TxDOT contract A00136586 bid tabulation
Bridge Replacement, POST OAK RD (STR. (AA0145001) Post Oak Rd to Approx. .30 MI E of FM 1726). Let by Texas DOT on May 6, 2026, Goliad, Corpus Christi District. 13 bids received; low bid $1,135,008 by Delgado'S Contractors, LLC, -5.5% against the engineer's estimate of $1,200,910.
- Owner
- Texas DOT
- Letting
- 06 MAY 2026
- Pay items
- 45
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Delgado'S Contractors, LLC | $1,135,008 | Low | -5.0% |
| 2 | Garret Shields Infrastructure | $1,138,135 | 0.0% | -5.0% |
| 3 | R Construction Civil, LLC | $1,149,885 | +1.0% | -4.0% |
| 4 | Presidio Contracting, LLC | $1,171,268 | +3.0% | -2.0% |
| 5 | E-Z Bel Construction, LLC | $1,194,888 | +5.0% | -1.0% |
| 6 | Lucania Contractors LLC | $1,280,548 | +13% | +7.0% |
| 7 | Hunter Industries, LTD. | $1,290,349 | +14% | +7.0% |
| 8 | Acme Bridge Company, Inc. | $1,334,440 | +18% | +11% |
| 9 | J. Carroll Weaver, Inc. | $1,450,415 | +28% | +21% |
| 10 | Hodges and Son Construction Company, Inc. | $1,474,491 | +30% | +23% |
| 11 | James Construction Group, LLC | $1,499,417 | +32% | +25% |
| 12 | CK Newberry, LLC | $1,696,578 | +49% | +41% |
| 13 | Foremost Paving, Inc. | $1,974,928 | +74% | +64% |
Engineer's estimate: $1,200,910.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Delgado'S Contractors, LLC | 2. Garret Shields Infrastructure | 3. R Construction Civil, LLC | 4. Presidio Contracting, LLC | 5. E-Z Bel Construction, LLC | 6. Lucania Contractors LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 4.40 | $2,000.00 | $1,000.00 | $1,000.00 | $2,500.00 | $5,600.00 | $6,620.00 | $2,500.00 |
| 2 | Remove (0"-11") TRT/untrt base & asphalt pavement (105-7051) | SY | 596 | $18.00 | $15.00 | $25.00 | $18.00 | $22.10 | $3.00 | $20.00 |
| 3 | Excavation (roadway) (110-7001) | CY | 199 | $25.00 | $20.00 | $30.00 | $40.00 | $30.70 | $21.00 | $15.00 |
| 4 | Embankment (final)(DC)(type C) (132-7006) | CY | 1,507 | $22.00 | $45.00 | $30.00 | $34.00 | $18.30 | $34.00 | $25.00 |
| 5 | Furn & place topsoil (4") (160-7002) | SY | 1,228 | $3.00 | $4.50 | $4.00 | $4.50 | $2.65 | $0.50 | $6.00 |
| 6 | Broadcast seed (permanent_rural_clay) (164-7002) | SY | 1,228 | $1.00 | $1.00 | $1.00 | $3.50 | $2.10 | $2.00 | $2.50 |
| 7 | Broadcast seed (temporary_warm) (164-7005) | SY | 614 | $0.75 | $1.00 | $1.00 | $5.00 | $2.30 | $2.50 | $2.50 |
| 8 | Broadcast seed (temporary_cool) (164-7006) | SY | 614 | $0.75 | $1.00 | $1.00 | $5.00 | $2.30 | $2.50 | $2.50 |
| 9 | Vegetative watering (168-7001) | TGL | 43 | $75.00 | $25.00 | $50.00 | $225.00 | $80.00 | $78.00 | $10.00 |
| 10 | FL BS (compacted in place)(tya GR1-2)(final pos) (247-7176) | CY | 262 | $110.00 | $110.00 | $25.00 | $127.00 | $124.65 | $110.00 | $130.00 |
| 11 | Prime coat(MC-30 or AE-P) (310-7013) | GAL | 135 | $6.50 | $10.00 | $100.00 | $11.00 | $15.70 | $29.00 | $10.00 |
| 12 | D-GR HMA type-B PG64-22 (341-7001) | TON | 220 | $130.00 | $250.00 | $225.00 | $325.00 | $282.40 | $135.00 | $260.00 |
| 13 | D-GR HMA type D sac-B PG70-22 (341-7050) | TON | 73 | $150.00 | $250.00 | $400.00 | $210.00 | $298.10 | $180.00 | $260.00 |
| 14 | Tack coat (341-7082) | GAL | 53 | $5.00 | $15.00 | $35.00 | $10.00 | $3.15 | $9.00 | $10.00 |
| 15 | Cem stabil BKFL (400-7010) | CY | 94 | $220.00 | $175.00 | $200.00 | $90.00 | $275.00 | $285.00 | $110.00 |
| 16 | Drilled shaft (18 in) (416-7002) | LF | 168 | $180.00 | $160.00 | $130.00 | $160.00 | $70.45 | $77.00 | $100.00 |
| 17 | Drilled shaft (36 in) (416-7006) | LF | 480 | $300.00 | $300.00 | $300.00 | $305.00 | $247.40 | $250.00 | $295.00 |
| 18 | Class C concrete (abutment) (420-7012) | CY | 43.80 | $1,500.00 | $1,500.00 | $1,000.00 | $660.00 | $1,200.00 | $1,200.00 | $1,500.00 |
| 19 | Class C concrete (cap) (420-7022) | CY | 21.80 | $1,780.00 | $1,500.00 | $1,000.00 | $1,000.00 | $1,420.00 | $1,580.00 | $2,100.00 |
| 20 | Class C concrete (column) (420-7038) | CY | 14.10 | $1,500.00 | $1,500.00 | $1,000.00 | $1,200.00 | $1.00 | $480.00 | $1,000.00 |
| 21 | Reinforced concrete slab (422-7001) | SF | 4,680 | $26.00 | $27.50 | $28.00 | $25.00 | $29.00 | $30.00 | $27.00 |
| 22 | Approach slab (422-7013) | CY | 40 | $800.00 | $1,000.00 | $700.00 | $850.00 | $650.00 | $600.00 | $900.00 |
| 23 | Prestressed concrete girder (TX40) (425-7003) | LF | 714 | $210.00 | $225.00 | $280.00 | $210.00 | $267.60 | $260.00 | $310.00 |
| 24 | Riprap (mow strip)(4 in) (432-7013) | CY | 39 | $700.00 | $650.00 | $600.00 | $630.00 | $685.00 | $700.00 | $500.00 |
| 25 | Riprap (stone protection)(18 in) (432-7043) | CY | 203 | $200.00 | $205.00 | $200.00 | $210.00 | $196.00 | $300.00 | $250.00 |
| 26 | Rail (type T223) (450-7008) | LF | 420 | $130.00 | $150.00 | $150.00 | $220.00 | $135.00 | $209.00 | $200.00 |
| 27 | Armor joint (sealed) (454-7003) | LF | 50 | $160.00 | $175.00 | $200.00 | $110.00 | $150.00 | $169.00 | $180.00 |
| 28 | Removing structure (bridge 100 - 499 FT length) (496-7010) | EACH | 1 | $90,000 | $35,000 | $15,000 | $45,000 | $54,250 | $45,000 | $60,000 |
| 29 | Mobilization (500-7001) | LS | 1 | $100,000 | $52,000 | $100,000 | $50,000 | $117,000 | $120,000 | $100,000 |
| 30 | Barricades, signs and traffic handling (502-7001) | MO | 8 | $10,000 | $2,750.00 | $5,000.00 | $6,100.00 | $2,715.00 | $2,000.00 | $900.00 |
| 31 | Construction exits (install) (type 1) (506-7020) | SY | 100 | $30.00 | $35.00 | $25.00 | $75.00 | $41.20 | $41.20 | $90.00 |
| 32 | Construction exits (remove) (506-7024) | SY | 100 | $10.00 | $4.00 | $10.00 | $37.00 | $8.30 | $8.30 | $5.00 |
| 33 | Temporary sediment control fence (install) (506-7039) | LF | 498 | $4.00 | $5.75 | $5.00 | $5.00 | $5.25 | $5.00 | $6.00 |
| 34 | Temporary sediment control fence (remove) (506-7041) | LF | 498 | $1.00 | $1.00 | $1.00 | $2.50 | $1.00 | $1.00 | $2.00 |
| 35 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 84 | $6.50 | $5.00 | $5.00 | $8.00 | $10.50 | $10.00 | $7.00 |
| 36 | Biodegradable erosion control logs (remove) (506-7046) | LF | 84 | $1.50 | $1.00 | $1.00 | $2.50 | $2.50 | $2.50 | $2.00 |
| 37 | Metal W-beam guard fence (timber post) (540-7001) | LF | 300 | $30.00 | $29.00 | $30.00 | $29.00 | $35.30 | $28.50 | $34.00 |
| 38 | Metal beam guard fence trans (TL2) (540-7006) | EACH | 4 | $1,300.00 | $1,450.00 | $1,000.00 | $1,400.00 | $1,860.00 | $1,450.00 | $1,850.00 |
| 39 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $3,500.00 | $3,750.00 | $3,500.00 | $3,800.00 | $4,250.00 | $3,850.00 | $7,900.00 |
| 40 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 2 | $730.00 | $850.00 | $800.00 | $1,200.00 | $900.00 | $890.00 | $1,100.00 |
| 41 | Remove SM RD SN sup&AM (644-7073) | EACH | 4 | $125.00 | $100.00 | $100.00 | $195.00 | $100.00 | $150.00 | $100.00 |
| 42 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 18 | $35.00 | $45.00 | $30.00 | $50.00 | $25.00 | $52.50 | $80.00 |
| 43 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 28 | $35.00 | $45.00 | $30.00 | $50.00 | $50.00 | $63.50 | $80.00 |
| 44 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 960 | $1.00 | $11.00 | $5.00 | $11.00 | $4.25 | $10.00 | $12.50 |
| 45 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 12 | $8.00 | $55.00 | $5.00 | $53.00 | $8.00 | $50.00 | $60.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of May 6, 2026. Compiled by Mirage Metrics.