TxDOT letting results, January 7, 2022
36 contracts let by Texas DOT on January 7, 2022, $309,095,336 in low bids, a median of 3.5 bidders per contract. On the 36 with an engineer's estimate, the low bid came in under it 15 times; median low bid 0.0% against the estimate.
- Owner
- Texas DOT
- Contracts
- 36
- Low bids, total
- $309,095,336
- Data through
- 19 NOV 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 01223235 | SS 366 Construct pedestrian infrastructure from WEST OF AKARD ST to SAINT PAUL ST | Dallas District | 2 | Archer Western Construction, LLC | $94,966,148 | $107,624,545 | +13% | +101% | TxDOT |
| 01223204 | US 385 Roadway rehabilitation from AVE K, ETC. to GAINES COUNTY LINE, ETC. | Odessa District | 5 | Reece Albert, Inc. | $37,642,802 | $38,540,785 | +2.0% | -6.0% | TxDOT |
| 01223202 | SH 191 Construct bridge from AT YUKON RD | Odessa District | 4 | Reece Albert, Inc. | $27,535,250 | $29,396,575 | +7.0% | 0.0% | TxDOT |
| 01223201 | US 83 Widen road - add lanes from KING COUNTY LINE to US 380 | Abilene District | 4 | Delhur Industries, Inc. | $19,299,562 | $19,912,192 | +3.0% | 0.0% | TxDOT |
| 01223234 | US 62 Rehabilitation of roadway from US 180 to CR 104 | Lubbock District | 2 | Webber, LLC | $18,829,752 | $19,807,030 | +5.0% | 0.0% | TxDOT |
| 01223233 | FM 2113 Widen pavement and add curb & gutter from FM 2063 to FM 1695 | Waco District | 3 | Big Creek Construction, LTD. | $15,387,558 | $15,603,363 | +1.0% | 0.0% | TxDOT |
| 01223203 | SH 239 Rehabilitate existing roadway from FM 81 to N INTERS. OF FM 2043 | Corpus Christi District | 5 | Hunter Industries, LTD. | $10,110,263 | $10,597,661 | +5.0% | -1.0% | TxDOT |
| 01223236 | SH 136 Rehabilitate existing roadway from HOYNE AVENUE IN FRITCH to CARSON COUNTY LINE | Amarillo District | 5 | Duininck, Inc. | $9,504,385 | $9,569,172 | +1.0% | +2.0% | TxDOT |
| 01223230 | FM 2451 Rehabilitate existing roadway from MIDLAND DRIVE to FM 148 | Dallas District | 8 | Knife River Corporation - South | $7,647,971 | $7,784,423 | +2.0% | +2.0% | TxDOT |
| 01223205 | US 180 Preventive maintenance from US 84 to FISHER CO LINE | Abilene District | 3 | RK Hall, LLC | $7,417,904 | $7,988,594 | +8.0% | -7.0% | TxDOT |
| 01223232 | US 385 Highway improvement from SH 191 to 8TH STREET | Odessa District | 2 | Jones Bros. Dirt & Paving Contractors, Inc. | $6,752,984 | $7,005,716 | +4.0% | -9.0% | TxDOT |
| 01223206 | IH 35 Rehabilitate existing roadway from 3.055 MI N OF FM 133 to FM 133 (EFR) | Laredo District | 7 | J. Carroll Weaver, Inc. | $4,380,302 | $4,388,971 | 0.0% | -5.0% | TxDOT |
| 01223207 | FM 1201 Surfacing/roadway restoration from END STATE MAINTENANCE to FS 1201 | Wichita Falls District | 2 | Jagoe-Public Company | $4,085,241 | $4,887,463 | +20% | -12% | TxDOT |
| 01223208 | FM 845 Preventive maintenance from US 190 to SOUTH KARNES AVENUE | Bryan District | 4 | Brazos Paving, Inc. | $3,982,426 | $4,676,427 | +17% | -3.0% | TxDOT |
| 01223213 | FM 707 Bridge replacement from BITTER CREEK | Abilene District | 1 | Earth Builders, L.P. | $3,778,142 | +38% | TxDOT | ||
| 01223215 | SH 59 Intersection improvements with right and/or left from CITY LIMIT - OAKWOOD AVE to PARK | Fort Worth District | 3 | Jagoe-Public Company | $3,685,480 | $4,610,120 | +25% | +12% | TxDOT |
| 01223209 | RM 150 Hazard elimination & safety from 0.157 MI. EAST OF OAK SPRINGS DRIVE to 2.098 MI. NORTH OF RM 1826 | Austin District | 3 | Texas Materials Group, Inc. | $3,601,691 | $4,008,263 | +11% | +17% | TxDOT |
| 01223214 | US 283 Highway improvement from CR 256 to 0.490 MI S OF CR 248 | Brownwood District | 3 | J. H. Strain & Sons, Inc. | $3,177,409 | $3,768,855 | +19% | +8.0% | TxDOT |
| 01223231 | IH 35E Rehabilitate existing roadway from US 377 to FM 2181 | Dallas District | 3 | Roy Jorgensen Associates, Inc. | $3,081,758 | $3,318,265 | +8.0% | +17% | TxDOT |
| 01223210 | US 287 Safety improvement projects from FM 813 to BUS 287R | Dallas District | 7 | Gratiot Construction, LTD. | $2,840,168 | $3,085,370 | +9.0% | -15% | TxDOT |
| 01223219 | US 281 Surfacing/roadway restoration from FM 172 to SH 25 | Wichita Falls District | 4 | Zack Burkett Co. | $2,498,172 | $2,556,191 | +2.0% | +9.0% | TxDOT |
| 01223212 | SH 21 Bridge replacement from SH 21 AT CARRIZO CREEK | Lufkin District | 6 | Drewery Construction Company, Incorporated | $2,490,125 | $2,565,699 | +3.0% | +11% | TxDOT |
| 01223211 | US 287 Acp overlay from FM 1166, SOUTH to FM 2568 (WEST) | Childress District | 3 | Zack Burkett Co. | $2,452,566 | $2,494,320 | +2.0% | -6.0% | TxDOT |
| 01223216 | CR Bridge replacement from CR 340 AT LEON RIVER | Brownwood District | 5 | Knife River Corporation - South | $1,969,718 | $2,034,357 | +3.0% | +8.0% | TxDOT |
| 01223217 | FM 734 Depth repair, underseal & ov from SH45 WBFR to TRAVIS COUNTY LINE | Austin District | 2 | Lone Star Paving Company | $1,965,252 | $1,999,651 | +2.0% | +25% | TxDOT |
| 01223221 | CR Bridge maintenance from ON CR 190 AT ONION CREEK to STR AA0190001 | Austin District | 4 | Austin Underground Incorporated | $1,535,479 | $1,627,956 | +6.0% | -5.0% | TxDOT |
| 01223218 | CR Bridge replacement from AT BRUSHY CREEK to STR # AA02-74-001_(SEYDLER RD) | Yoakum District | 3 | Fuqua Construction Co., Inc. | $1,498,743 | $1,685,719 | +12% | +5.0% | TxDOT |
| 01223223 | CR Bridge replacement from CR 2132 to AT EAST CADDO CREEK BRANCH | Paris District | 5 | Highway 19 Construction LLC | $1,348,336 | $1,576,099 | +17% | -2.0% | TxDOT |
| 01223220 | CS Bridge replacement from CR2110 AT KICKAPOO CREEK to S OF ARP, E OF SH 135 | Tyler District | 9 | THK Construction LLC | $1,258,294 | $1,289,878 | +3.0% | 0.0% | TxDOT |
| 01223224 | SH 6 Safety lighting from .5 MI N OF SP 412 to SP 412 | Waco District | 11 | South Texas Illumination, LLC | $770,035 | $814,792 | +6.0% | -13% | TxDOT |
| 01223228 | VA State park improvements from OLD TUNNEL WILDLIFE MANAGEMENT AREA | San Antonio District | 3 | LCR Total Transport LLC | $723,891 | $743,804 | +3.0% | +17% | TxDOT |
| 01223222 | FM 3325 Intersection improvements with right and/or left from AT OLD WEATHERFORD ROAD | Fort Worth District | 2 | Jay Mills Contracting, Incorporated | $714,694 | $736,275 | +3.0% | -22% | TxDOT |
| 01223225 | FM 2240 Resurface existing roadway from FM 559 to FM 1397 | Atlanta District | 3 | RK Hall, LLC | $651,270 | $690,303 | +6.0% | +2.0% | TxDOT |
| 01223226 | VA Bridge maintenance from AUSTIN, COLORADO, WHARTON & MATAGOR | Yoakum District | 7 | SCR Civil Construction, LLC | $573,383 | $629,910 | +10% | -14% | TxDOT |
| 01223227 | IH 610 Hazard elimination & safety from AT HARDY STREET | Houston District | 8 | Allstate Signal & Construction, LLC | $539,001 | $562,527 | +4.0% | -12% | TxDOT |
| 01223229 | IH 35 Preventive maintenance from TRAVIS COUNTY LINE to HESTERS CROSSING | Austin District | 2 | Texas Materials Group, Inc. | $399,183 | $428,388 | +7.0% | +46% | TxDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than TxDOT received, the others did not match their published totals and are left out.