TxDOT contract A00183266 bid tabulation
Bicycle And Pedestrian Improvements, Various (DISTRICT WIDE to .). Let by Texas DOT on January 7, 2025, Jefferson, Beaumont District. 4 bids received; low bid $2,688,467 by Ti-Zack Concrete, LLC, -11% against the engineer's estimate of $3,021,841.
- Owner
- Texas DOT
- Letting
- 07 JAN 2025
- Pay items
- 77
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ti-Zack Concrete, LLC | $2,688,467 | Low | -11% |
| 2 | STX Civil | $2,969,542 | +10% | -2.0% |
| 3 | Talbert Companies LLC | $2,999,599 | +12% | -1.0% |
| 4 | Ragle Construction, Inc. | $3,594,489 | +34% | +19% |
Engineer's estimate: $3,021,841.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Ti-Zack Concrete, LLC | 2. STX Civil | 3. Talbert Companies LLC | 4. Ragle Construction, Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 3 | $3,000.00 | $1,100.00 | $6,000.00 | $11,000 | $95,000 |
| 2 | Tree protection (install) (100-7013) | EACH | 3 | $185.00 | $1.10 | $600.00 | $385.00 | $885.00 |
| 3 | Tree protection (remove) (100-7015) | EACH | 3 | $25.00 | $1.10 | $300.00 | $165.00 | $375.00 |
| 4 | Removing concrete (pavement) (104-7001) | SY | 234 | $10.00 | $34.10 | $45.00 | $25.83 | $30.00 |
| 5 | Removing concrete (driveways) (104-7011) | SY | 2,358 | $30.00 | $23.69 | $21.00 | $28.05 | $28.00 |
| 6 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 358 | $30.00 | $22.29 | $21.00 | $38.50 | $22.00 |
| 7 | Removing concrete (curb or curb & gutter) (104-7018) | LF | 1,971 | $25.00 | $12.15 | $14.00 | $36.89 | $10.00 |
| 8 | Removing concrete (miscellaneous) (104-7046) | SY | 46 | $30.00 | $34.70 | $30.00 | $86.90 | $55.00 |
| 9 | Remove (2"-6") TRT/untrt base & asphalt pavement (105-7002) | SY | 29 | $10.00 | $55.03 | $14.00 | $50.08 | $24.00 |
| 10 | Furn & place topsoil (4") (160-7002) | SY | 212 | $8.00 | $3.76 | $5.00 | $9.35 | $13.00 |
| 11 | Block sodding (162-7002) | SY | 212 | $8.00 | $11.00 | $8.00 | $16.50 | $15.00 |
| 12 | Prestressed concrete pil (16 in SQ) (409-7001) | LF | 344 | $160.00 | $264.00 | $393.00 | $174.34 | $245.00 |
| 13 | Drilled shaft (30 in) (416-7005) | LF | 8 | $325.00 | $255.15 | $350.00 | $255.15 | $183.00 |
| 14 | Class A concrete (flume) (420-7006) | CY | 0.37 | $1,500.00 | $2,202.22 | $2,000.00 | $770.00 | $2,400.00 |
| 15 | Class C concrete (abutment) (420-7012) | CY | 16.80 | $2,000.00 | $2,420.00 | $1,200.00 | $1,430.00 | $1,500.00 |
| 16 | Class C concrete (abutment)(extend) (420-7016) | CY | 1.40 | $5,500.00 | $3,300.00 | $3,000.00 | $2,750.00 | $5,500.00 |
| 17 | Reinforced concrete slab (extend slab) (422-7003) | SF | 569 | $50.00 | $66.00 | $31.00 | $40.70 | $100.00 |
| 18 | Riprap (concrete)(5 in) (432-7002) | CY | 44 | $950.00 | $1,100.00 | $750.00 | $770.00 | $725.00 |
| 19 | STR steel (miscellaneous non-bridge) (442-7007) | LB | 115 | $25.00 | $5.50 | $185.00 | $35.20 | $65.00 |
| 20 | Rail (type PR11) (450-7044) | LF | 157.20 | $200.00 | $161.70 | $210.00 | $161.70 | $150.00 |
| 21 | Rail (handrail)(type B) (450-7059) | LF | 160 | $200.00 | $143.00 | $210.00 | $143.00 | $150.00 |
| 22 | Rail (handrail)(type F) (450-7063) | LF | 76 | $200.00 | $176.00 | $210.00 | $176.00 | $225.00 |
| 23 | Grate (471-7001) | EACH | 8 | $5,000.00 | $2,202.22 | $5,000.00 | $2,750.00 | $2,600.00 |
| 24 | Adjusting manholes (479-7001) | EACH | 43 | $2,000.00 | $185.58 | $2,200.00 | $2,420.00 | $1,200.00 |
| 25 | Adjusting inlets (479-7002) | EACH | 1 | $1,400.00 | $7,980.00 | $3,500.00 | $1,872.94 | $1,275.00 |
| 26 | Removing structure (bridge slab) (496-7013) | EACH | 1 | $45,000 | $99,000 | $25,000 | $44,000 | $400,000 |
| 27 | Remove STR (rail) (496-7017) | LF | 110 | $300.00 | $110.00 | $50.00 | $44.00 | $75.00 |
| 28 | Mobilization (500-7001) | LS | 1 | $298,438 | $285,610 | $270,000 | $427,346 | $350,000 |
| 29 | Barricades, signs and traffic handling (502-7001) | MO | 23 | $5,000.00 | $2,200.00 | $5,000.00 | $11,000 | $7,500.00 |
| 30 | Portable changeable message sign (503-7001) | DAY | 337 | $170.00 | $1.10 | $100.00 | $148.50 | $50.00 |
| 31 | TMA (stationary) (505-7001) | DAY | 337 | $300.00 | $1.10 | $190.00 | $361.05 | $50.00 |
| 32 | Temporary SDMT cont fence (inlet protection) (506-7040) | LF | 167 | $11.00 | $1.10 | $11.00 | $12.10 | $5.00 |
| 33 | Concrete curb (type II) (529-7002) | LF | 596 | $47.00 | $49.64 | $35.00 | $54.32 | $17.00 |
| 34 | Concrete curb (type F1) (529-7017) | LF | 119 | $150.00 | $163.80 | $325.00 | $104.50 | $210.00 |
| 35 | Driveways (concrete) (530-7006) | SY | 2,358 | $200.00 | $122.46 | $165.00 | $121.00 | $150.00 |
| 36 | Concrete sidewalks (4") (531-7001) | SY | 5,236 | $110.00 | $111.03 | $110.00 | $104.50 | $62.00 |
| 37 | Curb ramps (type 1) (531-7005) | EACH | 9 | $2,500.00 | $2,003.07 | $3,500.00 | $2,970.00 | $2,100.00 |
| 38 | Curb ramps (type 2) (531-7006) | EACH | 1 | $2,600.00 | $2,003.07 | $3,500.00 | $3,190.00 | $2,500.00 |
| 39 | Curb ramps (type 5) (531-7008) | EACH | 5 | $3,400.00 | $2,003.07 | $3,500.00 | $2,970.00 | $2,300.00 |
| 40 | Curb ramps (type 6) (531-7009) | EACH | 8 | $3,000.00 | $2,003.07 | $3,500.00 | $2,970.00 | $1,650.00 |
| 41 | Curb ramps (type 7) (531-7010) | EACH | 25 | $2,900.00 | $2,003.07 | $3,500.00 | $3,300.00 | $2,500.00 |
| 42 | Curb ramps (type 10) (531-7011) | EACH | 1 | $2,700.00 | $2,003.07 | $3,500.00 | $3,630.00 | $3,050.00 |
| 43 | Concrete sidewalks (special) (531-7025) | SY | 13 | $500.00 | $539.42 | $350.00 | $275.00 | $3,500.00 |
| 44 | Relocate existing mailbox (560-7012) | EACH | 1 | $500.00 | $357.50 | $350.00 | $357.50 | $325.00 |
| 45 | Relocate RD IL asm (trans-base) (610-7004) | EACH | 1 | $4,000.00 | $4,344.15 | $5,141.00 | $4,344.15 | $2,617.00 |
| 46 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 10 | $26.00 | $45.82 | $55.00 | $45.82 | $13.85 |
| 47 | Conduit (PVC) (schedule 80) (3") (618-7060) | LF | 155 | $20.00 | $36.23 | $43.00 | $36.23 | $22.65 |
| 48 | Electrical conductor (no.8) bare (620-7007) | LF | 155 | $2.00 | $1.55 | $2.00 | $1.55 | $2.00 |
| 49 | Electrical conductor (no.6) bare (620-7009) | LF | 10 | $3.00 | $1.72 | $2.00 | $1.72 | $2.00 |
| 50 | Electrical conductor (no.6) insulated (620-7010) | LF | 80 | $3.00 | $2.01 | $3.00 | $2.01 | $2.31 |
| 51 | Ground box type A (122311)W/apron (624-7002) | EACH | 1 | $1,500.00 | $3,401.17 | $4,025.00 | $3,401.17 | $1,223.00 |
| 52 | Ground box type D (162922)W/apron (624-7008) | EACH | 2 | $1,500.00 | $2,755.19 | $3,261.00 | $2,755.19 | $1,241.00 |
| 53 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 4 | $900.00 | $715.00 | $800.00 | $715.00 | $650.00 |
| 54 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 12 | $550.00 | $517.00 | $550.00 | $517.00 | $470.00 |
| 55 | Remove SM RD SN (foundation only) (644-7106) | EACH | 2 | $130.00 | $104.50 | $200.00 | $104.50 | $1,115.82 |
| 56 | Reflectorized pavement marking type I (W)8"(solid)(090MIL) (666-7023) | LF | 13 | $2.00 | $22.00 | $26.50 | $22.00 | $20.00 |
| 57 | Reflectorized pavement marking type II (W) 4" (solid) (666-7171) | LF | 15 | $2.00 | $11.00 | $13.50 | $11.00 | $10.00 |
| 58 | Reflectorized pavement marking type II (W) 8" (solid) (666-7179) | LF | 13 | $2.00 | $22.00 | $26.50 | $22.00 | $20.00 |
| 59 | Reflectorized pavement marking type II (Y) 4" (solid) (666-7210) | LF | 13 | $2.00 | $11.00 | $13.50 | $11.00 | $10.00 |
| 60 | Reflectorized pavement marking type I (W)4"(solid)(090MIL) (666-7404) | LF | 15 | $6.00 | $11.00 | $13.50 | $11.00 | $10.00 |
| 61 | Reflectorized pavement marking type I (Y)4"(solid)(090MIL) (666-7416) | LF | 13 | $6.00 | $11.00 | $13.50 | $11.00 | $10.00 |
| 62 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 2,424 | $20.00 | $8.97 | $11.00 | $8.97 | $8.15 |
| 63 | Eliminating existing PM & markers (4") (677-7001) | LF | 97 | $1.00 | $1.10 | $1.50 | $1.10 | $1.00 |
| 64 | Eliminating existing PM & markers (8") (677-7004) | LF | 6 | $1.00 | $2.20 | $3.00 | $2.20 | $2.00 |
| 65 | Eliminating existing PM & markers (24") (677-7008) | LF | 359 | $7.00 | $3.30 | $4.00 | $3.30 | $3.00 |
| 66 | Pavement surface preparation for marking (4") (678-7001) | LF | 28 | $1.00 | $1.10 | $1.50 | $1.10 | $1.00 |
| 67 | Pavement surface preparation for marking (8") (678-7004) | LF | 13 | $1.00 | $2.20 | $3.00 | $2.20 | $2.00 |
| 68 | Pavement surface preparation for marking (24") (678-7008) | LF | 2,424 | $1.00 | $1.10 | $1.50 | $1.10 | $1.00 |
| 69 | Install highway traffic signal (isolated) (680-7002) | EACH | 4 | $15,000 | $26,505 | $31,400 | $26,505 | $22,783 |
| 70 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 28 | $730.00 | $1,063.02 | $1,258.00 | $1,063.02 | $590.00 |
| 71 | Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031) | LF | 3,965 | $3.00 | $2.88 | $3.50 | $2.88 | $2.20 |
| 72 | Traffic signal CBL (type C)(14 AWG)(2 conductor) (684-7080) | LF | 3,845 | $3.00 | $1.40 | $2.00 | $1.40 | $1.80 |
| 73 | Pedestrian pole assembly (687-7001) | EACH | 12 | $2,000.00 | $2,268.96 | $2,685.00 | $2,268.96 | $3,817.00 |
| 74 | Pedestrian detect push button (APS) (688-7001) | EACH | 28 | $1,000.00 | $1,268.38 | $1,525.00 | $1,268.38 | $797.00 |
| 75 | Pedestrian detector controller unit (688-7003) | EACH | 4 | $3,200.00 | $4,546.01 | $5,380.00 | $4,546.01 | $3,767.00 |
| 76 | Shrub planting and removal (751-7009) | EACH | 8 | $200.00 | $605.00 | $500.00 | $82.50 | $450.00 |
| 77 | Prefabricated pedestrian steel truss BRG span (155 FT) (4004-7003) | EACH | 1 | $355,000 | $495,000 | $327,500 | $225,500 | $750,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of January 7, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.