TxDOT letting results, January 6, 2022
42 contracts let by Texas DOT on January 6, 2022, $216,123,406 in low bids, a median of 4 bidders per contract. On the 42 with an engineer's estimate, the low bid came in under it 23 times; median low bid -1.0% against the estimate.
- Owner
- Texas DOT
- Contracts
- 42
- Low bids, total
- $216,123,406
- Data through
- 19 NOV 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 01223044 | IH 35E Interchange improvement from AT FM 387 (BUTCHER ROAD) | Dallas District | 8 | Austin Bridge & Road Services, LP | $51,184,067 | $51,876,450 | +1.0% | +6.0% | TxDOT |
| 01223001 | US 83 Widen road - add lanes from US 380 to FISHER COUNTY LINE | Abilene District | 6 | J. H. Strain & Sons, Inc. | $14,492,854 | $14,621,941 | +1.0% | +2.0% | TxDOT |
| 01223002 | SH 71 Highway improvement from BLANCO COUNTY LINE to 0.4 MILES WEST OF RM 2322 | Austin District | 3 | Hunter Industries, LTD. | $13,908,751 | $14,984,693 | +8.0% | +8.0% | TxDOT |
| 01223003 | FM 932 Rehabilitate and widen roadway from SH 36 to CORYELL CO LINE | Waco District | 4 | Big Creek Construction, LTD. | $13,587,883 | $14,971,009 | +10% | -1.0% | TxDOT |
| 01223004 | IH 820 Resurface roadway from QUEBEC ST. to IH 35W | Fort Worth District | 5 | Jagoe-Public Company | $10,558,103 | $11,094,414 | +5.0% | -2.0% | TxDOT |
| 01223035 | SH 6 Highway improvement from SL 389 to 0.18 MI. N. OF CRESSENT ST | Brownwood District | 2 | Big Creek Construction, LTD. | $10,087,855 | $10,458,210 | +4.0% | -7.0% | TxDOT |
| 01223040 | US 87 Preventive maintenance from SL 570 NORTH OF WALL to CONCHO COUNTY LINE | San Angelo District | 4 | Reece Albert, Inc. | $9,737,926 | $11,693,117 | +20% | -5.0% | TxDOT |
| 01223005 | SH 304 Widen road - add shoulders from FM 535 to CALDWELL COUNTY LINE | Austin District | 4 | Big Creek Construction, LTD. | $9,387,686 | $9,561,472 | +2.0% | +9.0% | TxDOT |
| 01223036 | US 54 Highway improvement from FM 807 NORTH to SHERMAN COUNTY LINE | Amarillo District | 3 | RK Hall, LLC | $8,285,085 | $10,363,722 | +25% | -3.0% | TxDOT |
| 01223009 | SH 35 Surfacing/roadway restoration from 0.437 MI WEST FM 1468 to 0.27 MI EAST FM 1095 | Yoakum District | 4 | James Construction Group, LLC | $6,659,956 | $6,790,109 | +2.0% | +12% | TxDOT |
| 01223006 | IH 35E Resurfacing from US 77/IH35E/IH35W CORINTH PKWY to IH 35/IH 35W/US 380/US 77 | Dallas District | 3 | Jagoe-Public Company | $6,077,319 | $7,821,734 | +29% | -15% | TxDOT |
| 01223042 | US 82 Rehabilitation from 0.5 MILES WEST OF SH 222, EAST to KNOX C/L | Childress District | 5 | A. L. Helmcamp, Inc. | $5,768,976 | $5,998,580 | +4.0% | -5.0% | TxDOT |
| 01223041 | US 83 Highway improvement from OKLAHOMA STATE LINE to SH 15 | Ochiltree | 4 | Duininck, Inc. | $5,571,551 | $5,889,421 | +6.0% | 0.0% | TxDOT |
| 01223007 | US 277 Preventive maintenance from SOUTH Y IN HASKELL to JONES COUNTY | Abilene District | 5 | Zack Burkett Co. | $5,473,497 | $5,582,694 | +2.0% | -3.0% | TxDOT |
| 01223008 | SH 135 Bridge replacement from AT MUD CREEK to STR #007, S OF TROUP | Tyler District | 6 | Highway 19 Construction LLC | $4,193,459 | $4,274,419 | +2.0% | 0.0% | TxDOT |
| 01223014 | FM 616 Surfacing/roadway restoration from CR 325 (INEZ ROAD) to FM 234 | Yoakum District | 6 | Brannan Paving Co., LTD. | $3,684,182 | $3,811,239 | +3.0% | -4.0% | TxDOT |
| 01223011 | FM 462 Bridge replacement from AT HONDO CREEK to 8.5 MI S OF BANDERA/MEDINA COUNTY L | San Antonio District | 4 | Relmco, Inc. | $3,176,381 | $3,472,261 | +9.0% | +9.0% | TxDOT |
| 01223010 | US 67 Railroad crossing improvements from AT FORT WORTH & WESTERN RAILROAD | Brownwood District | 4 | Prater Dirt Work LLC | $3,046,555 | $3,332,379 | +9.0% | +10% | TxDOT |
| 01223038 | US 69 Bridge maintenance from 11TH STREET SB OVERPASS | Beaumont District | 5 | Forde Construction Company, Inc. | $2,889,132 | $2,972,767 | +3.0% | -21% | TxDOT |
| 01223012 | US 183 Preventive maintenance from IH 20 to CR 173 | Brownwood District | 5 | Duininck, Inc. | $2,839,911 | $2,848,952 | 0.0% | -4.0% | TxDOT |
| 01223013 | VA Surfacing/roadway restoration from VARIOUS LOCATIONS IN to THE LUBBOCK DISTRICT | Lubbock District | 2 | O. Trevino Construction, LLC | $2,816,960 | $3,494,915 | +24% | -1.0% | TxDOT |
| 01223020 | VA Highway improvement from VARIOUS LOCATIONS IN SJT DISTRICT | San Angelo District | 7 | L&L Company | $2,812,849 | $2,920,696 | +4.0% | -13% | TxDOT |
| 01223039 | FM 66 Rehabilitate roadway and add concrete pavement from SH 81 to HCR 4421 | Waco District | 3 | Big Creek Construction, LTD. | $2,787,393 | $2,837,565 | +2.0% | +16% | TxDOT |
| 01223015 | US 287 Rehabilitate existing roadway from NEAR US 82 to SH 148 | Wichita Falls District | 4 | Jagoe-Public Company | $2,016,367 | $2,353,257 | +17% | -2.0% | TxDOT |
| 01223019 | VA Preventive maintenance from VARIOUS LOCATIONS ON US 75 | Paris District | 3 | GHB Equipment Company, L.L.C. | $1,790,000 | $2,042,800 | +14% | +20% | TxDOT |
| 01223021 | US 59 Highway improvement from SB ONLY FROM 2.6 MI N OF FM 1127 to CONCRETE PAVEMENT N OF FM 223 | Lufkin District | 2 | Moore Brothers Construction Company | $1,479,910 | $1,805,168 | +22% | -7.0% | TxDOT |
| 01223022 | CR Bridge replacement from CR237/SIGN CR 333 AT FLAT CREEK | Wichita Falls District | 5 | CDM Holdings | $1,461,248 | $1,704,183 | +17% | -8.0% | TxDOT |
| 01223016 | US 190 Install raised median from SH OSR to FM 2818 | Bryan District | 6 | Gratiot Construction, LTD. | $1,448,127 | $1,704,217 | +18% | -21% | TxDOT |
| 01223027 | SH 237 Bridge repair & upgrading railing from AT BRANCH ROCKY CREEK to STR# 0267-01-002 | Yoakum District | 2 | Acme Bridge Company, Inc. | $1,212,845 | $1,256,181 | +4.0% | +34% | TxDOT |
| 01223024 | VA Striping from DISTRICT WIDE | Childress District | 3 | Texas Panhandle Construction, Inc. | $991,061 | $1,331,268 | +34% | -7.0% | TxDOT |
| 01223026 | VA Highway improvement from DISTRICT WIDE | Amarillo District | 3 | Centerline Technologies, LLC | $989,731 | $1,005,000 | +2.0% | +17% | TxDOT |
| 01223018 | VA Seal coat pavement markings from VARIOUS LOCATIONS to VARIOUS LOCATIONS | Atlanta District | 4 | Striping Technology, L.P. | $934,909 | $996,680 | +7.0% | -18% | TxDOT |
| 01223028 | CR Bridge replacement from ON CR3755(CR81) AT DRAINAGE DITCH to APPROX. 3.2 MI S OF SH 188 | Corpus Christi District | 4 | MB Western Industrial Contracting Co. | $796,205 | $863,472 | +8.0% | +22% | TxDOT |
| 01223043 | BU 175G Hazard elimination & safety from BS 19J to GRASS MEDIAN 1 MI W OF SL 7 | Tyler District | 2 | Reynolds & Kay, LTD. | $695,974 | $827,215 | +19% | +17% | TxDOT |
| 01223029 | FM 700 Install traffic signal from INTERSECTION to 11TH STREEET | Abilene District | 2 | WG Engineering & Construction, LLC | $549,094 | $590,412 | +8.0% | -5.0% | TxDOT |
| 01223031 | PR 1C Rehabilitate existing roadway from PR 1A to 0.387 MI E OF ANN POWELL ROAD | Austin District | 3 | Lone Star Paving Company | $547,399 | $574,038 | +5.0% | +17% | TxDOT |
| 01223032 | CR Bridge replacement from ON CR143 (SEILER RD) COW CREEK STR1 to APPROX. .7 MI W OF FM 884 | Corpus Christi District | 8 | Liska Construction Company, Inc. | $459,836 | $467,477 | +2.0% | +16% | TxDOT |
| 01223025 | VA Bridge maintenance from DISTRICTWIDE | Odessa District | 6 | Reynolds & Kay, LTD. | $417,342 | $443,199 | +6.0% | -28% | TxDOT |
| 01223023 | VA Rehab dynamic message signs & improve ped signals from VARIOUS LOCATIONS to IN THE DALLAS DISTRICT | Dallas District | 2 | Highway Intelligent Traffic Solutions, Inc. | $410,372 | $512,888 | +25% | +22% | TxDOT |
| 01223030 | SH 249 Traffic signal improvements from AT ALICE ROAD | Houston District | 6 | Allstate Signal & Construction, LLC | $375,697 | $380,225 | +1.0% | -3.0% | TxDOT |
| 01223033 | VA State park improvements from AT AE WOODS FISH HATCHERY | Austin District | 2 | Cornerstone Paving and Construction, L.L.C. | $345,406 | $363,290 | +5.0% | 0.0% | TxDOT |
| 01223034 | FM 1331 Install/replace signs from FM 672 to 0.5 MI SE OF FM 672 | Austin District | 5 | The Levy Company, Inc. | $173,551 | $178,166 | +3.0% | -4.0% | TxDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than TxDOT received, the others did not match their published totals and are left out.
Your own bid history, read the same way