TxDOT contract A00064705 bid tabulation
Widen Road - Add Shoulders, FM 600 (US 380 to FM 618). Let by Texas DOT on January 6, 2026, Haskell, Abilene District. 4 bids received; low bid $5,128,777 by Zack Burkett Co., -6.5% against the engineer's estimate of $5,488,052.
- Owner
- Texas DOT
- Letting
- 06 JAN 2026
- Pay items
- 56
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Zack Burkett Co. | $5,128,777 | Low | -7.0% |
| 2 | J. H. Strain & Sons, Inc. | $5,475,914 | +7.0% | 0.0% |
| 3 | CK Newberry, LLC | $6,098,537 | +19% | +11% |
| 4 | A. L. Helmcamp, Inc. | $6,202,675 | +21% | +13% |
Engineer's estimate: $5,488,052.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Zack Burkett Co. | 2. J. H. Strain & Sons, Inc. | 3. CK Newberry, LLC | 4. A. L. Helmcamp, Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (driveways) (104-7011) | SY | 402 | $30.00 | $56.00 | $25.00 | $35.00 | $25.00 |
| 2 | Remove (0"-12") TRT/untrt base & asphalt pavement (105-7052) | SY | 934 | $20.00 | $9.90 | $16.50 | $8.00 | $8.00 |
| 3 | Remove (7"-13") TRT/untrt base & asphalt pavement (105-7058) | SY | 5,184 | $13.00 | $7.50 | $13.25 | $1.50 | $3.00 |
| 4 | Excavation (roadway) (110-7001) | CY | 47 | $15.00 | $100.00 | $150.00 | $100.00 | $25.00 |
| 5 | Subgr widen (OC) (112-7001) | STA | 466 | $400.00 | $330.00 | $350.00 | $700.00 | $400.00 |
| 6 | Embankment (final)(OC)(type B) (132-7003) | CY | 5,000 | $35.00 | $44.00 | $14.00 | $12.00 | $35.00 |
| 7 | Backfill (type B) (134-7002) | STA | 466 | $250.00 | $185.00 | $250.00 | $125.00 | $220.00 |
| 8 | Blading (150-7002) | HR | 10 | $140.00 | $200.00 | $250.00 | $175.00 | $200.00 |
| 9 | Lime (com or QK)(slurry) or QK(dry) (260-7001) | TON | 1,301 | $360.00 | $351.00 | $390.00 | $350.00 | $300.00 |
| 10 | Lime TRT (existing material)(10") (260-7008) | SY | 53,430 | $5.50 | $8.70 | $8.50 | $6.00 | $10.00 |
| 11 | Prime coat (MC-30) (310-7004) | GAL | 11,286 | $6.00 | $4.60 | $5.75 | $6.00 | $10.00 |
| 12 | D-GR HMA type-B PG64-22 (341-7001) | TON | 7,051 | $105.00 | $109.50 | $124.02 | $160.00 | $140.00 |
| 13 | Tack coat (341-7082) | GAL | 14,839 | $6.50 | $3.40 | $3.50 | $4.00 | $4.00 |
| 14 | SP mixes SP-D PG70-22 (344-7051) | TON | 12,349 | $120.00 | $116.00 | $153.75 | $170.00 | $140.00 |
| 15 | Flexible pavement structure repair(4") (351-7003) | SY | 2,000 | $45.00 | $43.00 | $45.00 | $50.00 | $75.00 |
| 16 | Plane & text asphalt concrete pavement(0" to 4") (354-7004) | SY | 769 | $3.00 | $6.50 | $10.00 | $10.00 | $10.00 |
| 17 | Cut & restore asphalt paving (400-7008) | SY | 105 | $200.00 | $98.00 | $150.00 | $250.00 | $60.00 |
| 18 | Flowable backfill (401-7001) | CY | 107 | $450.00 | $336.00 | $235.00 | $325.00 | $320.00 |
| 19 | RC pipe (CL III)(18 in) (464-7003) | LF | 80 | $88.00 | $106.40 | $115.00 | $100.00 | $100.00 |
| 20 | RC pipe (CL III)(24 in) (464-7005) | LF | 288 | $130.00 | $117.60 | $145.00 | $115.00 | $120.00 |
| 21 | Adjusting manholes (479-7001) | EACH | 3 | $1,100.00 | $3,920.00 | $1,250.00 | $3,000.00 | $22.00 |
| 22 | Removing structure (pipe) (496-7007) | LF | 240 | $50.00 | $22.40 | $15.00 | $50.00 | $190.00 |
| 23 | Mobilization (500-7001) | LS | 1 | $435,452 | $350,000 | $200,000 | $600,000 | $600,000 |
| 24 | Barricades, signs and traffic handling (502-7001) | MO | 13 | $15,000 | $6,800.00 | $12,000 | $5,000.00 | $15,000 |
| 25 | TMA (stationary) (505-7001) | DAY | 72 | $300.00 | $200.00 | $250.00 | $200.00 | $300.00 |
| 26 | TMA (mobile operation) (505-7003) | DAY | 90 | $600.00 | $0.01 | $250.00 | $100.00 | $200.00 |
| 27 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 6,249 | $7.00 | $5.21 | $6.00 | $5.00 | $4.80 |
| 28 | Biodegradable erosion control logs (remove) (506-7046) | LF | 6,249 | $2.00 | $0.84 | $1.50 | $1.00 | $0.80 |
| 29 | One-way traffic control (port traffic signal) (510-7003) | MO | 10 | $6,500.00 | $0.01 | $5,500.00 | $5,000.00 | $4,000.00 |
| 30 | Driveways (concrete) (530-7006) | SY | 402 | $100.00 | $201.60 | $115.00 | $180.00 | $185.00 |
| 31 | Driveways (ACP) (530-7010) | SY | 358 | $80.00 | $40.00 | $28.00 | $75.00 | $100.00 |
| 32 | Driveways (base) (530-7015) | SY | 5,570 | $37.00 | $32.50 | $18.00 | $20.00 | $50.00 |
| 33 | Turnouts (surface treat) (530-7019) | SY | 363 | $85.00 | $30.00 | $15.00 | $17.00 | $40.00 |
| 34 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 82,019 | $0.20 | $0.25 | $0.17 | $0.15 | $0.23 |
| 35 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 40,357 | $0.20 | $0.29 | $0.20 | $0.15 | $0.27 |
| 36 | Mailbox install-S (TWG-post) type 2 (560-7002) | EACH | 31 | $350.00 | $336.00 | $350.00 | $225.00 | $240.00 |
| 37 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 4 | $500.00 | $448.00 | $490.00 | $280.00 | $290.00 |
| 38 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 51 | $820.00 | $952.00 | $785.00 | $650.00 | $680.00 |
| 39 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 24 | $1,000.00 | $952.00 | $850.00 | $675.00 | $700.00 |
| 40 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 14 | $1,200.00 | $1,484.00 | $1,295.00 | $950.00 | $1,000.00 |
| 41 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 1 | $1,200.00 | $1,540.00 | $1,290.00 | $975.00 | $1,000.00 |
| 42 | Install small roadside sign support and assembly TYS80(1)SA(U-BM) (644-7034) | EACH | 1 | $1,200.00 | $1,680.00 | $1,500.00 | $1,100.00 | $1,200.00 |
| 43 | Remove SM RD SN sup&AM (644-7073) | EACH | 79 | $120.00 | $112.00 | $100.00 | $100.00 | $110.00 |
| 44 | Install object marker assembly (OM-2Y)(WC)GND(BI) (658-7057) | EACH | 31 | $88.00 | $95.20 | $69.00 | $75.00 | $80.00 |
| 45 | Work zone pavement marking non-removing (Y)4"(solid) (662-7035) | LF | 48,520 | $0.50 | $0.34 | $0.20 | $0.18 | $0.26 |
| 46 | Work zone pavement marking removing (reflectorized) type II-A-A (662-7051) | EACH | 1,840 | $5.50 | $5.04 | $5.60 | $5.00 | $4.20 |
| 47 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 91,560 | $0.75 | $0.62 | $0.43 | $0.40 | $0.42 |
| 48 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 220 | $15.00 | $16.80 | $2.25 | $2.00 | $3.15 |
| 49 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 4,553 | $2.00 | $1.40 | $2.00 | $0.60 | $0.53 |
| 50 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 91,467 | $0.85 | $0.69 | $0.56 | $0.50 | $0.54 |
| 51 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 6,200 | $1.00 | $0.69 | $0.56 | $0.50 | $0.54 |
| 52 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 60,414 | $0.85 | $0.69 | $0.56 | $0.50 | $0.54 |
| 53 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 128 | $25.00 | $15.68 | $25.00 | $22.00 | $12.60 |
| 54 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 1,066 | $7.00 | $4.76 | $5.60 | $5.00 | $3.90 |
| 55 | Eliminating existing PM & markers (4") (677-7001) | LF | 2,000 | $1.00 | $4.48 | $1.00 | $0.50 | $1.10 |
| 56 | Relocate RDSD flash beacon assembly (685-7002) | EACH | 2 | $4,500.00 | $9,520.00 | $9,500.00 | $8,500.00 | $9,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of January 6, 2026. Compiled by Mirage Metrics.