TxDOT contract A00194650 bid tabulation

Rehabilitate Existing Roadway, US 82 (0.422 Miles East of Guthrie Airport, E to 0.109 Miles East of US 83). Let by Texas DOT on August 5, 2026, King, Childress District. 5 bids received; low bid $28,760,605 by Zack Burkett Co., +5.4% against the engineer's estimate of $27,289,982.

Owner
Texas DOT
Letting
05 AUG 2026
Pay items
56
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Zack Burkett Co.$28,760,605Low+5.0%
2Overland Corporation$29,743,290+3.0%+9.0%
3CK Newberry, LLC$29,815,596+4.0%+9.0%
4RK Hall, LLC$30,406,275+6.0%+11%
5A. L. Helmcamp, Inc.$31,812,630+11%+17%
TxDOT contract A00194650: bids by rank

Engineer's estimate: $27,289,982.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Zack Burkett Co.2. Overland Corporation3. CK Newberry, LLC4. RK Hall, LLC5. A. L. Helmcamp, Inc.
1Remove (3") TRT/untrt base & asphalt pavement (105-7023)SY181,673$3.10$1.05$2.00$3.30$3.00
2Remove (17") TRT/untrt base & asphalt pavement (105-7037)SY112,773$12.50$10.50$5.75$10.00$12.13$13.00
3Excavation (roadway) (110-7001)CY21,934$12.36$10.80$11.00$15.00$15.42$23.00
4Embankment (final)(DC)(type A) (132-7002)CY25,696$26.39$32.15$24.00$23.00$12.37$22.00
5Backfill (type A or B) (134-7004)STA874$202.13$138.85$271.73$375.00$219.44$340.00
6Drill seed (permanent_rural_sand) (164-7041)ACRE47$642.98$677.35$2,999.02$600.00$624.34$620.00
7Vegetative watering (168-7001)TGL176$26.92$62.50$1.00$60.00$70.06$50.00
8Proof rolling (216-7001)HR31$160.18$0.01$183.90$75.00$172.04$210.00
9FL BS (compacted in place)(type A GR 1-2) (8") (247-7067)SY127,119$21.18$24.65$15.00$17.25$12.24$17.50
10Cement (275-7001)TON2,897$231.62$299.00$250.00$275.00$296.42$270.00
11Cement TRT (existing material)(10") (275-7004)SY183,504$5.00$1.50$2.50$3.96$2.70
12Cement TRT (subgrade) (8") (275-7018)SY113,994$4.10$4.60$1.00$1.10$3.63$2.10
13Prime coat (MC-30) (310-7004)GAL57,076$5.82$4.80$5.37$5.50$6.30$6.50
14D-GR HMA type-B PG70-28 (341-7009)TON58,802$96.00$126.25$153.00$145.00$145.36$151.00
15D-GR HMA type D sac-A PG70-28 (341-7053)TON65,824$126.00$137.25$157.00$150.00$152.12$161.00
16Tack coat (341-7082)GAL72,316$4.50$4.30$5.00$3.25$5.38$4.00
17Plane & text asphalt concrete pavement(0" to 2") (354-7002)SY57,233$5.00$2.40$2.25$1.00$2.54$3.60
18Riprap (mow strip)(4 in) (432-7013)CY220$773.73$931.50$670.33$850.00$848.00$850.00
19Mobilization (500-7001)LS1$2,471,357$1,560,000$2,906,400$2,750,000$2,432,502$2,600,000
20Barricades, signs and traffic handling (502-7001)MO21$5,000.00$13,890$11,500$15,000$20,612$11,800
21Portable changeable message sign (503-7002)EACH6$900.00$0.01$14,000$15,000$16,013$18,000
22TMA (stationary) (505-7001)DAY752$230.88$200.00$351.75$275.00$533.89$200.00
23TMA (mobile operation) (505-7002)HR600$51.34$0.01$0.01$25.00$101.35$60.00
24Biodegradable erosion control logs (install) (18") (506-7045)LF2,606$7.50$5.00$10.30$8.00$5.14$5.00
25Biodegradable erosion control logs (remove) (506-7046)LF2,606$1.13$1.00$1.07$1.00$1.06$1.00
26One-way traffic control (port traffic signal) (510-7003)MO12$2,000.00$12,401$6,500.00$4,600.40$8,000.00
27Portable concrete traffic barrier (des source)(single slope)(type 1) (512-7013)LF1,620$18.09$26.45$10.01$25.00$26.85$30.00
28Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025)LF1,620$14.49$17.25$4.77$15.00$13.22$23.00
29Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049)LF1,620$19.53$17.25$10.01$15.00$26.85$23.00
30Mill rumble strips (asphalt) (shoulder) (533-7001)LF176,306$0.25$0.23$0.07$0.15$0.15$0.21
31Mill rumble strips (asphalt) (centerline) (533-7002)LF142,710$0.26$0.26$0.09$0.15$0.15$0.24
32Metal W-beam guard fence (steel post) (540-7002)LF4,125$36.22$39.10$32.00$35.00$33.92$34.00
33Metal beam guard fence trans (thrie-beam) (540-7005)EACH16$2,942.52$3,220.00$2,300.00$2,800.00$3,022.04$2,400.00
34Downstream anchor terminal section (540-7015)EACH4$1,706.30$1,955.00$1,450.00$1,700.00$1,537.00$1,500.00
35Metal beam guard fence trans (anchor plate) (540-7029)EACH16$1,086.25$920.00$850.00$800.00$901.00$900.00
36Remove metal beam guard fence (542-7001)LF4,125$1.41$1.15$3.00$1.00$3.18$3.00
37Remove downstream anchor terminal (542-7003)EACH4$275.00$230.00$330.00$200.00$349.80$350.00
38RM metal beam guard fence trans (thrie-beam) (542-7004)EACH12$272.46$230.00$300.00$200.00$318.00$320.00
39Guardrail end treatment (install) (544-7001)EACH12$3,780.25$3,680.00$3,150.00$3,200.00$3,339.00$3,300.00
40Guardrail end treatment (remove) (544-7003)EACH12$245.57$230.00$300.00$200.00$318.00$320.00
41Crash cushion attenuator (move & reset) (545-7002)EACH4$1,372.82$1,725.00$2,750.00$1,500.00$2,915.00$1,800.00
42Crash cushion attenuator (remove) (545-7004)EACH4$753.47$1,150.00$1,500.00$1,000.00$1,590.00$1,200.00
43Crash cushion attenuator (install)(S)(N)(TL3) (545-7014)EACH4$8,667.08$11,500$10,500$10,000$11,130$10,500
44Work zone pavement marking non-removing (W)6"(solid) (662-7008)LF130,765$0.21$0.25$0.20$0.19$0.19
45Work zone pavement marking non-removing (W)24"(solid) (662-7017)LF384$14.38$3.00$12.50$13.25$13.00
46Work zone pavement marking non-removing (Y)6"(solid) (662-7038)LF172,400$0.41$0.21$0.25$0.20$0.19$0.19
47Work zone pavement marking removing (Y)6"(solid) (662-7100)LF8,959$0.82$0.86$0.80$0.75$0.80$0.80
48Reflectorized pavement marking type I(W)(lane drop arrow)(100MIL) (666-7060)EACH8$378.84$460.00$375.00$400.00$424.00$430.00
49Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408)LF32,585$0.82$0.75$0.55$0.65$0.69$0.70
50Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF154,350$0.78$0.69$0.52$0.60$0.64$0.63
51Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420)LF1,013$0.81$0.55$0.70$0.74$0.75
52Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF150,290$1.16$0.69$0.52$0.60$0.64$0.63
53Reflectorized pavement marker type II-A-A (672-7004)EACH180$4.82$11.50$3.90$10.00$10.60$11.00
54Reflectorized pavement marker type II-C-R (672-7006)EACH1,051$4.15$5.75$3.80$5.00$5.30$5.30
55Eliminating existing PM & markers (6") (677-7002)LF96,434$1.10$0.69$0.52$0.60$0.64$0.60
56Eliminating existing PM & markers (24") (677-7008)LF384$5.75$3.00$5.00$5.30$5.30
TxDOT contract A00194650: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of August 5, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy