TxDOT contract A00196404 bid tabulation
Bridge Maintenance, Various (Various Locations Districtwide to .). Let by Texas DOT on April 3, 2025, Bexar, San Antonio District. 4 bids received; low bid $7,263,765 by Relmco, Inc., -20% against the engineer's estimate of $9,122,455.
- Owner
- Texas DOT
- Letting
- 03 APR 2025
- Pay items
- 94
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Relmco, Inc. | $7,263,765 | Low | -20% |
| 2 | Icos Management, LLC | $7,514,627 | +3.0% | -18% |
| 3 | Built Right Construction of Oklahoma, LLC | $9,148,926 | +26% | 0.0% |
| 4 | Dan Williams Company | $11,895,138 | +64% | +30% |
Engineer's estimate: $9,122,455.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Relmco, Inc. | 2. Icos Management, LLC | 3. Built Right Construction of Oklahoma, LLC | 4. Dan Williams Company |
|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 5 | $2,500.00 | $15,000 | $1,080.00 | $7,500.00 | $5,000.00 |
| 2 | Removing concrete (mowstrip) (104-7005) | LF | 8,535 | $20.00 | $15.00 | $5.40 | $7.50 | $5.00 |
| 3 | Removing concrete (riprap) (104-7006) | SY | 183 | $64.57 | $30.00 | $108.00 | $20.00 | $50.00 |
| 4 | Removing concrete (riprap) (104-7007) | CY | 9 | $100.00 | $200.00 | $242.00 | $75.00 | $500.00 |
| 5 | Removing concrete (curb) (104-7016) | LF | 60 | $12.00 | $50.00 | $44.00 | $10.00 | $15.00 |
| 6 | Removing concrete (sawcut) (104-7020) | LF | 184 | $60.00 | $15.00 | $16.20 | $10.00 | $7.00 |
| 7 | Removing concrete (abutment backwall) (104-7032) | CY | 3 | $1,650.00 | $2,000.00 | $1,080.00 | $100.00 | $2,000.00 |
| 8 | Removing concrete (rail) (104-7036) | LF | 299 | $50.00 | $50.00 | $86.40 | $25.00 | $50.00 |
| 9 | Remove (9") TRT/untrt base & asphalt pavement (105-7029) | SY | 107 | $40.00 | $20.00 | $44.00 | $20.00 | $30.00 |
| 10 | Excavation (roadway) (110-7001) | CY | 1,947 | $30.00 | $35.00 | $65.00 | $20.00 | $75.00 |
| 11 | Excavation (channel) (110-7002) | CY | 1,540 | $70.00 | $35.00 | $86.00 | $20.00 | $75.00 |
| 12 | Embankment (final)(DC)(type C) (132-7006) | CY | 2,071 | $60.00 | $75.00 | $75.00 | $20.00 | $145.00 |
| 13 | Furn & place topsoil (6") (160-7004) | SY | 8,029 | $2.00 | $8.00 | $11.00 | $10.00 | $5.00 |
| 14 | Broadcast seed (permanent_urban_clay) (164-7004) | SY | 8,029 | $0.30 | $0.60 | $0.10 | $2.00 | $1.25 |
| 15 | Soil ret BLKT(SL_mod_clay_short) (169-7001) | SY | 8,029 | $8.00 | $3.00 | $1.00 | $15.00 | $1.75 |
| 16 | D-GR HMA type-B PG64-22 (341-7001) | TON | 9 | $175.00 | $350.00 | $432.00 | $250.00 | $3,000.00 |
| 17 | D-GR HMA type-C sac-B PG70-22 (341-7024) | TON | 36 | $175.00 | $350.00 | $324.00 | $250.00 | $775.00 |
| 18 | Temporary special shoring (403-7001) | SF | 3,963 | $40.00 | $30.00 | $1.00 | $100.00 | $100.00 |
| 19 | Class C concrete (abutment)(extend) (420-7016) | CY | 5 | $1,651.75 | $3,075.00 | $2,160.00 | $1,000.00 | $6,000.00 |
| 20 | Class C concrete (cap)(extend) (420-7026) | CY | 52 | $3,000.00 | $1,950.00 | $1,080.00 | $2,500.00 | $15,000 |
| 21 | Concrete structure repair (epoxy mortar) (429-7002) | SF | 9 | $1,500.00 | $350.00 | $432.00 | $325.00 | $900.00 |
| 22 | Concrete structure repair(deck rep(part depth)) (429-7003) | SF | 335 | $155.59 | $275.00 | $275.00 | $330.00 | $400.00 |
| 23 | Concrete structure repair(deck rep (full depth)) (429-7005) | SF | 49 | $677.50 | $350.00 | $540.00 | $350.00 | $1,000.00 |
| 24 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 233 | $290.71 | $275.00 | $232.00 | $275.00 | $450.00 |
| 25 | Concrete structure repair (standard) (429-7009) | SF | 19 | $2,000.00 | $350.00 | $262.00 | $275.00 | $850.00 |
| 26 | Riprap (concrete)(5 in) (432-7002) | CY | 22 | $700.00 | $525.00 | $756.00 | $850.00 | $1,000.00 |
| 27 | Riprap (concrete)(CL B) (432-7005) | CY | 99 | $1,000.00 | $525.00 | $648.00 | $850.00 | $900.00 |
| 28 | Riprap (concrete) (CL B) (4 in) (432-7007) | CY | 3 | $1,265.96 | $900.00 | $648.00 | $850.00 | $1,800.00 |
| 29 | Riprap (concrete) (CL B) (6 in) (432-7009) | CY | 6 | $1,250.00 | $800.00 | $972.00 | $1,000.00 | $1,500.00 |
| 30 | Riprap (mow strip)(4 in) (432-7013) | CY | 643 | $700.00 | $515.00 | $648.00 | $750.00 | $750.00 |
| 31 | Riprap (stone common)(dry)(18 in) (432-7033) | CY | 315 | $250.00 | $195.00 | $216.00 | $325.00 | $350.00 |
| 32 | Riprap (stone common)(dry)(24 in) (432-7034) | CY | 374 | $300.00 | $195.00 | $216.00 | $350.00 | $350.00 |
| 33 | Riprap (stone common)(grout)(12 in) (432-7038) | CY | 171 | $350.00 | $195.00 | $400.00 | $250.00 | $500.00 |
| 34 | Riprap (stone protection)(18 in) (432-7043) | CY | 48 | $236.63 | $195.00 | $270.00 | $300.00 | $350.00 |
| 35 | Elastomeric bearing (EE1) (434-7003) | EACH | 13 | $6,135.00 | $4,500.00 | $8,640.00 | $2,500.00 | $12,000 |
| 36 | STR steel (miscellaneous non-bridge) (442-7007) | LB | 1,120 | $27.07 | $35.00 | $44.00 | $25.00 | $25.00 |
| 37 | STR steel (pedestal) (442-7010) | LB | 15 | $36.00 | $300.00 | $108.00 | $250.00 | $400.00 |
| 38 | Rail (type T2P) (450-7003) | LF | 4,647 | $225.00 | $300.00 | $324.00 | $200.00 | $375.00 |
| 39 | Rail (type T221) (450-7004) | LF | 14 | $169.00 | $600.00 | $864.00 | $200.00 | $450.00 |
| 40 | Rail (type T223) (450-7008) | LF | 55 | $231.16 | $600.00 | $756.00 | $200.00 | $225.00 |
| 41 | Rail (type SSTR) (450-7024) | LF | 136 | $250.00 | $600.00 | $540.00 | $200.00 | $175.00 |
| 42 | Rail (type C223) (450-7034) | LF | 128 | $231.16 | $600.00 | $540.00 | $200.00 | $400.00 |
| 43 | Gabions (3' X 3')(galvanized) (459-7010) | CY | 364 | $300.00 | $250.00 | $162.00 | $350.00 | $350.00 |
| 44 | Raising existing struct (495-7002) | EACH | 3 | $17,500 | $75,000 | $21,600 | $30,000 | $135,000 |
| 45 | Removing structure (headwall) (496-7006) | EACH | 2 | $3,357.30 | $4,500.00 | $2,160.00 | $1,000.00 | $5,000.00 |
| 46 | Remove STR (rail) (496-7017) | LF | 4,464 | $111.67 | $25.00 | $13.00 | $10.00 | $12.00 |
| 47 | Remove STR (gabion) (496-7018) | LF | 253 | $80.00 | $50.00 | $22.00 | $50.00 | $25.00 |
| 48 | Adjust steel shoes (499-7001) | EACH | 1 | $12,767 | $8,500.00 | $8,640.00 | $500.00 | $2,500.00 |
| 49 | Mobilization (500-7001) | LS | 1 | $811,490 | $700,000 | $605,000 | $885,000 | $1,800,000 |
| 50 | Barricades, signs and traffic handling (502-7001) | MO | 22 | $5,000.00 | $8,500.00 | $1.00 | $12,000 | $53,000 |
| 51 | Rock filter dams (install) (type 2) (506-7002) | LF | 131 | $60.00 | $55.00 | $10.00 | $55.00 | $75.00 |
| 52 | Rock filter dams (install) (type 3) (506-7003) | LF | 146 | $100.00 | $80.00 | $10.00 | $70.00 | $100.00 |
| 53 | Rock filter dams (remove) (506-7011) | LF | 277 | $20.00 | $15.00 | $5.00 | $20.00 | $30.00 |
| 54 | Construction exits (install) (type 1) (506-7020) | SY | 587 | $40.00 | $30.00 | $1.00 | $40.00 | $30.00 |
| 55 | Construction exits (remove) (506-7024) | SY | 587 | $15.00 | $15.00 | $1.00 | $10.00 | $25.00 |
| 56 | Temporary sediment control fence (install) (506-7039) | LF | 1,069 | $5.00 | $10.00 | $2.00 | $10.00 | $4.50 |
| 57 | Temporary sediment control fence (remove) (506-7041) | LF | 1,069 | $2.00 | $4.00 | $1.00 | $2.00 | $1.00 |
| 58 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 115 | $8.00 | $12.00 | $10.00 | $20.00 | $6.00 |
| 59 | Biodegradable erosion control logs (remove) (506-7046) | LF | 115 | $4.00 | $5.00 | $5.00 | $5.00 | $1.00 |
| 60 | Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001) | LF | 6,470 | $72.00 | $40.00 | $97.00 | $100.00 | $75.00 |
| 61 | Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009) | LF | 1,990 | $70.00 | $30.00 | $97.00 | $100.00 | $30.00 |
| 62 | Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010) | LF | 240 | $75.00 | $30.00 | $108.00 | $100.00 | $30.00 |
| 63 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 29,620 | $16.00 | $15.00 | $16.00 | $40.00 | $16.00 |
| 64 | Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033) | LF | 2,053 | $15.00 | $15.00 | $22.00 | $20.00 | $15.00 |
| 65 | Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034) | LF | 420 | $20.00 | $15.00 | $22.00 | $20.00 | $19.00 |
| 66 | Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049) | LF | 29,570 | $19.75 | $18.00 | $13.00 | $35.00 | $15.50 |
| 67 | Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057) | LF | 2,053 | $20.00 | $15.00 | $22.00 | $30.00 | $14.25 |
| 68 | Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058) | LF | 420 | $20.00 | $15.00 | $22.00 | $30.00 | $18.50 |
| 69 | Concrete curb (type II) (529-7002) | LF | 13 | $50.00 | $200.00 | $108.00 | $50.00 | $200.00 |
| 70 | Metal W-beam guard fence (timber post) (540-7001) | LF | 8,445 | $30.00 | $27.95 | $30.00 | $30.00 | $35.00 |
| 71 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 65 | $2,300.00 | $2,096.25 | $2,376.00 | $2,500.00 | $2,600.00 |
| 72 | Downstream anchor terminal section (540-7015) | EACH | 18 | $1,600.00 | $1,451.25 | $2,700.00 | $2,500.00 | $1,700.00 |
| 73 | TL-3 31" short radius (complete) (540-7039) | EACH | 1 | $30,000 | $31,175 | $2,160.00 | $40,000 | $32,000 |
| 74 | Remove metal beam guard fence (542-7001) | LF | 10,327 | $5.00 | $2.68 | $2.25 | $6.00 | $5.00 |
| 75 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 12 | $385.00 | $268.75 | $540.00 | $500.00 | $325.00 |
| 76 | Guardrail end treatment (install) (544-7001) | EACH | 43 | $3,400.00 | $3,332.50 | $4,320.00 | $3,700.00 | $4,200.00 |
| 77 | Guardrail end treatment (remove) (544-7003) | EACH | 32 | $370.00 | $268.75 | $540.00 | $500.00 | $300.00 |
| 78 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 50 | $1,700.00 | $800.00 | $2,160.00 | $2,000.00 | $900.00 |
| 79 | Crash cushion attenuator (remove) (545-7004) | EACH | 50 | $1,000.00 | $800.00 | $1,080.00 | $750.00 | $800.00 |
| 80 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 10 | $10,000 | $8,500.00 | $10,800 | $12,000 | $10,000 |
| 81 | Relocate electrical services (628-7001) | EACH | 2 | $1,500.00 | $5,500.00 | $6,480.00 | $12,000 | $2,000.00 |
| 82 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 125 | $40.00 | $27.50 | $54.00 | $50.00 | $35.00 |
| 83 | Driftwood removal (735-7060) | CY | 445 | $262.93 | $100.00 | $66.00 | $100.00 | $75.00 |
| 84 | Concrete rail replacement (in-kind) (778-7004) | LF | 41 | $951.29 | $400.00 | $1,080.00 | $250.00 | $600.00 |
| 85 | Rep steel bridge MBR (straighten memb) (784-7020) | EACH | 3 | $34,575 | $45,000 | $10,800 | $15,000 | $25,000 |
| 86 | Rep steel bridge MBR (anchor bolt nuts) (784-7021) | EACH | 2 | $34,575 | $1,200.00 | $5,400.00 | $300.00 | $1,500.00 |
| 87 | Bridge joint repair (armor) (785-7004) | LF | 33 | $582.27 | $400.00 | $486.00 | $500.00 | $1,200.00 |
| 88 | Carbon fiber reinforced polymer strengthning (786-7002) | SF | 63 | $13,000 | $165.00 | $270.00 | $150.00 | $450.00 |
| 89 | Concrete beam repair (CFRP) (788-7002) | EACH | 12 | $25,000 | $9,500.00 | $10,800 | $10,000 | $15,000 |
| 90 | Concrete beam rep(strand splice & CFRP) (788-7003) | EACH | 2 | $25,000 | $4,500.00 | $43,200 | $10,000 | $25,000 |
| 91 | Lane closure(setup & rem)(typ 1) (790-7001) | EACH | 2 | $3,000.00 | $3,500.00 | $8,640.00 | $2,000.00 | $1,000.00 |
| 92 | Lane closure(setup & rem)(typ 14) (790-7014) | EACH | 2 | $3,000.00 | $3,500.00 | $8,640.00 | $2,000.00 | $1,000.00 |
| 93 | Underseal course (3006-7001) | GAL | 24 | $10.00 | $75.00 | $220.00 | $40.00 | $25.00 |
| 94 | Bonding course (3007-7001) | GAL | 20 | $10.00 | $75.00 | $220.00 | $40.00 | $25.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of April 3, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.