Zack Burkett Co.: TxDOT bid record
Zack Burkett Co. submitted 119 bids on Texas DOT contracts in the data, from 09 JAN 2020 to 10 NOV 2026, and was the low bidder on 68 of them (57%). When it was not low, its total sat a median +8.0% above the low bid.
- Owner
- Texas DOT
- Low bid volume
- $265,085,457
- Latest bid
- 10 NOV 2026
- Data through
- 19 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2020 | 10 | 4 | 40% |
| 2021 | 15 | 11 | 73% |
| 2022 | 15 | 10 | 67% |
| 2023 | 11 | 5 | 45% |
| 2024 | 12 | 8 | 67% |
| 2025 | 31 | 16 | 52% |
| 2026 | 25 | 14 | 56% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| Wichita Falls District | 62 | 39 | 63% |
| Childress District | 18 | 8 | 44% |
| Abilene District | 17 | 10 | 59% |
| Brownwood District | 7 | 3 | 43% |
| Odessa District | 6 | 3 | 50% |
| Fort Worth District | 5 | 3 | 60% |
| Lubbock District | 2 | 1 | 50% |
| Dallas District | 2 | 1 | 50% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Barricades, signs and traffic handling | 502-7001 | MO | 70 | 49 (70%) | $4,822.50 | $5,000.00 |
| TMA (stationary) | 505-7001 | DAY | 65 | 29 (45%) | $200.00 | $230.00 |
| Planing asphalt concrete pavement(0" to 2") | 354-7032 | SY | 33 | 12 (36%) | $3.00 | $4.40 |
| Prime coat (MC-30) | 310-7004 | GAL | 19 | 11 (58%) | $5.00 | $6.42 |
| Driveways (ACP) | 530-7010 | SY | 21 | 10 (48%) | $39.00 | $60.00 |
| Work zone pavement marking SHT terminal (tab)type W | 662-7112 | EACH | 46 | 9 (20%) | $1.20 | $1.45 |
| Excavation (roadway) | 110-7001 | CY | 17 | 9 (53%) | $11.70 | $20.00 |
| Biodegradable erosion control logs (remove) | 506-7046 | LF | 39 | 8 (21%) | $1.13 | $1.40 |
| Flexible pavement structure repair(8") | 351-7007 | SY | 19 | 8 (42%) | $70.00 | $77.00 |
| Flexible pavement structure repair(4") | 351-7003 | SY | 14 | 8 (57%) | $37.75 | $42.00 |
| D-GR HMA type D PG 64-22 (del) site 1 | 8011-7056 | TON | 12 | 8 (67%) | $97.20 | $105.12 |
| Backfill (type B) | 134-7002 | STA | 24 | 7 (29%) | $225.00 | $235.26 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| A. L. Helmcamp, Inc. | 68 | 16 of 68 |
| Duininck, Inc. | 47 | 7 of 47 |
| Jagoe-Public Company | 28 | 9 of 28 |
| Eurovia Atlantic Coast LLC | 28 | 4 of 28 |
| RK Hall, LLC | 20 | 6 of 20 |
| Overland Corporation | 19 | 5 of 19 |
| Touchstone Resources, LLC | 14 | 6 of 14 |
| Gilvin-Terrill, LTD. | 13 | 1 of 13 |
| J. H. Strain & Sons, Inc. | 10 | 3 of 10 |
| J. Lee Milligan, Inc. | 9 | 1 of 9 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 10 NOV 2026 | A00224604 | Childress District | ASPHALTIC PATCHING MATERIAL, US0287 (Districtwide to Districtwide) | 1 of 3 | $109,174 | Low, 15% under the second |
| 04 NOV 2026 | A00140672 | Abilene District | Preventive Maintenance, US 277 (SOUTH Y IN HASKELL SOUTHBOUND to JONES COUNTY) | 3 of 9 | $7,966,171 | +18% |
| 06 OCT 2026 | A00195499 | Wichita Falls District | Resurface Roadway, US 281 (FM 1954 to Lake Creek) | 2 of 5 | $3,888,262 | +6.0% |
| 06 AUG 2026 | A00195300 | Wichita Falls District | Widen Road - Add Lanes, SH 79 (Near FM 2224 to 1.7 miles south) | 2 of 5 | $13,191,271 | +1.0% |
| 05 AUG 2026 | A00194650 | Childress District | Rehabilitate Existing Roadway, US 82 (0.422 Miles East of Guthrie Airport, E to 0.109 Miles East of US 83) | 1 of 5 | $28,760,605 | Low, 3.0% under the second |
| 17 JUN 2026 | A00221757 | Wichita Falls District | AGGREGATE, US0287 (Districtwide Locations to Wichita Falls District) | 1 of 2 | $594,170 | Low, 17% under the second |
| 17 JUN 2026 | A00221760 | Wichita Falls District | HOT MIX, US0380 (Deliver in Young County to to Designated Locations) | 1 of 4 | $570,948 | Low, 15% under the second |
| 17 JUN 2026 | A00221762 | Wichita Falls District | HOT MIX, US0380 (Deliver in Throckmorton County to to Designated Locations) | 1 of 1 | $621,369 | Low |
| 17 JUN 2026 | A00221763 | Wichita Falls District | HOT MIX, US0070 (Deliver in Wilbarger County to to Designated Locations) | 2 of 2 | $770,385 | +1.0% |
| 17 JUN 2026 | A00221764 | Wichita Falls District | HOT MIX, US0287 (Deliver in Wichita County to to Designated Locations) | 3 of 3 | $830,410 | +16% |
| 04 JUN 2026 | A00220791 | Abilene District | DENSE GRADED HOT MIX, US0180 (East Region to Of the Abilene District) | 1 of 2 | $398,680 | Low, 18% under the second |
| 03 JUN 2026 | A00076951 | Childress District | Highway Improvement, SH 70 (8 Miles North of US 82, South to US 82) | 3 of 6 | $4,187,184 | +4.0% |
| 02 JUN 2026 | A00195498 | Wichita Falls District | Resurface Roadway, SH 114 (FM 2178N to Avenue C) | 1 of 2 | $3,044,169 | Low, 4.0% under the second |
| 30 APR 2026 | A00220884 | Childress District | FLEXIBLE BASE, US0287 (Districtwide to Districtwide) | 3 of 4 | $465,980 | +59% |
| 23 APR 2026 | A00220893 | Wichita Falls District | HOT MIX, SH0079 (Archer County to Designated Locations) | 1 of 2 | $891,854 | Low, 16% under the second |
| 23 APR 2026 | A00220894 | Wichita Falls District | HOT MIX, US0082 (Baylor County to Various Locations) | 1 of 1 | $726,664 | Low |
| 22 APR 2026 | A00219439 | Brownwood District | AGGREGATE, SH0006 (EASTLAND COUNTY to EASTLAND COUNTY) | 2 of 3 | $147,975 | +3.0% |
| 05 FEB 2026 | A00213998 | Wichita Falls District | Resurface Roadway, US 287 (BU 287 H to 1 mi west of Johnson Rd) | 2 of 5 | $2,767,364 | +3.0% |
| 05 FEB 2026 | A00195490 | Wichita Falls District | Resurface Roadway, US 380 (US 183 to Young County Line) | 1 of 4 | $4,679,213 | Low, 10% under the second |
| 05 FEB 2026 | A00077453 | Childress District | Highway Improvement, SH 6 (882' South of US 70, South to Knox C/L) | 1 of 7 | $6,793,699 | Low, 9.0% under the second |
| 08 JAN 2026 | A00218265 | Abilene District | HOT-MIX COLD-LAID, US0180 (Various Locations to Abilene District) | 2 of 2 | $813,170 | +1.0% |
| 07 JAN 2026 | A00208588 | Childress District | Widen Road - Add Shoulders, FM 104 (US 70, North to 10 Miles) | 1 of 8 | $6,279,570 | Low, 5.0% under the second |
| 06 JAN 2026 | A00064705 | Abilene District | Widen Road - Add Shoulders, FM 600 (US 380 to FM 618) | 1 of 4 | $5,128,777 | Low, 7.0% under the second |
| 06 JAN 2026 | A00206074 | Fort Worth District | Rehabilitate Existing Roadway, FM 3325 (IH 20 to FM 1886) | 3 of 9 | $6,804,349 | +9.0% |
| 06 JAN 2026 | A00190019 | Childress District | Highway Improvement, US 83 (FM 1038, South to King C/L) | 1 of 9 | $46,493,743 | Low, 4.0% under the second |
How this record was read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Every bid counted here matched its published total to within one dollar; TxDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.