TxDOT contract A00190019 bid tabulation
Highway Improvement, US 83 (FM 1038, South to King C/L). Let by Texas DOT on January 6, 2026, Cottle, Childress District. 9 bids received; low bid $46,493,743 by Zack Burkett Co., +2.4% against the engineer's estimate of $45,384,888.
- Owner
- Texas DOT
- Letting
- 06 JAN 2026
- Pay items
- 120
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Zack Burkett Co. | $46,493,743 | Low | +2.0% |
| 2 | A. L. Helmcamp, Inc. | $48,182,383 | +4.0% | +6.0% |
| 3 | RK Hall, LLC | $50,198,785 | +8.0% | +11% |
| 4 | CK Newberry, LLC | $50,987,743 | +10% | +12% |
| 5 | FNF Construction, Inc. | $51,673,397 | +11% | +14% |
| 6 | Overland Corporation | $53,236,607 | +15% | +17% |
| 7 | Duininck, Inc. | $55,813,373 | +20% | +23% |
| 8 | J. Lee Milligan, Inc. | $56,600,784 | +22% | +25% |
| 9 | Gilvin-Terrill, LTD. | $58,245,487 | +25% | +28% |
Engineer's estimate: $45,384,888.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Zack Burkett Co. | 2. A. L. Helmcamp, Inc. | 3. RK Hall, LLC | 4. CK Newberry, LLC | 5. FNF Construction, Inc. | 6. Overland Corporation |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 13 | $5,262.49 | $1,000.00 | $7,500.00 | $670.74 | $10,000 | $2,900.00 | $3,250.00 |
| 2 | Preparation row (tree remove) (12"-24" diameter) (100-7004) | EACH | 1 | $1,336.59 | $2,500.00 | $2,500.00 | $2,012.40 | $5,000.00 | $1,500.00 | $2,000.00 |
| 3 | Preparation row (tree remove) (36"-48" diameter) (100-7006) | EACH | 1 | $5,321.43 | $2,500.00 | $5,500.00 | $2,012.40 | $7,500.00 | $6,500.00 | $3,000.00 |
| 4 | Removing concrete (mowstrip) (104-7005) | LF | 1,339 | $22.00 | $11.00 | $22.76 | $20.00 | $14.00 | $13.00 | |
| 5 | Removing stab base and asphalt pavement(0"-16") (105-7129) | SY | 72 | $1.42 | $25.00 | $36.00 | $43.48 | $60.00 | $55.00 | $4.98 |
| 6 | Excavation (roadway) (110-7001) | CY | 29,762 | $18.00 | $6.50 | $9.00 | $18.92 | $12.00 | $18.00 | $16.80 |
| 7 | Excavation (special) (110-7003) | CY | 2,030 | $16.39 | $22.00 | $25.00 | $18.38 | $20.00 | $23.00 | $48.00 |
| 8 | Embankment (final)(DC)(type A) (132-7002) | CY | 81,084 | $25.00 | $25.50 | $18.00 | $19.85 | $14.00 | $25.00 | $31.30 |
| 9 | Backfill (type A or B) (134-7004) | STA | 2,153.05 | $330.34 | $100.00 | $180.00 | $189.27 | $115.00 | $110.00 | $418.50 |
| 10 | Drill seed (permanent_rural_sand) (164-7041) | ACRE | 90 | $790.00 | $599.50 | $580.00 | $566.80 | $550.00 | $570.00 | $545.00 |
| 11 | Drill seed (temporary_warm) (164-7045) | ACRE | 45 | $550.00 | $388.30 | $460.00 | $367.12 | $460.00 | $480.00 | $353.00 |
| 12 | Drill seed (temporary_cool) (164-7046) | ACRE | 45 | $891.00 | $657.80 | $460.00 | $621.92 | $460.00 | $480.00 | $598.00 |
| 13 | Vegetative watering (168-7001) | TGL | 6,562 | $60.00 | $27.48 | $7.00 | $2.00 | $14.00 | $52.00 | $2.00 |
| 14 | Emuls asphalt (erosion control)(CSS-1H) (314-7011) | GAL | 81,600 | $4.12 | $3.60 | $3.50 | $5.18 | $3.50 | $3.25 | $3.20 |
| 15 | D-GR HMA type-B PG70-28 (341-7009) | TON | 100,852 | $110.00 | $123.15 | $124.50 | $128.97 | $128.00 | $120.00 | $134.15 |
| 16 | D-GR HMA type D sac-A PG70-28 (341-7053) | TON | 131,998 | $100.00 | $120.70 | $133.00 | $139.89 | $138.00 | $135.00 | $141.55 |
| 17 | D-GR HMA type D PG70-28 (level-UP) (341-7055) | TON | 42,715 | $100.00 | $129.30 | $135.00 | $134.02 | $137.00 | $120.00 | $137.00 |
| 18 | Tack coat (341-7082) | GAL | 181,193 | $4.00 | $4.40 | $4.00 | $4.92 | $3.00 | $6.00 | $4.15 |
| 19 | Flexible pavement structure repair(3") (351-7002) | SY | 1,500 | $46.58 | $44.60 | $70.00 | $31.93 | $50.00 | $36.00 | $50.00 |
| 20 | Planing asphalt concrete pavement(0" to 2") (354-7032) | SY | 325,777 | $3.00 | $1.50 | $0.75 | $0.99 | $0.25 | $1.10 | $2.20 |
| 21 | Flowable backfill (401-7001) | CY | 885 | $400.00 | $302.50 | $290.00 | $286.00 | $300.00 | $290.00 | $280.00 |
| 22 | Trench excavation protection (402-7001) | LF | 1,050 | $60.00 | $49.50 | $48.00 | $15.60 | $45.00 | $46.00 | $1.00 |
| 23 | Class C concrete (rac-R) (420-7055) | CY | 71.40 | $2,200.00 | $2,200.00 | $2,912.00 | $2,000.00 | $2,100.00 | $890.00 | |
| 24 | Class C concrete (collar) (420-7061) | EACH | 1 | $1,100.00 | $1,100.00 | $780.00 | $1,000.00 | $1,050.00 | $2,900.00 | |
| 25 | Riprap (concrete)(5 in) (432-7002) | CY | 134 | $800.00 | $715.00 | $690.00 | $832.00 | $650.00 | $670.00 | $685.00 |
| 26 | Riprap (mow strip)(4 in) (432-7013) | CY | 570 | $842.92 | $715.00 | $690.00 | $780.00 | $700.00 | $670.00 | $700.00 |
| 27 | Rail (type T631) (450-7020) | LF | 440 | $110.00 | $85.00 | $83.20 | $85.00 | $82.00 | $143.00 | |
| 28 | CMP (gal steel 24 in) (460-7005) | LF | 7 | $165.00 | $160.00 | $208.00 | $175.00 | $160.00 | $80.00 | |
| 29 | Concrete box culvert (3 FT X 2 FT) (462-7001) | LF | 171 | $344.77 | $649.00 | $620.00 | $754.00 | $625.00 | $650.00 | $555.00 |
| 30 | Concrete box culvert (3 FT X 3 FT) (462-7002) | LF | 186 | $372.31 | $737.00 | $700.00 | $806.00 | $720.00 | $730.00 | $815.00 |
| 31 | Concrete box culvert (4 FT X 2 FT) (462-7003) | LF | 22 | $445.77 | $759.00 | $720.00 | $832.00 | $725.00 | $800.00 | $1,025.00 |
| 32 | Concrete box culvert (4 FT X 3 FT) (462-7004) | LF | 19 | $847.00 | $810.00 | $910.00 | $800.00 | $870.00 | $1,185.00 | |
| 33 | Concrete box culvert (4 FT X 4 FT) (462-7005) | LF | 45 | $990.00 | $950.00 | $936.00 | $950.00 | $940.00 | $1,200.00 | |
| 34 | Concrete box culvert (5 FT X 2 FT) (462-7006) | LF | 21 | $874.50 | $840.00 | $910.00 | $850.00 | $880.00 | $1,080.00 | |
| 35 | Concrete box culvert (5 FT X 4 FT) (462-7008) | LF | 25 | $1,078.00 | $1,100.00 | $1,040.00 | $1,050.00 | $1,050.00 | $1,320.00 | |
| 36 | Concrete box culvert (5 FT X 5 FT) (462-7009) | LF | 45 | $1,155.00 | $1,100.00 | $1,092.00 | $1,100.00 | $1,120.00 | $1,465.00 | |
| 37 | Concrete box culvert (6 FT X 5 FT) (462-7013) | LF | 34 | $650.00 | $1,430.00 | $1,400.00 | $1,196.00 | $1,400.00 | $1,400.00 | $1,590.00 |
| 38 | Concrete box culvert (8 FT X 5 FT) (462-7022) | LF | 38 | $1,540.00 | $1,500.00 | $1,248.00 | $1,500.00 | $1,500.00 | $1,890.00 | |
| 39 | Concrete box culvert (9 FT X 9 FT) (462-7031) | LF | 14 | $1,540.00 | $1,925.00 | $1,900.00 | $1,456.00 | $1,800.00 | $2,000.00 | $2,900.00 |
| 40 | Concrete box culvert (10 FT X 7 FT) (462-7035) | LF | 30 | $1,650.00 | $1,600.00 | $1,482.00 | $1,600.00 | $1,650.00 | $2,200.00 | |
| 41 | RC pipe (CL III)(36 in) (464-7009) | LF | 3 | $275.00 | $260.00 | $208.00 | $250.00 | $280.00 | $600.00 | |
| 42 | Inlet (complete)(PSL)(FG)(5FTX5FT-4FTX4FT) (465-7135) | EACH | 1 | $12,650 | $12,000 | $16,640 | $12,000 | $13,000 | $6,300.00 | |
| 43 | Headwall (CH - FW - 0) (diameter= 24 in) (466-7005) | EACH | 2 | $6,050.00 | $6,000.00 | $6,240.00 | $6,000.00 | $6,000.00 | $6,000.00 | |
| 44 | Headwall (CH - FW - 0) (diameter= 36 in) (466-7009) | EACH | 1 | $11,550 | $11,000 | $8,320.00 | $11,000 | $12,000 | $8,000.00 | |
| 45 | Wingwall (FW - 0) (HW=3 FT) (466-7145) | EACH | 11 | $8,250.00 | $8,000.00 | $7,280.00 | $8,000.00 | $8,000.00 | $8,200.00 | |
| 46 | Wingwall (FW - 0) (HW=4 FT) (466-7146) | EACH | 10 | $11,867 | $11,550 | $11,000 | $8,840.00 | $11,000 | $11,000 | $11,000 |
| 47 | Wingwall (FW - 0) (HW=5 FT) (466-7147) | EACH | 4 | $12,925 | $12,000 | $10,400 | $12,500 | $12,500 | $14,000 | |
| 48 | Wingwall (FW - 0) (HW=7 FT) (466-7149) | EACH | 2 | $25,300 | $24,000 | $15,080 | $24,000 | $25,000 | $26,000 | |
| 49 | Wingwall (FW - 0) (HW=8 FT) (466-7150) | EACH | 1 | $36,575 | $35,000 | $18,720 | $35,000 | $36,000 | $40,000 | |
| 50 | Wingwall (PW - 2) (HW=3 FT) (466-7187) | EACH | 2 | $10,120 | $8,250.00 | $8,000.00 | $10,400 | $8,000.00 | $8,500.00 | $8,000.00 |
| 51 | Wingwall (PW - 2) (HW=4 FT) (466-7188) | EACH | 3 | $11,220 | $11,000 | $13,520 | $11,000 | $11,500 | $10,750 | |
| 52 | Wingwall (PW - 2) (HW=5 FT) (466-7189) | EACH | 3 | $15,950 | $16,000 | $17,160 | $15,000 | $15,500 | $17,000 | |
| 53 | Wingwall (PW - 2) (HW=6 FT) (466-7190) | EACH | 6 | $44,520 | $27,500 | $26,000 | $26,000 | $26,000 | $27,500 | $20,000 |
| 54 | Wingwall (PW - 2) (HW=7 FT) (466-7191) | EACH | 3 | $35,200 | $34,000 | $41,600 | $34,000 | $34,500 | $41,750 | |
| 55 | Wingwall (PW - 2) (HW=15 FT) (466-7199) | EACH | 1 | $112,000 | $214,500 | $200,000 | $135,200 | $210,000 | $210,000 | $185,000 |
| 56 | Set (replace pipe runner assembly) (467-7003) | EACH | 4 | $3,250.00 | $4,400.00 | $4,500.00 | $5,200.00 | $4,250.00 | $4,200.00 | $3,500.00 |
| 57 | Set (type I)(S= 3 FT)(HW= 2 FT)(4:1)(C) (467-7037) | EACH | 1 | $5,500.00 | $9,900.00 | $10,000 | $8,320.00 | $14,000 | $10,000 | $8,900.00 |
| 58 | Set (type I)(S= 3 FT)(HW= 3 FT)(4:1)(C) (467-7041) | EACH | 5 | $9,785.96 | $11,275 | $10,500 | $10,920 | $11,000 | $11,500 | $10,700 |
| 59 | Set (type I)(S= 3 FT)(HW= 4 FT)(4:1)(C) (467-7045) | EACH | 1 | $12,843 | $12,500 | $11,440 | $12,500 | $13,000 | $16,000 | |
| 60 | Set (type I)(S= 5 FT)(HW= 3 FT)(4:1)(C) (467-7096) | EACH | 1 | $12,430 | $12,000 | $12,480 | $12,000 | $12,500 | $13,000 | |
| 61 | Clean existing culverts (480-7001) | EACH | 98 | $2,587.09 | $2,805.00 | $2,600.00 | $1,872.00 | $3,000.00 | $2,500.00 | $3,100.00 |
| 62 | Mobilization (500-7001) | LS | 1 | $4,000,000 | $2,438,920 | $2,700,000 | $2,509,939 | $5,000,000 | $5,023,802 | $3,263,250 |
| 63 | Barricades, signs and traffic handling (502-7001) | MO | 27 | $1,000.00 | $6,000.00 | $14,300 | $16,091 | $20,000 | $36,000 | $15,555 |
| 64 | Portable changeable message sign (503-7001) | DAY | 33 | $100.00 | $0.01 | $250.00 | $175.47 | $200.00 | $80.00 | $120.00 |
| 65 | TMA (stationary) (505-7001) | DAY | 678 | $50.00 | $36.50 | $240.00 | $517.77 | $325.00 | $215.00 | $342.85 |
| 66 | TMA (mobile operation) (505-7003) | DAY | 200 | $260.00 | $0.01 | $100.00 | $786.33 | $325.00 | $560.00 | $342.85 |
| 67 | Rock filter dams (install) (type 3) (506-7003) | LF | 1,295 | $89.93 | $21.20 | $90.00 | $102.96 | $100.00 | $110.00 | $86.00 |
| 68 | Rock filter dams (remove) (506-7011) | LF | 1,295 | $5.00 | $5.00 | $15.00 | $15.60 | $15.00 | $16.00 | $21.00 |
| 69 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 10,560 | $8.61 | $5.23 | $5.00 | $4.94 | $6.25 | $7.00 | $4.75 |
| 70 | Biodegradable erosion control logs (remove) (506-7046) | LF | 10,560 | $1.33 | $0.83 | $0.80 | $0.78 | $1.00 | $1.10 | $0.75 |
| 71 | One-way traffic control (port traffic signal) (510-7003) | MO | 3 | $0.01 | $7,000.00 | $4,853.68 | $10,000 | $8,500.00 | $2,500.00 | |
| 72 | Portable concrete traffic barrier (des source)(single slope)(type 2) (512-7014) | LF | 550 | $33.00 | $45.00 | $24.00 | $30.00 | $9.00 | $41.10 | |
| 73 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 2,750 | $27.50 | $35.00 | $18.77 | $25.00 | $7.00 | $11.11 | |
| 74 | Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049) | LF | 550 | $33.00 | $45.00 | $24.00 | $30.00 | $10.00 | $24.25 | |
| 75 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 427,241 | $0.19 | $0.22 | $0.20 | $0.12 | $0.15 | $0.10 | $0.12 |
| 76 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 213,032 | $0.23 | $0.26 | $0.24 | $0.12 | $0.15 | $0.12 | $0.12 |
| 77 | Metal W-beam guard fence (steel post) (540-7002) | LF | 5,160 | $40.00 | $37.40 | $27.00 | $26.00 | $30.00 | $31.00 | $25.00 |
| 78 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 16 | $3,100.00 | $3,300.00 | $2,000.00 | $2,453.45 | $2,200.00 | $2,300.00 | $1,975.00 |
| 79 | Metal W - beam guard fence (low fill culvert) (540-7018) | LF | 100 | $107.80 | $85.00 | $83.20 | $75.00 | $80.00 | $80.00 | |
| 80 | Metal beam guard fence (long span system) (540-7027) | EACH | 6 | $1,595.00 | $1,400.00 | $1,326.00 | $1,250.00 | $1,300.00 | $1,275.00 | |
| 81 | Metal beam guard fence trans (anchor plate) (540-7029) | EACH | 8 | $1,017.50 | $1,100.00 | $1,066.00 | $950.00 | $1,000.00 | $1,025.00 | |
| 82 | Remove metal beam guard fence (542-7001) | LF | 8,775 | $3.40 | $2.20 | $2.00 | $2.08 | $2.75 | $3.00 | $2.00 |
| 83 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 16 | $356.20 | $330.00 | $220.00 | $208.00 | $250.00 | $260.00 | $200.00 |
| 84 | Guardrail end treatment (install) (544-7001) | EACH | 64 | $3,970.00 | $3,630.00 | $3,000.00 | $2,964.00 | $3,000.00 | $3,100.00 | $2,850.00 |
| 85 | Guardrail end treatment (remove) (544-7003) | EACH | 64 | $322.65 | $330.00 | $220.00 | $208.00 | $250.00 | $260.00 | $200.00 |
| 86 | Crash cushion attenuator (des source) (545-7001) | EACH | 2 | $4,400.00 | $3,000.00 | $3,900.00 | $4,000.00 | $535.00 | $3,750.00 | |
| 87 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 10 | $1,100.00 | $1,600.00 | $2,860.00 | $1,000.00 | $470.00 | $2,750.00 | |
| 88 | Crash cushion attenuator (remove) (545-7004) | EACH | 2 | $1,650.00 | $1,100.00 | $1,248.00 | $1,500.00 | $535.00 | $1,200.00 | |
| 89 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 5 | $304.39 | $335.50 | $240.00 | $234.00 | $275.00 | $300.00 | $220.00 |
| 90 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 95 | $975.18 | $874.50 | $740.00 | $728.00 | $635.00 | $650.00 | $735.00 |
| 91 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 76 | $1,450.00 | $1,039.50 | $780.00 | $780.00 | $725.00 | $750.00 | $815.00 |
| 92 | Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007) | EACH | 2 | $1,237.50 | $870.00 | $858.00 | $1,100.00 | $1,120.00 | $850.00 | |
| 93 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 24 | $1,013.79 | $1,402.50 | $970.00 | $962.00 | $1,200.00 | $1,250.00 | $990.00 |
| 94 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 2 | $1,232.84 | $1,347.50 | $1,100.00 | $1,040.00 | $1,500.00 | $1,575.00 | $990.00 |
| 95 | Remove SM RD SN sup&AM (644-7073) | EACH | 124 | $200.00 | $110.00 | $110.00 | $104.00 | $85.00 | $90.00 | $100.00 |
| 96 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 24 | $36.60 | $38.50 | $26.00 | $26.00 | $15.00 | $16.00 | $25.00 |
| 97 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 144 | $65.00 | $44.00 | $33.00 | $29.12 | $25.00 | $26.00 | $31.00 |
| 98 | Install object marker assembly (OM-2Z)(WFLX)GND (658-7058) | EACH | 312 | $107.84 | $99.00 | $80.00 | $78.00 | $65.00 | $67.00 | $75.00 |
| 99 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 316,261 | $0.30 | $0.18 | $0.16 | $0.17 | $0.20 | $0.17 | $0.16 |
| 100 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 646,800 | $0.31 | $0.18 | $0.16 | $0.17 | $0.20 | $0.17 | $0.16 |
| 101 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 4,200 | $0.87 | $0.95 | $0.90 | $0.89 | $0.30 | $0.90 | $0.86 |
| 102 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 384 | $14.53 | $17.38 | $17.00 | $16.43 | $10.00 | $16.25 | $15.80 |
| 103 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 4,200 | $0.98 | $0.95 | $0.90 | $0.89 | $0.60 | $0.90 | $0.86 |
| 104 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 7,656 | $1.09 | $1.40 | $0.53 | $1.75 | $0.60 | $0.80 | $0.60 |
| 105 | Work zone pavement marking SHT terminal (tab)type Y (662-7113) | EACH | 21,651 | $2.35 | $1.40 | $0.53 | $1.75 | $0.60 | $0.80 | $0.60 |
| 106 | Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009) | LF | 4,935 | $1.00 | $0.94 | $0.89 | $0.88 | $1.10 | $0.90 | $0.85 |
| 107 | Reflectorized pavement marking type I(W)(lane drop arrow)(100MIL) (666-7060) | EACH | 30 | $621.25 | $467.50 | $450.00 | $442.00 | $550.00 | $440.00 | $425.00 |
| 108 | Pavement sler 6" (666-7347) | LF | 2,921 | $1.00 | $0.79 | $0.75 | $0.75 | $1.00 | $0.75 | $0.72 |
| 109 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 31,467 | $1.00 | $0.68 | $0.65 | $0.64 | $0.55 | $0.65 | $0.62 |
| 110 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 431,729 | $1.00 | $0.61 | $0.58 | $0.57 | $0.55 | $0.60 | $0.55 |
| 111 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 41,546 | $1.00 | $0.68 | $0.65 | $0.64 | $0.55 | $0.65 | $0.62 |
| 112 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 234,725 | $1.00 | $0.61 | $0.58 | $0.57 | $0.55 | $0.60 | $0.55 |
| 113 | Reflectorized pavement marker type I-C (672-7002) | EACH | 1,605 | $4.65 | $4.95 | $4.70 | $4.68 | $5.00 | $4.75 | $4.50 |
| 114 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 5,040 | $4.35 | $4.95 | $4.70 | $4.68 | $5.00 | $4.75 | $4.50 |
| 115 | Eliminating existing PM & markers (4") (677-7001) | LF | 462,284 | $0.45 | $0.44 | $0.40 | $0.42 | $0.01 | $0.45 | $0.40 |
| 116 | Eliminating existing PM & markers (6") (677-7002) | LF | 503,703 | $0.80 | $0.55 | $0.50 | $0.52 | $0.13 | $0.55 | $0.50 |
| 117 | Eliminating existing PM & markers (24") (677-7008) | LF | 384 | $4.12 | $4.40 | $4.00 | $4.16 | $1.00 | $4.10 | $4.00 |
| 118 | Pavement surface preparation for marking (6") (678-7002) | LF | 2,921 | $0.80 | $0.69 | $0.65 | $0.66 | $0.60 | $0.65 | $0.63 |
| 119 | Full - width mowing (730-7019) | CYC | 3 | $208.12 | $32,000 | $12,000 | $8,257.88 | $7,500.00 | $10,000 | $10,000 |
| 120 | Portable changeable message sign (6033-7001) | EACH | 9 | $24,504 | $0.01 | $10,000 | $6,580.15 | $30,000 | $14,500 | $20,568 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of January 6, 2026. Compiled by Mirage Metrics.