TxDOT contract A00027293 bid tabulation
Widen Road - Add Lanes, FM 756 (JEFF DAVIS DR (CR 1167), S to FM 346). Let by Texas DOT on July 2, 2026, Smith, Tyler District. 9 bids received; low bid $58,705,654 by Baker & Company Construction, LLC, -8.8% against the engineer's estimate of $64,389,274.
- Owner
- Texas DOT
- Letting
- 02 JUL 2026
- Pay items
- 280
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Baker & Company Construction, LLC | $58,705,654 | Low | -9.0% |
| 2 | Longview Bridge and Road, LTD. | $59,196,150 | +1.0% | -8.0% |
| 3 | East Texas Bridge, Inc. | $61,684,409 | +5.0% | -4.0% |
| 4 | Highway 19 Construction LLC | $63,873,899 | +9.0% | -1.0% |
| 5 | Indus Road & Bridge, Inc. | $64,673,884 | +10% | 0.0% |
| 6 | Drake Companies LLC | $65,286,576 | +11% | +1.0% |
| 7 | A. L. Helmcamp, Inc. | $68,177,129 | +16% | +6.0% |
| 8 | James Construction Group, LLC | $72,854,862 | +24% | +13% |
| 9 | Big Creek Construction, LTD. | $75,487,342 | +29% | +17% |
Engineer's estimate: $64,389,274.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Baker & Company Construction, LLC | 2. Longview Bridge and Road, LTD. | 3. East Texas Bridge, Inc. | 4. Highway 19 Construction LLC | 5. Indus Road & Bridge, Inc. | 6. Drake Companies LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 238 | $3,500.00 | $1,420.00 | $8,000.00 | $10,000 | $4,110.00 | $23,008 | $2,850.00 |
| 2 | Removing concrete (pavement) (104-7001) | SY | 1,028 | $11.60 | $5.60 | $7.50 | $10.00 | $15.00 | $15.00 | $18.70 |
| 3 | Removing concrete (riprap) (104-7006) | SY | 936 | $11.75 | $6.13 | $8.50 | $10.00 | $25.00 | $9.00 | $12.60 |
| 4 | Removing concrete (driveways) (104-7011) | SY | 2,386 | $13.85 | $7.25 | $13.00 | $13.00 | $15.00 | $15.00 | $14.50 |
| 5 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 202 | $13.15 | $14.25 | $13.00 | $10.00 | $15.00 | $6.00 | $15.50 |
| 6 | Removing concrete (curb & gutter) (104-7017) | LF | 2,012 | $5.00 | $7.15 | $5.25 | $6.00 | $5.00 | $5.50 | $6.30 |
| 7 | Remove (12"-16") TRT/untrt base & asphalt pavement (105-7012) | SY | 31,416 | $8.50 | $5.50 | $7.20 | $7.85 | $6.00 | $8.60 | $14.00 |
| 8 | Remove (16"-20") TRT/untrt base & asphalt pavement (105-7016) | SY | 6,032 | $9.50 | $7.75 | $8.40 | $10.00 | $7.00 | $11.10 | $13.85 |
| 9 | Remove (8") TRT/untrt base & asphalt pavement (105-7028) | SY | 51,603 | $8.00 | $2.40 | $4.95 | $5.50 | $5.00 | $5.00 | $10.65 |
| 10 | Remove (16") TRT/untrt base & asphalt pavement (105-7036) | SY | 14,006 | $9.00 | $6.00 | $8.25 | $9.25 | $5.00 | $10.40 | $17.75 |
| 11 | Excavation (roadway) (110-7001) | CY | 550,728 | $8.75 | $6.50 | $6.00 | $7.00 | $6.00 | $5.00 | $7.00 |
| 12 | Excavation (channel) (110-7002) | CY | 18 | $16.80 | $100.00 | $50.00 | $25.00 | $25.00 | $28.00 | $50.00 |
| 13 | Embankment (final)(DC)(type A) (132-7002) | CY | 113,872 | $12.00 | $2.75 | $6.00 | $7.50 | $9.00 | $5.00 | $10.00 |
| 14 | Spec excavation work (backhoe) (158-7001) | HR | 84 | $162.50 | $125.40 | $207.00 | $100.00 | $50.00 | $220.00 | $150.00 |
| 15 | Furn & place topsoil (4") (160-7002) | SY | 242,659 | $1.50 | $0.82 | $1.50 | $1.25 | $1.00 | $1.00 | $1.85 |
| 16 | Broadcast seed (permanent_rural_sand) (164-7001) | SY | 225,593 | $0.25 | $0.12 | $0.11 | $0.11 | $0.10 | $0.11 | $0.12 |
| 17 | Bond fiber MTRX seed (permanent)(rural)(sand) (164-7073) | SY | 451,204 | $0.55 | $0.65 | $0.53 | $0.52 | $0.48 | $0.49 | $0.53 |
| 18 | Bond fiber MTRX seed (temporary)(warm) (164-7077) | SY | 225,593 | $0.58 | $0.45 | $0.52 | $0.52 | $0.48 | $0.49 | $0.53 |
| 19 | Bond fiber MTRX seed (temporary)(cool) (164-7078) | SY | 225,593 | $0.58 | $0.45 | $0.51 | $0.52 | $0.48 | $0.49 | $0.53 |
| 20 | Vegetative watering (168-7001) | TGL | 9,926 | $7.15 | $5.00 | $11.75 | $6.00 | $10.00 | $9.00 | $9.00 |
| 21 | Soil ret BLKT(SL_mod_sand_long) (169-7004) | SY | 8,128 | $1.50 | $1.85 | $0.65 | $0.85 | $1.00 | $0.80 | $0.80 |
| 22 | Wildflower seeding (180-7001) | ACRE | 11.18 | $950.00 | $1,155.00 | $572.00 | $435.00 | $400.00 | $405.00 | $450.00 |
| 23 | Proof rolling (216-7001) | HR | 400 | $185.00 | $143.00 | $50.00 | $60.00 | $50.00 | $140.00 | $135.00 |
| 24 | FL BS (compacted in place)(type A GR 1-2) (9") (247-7350) | SY | 230,417 | $27.00 | $24.85 | $22.00 | $27.00 | $20.00 | $21.00 | $27.80 |
| 25 | Lime (quicklime (dry)) (260-7002) | TON | 2,592 | $365.00 | $350.00 | $416.00 | $380.00 | $350.00 | $371.00 | $395.00 |
| 26 | Lime TRT (existing material)(10") (260-7008) | SY | 115,221 | $7.00 | $5.00 | $2.50 | $3.25 | $3.50 | $6.25 | $3.65 |
| 27 | Cement (275-7001) | TON | 2,592 | $210.00 | $263.00 | $282.00 | $265.00 | $210.00 | $215.00 | $270.00 |
| 28 | Cement TRT (existing material)(10") (275-7004) | SY | 115,221 | $3.55 | $5.50 | $1.60 | $2.35 | $3.50 | $4.15 | $3.60 |
| 29 | Prime coat & blotter (MC-30) (310-7010) | GAL | 69,125 | $5.00 | $8.40 | $5.80 | $5.75 | $5.00 | $8.00 | $5.70 |
| 30 | Asphalt (AC-20XP, AC-10-2TR, or AC-20-5TR) (316-7068) | GAL | 123,960 | $4.60 | $9.45 | $4.20 | $4.65 | $5.25 | $5.20 | $4.20 |
| 31 | Aggregate (type-PD or PL, GR-4) (316-7258) | CY | 1,809 | $220.00 | $168.00 | $161.00 | $185.00 | $165.00 | $220.00 | $179.00 |
| 32 | Aggregate (type-PD GR-5 or type-PL GR-5) (316-7283) | CY | 1,468 | $240.00 | $168.00 | $151.00 | $170.00 | $155.00 | $210.00 | $165.00 |
| 33 | SP mixes SP-B PG64-22 (344-7001) | TON | 52,866 | $135.00 | $139.40 | $143.00 | $139.00 | $145.00 | $133.00 | $132.00 |
| 34 | SP mixes SP-C sac-A PG70-22 (344-7020) | TON | 25,740 | $142.00 | $150.50 | $155.00 | $147.00 | $157.00 | $141.00 | $149.00 |
| 35 | Tack coat (344-7077) | GAL | 22,709 | $5.50 | $8.40 | $4.00 | $4.75 | $2.00 | $5.00 | $4.20 |
| 36 | Planing asphalt concrete pavement(0" to 2") (354-7032) | SY | 9,523 | $4.75 | $2.30 | $2.20 | $2.25 | $5.00 | $2.40 | $3.80 |
| 37 | Concrete pavement (CRCP) (10") (360-7004) | SY | 923 | $135.00 | $118.60 | $2.20 | $120.00 | $110.00 | $105.00 | $135.00 |
| 38 | Cut & restoring pavement (400-7006) | SY | 131 | $250.00 | $850.00 | $115.00 | $100.00 | $250.00 | $265.00 | $148.00 |
| 39 | Cem stabil BKFL (400-7010) | CY | 1,173 | $215.00 | $235.60 | $276.00 | $165.00 | $180.00 | $275.00 | $215.00 |
| 40 | Cement stab backfill (inlet or MH) (400-7011) | CY | 187 | $98.00 | $225.00 | $175.00 | $180.00 | $290.00 | $220.00 | |
| 41 | Trench excavation protection (402-7001) | LF | 22,974 | $7.50 | $3.20 | $1.72 | $8.00 | $5.00 | $3.25 | $8.85 |
| 42 | Temporary special shoring (403-7001) | SF | 14,744 | $35.00 | $42.90 | $38.00 | $42.00 | $55.00 | $45.00 | $45.00 |
| 43 | Soil nail anchors (410-7001) | LF | 37,719 | $30.60 | $28.15 | $25.00 | $25.00 | $32.00 | $29.00 | |
| 44 | Drilled shaft (18 in) (416-7002) | LF | 240 | $123.00 | $122.40 | $145.00 | $127.00 | $310.00 | $125.00 | $140.00 |
| 45 | Drilled shaft (36 in) (416-7006) | LF | 2,670 | $240.00 | $255.00 | $260.00 | $280.00 | $400.00 | $305.00 | $290.00 |
| 46 | Drilled shaft (42 in) (416-7007) | LF | 1,480 | $257.75 | $326.50 | $380.00 | $380.00 | $550.00 | $350.00 | $395.00 |
| 47 | Drilled shaft (60 in) (416-7010) | LF | 340 | $700.00 | $663.00 | $740.00 | $770.00 | $860.00 | $575.00 | $790.00 |
| 48 | Drilled shaft (non - reinforced) (12 in) (416-7024) | LF | 14 | $153.00 | $160.00 | $160.00 | $145.00 | $265.00 | $160.00 | |
| 49 | Drilled shaft (sign mounts) (24 in) (416-7028) | LF | 48 | $205.00 | $215.00 | $215.00 | $195.00 | $196.00 | $215.00 | |
| 50 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 24 | $298.75 | $281.50 | $295.00 | $290.00 | $268.00 | $285.00 | $295.00 |
| 51 | Drilled shaft (traffic signal pole) (24 in) (416-7042) | LF | 42 | $363.50 | $209.00 | $220.00 | $215.00 | $199.00 | $211.00 | $220.00 |
| 52 | Drilled shaft (traffic signal pole) (36 in) (416-7044) | LF | 65 | $449.00 | $336.00 | $352.00 | $350.00 | $320.00 | $340.00 | $352.00 |
| 53 | Drilled shaft (traffic signal pole) (48 in) (416-7046) | LF | 44 | $724.50 | $855.75 | $900.00 | $880.00 | $815.00 | $860.00 | $895.00 |
| 54 | Class A concrete (curb outlet)(type I) (420-7004) | EACH | 1 | $1,980.00 | $3,100.00 | $2,000.00 | $500.00 | $4,300.00 | $2,500.00 | |
| 55 | Class A concrete (curb outlet)(type II) (420-7005) | EACH | 2 | $2,000.00 | $2,700.00 | $1,625.00 | $1,500.00 | $500.00 | $4,200.00 | $2,500.00 |
| 56 | Class C concrete (abutment) (420-7012) | CY | 216.20 | $1,050.00 | $1,122.00 | $900.00 | $1,100.00 | $1,100.00 | $1,050.00 | $1,100.00 |
| 57 | Class C concrete (abutment)(extend) (420-7016) | CY | 57.90 | $1,875.00 | $1,530.00 | $1,030.00 | $1,250.00 | $1,500.00 | $1,200.00 | $1,600.00 |
| 58 | Class C concrete (cap) (420-7022) | CY | 231.20 | $1,835.00 | $1,377.00 | $955.00 | $1,150.00 | $1,300.00 | $1,450.00 | $1,100.00 |
| 59 | Class C concrete (cap)(mass) (420-7024) | CY | 108.10 | $1,500.00 | $1,632.00 | $1,365.00 | $1,550.00 | $2,350.00 | $1,400.00 | $1,950.00 |
| 60 | Class C concrete (column) (420-7038) | CY | 87.40 | $1,575.00 | $1,530.00 | $1,085.00 | $1,100.00 | $1,100.00 | $1,550.00 | $1,615.00 |
| 61 | Class C concrete (column)(mass) (420-7040) | CY | 112.40 | $1,350.00 | $1,580.00 | $1,090.00 | $1,625.00 | $2,550.00 | $1,950.00 | $1,720.00 |
| 62 | Class C concrete (footing)(mass) (420-7046) | CY | 78 | $1,175.00 | $1,326.00 | $1,136.00 | $1,250.00 | $1,800.00 | $1,400.00 | $1,720.00 |
| 63 | Class C concrete (rail foundation) (420-7052) | CY | 251.60 | $750.00 | $582.00 | $660.00 | $735.00 | $1,500.00 | $480.00 | $705.00 |
| 64 | Class C concrete (collar) (420-7061) | EACH | 2 | $2,500.00 | $4,725.00 | $990.00 | $1,500.00 | $2,500.00 | $2,300.00 | $1,800.00 |
| 65 | Class C concrete (miscellaneous) (420-7067) | CY | 1 | $1,100.00 | $3,940.00 | $990.00 | $2,000.00 | $1,500.00 | $1,600.00 | $3,000.00 |
| 66 | Reinforced concrete slab (422-7001) | SF | 63,350 | $26.00 | $26.50 | $26.00 | $27.00 | $23.00 | $20.00 | $25.75 |
| 67 | Reinforced concrete slab (extend slab) (422-7003) | SF | 15,187 | $45.00 | $32.65 | $28.00 | $32.00 | $28.00 | $20.00 | $36.00 |
| 68 | Approach slab (422-7013) | CY | 397.10 | $750.00 | $816.00 | $685.00 | $780.00 | $750.00 | $750.00 | $805.00 |
| 69 | Approach slab (extend) (422-7016) | CY | 65.80 | $1,080.00 | $970.00 | $965.00 | $830.00 | $850.00 | $1,200.00 | $1,265.00 |
| 70 | Retaining wall (MSE) (423-7001) | SF | 21,387 | $94.65 | $105.00 | $80.00 | $85.00 | $80.00 | $105.00 | |
| 71 | Retaining wall (soil nail) (fascia) (423-7023) | SF | 26,709 | $67.75 | $65.00 | $65.00 | $65.00 | $50.00 | $82.00 | |
| 72 | Prestressed concrete girder (TX46) (425-7004) | LF | 2,785.40 | $270.00 | $214.00 | $220.00 | $250.00 | $208.00 | $235.00 | |
| 73 | Prestressed concrete girder (TX54) (425-7005) | LF | 6,672.13 | $235.75 | $270.00 | $218.00 | $225.00 | $250.00 | $208.00 | $245.00 |
| 74 | Riprap (concrete)(4 in) (432-7001) | CY | 75.80 | $544.50 | $596.70 | $595.00 | $650.00 | $600.00 | $530.00 | $595.00 |
| 75 | Riprap (concrete)(5 in) (432-7002) | CY | 54 | $705.00 | $607.00 | $667.00 | $650.00 | $600.00 | $560.00 | $620.00 |
| 76 | Riprap (concrete)(CL A) (432-7004) | CY | 1 | $1,300.00 | $1,100.00 | $1,050.00 | $1,100.00 | $950.00 | $1,150.00 | $2,000.00 |
| 77 | Riprap (concrete)(CL B) (432-7005) | CY | 10.20 | $602.00 | $790.00 | $650.00 | $1,000.00 | $770.00 | $600.00 | |
| 78 | Riprap (mow strip)(4 in) (432-7013) | CY | 70.90 | $638.00 | $715.00 | $525.00 | $550.00 | $545.00 | $595.00 | |
| 79 | Riprap (stone common)(dry)(12 in) (432-7031) | CY | 836 | $147.50 | $87.15 | $221.00 | $215.00 | $170.00 | $175.00 | $210.00 |
| 80 | Riprap (stone protection)(12 in) (432-7041) | CY | 695 | $210.00 | $87.20 | $221.00 | $222.00 | $170.00 | $175.00 | $210.00 |
| 81 | Riprap (stone protection)(18 in) (432-7043) | CY | 400 | $210.00 | $89.00 | $253.00 | $222.00 | $170.00 | $180.00 | $210.00 |
| 82 | Cleaning and sealing existing joints (CL7) (438-7007) | LF | 136 | $45.47 | $60.00 | $95.00 | $100.00 | $75.00 | $60.00 | $66.00 |
| 83 | STR steel (miscellaneous non-bridge) (442-7007) | LB | 1,308 | $24.00 | $12.25 | $20.25 | $30.00 | $30.00 | $14.00 | $55.00 |
| 84 | Miscellaneous non-bridge (nbis) (442-7017) | LB | 28 | $22.00 | $92.00 | $100.00 | $50.00 | $65.00 | $31.00 | $55.00 |
| 85 | Rail (type SSTR) (450-7024) | LF | 2,607.48 | $67.35 | $79.00 | $85.00 | $200.00 | $89.00 | $80.00 | |
| 86 | Rail (type C221) (450-7032) | LF | 1,432 | $155.00 | $88.75 | $118.00 | $145.00 | $250.00 | $150.00 | $182.00 |
| 87 | Rail (type SSTR)(mod) (450-7066) | LF | 1,799.70 | $100.00 | $73.45 | $100.00 | $92.00 | $250.00 | $100.00 | $95.00 |
| 88 | Retrofit rail (type C221) (451-7032) | LF | 374 | $229.00 | $89.80 | $260.00 | $150.00 | $190.00 | $200.00 | $200.00 |
| 89 | Sealed expansion joint (4 in) (SEJ - M) (454-7004) | LF | 466 | $208.75 | $204.00 | $236.00 | $200.00 | $190.00 | $140.00 | $229.00 |
| 90 | Armor joint sealed (mod) (454-7012) | LF | 126 | $200.00 | $153.00 | $146.00 | $135.00 | $200.00 | $180.00 | $135.00 |
| 91 | Concrete box culvert (5 FT X 3 FT) (462-7007) | LF | 85 | $480.00 | $457.00 | $390.00 | $450.00 | $474.00 | $470.00 | $465.00 |
| 92 | Concrete box culvert (5 FT X 5 FT) (462-7009) | LF | 146 | $464.00 | $477.00 | $550.00 | $550.00 | $500.00 | $550.00 | |
| 93 | Concrete box culvert (6 FT X 5 FT) (462-7013) | LF | 132 | $495.00 | $595.00 | $620.00 | $725.00 | $650.00 | $625.00 | $700.00 |
| 94 | Concrete box culvert (10 FT X 10 FT) (462-7038) | LF | 344 | $1,500.00 | $1,525.00 | $1,285.00 | $1,450.00 | $1,500.00 | $1,500.00 | $1,400.00 |
| 95 | Concrete box culvert (5 FT X 3 FT)(extend) (462-7062) | LF | 120 | $680.00 | $1,270.00 | $475.00 | $475.00 | $574.00 | $550.00 | $500.00 |
| 96 | Concrete box culvert (6 FT X 11 FT) (462-7133) | LF | 20 | $875.00 | $1,050.00 | $1,225.00 | $1,350.00 | $1,800.00 | $2,400.00 | $1,000.00 |
| 97 | RC pipe (CL III)(18 in) (464-7003) | LF | 12,426 | $55.00 | $41.70 | $43.00 | $53.00 | $46.00 | $65.00 | $58.00 |
| 98 | RC pipe (CL III)(24 in) (464-7005) | LF | 6,368 | $75.00 | $60.35 | $63.50 | $74.00 | $65.00 | $100.00 | $77.00 |
| 99 | RC pipe (CL III)(30 in) (464-7007) | LF | 2,736 | $98.00 | $85.40 | $87.60 | $104.00 | $87.00 | $135.00 | $100.00 |
| 100 | RC pipe (CL III)(36 in) (464-7009) | LF | 3,141 | $145.00 | $117.60 | $118.50 | $145.00 | $120.00 | $165.00 | $145.00 |
| 101 | RC pipe (CL III)(42 in) (464-7010) | LF | 1,162 | $200.00 | $161.00 | $156.00 | $185.00 | $156.00 | $215.00 | $175.00 |
| 102 | RC pipe (CL III)(48 in) (464-7011) | LF | 1,978 | $205.00 | $194.00 | $192.00 | $225.00 | $215.00 | $260.00 | $215.00 |
| 103 | RC pipe (CL III)(54 in) (464-7012) | LF | 13 | $300.00 | $460.50 | $295.00 | $275.00 | $255.00 | $370.00 | $315.00 |
| 104 | Junction box(complete)(PJB)(4FTX4FT) (465-7006) | EACH | 14 | $7,250.00 | $6,225.00 | $5,870.00 | $8,800.00 | $5,000.00 | $8,000.00 | $7,500.00 |
| 105 | Junction box(complete)(PJB)(5FTX5FT) (465-7009) | EACH | 1 | $7,900.00 | $9,705.00 | $9,800.00 | $13,000 | $10,000 | $12,000 | $11,500 |
| 106 | Junction box(complete)(PJB)(6FTX6FT) (465-7011) | EACH | 3 | $10,300 | $9,000.00 | $9,000.00 | $12,000 | $10,000 | $12,000 | $9,300.00 |
| 107 | Junction box(complete)(PJB)(8FTX8FT) (465-7012) | EACH | 1 | $15,910 | $26,898 | $31,000 | $33,500 | $31,000 | $28,000 | $33,500 |
| 108 | Inlet (complete)(pco)(3FT)(both) (465-7016) | EACH | 133 | $6,700.00 | $5,480.00 | $5,800.00 | $8,500.00 | $5,000.00 | $6,600.00 | $7,600.00 |
| 109 | Inlet (complete)(pco)(4FT)(both) (465-7020) | EACH | 23 | $7,000.00 | $6,275.00 | $6,500.00 | $9,200.00 | $6,000.00 | $6,600.00 | $8,500.00 |
| 110 | Inlet (complete)(pco)(5FT)(both) (465-7024) | EACH | 6 | $9,500.00 | $7,095.00 | $7,000.00 | $9,800.00 | $6,400.00 | $7,000.00 | $9,100.00 |
| 111 | Inlet (complete)(pco)(6FT)(both) (465-7028) | EACH | 6 | $15,000 | $7,650.00 | $7,350.00 | $10,000 | $6,700.00 | $7,300.00 | $9,750.00 |
| 112 | Inlet(complete)(pazd)(FG)(3FTX3FT-3FTX3FT) (465-7158) | EACH | 9 | $5,760.00 | $8,015.00 | $5,100.00 | $8,500.00 | $6,500.00 | $6,000.00 | $6,875.00 |
| 113 | Inlet(complete)(pazd)(FG)(4FTX4FT-4FTX4FT) (465-7160) | EACH | 5 | $9,540.00 | $6,600.00 | $10,000 | $7,500.00 | $7,100.00 | $8,350.00 | |
| 114 | Inlet(complete)(pazd)(FG)(5FTX5FT-4FTX4FT) (465-7162) | EACH | 1 | $10,310 | $7,200.00 | $10,500 | $8,000.00 | $7,400.00 | $8,800.00 | |
| 115 | JCT box (complete)(special) (465-7332) | EACH | 1 | $26,860 | $36,200 | $22,000 | $16,000 | $40,000 | $22,000 | |
| 116 | Inlet (complete) (type MSE2) (465-7352) | EACH | 12 | $5,930.00 | $6,150.00 | $10,000 | $15,000 | $2,000.00 | $13,000 | |
| 117 | Headwall (CH - FW - 30) (diameter= 42 in) (466-7040) | EACH | 1 | $16,145 | $11,640 | $7,500.00 | $12,000 | $11,000 | $10,500 | |
| 118 | Wingwall (PW - 2) (HW=7 FT) (466-7191) | EACH | 2 | $18,495 | $23,400 | $20,000 | $21,000 | $25,000 | $27,000 | |
| 119 | Wingwall (PW - 2) (HW=8 FT) (466-7192) | EACH | 1 | $28,000 | $23,440 | $26,360 | $28,000 | $24,000 | $31,000 | $30,500 |
| 120 | Wingwall (PW - 2) (HW=12 FT) (466-7196) | EACH | 2 | $58,880 | $45,940 | $38,950 | $50,000 | $48,000 | $55,000 | $63,000 |
| 121 | Wingwall (PW - 2) (HW=16 FT) (466-7200) | EACH | 1 | $75,000 | $80,380 | $59,700 | $90,000 | $64,000 | $83,000 | $83,300 |
| 122 | Set (type II) (18 in) (RCP) (4: 1) (C) (467-7306) | EACH | 1 | $1,290.00 | $772.50 | $650.00 | $550.00 | $1,900.00 | $1,200.00 | |
| 123 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 27 | $1,120.00 | $965.00 | $915.00 | $860.00 | $786.00 | $2,100.00 | $1,115.00 |
| 124 | Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326) | EACH | 9 | $1,410.00 | $1,200.00 | $1,215.00 | $1,150.00 | $1,000.00 | $2,300.00 | $1,400.00 |
| 125 | Set (type II) (30 in) (RCP) (3: 1) (C) (467-7345) | EACH | 2 | $2,725.00 | $1,925.00 | $1,385.00 | $1,800.00 | $1,400.00 | $2,700.00 | $1,900.00 |
| 126 | Set (type II) (30 in) (RCP) (4: 1) (C) (467-7346) | EACH | 4 | $2,450.00 | $1,670.00 | $1,620.00 | $2,100.00 | $2,500.00 | $3,100.00 | $1,750.00 |
| 127 | Set (type II) (36 in) (RCP) (3: 1) (C) (467-7365) | EACH | 2 | $2,075.00 | $2,100.00 | $3,000.00 | $2,500.00 | $3,100.00 | $2,600.00 | |
| 128 | Set (type I)(S= 5 FT)(HW= 4 FT)(6:1) (P) (467-7479) | EACH | 1 | $13,400 | $13,125 | $10,220 | $10,000 | $16,000 | $18,000 | $17,600 |
| 129 | Pipe (PVC) (schedule 40) (6 in) (481-7013) | LF | 145 | $52.50 | $17.00 | $32.00 | $15.00 | $32.00 | $45.00 | |
| 130 | Removing structure (box culvert) (496-7001) | EACH | 2 | $3,200.00 | $3,655.00 | $4,550.00 | $3,500.00 | $10,000 | $7,000.00 | $5,000.00 |
| 131 | Removing structure (inlet) (496-7002) | EACH | 6 | $890.00 | $1,828.00 | $505.00 | $500.00 | $1,000.00 | $1,400.00 | $800.00 |
| 132 | Remove STR (rail) (496-7017) | LF | 374 | $32.00 | $23.00 | $16.00 | $25.00 | $100.00 | $30.00 | $85.00 |
| 133 | Removing structure (pipe) (496-7037) | EACH | 95 | $582.50 | $385.00 | $370.00 | $525.00 | $1,500.00 | $1,000.00 | $520.00 |
| 134 | Mobilization (500-7001) | LS | 1 | $4,782,606 | $2,300,000 | $5,000,000 | $3,430,000 | $5,000,000 | $6,400,000 | $5,000,000 |
| 135 | Barricades, signs and traffic handling (502-7001) | MO | 44 | $6,500.00 | $9,400.00 | $4,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | $7,000.00 |
| 136 | Portable changeable message sign (503-7001) | DAY | 600 | $100.00 | $134.00 | $132.00 | $125.00 | $100.00 | $125.00 | $110.00 |
| 137 | TMA (stationary) (505-7001) | DAY | 1,296 | $195.00 | $432.00 | $132.00 | $100.00 | $250.00 | $235.00 | $165.00 |
| 138 | TMA (mobile operation) (505-7003) | DAY | 129 | $237.00 | $721.65 | $200.00 | $300.00 | $500.00 | $650.00 | $275.00 |
| 139 | Rock filter dams (install) (type 2) (506-7002) | LF | 2,323 | $50.00 | $33.80 | $31.00 | $37.00 | $34.00 | $40.00 | $38.00 |
| 140 | Rock filter dams (remove) (506-7011) | LF | 2,323 | $13.75 | $9.25 | $9.00 | $5.50 | $5.00 | $5.20 | $6.00 |
| 141 | Construction exits (install) (type 1) (506-7020) | SY | 880 | $34.75 | $25.50 | $38.50 | $36.00 | $33.00 | $40.00 | $37.00 |
| 142 | Construction exits (remove) (506-7024) | SY | 880 | $11.25 | $4.10 | $8.80 | $5.50 | $5.00 | $5.20 | $5.50 |
| 143 | Temporary sediment control fence (install) (506-7039) | LF | 37,011 | $3.50 | $3.15 | $3.50 | $4.00 | $3.75 | $4.40 | $4.00 |
| 144 | Temporary sediment control fence (remove) (506-7041) | LF | 37,011 | $1.00 | $1.05 | $0.55 | $0.30 | $0.75 | $0.29 | $0.50 |
| 145 | Constructing detours (508-7001) | SY | 12,021 | $55.50 | $87.75 | $56.00 | $67.00 | $80.00 | $68.00 | $90.00 |
| 146 | Portable concrete traffic barrier (des source)(F-shape)(type 1) (512-7017) | LF | 1,980 | $50.00 | $9.30 | $14.20 | $15.00 | $25.00 | $8.00 | $11.30 |
| 147 | Portable concrete traffic barrier (move)(F-shape)(type 1) (512-7029) | LF | 450 | $11.25 | $29.95 | $13.50 | $10.00 | $10.00 | $9.00 | $11.00 |
| 148 | Portable concrete traffic barrier (stockpile)(F-shape)(type 1) (512-7041) | LF | 1,980 | $18.00 | $9.30 | $9.50 | $12.00 | $25.00 | $9.00 | $10.75 |
| 149 | PTB (fur&inst)(SSCB or CSB)(type 1)or(steel) (512-7085) | LF | 333.80 | $47.00 | $18.15 | $80.00 | $100.00 | $98.00 | $135.00 | |
| 150 | Permanent CTB (single slope) (type 1) (42 ) (514-7001) | LF | 2,346.20 | $90.40 | $88.00 | $110.00 | $110.00 | $112.00 | $112.00 | |
| 151 | Concrete curb (mono) (type II) (529-7007) | LF | 319 | $4.50 | $10.50 | $32.00 | $8.00 | $25.00 | $3.00 | $25.00 |
| 152 | Concrete curb & gutter (type I) (529-7008) | LF | 408 | $28.00 | $42.00 | $26.50 | $30.00 | $25.00 | $27.00 | $45.00 |
| 153 | Concrete curb & gutter (type II) (529-7009) | LF | 47,129 | $23.00 | $28.60 | $16.00 | $28.00 | $30.00 | $21.00 | $38.00 |
| 154 | Driveways (concrete) (hes) (530-7007) | SY | 4,421 | $130.00 | $115.00 | $111.00 | $110.00 | $100.00 | $118.00 | $120.00 |
| 155 | Driveways (ACP) (530-7010) | SY | 9,176 | $80.00 | $44.10 | $52.00 | $45.00 | $55.00 | $98.00 | $42.00 |
| 156 | Concrete sidewalks (4") (531-7001) | SY | 20,456 | $60.00 | $70.20 | $64.00 | $72.00 | $75.00 | $50.00 | $67.00 |
| 157 | Curb ramps (type 1) (531-7005) | EACH | 20 | $2,735.00 | $2,845.00 | $2,930.00 | $2,500.00 | $1,100.00 | $2,800.00 | $2,300.00 |
| 158 | Curb ramps (type 7) (531-7010) | EACH | 24 | $2,450.00 | $2,535.00 | $2,980.00 | $2,500.00 | $1,100.00 | $2,800.00 | $2,300.00 |
| 159 | Curb ramps (type 21) (531-7013) | EACH | 2 | $3,990.00 | $2,260.00 | $3,200.00 | $2,500.00 | $3,500.00 | $3,000.00 | |
| 160 | Curb ramps (type 22) (531-7014) | EACH | 6 | $3,250.00 | $4,105.00 | $3,030.00 | $4,000.00 | $2,500.00 | $4,200.00 | $3,000.00 |
| 161 | Concrete median (536-7002) | SY | 2,129 | $87.00 | $89.25 | $100.00 | $85.00 | $180.00 | $85.00 | $65.00 |
| 162 | Metal W-beam guard fence (steel post) (540-7002) | LF | 100 | $29.80 | $29.50 | $31.35 | $42.00 | $35.10 | $31.00 | $31.50 |
| 163 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 6 | $2,300.00 | $2,205.00 | $2,400.00 | $2,400.00 | $2,569.00 | $2,250.00 | $2,400.00 |
| 164 | Remove metal beam guard fence (542-7001) | LF | 637.50 | $2.65 | $2.10 | $2.20 | $2.20 | $2.75 | $3.50 | $2.20 |
| 165 | Guardrail end treatment (install) (544-7001) | EACH | 6 | $3,300.00 | $3,255.00 | $3,440.00 | $3,375.00 | $3,355.00 | $3,100.00 | $3,500.00 |
| 166 | Guardrail end treatment (remove) (544-7003) | EACH | 8 | $232.50 | $210.00 | $220.00 | $220.00 | $275.00 | $260.00 | $220.00 |
| 167 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 4 | $1,093.75 | $2,363.00 | $2,200.00 | $2,200.00 | $1,145.00 | $1,200.00 | $2,200.00 |
| 168 | Crash cushion attenuator (remove) (545-7004) | EACH | 12 | $713.75 | $840.00 | $880.00 | $900.00 | $985.00 | $1,000.00 | $880.00 |
| 169 | Crash cushion attenuator (install)(L)(N)(TL3) (545-7006) | EACH | 6 | $30,000 | $27,195 | $27,450 | $27,000 | $31,205 | $28,000 | $27,500 |
| 170 | Cca (install)(N)(TL3)(work zone) (545-7018) | EACH | 8 | $7,500.00 | $8,820.00 | $9,240.00 | $9,500.00 | $7,575.00 | $8,900.00 | $9,300.00 |
| 171 | Pipe underdrains (type 8) (6") (556-7008) | LF | 2,362 | $28.70 | $32.00 | $50.00 | $45.00 | $38.00 | $36.00 | |
| 172 | Mailbox install-M (TWG-post) type 1 (560-7001) | EACH | 1 | $632.50 | $693.00 | $835.00 | $820.00 | $775.00 | $785.00 | $840.00 |
| 173 | Mailbox install-S (TWG-post) type 2 (560-7002) | EACH | 48 | $288.75 | $315.00 | $360.00 | $360.00 | $275.00 | $270.00 | $365.00 |
| 174 | Mailbox install-D (TWG-post) type 2 (560-7003) | EACH | 5 | $315.00 | $331.00 | $415.00 | $410.00 | $315.00 | $290.00 | $420.00 |
| 175 | Relocate RD IL asm (shoe-base) (610-7002) | EACH | 3 | $1,330.00 | $2,153.00 | $2,255.00 | $2,215.00 | $2,050.00 | $1,050.00 | $2,255.00 |
| 176 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 1,054 | $16.00 | $8.50 | $9.00 | $8.75 | $8.10 | $9.00 | $9.00 |
| 177 | Conduit (PVC) (schedule 40) (3") (618-7036) | LF | 210 | $22.00 | $17.60 | $18.50 | $18.25 | $16.75 | $18.00 | $18.50 |
| 178 | Conduit (PVC) (schedule 40) (4") (618-7040) | LF | 290 | $20.75 | $18.90 | $20.00 | $19.50 | $18.00 | $19.00 | $20.00 |
| 179 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 684 | $27.75 | $16.80 | $17.50 | $17.50 | $16.00 | $17.00 | $17.75 |
| 180 | Conduit (PVC) (schedule 80) (4") (bore) (618-7065) | LF | 430 | $37.00 | $32.55 | $34.00 | $33.50 | $31.00 | $33.00 | $34.00 |
| 181 | Electrical conductor (no.8) bare (620-7007) | LF | 3,008 | $2.10 | $2.40 | $2.50 | $2.50 | $2.25 | $2.50 | $2.50 |
| 182 | Electrical conductor (no.8) insulated (620-7008) | LF | 5,686 | $2.65 | $2.65 | $2.75 | $2.70 | $2.50 | $2.70 | $2.75 |
| 183 | Electrical conductor (no.6) bare (620-7009) | LF | 65 | $2.75 | $3.15 | $3.30 | $3.25 | $3.00 | $3.20 | $3.50 |
| 184 | Electrical conductor (no.6) insulated (620-7010) | LF | 130 | $3.10 | $3.70 | $3.85 | $3.80 | $3.50 | $3.70 | $3.85 |
| 185 | Ground box type A (122311)W/apron (624-7002) | EACH | 3 | $1,557.50 | $1,235.00 | $1,295.00 | $1,270.00 | $1,175.00 | $1,250.00 | $1,295.00 |
| 186 | Ground box type D (162922)W/apron (624-7008) | EACH | 11 | $1,660.00 | $1,470.00 | $1,500.00 | $1,515.00 | $1,400.00 | $1,500.00 | $1,550.00 |
| 187 | Remove ground box (624-7013) | EACH | 3 | $612.50 | $450.00 | $470.00 | $460.00 | $425.00 | $450.00 | $468.00 |
| 188 | Elc SRV type D 120/240 060(NS)SS(E)PS(U) (628-7147) | EACH | 2 | $7,250.00 | $8,140.00 | $8,500.00 | $8,400.00 | $7,750.00 | $8,200.00 | $8,525.00 |
| 189 | Aluminum signs (type G) (636-7002) | SF | 390 | $38.00 | $38.00 | $39.50 | $36.25 | $37.00 | $39.00 | |
| 190 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 70 | $633.75 | $735.00 | $740.00 | $730.00 | $640.00 | $660.00 | $740.00 |
| 191 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 16 | $767.50 | $840.00 | $900.00 | $900.00 | $725.00 | $900.00 | $915.00 |
| 192 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 4 | $1,050.00 | $1,150.00 | $1,135.00 | $1,199.00 | $900.00 | $1,150.00 | |
| 193 | Install small roadside sign support and assembly TYS80(1)SA(U-WC) (644-7035) | EACH | 3 | $1,155.00 | $1,340.00 | $1,315.00 | $1,495.00 | $900.00 | $1,340.00 | |
| 194 | Install small roadside sign support and assembly TYS80(2)SA(P) (644-7048) | EACH | 2 | $2,330.00 | $2,625.00 | $1,625.00 | $1,600.00 | $1,569.00 | $1,040.00 | $1,625.00 |
| 195 | Remove SM RD SN sup&AM (644-7073) | EACH | 109 | $87.50 | $52.50 | $101.00 | $100.00 | $79.00 | $110.00 | $100.00 |
| 196 | Install LRSS (struct steel) (647-7001) | LB | 2,035 | $7.60 | $7.90 | $7.85 | $7.25 | $8.00 | $8.00 | |
| 197 | Remove lrsa (647-7003) | EACH | 2 | $1,265.00 | $945.00 | $990.00 | $975.00 | $900.00 | $920.00 | $990.00 |
| 198 | Install delineator assembly (D-SW)SZ 1(WFLX)GND (658-7003) | EACH | 78 | $49.75 | $174.00 | $60.50 | $60.00 | $55.00 | $48.00 | $50.00 |
| 199 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 77 | $27.00 | $33.00 | $20.00 | $20.00 | $15.00 | $22.00 | $22.00 |
| 200 | Install delineator assembly (D-DY)SZ 1(BRF)GF2 (658-7052) | EACH | 10 | $22.00 | $39.00 | $27.50 | $30.00 | $25.00 | $26.00 | $38.00 |
| 201 | Install object marker assembly (OM-2Z)(WFLX)GND (658-7058) | EACH | 24 | $101.00 | $173.00 | $86.00 | $85.00 | $55.00 | $62.00 | $85.00 |
| 202 | Install object marker assembly (OM-3L)(WFLX)GND (658-7065) | EACH | 6 | $715.00 | $173.00 | $610.00 | $600.00 | $569.00 | $470.00 | $610.00 |
| 203 | Install object marker assembly (OM-3R)(WFLX)GND (658-7069) | EACH | 7 | $715.00 | $173.00 | $610.00 | $600.00 | $569.00 | $470.00 | $610.00 |
| 204 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 30,803 | $0.40 | $0.22 | $0.22 | $0.22 | $0.20 | $0.21 | $0.22 |
| 205 | Work zone pavement marking non-removing (W)8"(solid) (662-7012) | LF | 568 | $0.80 | $0.53 | $0.55 | $0.55 | $0.50 | $0.52 | $0.55 |
| 206 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 40,814 | $0.40 | $0.22 | $0.22 | $0.22 | $0.20 | $0.21 | $0.22 |
| 207 | Work zone pavement marking removing (reflectorized) type II-A-A (662-7051) | EACH | 2,795 | $4.30 | $4.20 | $4.40 | $4.35 | $4.00 | $4.10 | $4.40 |
| 208 | Work zone pavement marking removing (traffic BTN) type W (662-7057) | EACH | 122 | $4.30 | $5.25 | $5.50 | $5.40 | $5.00 | $5.10 | $5.50 |
| 209 | Work zone pavement marking removing (traffic BTN) type Y (662-7059) | EACH | 132 | $2.00 | $5.25 | $5.50 | $5.40 | $5.00 | $5.10 | $5.50 |
| 210 | Work zone pavement marking removing (W)6"(broken) (662-7065) | LF | 210 | $0.90 | $2.10 | $2.20 | $2.20 | $2.00 | $2.10 | $2.20 |
| 211 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 65,163 | $0.95 | $0.85 | $0.88 | $0.88 | $0.80 | $0.90 | $0.90 |
| 212 | Work zone pavement marking removing (W)8"(solid) (662-7072) | LF | 1,623 | $1.90 | $1.05 | $1.10 | $1.10 | $1.00 | $1.05 | $1.10 |
| 213 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 574 | $7.00 | $8.40 | $8.80 | $8.75 | $8.00 | $8.10 | $8.80 |
| 214 | Work zone pavement marking removing (W)(arrow) (662-7082) | EACH | 1 | $150.00 | $210.00 | $220.00 | $220.00 | $200.00 | $210.00 | $220.00 |
| 215 | Work zone pavement marking removing (W)(word) (662-7092) | EACH | 1 | $165.00 | $210.00 | $220.00 | $220.00 | $200.00 | $210.00 | $220.00 |
| 216 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 72,079 | $0.95 | $0.85 | $0.80 | $0.88 | $0.80 | $0.90 | $0.88 |
| 217 | Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009) | LF | 597 | $1.60 | $1.60 | $1.65 | $1.65 | $1.50 | $1.60 | $1.65 |
| 218 | Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018) | LF | 284 | $2.25 | $1.60 | $1.65 | $1.65 | $1.50 | $1.60 | $1.65 |
| 219 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 12,328 | $1.30 | $1.05 | $1.00 | $1.10 | $1.00 | $1.05 | $1.10 |
| 220 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 519 | $4.00 | $4.20 | $4.40 | $4.35 | $4.00 | $4.10 | $4.40 |
| 221 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 2,075 | $7.25 | $6.10 | $6.40 | $6.30 | $5.80 | $6.00 | $6.40 |
| 222 | Reflectorized pavement marking type I (Y)12"(solid)(100MIL) (666-7117) | LF | 1,486 | $4.00 | $4.20 | $4.40 | $4.35 | $4.00 | $4.10 | $4.50 |
| 223 | Type I high perf PM (W)6"(broken)(100MIL) (666-7290) | LF | 10,680 | $0.75 | $0.85 | $0.88 | $0.90 | $0.80 | $0.90 | $0.90 |
| 224 | Type I high perf PM (W)6"(solid)(100MIL) (666-7293) | LF | 55,007 | $0.70 | $0.75 | $0.77 | $0.75 | $0.70 | $0.80 | $0.80 |
| 225 | Type I high perf PM (Y)6"(broken)(100MIL) (666-7302) | LF | 6,960 | $0.75 | $0.85 | $0.88 | $0.90 | $0.80 | $0.90 | $0.90 |
| 226 | Type I high perf PM (Y)6"(solid)(100MIL) (666-7305) | LF | 78,580 | $0.75 | $0.75 | $0.77 | $0.75 | $0.70 | $0.80 | $0.80 |
| 227 | Pavement sler 6" (666-7347) | LF | 6,443 | $0.20 | $0.30 | $0.30 | $0.27 | $0.25 | $0.26 | $0.28 |
| 228 | Pavement sler 8" (666-7348) | LF | 464 | $0.35 | $0.55 | $0.55 | $0.55 | $0.50 | $0.52 | $0.55 |
| 229 | Pavement sler 24" (666-7352) | LF | 196 | $0.90 | $2.65 | $2.75 | $2.70 | $2.50 | $2.60 | $2.75 |
| 230 | Pavement sler (arrow) (666-7353) | EACH | 2 | $25.00 | $105.00 | $110.00 | $110.00 | $100.00 | $105.00 | $110.00 |
| 231 | Pavement sler (word) (666-7354) | EACH | 2 | $25.00 | $105.00 | $110.00 | $110.00 | $100.00 | $105.00 | $110.00 |
| 232 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 54 | $218.75 | $215.25 | $200.00 | $225.00 | $205.00 | $210.00 | $226.00 |
| 233 | Prefabricated PM type C (W)(double arrow) (668-7093) | EACH | 4 | $270.00 | $288.75 | $300.00 | $300.00 | $275.00 | $280.00 | $305.00 |
| 234 | Prefabricated PM type C (W)(LN reduct arrow) (668-7100) | EACH | 2 | $300.00 | $315.00 | $310.00 | $285.00 | $290.00 | $315.00 | |
| 235 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 42 | $247.50 | $252.00 | $265.00 | $260.00 | $240.00 | $250.00 | $265.00 |
| 236 | Prefabricated PM type C (W)(36")(yld tri) (668-7111) | EACH | 53 | $42.50 | $48.00 | $50.00 | $50.00 | $45.00 | $46.00 | $50.00 |
| 237 | Prefabricated PM type C (W)(bike arrow) (668-7113) | EACH | 41 | $265.00 | $185.00 | $195.00 | $190.00 | $175.00 | $180.00 | $195.00 |
| 238 | Prefabricated PM type C (W)(bike symbol) (668-7115) | EACH | 41 | $288.00 | $185.00 | $195.00 | $190.00 | $175.00 | $180.00 | $195.00 |
| 239 | Reflectorized pavement marker type I-C (672-7002) | EACH | 939 | $5.25 | $4.50 | $4.75 | $4.65 | $4.30 | $4.40 | $4.75 |
| 240 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 2,527 | $6.50 | $4.50 | $4.70 | $4.65 | $4.30 | $4.40 | $4.75 |
| 241 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 174 | $5.00 | $4.50 | $4.75 | $4.65 | $4.30 | $4.40 | $4.75 |
| 242 | Eliminating existing PM & markers (4") (677-7001) | LF | 44,216 | $0.65 | $0.50 | $0.48 | $0.50 | $0.45 | $0.47 | $0.50 |
| 243 | Eliminating existing PM & markers (6") (677-7002) | LF | 53,117 | $0.55 | $0.60 | $0.55 | $0.60 | $0.55 | $0.57 | $0.60 |
| 244 | Eliminating existing PM & markers (8") (677-7004) | LF | 2,237 | $0.85 | $0.80 | $0.90 | $0.82 | $0.75 | $0.77 | $0.83 |
| 245 | Eliminating existing PM & markers (12") (677-7006) | LF | 561 | $2.20 | $2.10 | $2.20 | $2.20 | $2.00 | $2.10 | $2.20 |
| 246 | Eliminating existing PM & markers (24") (677-7008) | LF | 395 | $4.35 | $4.20 | $4.40 | $4.35 | $4.00 | $4.10 | $4.40 |
| 247 | Install highway traffic signal (isolated) (680-7002) | EACH | 2 | $37,920 | $32,320 | $33,500 | $33,500 | $30,780 | $34,000 | $34,000 |
| 248 | Removing traffic signals (680-7004) | EACH | 2 | $2,100.00 | $7,615.00 | $7,975.00 | $7,850.00 | $7,250.00 | $8,000.00 | $8,000.00 |
| 249 | Temporary traffic signals (681-7001) | EACH | 2 | $58,950 | $120,750 | $125,000 | $125,000 | $1,115,000 | $125,000 | $126,500 |
| 250 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 15 | $385.00 | $283.00 | $300.00 | $300.00 | $269.00 | $290.00 | $300.00 |
| 251 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 12 | $400.00 | $290.00 | $300.00 | $300.00 | $275.00 | $290.00 | $305.00 |
| 252 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 15 | $385.00 | $283.00 | $300.00 | $300.00 | $269.00 | $290.00 | $300.00 |
| 253 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 17 | $400.00 | $290.00 | $300.00 | $300.00 | $275.00 | $290.00 | $305.00 |
| 254 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 19 | $385.00 | $283.00 | $300.00 | $300.00 | $269.00 | $290.00 | $300.00 |
| 255 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 5 | $385.00 | $290.00 | $300.00 | $300.00 | $275.00 | $290.00 | $305.00 |
| 256 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 14 | $835.00 | $567.00 | $600.00 | $585.00 | $540.00 | $570.00 | $595.00 |
| 257 | Backplate W/reflectorized border(3 sec)aluminum (682-7039) | EACH | 16 | $135.50 | $163.00 | $170.00 | $170.00 | $155.00 | $165.00 | $170.00 |
| 258 | Backplate W/reflectorized border(4 sec)aluminum (682-7040) | EACH | 5 | $205.00 | $235.00 | $250.00 | $245.00 | $224.00 | $240.00 | $250.00 |
| 259 | Backplate W/reflectorized border(5 sec)aluminum (682-7041) | EACH | 3 | $315.00 | $247.00 | $260.00 | $255.00 | $234.50 | $250.00 | $260.00 |
| 260 | Traffic signal CBL (type A)(12 AWG)(3 conductor) (684-7008) | LF | 2,350 | $3.00 | $3.00 | $3.00 | $3.00 | $2.75 | $3.00 | $3.00 |
| 261 | Traffic signal CBL (type A)(12 AWG)(5 conductor) (684-7010) | LF | 2,106 | $4.00 | $3.50 | $3.60 | $3.50 | $3.25 | $3.50 | $3.60 |
| 262 | Traffic signal CBL (type A)(12 AWG)(7 conductor) (684-7012) | LF | 432 | $5.00 | $4.20 | $4.40 | $4.35 | $4.00 | $4.30 | $4.40 |
| 263 | Traffic signal CBL (type A)(12 AWG)(16 conductor) (684-7021) | LF | 1,265 | $9.00 | $7.40 | $7.70 | $7.60 | $7.00 | $8.00 | $8.00 |
| 264 | Ins traffic signal PL AM(S)1 arm(40')lum&ilsn (686-7044) | EACH | 2 | $15,000 | $20,560 | $21,500 | $21,500 | $19,580 | $21,000 | $21,500 |
| 265 | Ins traffic signal PL AM(S)1 arm(44')lum&ilsn (686-7048) | EACH | 2 | $19,250 | $22,470 | $23,500 | $23,500 | $21,400 | $23,000 | $23,550 |
| 266 | Ins traffic signal PL AM(S)1 arm(48')lum&ilsn (686-7052) | EACH | 1 | $24,300 | $22,845 | $23,930 | $23,500 | $21,755 | $23,000 | $24,000 |
| 267 | Ins traffic signal PL AM(S)1 arm(50')lum&ilsn (686-7056) | EACH | 1 | $37,800 | $36,745 | $38,500 | $38,000 | $34,995 | $38,000 | $38,500 |
| 268 | Ins traffic signal PL AM(S)1 arm(55')lum&ilsn (686-7060) | EACH | 1 | $42,000 | $42,000 | $44,000 | $43,500 | $40,007 | $44,000 | $44,000 |
| 269 | Pedestrian pole assembly (687-7001) | EACH | 7 | $3,270.00 | $3,020.00 | $3,200.00 | $3,100.00 | $2,875.00 | $3,100.00 | $3,175.00 |
| 270 | Pedestrian detect push button (APS) (688-7001) | EACH | 14 | $1,080.00 | $795.00 | $830.00 | $815.00 | $755.00 | $800.00 | $830.00 |
| 271 | Pedestrian detector controller unit (688-7003) | EACH | 2 | $3,970.00 | $3,260.00 | $3,415.00 | $3,350.00 | $3,105.00 | $3,300.00 | $3,420.00 |
| 272 | Install bbu system (690-7131) | EACH | 2 | $12,100 | $7,298.00 | $7,650.00 | $7,500.00 | $6,950.00 | $7,400.00 | $7,650.00 |
| 273 | Full - width mowing (730-7019) | CYC | 8 | $7,050.00 | $3,675.00 | $4,600.00 | $3,000.00 | $5,000.00 | $8,100.00 | $8,250.00 |
| 274 | Litter removal (734-7002) | CYC | 8 | $2,987.50 | $7,300.00 | $1,840.00 | $2,500.00 | $1,000.00 | $4,200.00 | $6,000.00 |
| 275 | Install FTB (5002-7001) | LF | 580 | $60.00 | $47.00 | $55.00 | $40.00 | $55.00 | $72.00 | $40.00 |
| 276 | Remove FTB (5002-7002) | LF | 580 | $20.00 | $47.00 | $11.00 | $11.00 | $10.00 | $9.00 | $11.00 |
| 277 | VDS prosr sys (6017-7001) | EACH | 2 | $10,500 | $11,185 | $11,700 | $11,500 | $10,650 | $12,000 | $11,750 |
| 278 | HVDS W/var LNS (6017-7008) | EACH | 7 | $5,000.00 | $6,115.00 | $6,400.00 | $6,300.00 | $5,820.00 | $6,200.00 | $6,400.00 |
| 279 | VDS CNTRL software (6017-7009) | EACH | 2 | $585.00 | $425.00 | $450.00 | $440.00 | $405.00 | $430.00 | $445.00 |
| 280 | VDS cabling (6017-7012) | LF | 1,750 | $3.00 | $3.75 | $3.85 | $3.80 | $3.50 | $4.00 | $4.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of July 2, 2026. Compiled by Mirage Metrics.