) (464-7003)LF1,551$100.00$210.00$80.25$51.00$87.58$105.00$75.00
60RC pipe (CL III)(24 in) (464-7005)LF8,613$100.00$125.00$89.50$65.00$104.88$130.00$95.00
61RC pipe (CL III)(30 in) (464-7007)LF543$130.00$150.00$115.00$90.00$131.91$165.00$110.00
62RC pipe (CL III)(36 in) (464-7009)LF311$180.00$200.00$199.00$160.00$168.67$180.00$135.00
63RC pipe (CL III)(42 in) (464-7010)LF237$250.00$250.00$199.00$208.00$219.49$225.00$185.00
64Manh (complete)(PRM)(48IN) (465-7002)EACH1$9,000.00$8,000.00$9,370.00$4,600.00$9,244.41$14,750$12,500
65Manh (complete)(PRM)(60IN) (465-7003)EACH2$10,000$12,000$10,480$5,775.00$9,893.15$11,050$15,000
66Manh (complete)(PRM)(72IN) (465-7004)EACH2$13,500$15,000$14,030$9,175.00$14,705$18,150$20,000
67Junction box(complete)(PJB)(6FTX6FT) (465-7011)EACH1$13,000$17,000$10,250$7,500.00$9,406.60$20,200$25,000
68Junction box(complete)(PJB)(8FTX8FT) (465-7012)EACH2$25,000$27,000$14,780$13,500$15,786$24,000$45,000
69Inlet (complete)(pcu)(3FT)(none) (465-7029)EACH18$9,000.00$7,000.00$7,990.00$6,500.00$7,784.77$9,500.00$12,500
70Inlet (complete)(pcu)(3FT)(left) (465-7030)EACH34$8,000.00$7,000.00$8,570.00$7,277.00$8,487.56$10,500$12,500
71Inlet (complete)(pcu)(3FT)(right) (465-7031)EACH35$8,000.00$7,000.00$8,710.00$7,275.00$8,649.75$10,350$12,500
72Inlet (complete)(pcu)(4FT)(left) (465-7034)EACH10$7,500.00$8,500.00$9,480.00$7,675.00$9,730.97$11,975$13,500
73Inlet (complete)(pcu)(5FT)(none) (465-7037)EACH3$10,000$9,000.00$8,740.00$6,850.00$8,649.75$11,530$15,500
74Inlet (complete)(pcu)(5FT)(left) (465-7038)EACH5$11,000$9,000.00$8,910.00$8,525.00$8,920.05$12,200$16,000
75Inlet (complete)(pcu)(5FT)(right) (465-7039)EACH6$11,000$9,000.00$8,890.00$8,900.00$8,920.05$11,400$16,500
76Inlet (complete)(pcu)(6FT)(left) (465-7042)EACH7$12,000$10,000$10,990$8,900.00$11,785$15,200$17,500
77Inlet (complete)(PSL)(FG)(3FTX3FT-3FTX3FT) (465-7126)EACH6$7,200.00$5,500.00$7,950.00$5,125.00$6,811.68$8,500.00$12,500
78Inlet (complete)(PSL)(FG)(3FTX5FT-3FTX5FT) (465-7130)EACH1$8,000.00$7,000.00$9,550.00$6,100.00$7,676.65$13,325$15,000
79Headwall (CH - PW - 0) (diameter= 18 in) (466-7099)EACH2$10,000$5,000.00$5,910.00$1,800.00$7,568.53$16,500$1,500.00
80Headwall (CH - PW - 0) (diameter= 24 in) (466-7101)EACH2$8,000.00$10,000$7,220.00$3,600.00$9,730.97$17,500$2,500.00
81Wingwall (PW - 1) (HW=5 FT) (466-7175)EACH1$20,000$18,000$13,050$13,200$19,246$17,900$12,500
82Wingwall (PW - 1) (HW=6 FT) (466-7176)EACH8$24,000$25,000$20,690$15,500$23,787$22,650$13,500
83Wingwall (PW - 1) (HW=7 FT) (466-7177)EACH2$40,000$27,000$22,470$20,000$29,734$37,650$15,000
84Wingwall (PW - 1) (HW=8 FT) (466-7178)EACH1$50,000$30,000$25,420$24,000$35,680$61,200$17,000
85Wingwall (PW - 2) (HW=6 FT) (466-7190)EACH1$23,000$25,000$12,720$18,000$13,515$50,800$16,500
86Wingwall (PW - 2) (HW=8 FT) (466-7192)EACH1$35,000$28,000$26,960$24,000$31,896$65,950$20,000
87Set (type I)(S= 8 FT)(HW= 5 FT)(6:1)(P) (467-7186)EACH2$2,000.00$25,000$21,780$18,000$13,515$20,600$25,000
88Set(type II)(24 in)(RCP)(3:1)(P) (467-7469)EACH2$2,000.00$4,000.00$2,160.00$1,100.00$4,865.49$6,100.00$2,500.00
89Cast-in-place trench drain (474-7021)LF125$650.00$400.00$602.00$500.00$750.00$650.00$500.00
90Clean existing culverts (480-7001)EACH2$6,000.00$3,000.00$3,970.00$5,000.00$8,109.14$9,950.00$5,000.00
91Removing structure (inlet) (496-7002)EACH3$1,600.00$1,200.00$1,390.00$1,000.00$2,378.68$2,700.00$2,500.00
92Removing structure (set) (496-7004)EACH66$600.00$700.00$500.00$500.00$1,621.83$950.00$500.00
93Removing structure (wingwall) (496-7005)EACH6$2,000.00$1,800.00$2,380.00$1,000.00$4,216.75$3,900.00$2,500.00
94Removing structure (headwall) (496-7006)EACH8$2,000.00$2,800.00$1,750.00$500.00$4,324.87$2,700.00$2,500.00
95Removing structure (pipe) (496-7007)LF2,532$30.00$40.00$22.10$50.00$48.65$30.00$50.00
96Removing structure (box culvert) (496-7008)LF291$100.00$65.00$65.75$50.00$114.61$65.00$100.00
97Removing structure (junction box) (496-7044)EACH2$1,000.00$1,300.00$2,030.00$1,000.00$3,784.27$2,450.00$2,500.00
98Mobilization (500-7001)LS1$3,150,580$2,368,401$3,190,000$3,400,000$2,919,000$775,000$3,500,000
99Barricades, signs and traffic handling (502-7001)MO32$15,000$6,000.00$26,951$10,000$21,000$15,000$12,500
100Portable changeable message sign (503-7002)EACH2$20,000$15,000$24,780$15,000$22,000$37,500$20,000
101TMA (stationary) (505-7001)DAY410$500.00$183.33$230.00$200.00$200.00$350.00$250.00
102TMA (mobile operation) (505-7003)DAY18$400.00$875.00$230.00$1,000.00$1,000.00$900.00$550.00
103Rock filter dams (install) (type 2) (506-7002)LF800$50.00$39.56$39.50$38.00$60.00$36.87$30.00
104Rock filter dams (install) (type 3) (506-7003)LF200$98.00$89.70$89.75$85.00$135.00$42.14$40.00
105Rock filter dams (remove) (506-7011)LF1,000$17.00$15.76$15.80$10.00$25.00$16.85$20.00
106Construction exits (install) (type 1) (506-7020)SY429$31.00$38.47$25.00$25.00$40.00$17.82$50.00
107Construction exits (remove) (506-7024)SY429$12.00$12.48$10.00$10.00$10.00$26.44$20.00
108Temporary sediment control fence (install) (506-7039)LF11,567$4.00$3.31$4.00$4.00$4.00$2.05$4.00
109Temporary sediment control fence (remove) (506-7041)LF11,567$1.50$0.93$0.90$1.00$1.00$1.11$2.00
110Biodegradable erosion control logs (install) (8") (506-7043)LF2,030$10.00$6.01$4.00$5.00$5.00$3.27$12.00
111Biodegradable erosion control logs (remove) (506-7046)LF2,030$3.00$0.93$1.00$1.00$1.00$0.68$5.00
112Constructing detours (508-7001)SY9,570$85.00$113.73$122.00$141.00$125.00$115.00$50.00
113Portable concrete traffic barrier (furnish and install)(F-shape)(type 1) (512-7005)LF600$65.00$42.00$27.50$25.00$20.00$80.00$100.00
114Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009)LF7,660$55.00$40.00$21.70$65.00$35.00$80.00$100.00
115Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010)LF800$70.00$45.00$100.00$65.00$140.00$80.00$100.00
116Portable concrete traffic barrier (move)(F-shape)(type 1) (512-7029)LF300$12.00$10.00$16.00$25.00$18.00$40.00$20.00
117Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033)LF5,960$10.00$5.00$11.20$10.00$11.00$15.00$20.00
118Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034)LF240$25.00$7.00$19.70$10.00$42.00$15.00$20.00
119Portable concrete traffic barrier (remove)(F-shape)(type 1) (512-7053)LF600$15.00$15.00$12.80$25.00$12.00$20.00$20.00
120Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057)LF7,660$15.00$12.00$15.80$20.00$13.00$20.00$20.00
121Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058)LF800$20.00$12.00$29.70$20.00$35.00$25.76$20.00
122Portable concrete traffic barrier (pinning) (512-7071)EACH120$108.00$40.00$51.25$30.00$120.00$100.00$500.00
123Colored textured concrete (4") (527-7001)SY153$190.00$125.00$81.25$180.00$110.00$85.00$95.00
124Concrete curb (mono) (type II) (529-7007)LF22,527$8.00$2.50$4.50$15.00$5.00$2.00$6.00
125Concrete curb (doweled) (529-7012)LF369$50.00$40.00$20.00$35.00$40.00$15.00$65.00
126Driveways (concrete) (hes) (530-7007)SY2,404$130.00$120.00$136.00$110.00$150.00$105.00$105.00
127Driveways (ACP) (530-7010)SY289$80.00$110.00$76.00$75.00$215.00$95.00$45.00
128Concrete sidewalks (4") (531-7001)SY22,060$70.00$50.00$62.75$57.00$70.00$55.00$40.00
129Curb ramps (type 1) (531-7005)EACH4$4,000.00$2,500.00$2,970.00$1,500.00$33,000$2,500.00$2,850.00
130Curb ramps (type 3) (531-7007)EACH6$6,000.00$2,500.00$2,970.00$1,800.00$3,000.00$2,500.00$2,850.00
131Curb ramps (type 10) (531-7011)EACH6$6,000.00$3,000.00$2,970.00$1,500.00$3,000.00$2,500.00$2,850.00
132Right of way markers (538-7001)EACH102$210.00$75.00$405.00$50.00$431.33$300.00$100.00
133Metal W-beam guard fence (steel post) (540-7002)LF450$30.00$28.50$25.30$29.00$26.92$25.28$35.00
134Metal beam guard fence trans (thrie-beam) (540-7005)EACH4$3,200.00$2,200.00$2,270.00$2,200.00$2,416.49$2,269.00$1,850.00
135Downstream anchor terminal section (540-7015)EACH3$2,100.00$1,200.00$1,280.00$1,200.00$1,363.20$1,280.00$1,850.00
136Metal beam guard fence (long span system) (540-7027)EACH1$2,100.00$1,425.00$1,180.00$1,450.00$1,251.38$1,175.00$2,500.00
137Remove metal beam guard fence (542-7001)LF300$5.00$3.00$2.00$3.00$2.13$2.00$3.00
138Guardrail end treatment (install) (544-7001)EACH7$3,200.00$2,950.00$3,060.00$3,000.00$3,253.58$3,055.00$4,250.00
139Guardrail end treatment (remove) (544-7003)EACH4$300.00$250.00$200.00$250.00$213.00$200.00$1,500.00
140Crash cushion attenuator (move & reset) (545-7002)EACH2$2,600.00$2,000.00$1,090.00$1,500.00$2,000.00$2,750.00$6,500.00
141Crash cushion attenuator (remove) (545-7004)EACH5$1,600.00$1,200.00$720.00$1,000.00$1,000.00$1,200.00$2,500.00
142Crash cushion attenuator (install)(S)(N)(TL3) (545-7014)EACH5$14,000$8,000.00$7,290.00$6,500.00$8,000.00$12,000$21,000
143Mailbox install-S (TWW-post) type 4 (560-7008)EACH20$330.00$275.00$275.00$350.00$748.89$275.00$1,150.00
144Mailbox install-D (TWW-post) type 4 (560-7009)EACH2$300.00$315.00$315.00$350.00$791.49$315.00$1,150.00
145Mailbox install-M (TWW-post) type 4 (560-7010)EACH1$600.00$775.00$775.00$1,000.00$1,281.40$775.00$1,150.00
146Remove RD IL asm (shoe-base) (610-7007)EACH2$1,400.00$850.00$1,300.00$750.00$3,727.50$1,300.00$1,500.00
147Conduit (RM) (2") (618-7078)LF20$60.00$49.00$66.50$35.00$40.47$66.50$100.00
148Electrical conductor (no.8) insulated (620-7008)LF1,240$3.00$2.80$3.15$4.00$2.35$3.15$3.00
149Electrical conductor (no.6) bare (620-7009)LF10$3.00$2.70$3.30$4.00$3.20$3.30$3.00
150Electrical conductor (no.6) insulated (620-7010)LF30$3.50$2.90$3.50$4.00$3.20$3.50$3.00
151Zinc-coat steel wire strand (1/4") (625-7002)LF640$6.00$5.10$8.75$5.00$3.99$8.75$3.00
152Zinc-coat steel wire strand (3/8") (625-7004)LF1,920$7.00$5.50$8.75$5.00$3.49$8.75$3.00
153Timber pole (CL 2) 40 FT (627-7003)EACH2$3,000.00$5,583.00$2,420.00$4,000.00$3,328.13$2,415.00$5,000.00
154Aluminum signs (type A) (636-7001)SF75$60.00$33.35$35.50$46.00$75.00$75.25$30.00
155Replace existing aluminum signs(type A) (636-7004)SF21$60.00$33.35$35.50$50.00$100.00$100.00$30.00
156Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH29$800.00$610.00$648.00$1,000.00$649.65$610.00$1,150.00
157Install small roadside sign support and assembly type 10BWG(1)SA(P-BM) (644-7002)EACH5$800.00$730.00$776.00$1,000.00$777.45$730.00$1,150.00
158Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH3$900.00$720.00$765.00$1,000.00$766.80$720.00$1,150.00
159Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031)EACH6$1,300.00$110.00$1,180.00$1,350.00$1,182.15$1,110.00$1,150.00
160Install small roadside sign support and assembly TYS80(1)SA(U-1EXT) (644-7032)EACH1$1,300.00$1,345.00$1,430.00$1,300.00$1,432.43$1,345.00$1,150.00
161Install small roadside sign support and assembly TYS80(1)SA(U-BM) (644-7034)EACH4$1,300.00$1,495.00$1,590.00$1,320.00$1,592.18$1,495.00$1,150.00
162Install small roadside sign support and assembly TYS80(1)SA(U-WC) (644-7035)EACH1$1,300.00$1,390.00$1,480.00$1,700.00$1,480.35$1,390.00$1,150.00
163Install small roadside sign support and assembly (rail mount) (644-7063)EACH1$5,000.00$5,990.00$6,360.00$6,500.00$6,379.35$5,990.00$1,150.00
164Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012)EACH6$25.00$15.00$15.00$20.00$15.98$15.00$100.00
165Install delineator assembly (D-SW)SZ 1(BRF)GF1 (BI) (658-7016)EACH9$25.00$25.00$25.00$20.00$26.63$25.00$100.00
166Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018)EACH4$50.00$25.00$25.00$25.00$26.63$25.00$100.00
167Install object marker assembly (OM-2Z)(WFLX)GNDHH (658-7249)EACH26$70.00$245.00$245.00$155.00$260.93$245.00$100.00
168Work zone pavement marking non-removing (W)6"(DOT) (662-7006)LF75$2.00$0.90$0.50$2.00$0.53$0.98$2.00
169Work zone pavement marking non-removing (W)6"(solid) (662-7008)LF18,435$0.80$0.49$0.45$0.50$0.48$0.53$1.00
170Work zone pavement marking non-removing (W)8"(solid) (662-7012)LF626$2.00$0.75$0.75$1.00$0.80$0.81$5.00
171Work zone pavement marking non-removing (W)24"(solid) (662-7017)LF57$4.00$6.00$4.00$6.00$4.26$6.51$20.00
172Work zone pavement marking non-removing (Y)6"(solid) (662-7038)LF20,299$0.80$0.49$0.45$0.50$0.48$0.53$1.00
173Work zone pavement marking removing (W)6"(broken) (662-7065)LF4,260$1.00$0.55$0.95$1.50$1.01$0.60$1.00
174Work zone pavement marking removing (W)6"(DOT) (662-7066)LF228$1.50$2.00$0.95$2.00$1.01$2.17$1.00
175Work zone pavement marking removing (W)6"(solid) (662-7068)LF46,936$1.30$1.25$0.85$1.20$0.91$1.36$1.00
176Work zone pavement marking removing (W)8"(solid) (662-7072)LF4,351$2.30$1.75$1.95$2.00$2.08$1.90$3.00
177Work zone pavement marking removing (W)24"(solid) (662-7077)LF185$8.00$7.25$3.00$10.00$3.20$7.86$20.00
178Work zone pavement marking removing (Y)6"(broken) (662-7098)LF3,710$2.00$1.50$0.95$1.50$1.01$1.63$1.00
179Work zone pavement marking removing (Y)6"(solid) (662-7100)LF47,630$1.30$1.25$0.85$1.20$0.91$1.36$1.00
180Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018)LF227$3.00$2.50$1.20$1.50$1.28$2.71$5.00
181Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF2,755$2.00$1.75$0.95$1.25$1.01$1.90$5.00
182Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF340$10.00$6.75$12.00$6.00$12.78$7.32$20.00
183Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042)EACH52$190.00$189.00$160.00$145.00$170.40$204.93$250.00
184Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066)EACH22$220.00$215.00$175.00$165.00$186.38$233.12$250.00
185Pavement sler 6" (666-7347)LF58,962$0.60$0.20$0.30$0.20$0.32$0.22$1.00
186Pavement sler 8" (666-7348)LF2,982$0.90$0.35$0.60$0.30$0.64$0.38$3.00
187Pavement sler 24" (666-7352)LF340$4.00$0.90$2.50$2.50$2.66$0.98$20.00
188Pavement sler (arrow) (666-7353)EACH52$60.00$25.00$50.00$75.00$53.25$27.11$250.00
189Pavement sler (word) (666-7354)EACH22$60.00$25.00$65.00$75.00$69.23$27.11$250.00
190Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408)LF7,287$2.00$0.65$0.60$0.80$0.64$0.70$1.00
191Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF23,963$1.00$0.55$0.55$0.70$0.59$0.60$1.00
192Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420)LF3,712$2.00$0.65$0.60$0.80$0.64$0.70$1.00
193Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF24,000$1.50$0.55$0.55$0.70$0.59$0.60$1.00
194Reflectorized pavement marker type I-C (672-7002)EACH429$8.00$3.75$5.25$5.50$5.59$4.07$6.00
195Reflectorized pavement marker type II-A-A (672-7004)EACH577$8.00$3.95$5.25$5.50$5.59$4.28$6.00
196Eliminating existing PM & markers (4") (677-7001)LF2,950$1.00$0.65$0.65$0.65$0.69$0.70$1.00
197Eliminating existing PM & markers (8") (677-7004)LF500$2.00$0.65$1.35$1.00$1.44$0.70$3.00
198Eliminating existing PM & markers (24") (677-7008)LF25$8.00$4.00$3.00$3.00$3.20$4.34$20.00
199Eliminating existing PM & markers (arrow) (677-7009)EACH3$90.00$65.00$45.00$100.00$47.93$70.48$250.00
200Eliminating existing PM & markers (word) (677-7015)EACH3$75.00$65.00$50.00$100.00$53.25$70.48$250.00
201Pavement surface preparation for marking (6") (678-7002)LF58,962$0.40$0.06$0.15$0.10$0.16$0.07$1.00
202Pavement surface preparation for marking (8") (678-7004)LF2,982$0.80$0.06$0.30$0.10$0.32$0.07$3.00
203Pavement surface preparation for marking (24") (678-7008)LF340$3.00$0.18$2.00$1.00$2.13$0.20$20.00
204Pavement surface preparation for marking (arrow) (678-7009)EACH52$40.00$10.00$35.00$50.00$37.28$10.84$250.00
205Pavement surface preparation for marking (word) (678-7016)EACH22$50.00$10.00$40.00$50.00$42.60$10.84$250.00
206Removing traffic signals (680-7004)EACH1$10,000$18,127$5,510.00$7,000.00$10,991$5,510.00$12,500
207Install highway traffic signal (upgrade) (680-7011)EACH1$45,000$26,336$12,700$20,000$19,511$12,700$50,000
208Vehicle signal section (12")LED(green) (682-7001)EACH8$500.00$365.00$380.00$375.00$413.22$380.00$350.00
209Vehicle signal section (12")LED(green arrow) (682-7002)EACH4$500.00$365.00$390.00$375.00$420.68$390.00$350.00
210Vehicle signal section (12")LED(yel) (682-7003)EACH8$500.00$365.00$380.00$375.00$413.22$380.00$350.00
211Vehicle signal section (12")LED(yel arrow) (682-7004)EACH8$500.00$365.00$390.00$375.00$420.68$390.00$350.00
212Vehicle signal section (12")LED(red) (682-7005)EACH8$500.00$365.00$380.00$375.00$413.22$380.00$350.00
213Vehicle signal section (12")LED(red arrow) (682-7006)EACH8$500.00$365.00$390.00$375.00$420.68$390.00$350.00
214Backplate W/ref border(3 sec)(vent)aluminum (682-7042)EACH8$210.00$242.00$183.00$375.00$197.03$182.50$200.00
215Backplate W/ref border(5 sec)(vent)aluminum (682-7044)EACH4$280.00$285.00$272.00$280.00$239.63$272.00$250.00
216Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031)LF725$5.00$3.50$3.25$4.00$3.72$3.25$3.00
217Traffic signal CBL (type A)(14 AWG)(7 conductor) (684-7033)LF695$5.00$3.90$3.55$5.00$4.02$3.55$3.00
218Full - width mowing (730-7019)CYC8$5,000.00$8,384.96$7,000.00$500.00$5,000.00$4,970.28$3,000.00
219VIVDS prosr sys (6006-7001)EACH1$22,000$14,319$12,500$14,000$10,810$12,500$20,000
220VIVDS cam assy FXD LNS (6006-7002)EACH4$7,500.00$4,131.00$3,000.00$5,000.00$3,354.75$3,000.00$8,500.00
221VIVDS CNTRL software (6006-7005)EACH1$12,000$448.00$1,070.00$1,000.00$532.50$1,074.00$8,500.00
222VIVDS cabling (6006-7007)LF710$4.00$3.90$4.00$5.00$3.20$4.00$3.00
223RVDS (advance detection only) (6008-7002)EACH4$12,000$10,763$7,550.00$17,000$8,466.75$7,551.00$10,000
TxDOT contract A00045441: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of February 4, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy