TxDOT contract A00077453 bid tabulation
Highway Improvement, SH 6 (882' South of US 70, South to Knox C/L). Let by Texas DOT on February 5, 2026, Foard, Childress District. 7 bids received; low bid $6,793,699 by Zack Burkett Co., +4.8% against the engineer's estimate of $6,482,786.
- Owner
- Texas DOT
- Letting
- 05 FEB 2026
- Pay items
- 50
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Zack Burkett Co. | $6,793,699 | Low | +5.0% |
| 2 | RK Hall, LLC | $7,411,343 | +9.0% | +14% |
| 3 | Overland Corporation | $7,433,796 | +9.0% | +15% |
| 4 | Duininck, Inc. | $7,888,601 | +16% | +22% |
| 5 | A. L. Helmcamp, Inc. | $8,142,826 | +20% | +26% |
| 6 | Gilvin-Terrill, LTD. | $8,147,499 | +20% | +26% |
| 7 | J. Lee Milligan, Inc. | $8,772,061 | +29% | +35% |
Engineer's estimate: $6,482,786.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Zack Burkett Co. | 2. RK Hall, LLC | 3. Overland Corporation | 4. Duininck, Inc. | 5. A. L. Helmcamp, Inc. | 6. Gilvin-Terrill, LTD. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Backfill (type A or B) (134-7004) | STA | 615 | $230.00 | $313.00 | $374.55 | $160.00 | $800.00 | $269.00 | $500.00 |
| 2 | Drill seed (permanent_rural_sand) (164-7041) | ACRE | 28.22 | $791.00 | $642.97 | $580.38 | $569.00 | $575.00 | $575.00 | $700.00 |
| 3 | Vegetative watering (168-7001) | TGL | 2,298.70 | $20.00 | $30.00 | $3.00 | $5.00 | $27.00 | $5.00 | $30.00 |
| 4 | Emuls asphalt (erosion control)(CSS-1H) (314-7011) | GAL | 27,316 | $4.80 | $5.00 | $4.23 | $3.00 | $3.20 | $4.00 | $5.00 |
| 5 | D-GR HMA type D sac-A PG70-28 (341-7053) | TON | 30,749 | $100.00 | $113.50 | $129.29 | $131.00 | $124.00 | $147.00 | $130.00 |
| 6 | D-GR HMA type D PG70-28 (level-UP) (341-7055) | TON | 12,055 | $100.00 | $114.25 | $130.80 | $130.00 | $124.00 | $131.00 | $130.00 |
| 7 | Tack coat (341-7082) | GAL | 27,681 | $4.50 | $4.50 | $5.07 | $4.25 | $2.20 | $5.00 | $5.00 |
| 8 | Plane concrete pavement(0" to 2") (354-7066) | SY | 1,778 | $1.50 | $5.00 | $7.02 | $14.00 | $10.50 | $5.00 | $10.00 |
| 9 | Riprap (mow strip)(4 in) (432-7013) | CY | 256 | $733.00 | $853.15 | $816.00 | $875.00 | $800.00 | $850.00 | $800.00 |
| 10 | Rail (type T631) (450-7020) | LF | 362 | $100.00 | $111.80 | $81.60 | $80.00 | $81.00 | $85.00 | $80.00 |
| 11 | Mobilization (500-7001) | LS | 1 | $642,798 | $291,540 | $296,454 | $428,670 | $650,000 | $500,000 | $800,000 |
| 12 | Barricades, signs and traffic handling (502-7001) | MO | 9 | $7,166.70 | $3,860.00 | $7,378.51 | $13,500 | $24,000 | $10,900 | $9,000.00 |
| 13 | TMA (stationary) (505-7001) | DAY | 105 | $164.75 | $200.00 | $507.09 | $345.00 | $250.00 | $200.00 | $525.00 |
| 14 | TMA (mobile operation) (505-7003) | DAY | 38 | $78.60 | $0.01 | $770.11 | $345.00 | $910.00 | $200.00 | $525.00 |
| 15 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 4,320 | $7.50 | $5.36 | $4.83 | $4.74 | $4.80 | $4.80 | $6.00 |
| 16 | Biodegradable erosion control logs (remove) (506-7046) | LF | 4,320 | $1.60 | $1.13 | $1.02 | $1.00 | $1.00 | $1.00 | $1.00 |
| 17 | One-way traffic control (port traffic signal) (510-7003) | MO | 3 | $4,380.00 | $0.01 | $4,195.77 | $2,400.00 | $7,600.00 | $7,500.00 | $4,000.00 |
| 18 | Portable concrete traffic barrier (des source)(single slope)(type 1) (512-7013) | LF | 210 | $6.80 | $0.01 | $49.60 | $63.17 | $92.00 | $100.00 | $50.00 |
| 19 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 720 | $5.30 | $0.01 | $41.88 | $17.07 | $48.50 | $55.00 | $35.00 |
| 20 | Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049) | LF | 210 | $13.95 | $0.01 | $49.60 | $63.17 | $91.50 | $100.00 | $50.00 |
| 21 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 112,708 | $0.25 | $0.12 | $0.12 | $0.12 | $0.17 | $0.35 | |
| 22 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 56,354 | $0.27 | $0.12 | $0.12 | $0.16 | $0.19 | $0.35 | |
| 23 | Metal W-beam guard fence (steel post) (540-7002) | LF | 3,300 | $41.00 | $34.02 | $26.52 | $26.00 | $26.50 | $27.00 | $30.00 |
| 24 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 4 | $3,332.00 | $2,942.52 | $2,380.21 | $3,150.00 | $2,500.00 | $2,400.00 | $2,000.00 |
| 25 | Downstream anchor terminal section (540-7015) | EACH | 2 | $1,491.00 | $1,706.30 | $1,198.50 | $1,175.00 | $1,200.00 | $1,250.00 | $1,200.00 |
| 26 | Metal W - beam guard fence (low fill culvert) (540-7018) | LF | 46 | $96.00 | $123.75 | $83.64 | $82.00 | $83.00 | $86.00 | $100.00 |
| 27 | Metal beam guard fence (long span system) (540-7027) | EACH | 12 | $1,874.80 | $1,597.82 | $1,096.50 | $1,075.00 | $1,100.00 | $1,200.00 | $1,200.00 |
| 28 | Remove metal beam guard fence (542-7001) | LF | 2,825 | $2.90 | $1.41 | $3.06 | $3.00 | $3.05 | $3.20 | $5.00 |
| 29 | Remove terminal anchor section (542-7002) | EACH | 1 | $429.00 | $141.25 | $306.00 | $300.00 | $305.00 | $320.00 | $300.00 |
| 30 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 4 | $335.00 | $141.25 | $306.00 | $300.00 | $305.00 | $320.00 | $300.00 |
| 31 | Guardrail end treatment (install) (544-7001) | EACH | 42 | $3,647.00 | $3,961.78 | $2,958.00 | $2,900.00 | $2,900.00 | $3,100.00 | $3,000.00 |
| 32 | Guardrail end treatment (remove) (544-7003) | EACH | 39 | $179.00 | $141.25 | $306.00 | $300.00 | $305.00 | $320.00 | $300.00 |
| 33 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 8 | $1,606.60 | $0.01 | $2,805.00 | $2,547.36 | $2,800.00 | $1,250.00 | $3,000.00 |
| 34 | Crash cushion attenuator (remove) (545-7004) | EACH | 2 | $1,069.20 | $0.01 | $1,275.00 | $1,528.42 | $1,300.00 | $1,000.00 | $3,000.00 |
| 35 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 2 | $10,763 | $0.01 | $9,690.00 | $10,189 | $9,600.00 | $9,000.00 | $8,000.00 |
| 36 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 72 | $36.49 | $40.68 | $31.62 | $31.00 | $31.50 | $35.00 | $35.00 |
| 37 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 6,178 | $1.95 | $1.40 | $1.71 | $0.70 | $1.55 | $1.50 | $1.00 |
| 38 | Reflectorized pavement marking type II (W) 4" (solid) (666-7171) | LF | 7,600 | $1.20 | $0.19 | $0.20 | $0.20 | $0.20 | $0.21 | $0.20 |
| 39 | Reflectorized pavement marking type II (W) 24" (solid) (666-7184) | LF | 96 | $4.65 | $2.82 | $5.10 | $2.00 | $5.05 | $2.10 | $5.00 |
| 40 | Reflectorized pavement marking type II (Y) 4" (solid) (666-7210) | LF | 13,120 | $1.00 | $0.19 | $0.20 | $0.20 | $0.20 | $0.21 | $0.20 |
| 41 | Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266) | LF | 129,570 | $1.12 | $0.59 | $0.65 | $0.59 | $0.68 | $0.58 | |
| 42 | Reflectorized profile pavement marking type I(Y)6"(solid)(100MIL) (666-7270) | LF | 33,910 | $1.09 | $0.59 | $0.68 | $0.59 | $0.71 | $0.58 | |
| 43 | Reflectorized profile pavement marking type I(Y)6"(broken)(100MIL) (666-7274) | LF | 13,602 | $1.18 | $0.59 | $0.68 | $0.59 | $0.71 | $0.58 | |
| 44 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 124,806 | $0.70 | $0.75 | $0.53 | $0.51 | $0.52 | $0.54 | $0.52 |
| 45 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 11,776 | $0.75 | $0.81 | $0.53 | $0.51 | $0.52 | $0.54 | $0.52 |
| 46 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 56,288 | $0.60 | $0.72 | $0.53 | $0.51 | $0.52 | $0.54 | $0.52 |
| 47 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 1,264 | $4.25 | $4.82 | $4.85 | $3.70 | $4.80 | $3.90 | $4.75 |
| 48 | Traffic button type Y (672-7008) | EACH | 656 | $2.50 | $4.69 | $3.16 | $3.50 | $3.15 | $3.70 | $3.10 |
| 49 | Eliminating existing PM & markers (4") (677-7001) | LF | 7,600 | $0.25 | $0.42 | $0.56 | $0.89 | $0.56 | $0.90 | $0.55 |
| 50 | Eliminating existing PM & markers (24") (677-7008) | LF | 96 | $2.60 | $3.26 | $3.06 | $3.00 | $3.05 | $3.20 | $3.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of February 5, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.