Class C concrete (abutment)(extend), TxDOT 420-7016
Low bidders on TxDOT contracts carried a median of $1,987.14 per CY for this item, over the 24 months to 19 NOV 2026, across 10 low bids. Half of all 66 bids fell between $1,507.50 and $2,612.50.
- Owner
- Texas DOT
- Item
- 420-7016
- Unit
- CY
- Data through
- 19 NOV 2026
TxDOT prints this item as “CL C CONC (ABUT)(EXTEND)”.
TxDOT has bid this work under more than one code: 4206019 on lettings from 09 APR 2020 to 05 MAY 2022 (83 bids); 4206019001 on lettings from 03 AUG 2022 to 02 AUG 2024 (47 bids); 420-7016 on lettings from 07 JAN 2025 to 03 NOV 2026 (62 bids); 420-6019 on lettings from 07 JAN 2025 to 07 JAN 2025 (4 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 11 | 11 | $1,747.37 | 48 | $1,546.99 |
| 2021 | 6 | 6 | $1,100.00 | 27 | $1,420.00 |
| 2022 | 5 | 5 | $1,700.00 | 20 | $1,694.65 |
| 2023 | 3 | 3 | $2,050.00 | 12 | $1,803.76 |
| 2024 | 5 | 5 | $3,500.00 | 23 | $2,200.00 |
| 2025 | 5 | 5 | $3,075.00 | 29 | $2,000.00 |
| 2026 | 5 | 5 | $1,700.00 | 37 | $1,874.29 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Austin District | 3 | $2,802.13 | 18 | $2,094.26 |
| San Antonio District | 3 | $2,100.00 | 16 | $2,050.00 |
Districts with at least three low bids, over the last 24 months.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| James Construction Group, LLC | 16 | 6 (38%) |
| Webber, LLC | 20 | 3 (15%) |
| Pulice Construction, Inc. | 9 | 3 (33%) |
| Williams Brothers Construction Co., Inc. | 8 | 1 (13%) |
| Zachry Construction Corporation | 5 | 1 (20%) |
| Texas Materials Group, Inc. | 6 | 0 (0%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 03 NOV 2026 | A00184974 | Austin District | 104.60 | $2,802.13 | $2,973.79 | n/a | 6 | Austin Bridge & Road Services, LP | TxDOT |
| 05 AUG 2026 | A00191471 | Houston District | 74.60 | $1,405.83 | $1,480.35 | $2,215.00 | 8 | James Construction Group, LLC | TxDOT |
| 02 JUL 2026 | A00027293 | Tyler District | 57.90 | $1,530.00 | $1,530.00 | $1,875.00 | 9 | Baker & Company Construction, LLC | TxDOT |
| 01 JUL 2026 | A00190685 | Houston District | 42.70 | $1,700.00 | $1,957.33 | $3,200.00 | 11 | Harper Brothers Construction LLC | TxDOT |
| 07 MAY 2026 | A00031457 | San Antonio District | 48 | $1,874.29 | $2,332.00 | $2,600.00 | 3 | Webber, LLC | TxDOT |
| 06 NOV 2025 | A00062085 | Austin District | 25.30 | $3,603.82 | $1,969.18 | $1,700.00 | 8 | Webber, LLC | TxDOT |
| 05 JUN 2025 | A00011238 | San Antonio District | 50.90 | $2,100.00 | $1,920.00 | $5,500.00 | 9 | Jordan Foster Construction, LLC | TxDOT |
| 03 APR 2025 | A00196404 | San Antonio District | 5 | $3,075.00 | $2,617.50 | $1,651.75 | 4 | Relmco, Inc. | TxDOT |
| 07 JAN 2025 | A00064247 | Austin District | 42.40 | $1,485.73 | $1,744.38 | $2,307.00 | 4 | Webber, LLC | TxDOT |
| 07 JAN 2025 | A00183266 | Beaumont District | 1.40 | $3,300.00 | $3,150.00 | $5,500.00 | 4 | Ti-Zack Concrete, LLC | TxDOT |
| 02 AUG 2024 | 08243202 | Houston District | 2.10 | $4,774.45 | $6,279.32 | $2,300.00 | 4 | James Construction Group, LLC | TxDOT |
| 06 JUN 2024 | 06243201 | San Antonio District | 657.50 | $1,841.52 | $1,841.52 | $2,216.00 | 5 | Webber, LLC | TxDOT |
| 06 JUN 2024 | 06243203 | Houston District | 17.40 | $3,753.44 | $5,626.72 | $905.00 | 2 | James Construction Group, LLC | TxDOT |
| 02 FEB 2024 | 02243202 | Houston District | 268 | $1,475.81 | $1,500.00 | $1,900.00 | 8 | Brice Construction and Design LLC | TxDOT |
| 04 JAN 2024 | 01243002 | Yoakum District | 10.60 | $3,500.00 | $4,495.00 | $2,000.00 | 4 | Hunter Industries, LTD. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the TxDOT letting of 19 NOV 2026 and was rebuilt on 26 NOV 2026.