TxDOT contract A00121011 bid tabulation
Widen Road - Add Lanes, FM 2220 (FM 1925 to SH 107). Let by Texas DOT on May 6, 2026, Hidalgo, Pharr District. 6 bids received; low bid $25,599,271 by Ioc Company LLC, -25% against the engineer's estimate of $33,933,191.
- Owner
- Texas DOT
- Letting
- 06 MAY 2026
- Pay items
- 218
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ioc Company LLC | $25,599,271 | Low | -25% |
| 2 | Foremost Paving, Inc. | $28,603,848 | +12% | -16% |
| 3 | Reim Construction, Inc. | $28,650,242 | +12% | -16% |
| 4 | Texas Cordia Construction, LLC | $31,233,709 | +22% | -8.0% |
| 5 | 3LW Civil LLC | $36,832,483 | +44% | +9.0% |
| 6 | CK Newberry, LLC | $39,127,106 | +53% | +15% |
Engineer's estimate: $33,933,191.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Ioc Company LLC | 2. Foremost Paving, Inc. | 3. Reim Construction, Inc. | 4. Texas Cordia Construction, LLC | 5. 3LW Civil LLC | 6. CK Newberry, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7001) | ACRE | 1 | $4,500.00 | $7,500.00 | $10,000 | $67,000 | $15,000 | $4,737.27 | $10,000 |
| 2 | Preparing row (100-7002) | STA | 314 | $1,800.00 | $5,229.00 | $500.00 | $2,950.00 | $1,200.00 | $2,335.41 | $1,500.00 |
| 3 | Preparation row (tree remove) (0"-12" diameter) (100-7003) | EACH | 40 | $400.00 | $100.00 | $100.00 | $212.00 | $711.00 | $448.50 | $750.00 |
| 4 | Preparation row (tree remove) (12"-24" diameter) (100-7004) | EACH | 40 | $820.00 | $150.00 | $200.00 | $317.00 | $1,030.00 | $448.50 | $1,000.00 |
| 5 | Removing concrete (riprap) (104-7006) | SY | 1,636 | $21.00 | $10.00 | $20.00 | $12.55 | $10.00 | $67.85 | $5.50 |
| 6 | Removing concrete (riprap) (104-7007) | CY | 44 | $108.00 | $75.00 | $180.00 | $113.00 | $115.00 | $224.25 | $70.00 |
| 7 | Removing concrete (medians) (104-7008) | SY | 42 | $35.00 | $20.00 | $51.84 | $18.50 | $60.00 | $120.75 | $70.00 |
| 8 | Removing concrete (driveways) (104-7011) | SY | 1,772 | $20.00 | $15.00 | $27.54 | $10.50 | $6.00 | $17.54 | $15.00 |
| 9 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 343 | $50.00 | $15.00 | $21.73 | $8.20 | $6.00 | $53.76 | $10.00 |
| 10 | Removing concrete (curb & gutter) (104-7017) | LF | 1,985 | $9.00 | $5.00 | $9.61 | $3.05 | $4.00 | $11.21 | $8.00 |
| 11 | Removing concrete (gutter) (104-7019) | LF | 260 | $11.08 | $10.00 | $9.61 | $5.30 | $6.00 | $25.30 | $12.00 |
| 12 | Removing concrete (miscellaneous) (104-7046) | SY | 429 | $40.00 | $15.00 | $22.97 | $16.65 | $7.00 | $42.55 | $15.00 |
| 13 | Remove (22") TRT/untrt base & asphalt pavement (105-7042) | SY | 2,112 | $8.14 | $10.00 | $18.53 | $8.50 | $12.00 | $37.95 | $30.00 |
| 14 | Remove (10") TRT/untrt base & asphalt pavement (105-7089) | CY | 4,233 | $16.00 | $5.00 | $16.27 | $15.55 | $16.00 | $78.20 | $15.00 |
| 15 | Obliterating abandoned road (106-7002) | SY | 16,506 | $6.00 | $1.00 | $0.51 | $3.55 | $2.00 | $17.83 | $3.00 |
| 16 | Excavation (roadway) (110-7001) | CY | 95,450.70 | $9.00 | $5.00 | $6.98 | $6.50 | $13.00 | $14.95 | $15.00 |
| 17 | Excavation (channel) (110-7002) | CY | 67,198.90 | $17.00 | $5.00 | $14.80 | $8.10 | $12.00 | $11.50 | $18.00 |
| 18 | Embankment (final)(DC)(type C) (132-7006) | CY | 10,223.90 | $8.00 | $3.00 | $16.87 | $6.20 | $4.00 | $13.23 | $10.00 |
| 19 | Backfill (type A) (134-7001) | STA | 110 | $260.00 | $100.00 | $347.56 | $265.00 | $395.00 | $908.50 | $250.00 |
| 20 | Furn & place topsoil (vehicle) (160-7007) | CY | 4,971 | $58.00 | $1.00 | $28.15 | $18.90 | $45.00 | $63.25 | $20.00 |
| 21 | Hydro mulch seed (permanent_rural_clay) (164-7018) | SY | 93,325 | $0.70 | $0.41 | $0.45 | $0.50 | $0.75 | $0.69 | $0.70 |
| 22 | Hydro mulch seed (temporary_warm) (164-7021) | SY | 93,325 | $0.50 | $0.27 | $0.35 | $0.32 | $0.75 | $0.67 | $0.70 |
| 23 | Vegetative watering (168-7001) | TGL | 1,569 | $29.56 | $30.00 | $33.11 | $31.70 | $57.00 | $44.85 | $35.00 |
| 24 | Irrigation system (170-7001) | LS | 1 | $70,000 | $139,611 | $106,875 | $199,000 | $220,210 | $102,502 | $210,000 |
| 25 | Plant bed preparation (192-7009) | SY | 2,112 | $3.80 | $60.00 | $31.25 | $20.00 | $50.00 | $28.75 | $65.00 |
| 26 | Plant material (15 gal) (192-7030) | EACH | 408 | $199.07 | $30.00 | $219.50 | $497.00 | $50.00 | $246.22 | $300.00 |
| 27 | Plant material (30 gal) (192-7031) | EACH | 283 | $381.17 | $350.00 | $482.19 | $525.00 | $66.00 | $487.40 | $1,300.00 |
| 28 | Plant material (45 gal) (192-7032) | EACH | 99 | $520.00 | $350.00 | $935.25 | $580.00 | $83.00 | $949.36 | $2,100.00 |
| 29 | Plant material (3 gal) (shrub) (192-7046) | EACH | 266 | $47.19 | $75.00 | $31.56 | $107.00 | $94.00 | $33.35 | $100.00 |
| 30 | Plant material (5 gal) (shrub) (192-7047) | EACH | 2,826 | $27.42 | $110.00 | $38.13 | $160.00 | $116.00 | $39.68 | $70.00 |
| 31 | Landscape establish (193-7001) | MO | 3 | $3,900.00 | $1,500.00 | $4,500.00 | $4,700.00 | $2,750.00 | $5,175.00 | $9,000.00 |
| 32 | Irrig sys oper and maintenance (193-7007) | MO | 3 | $2,216.23 | $1,000.00 | $4,500.00 | $6,630.00 | $9,130.00 | $5,175.00 | $6,000.00 |
| 33 | Sprinkling (dust control) (204-7001) | TGL | 1,128 | $4.50 | $1.00 | $1.00 | $31.70 | $12.00 | $78.20 | $35.00 |
| 34 | FL BS (roadway del)(type E GR 4)(final pos) (247-7277) | CY | 43,130 | $54.00 | $30.00 | $24.97 | $33.50 | $42.00 | $50.58 | $40.00 |
| 35 | Rework BS metal (type B)(6")(DC)(org pos) (251-7034) | CY | 17,784 | $4.00 | $5.00 | $8.61 | $5.00 | $4.00 | $6.90 | $10.00 |
| 36 | Lime (com or QK)(slurry) (260-7005) | TON | 4,034 | $270.00 | $200.00 | $245.88 | $309.00 | $320.00 | $377.71 | $350.00 |
| 37 | Lime TRT (existing material)(12") (260-7009) | SY | 203,720 | $5.00 | $2.50 | $3.35 | $2.10 | $2.00 | $3.22 | $3.00 |
| 38 | Cement (275-7001) | TON | 1,863 | $200.00 | $182.75 | $185.30 | $216.00 | $220.00 | $241.50 | $210.00 |
| 39 | Cement TRT (existing material & new base)(10") (275-7008) | SY | 198,594 | $2.51 | $1.75 | $3.74 | $1.95 | $2.00 | $3.74 | $1.00 |
| 40 | Salvage, haul & stockpile reclaimed asphalt PV (1 1/2") (305-7015) | SY | 74,502 | $0.70 | $1.00 | $1.53 | $1.55 | $3.00 | $5.18 | $1.20 |
| 41 | Prime coat (MC-30) (310-7004) | GAL | 39,718 | $5.20 | $5.00 | $6.62 | $6.40 | $8.00 | $5.18 | $5.00 |
| 42 | Asphalt (tier II) (316-7266) | GAL | 55,463 | $4.50 | $3.75 | $5.33 | $4.05 | $7.00 | $4.66 | $4.75 |
| 43 | Aggregate (type-B GR-4P sac-B) (316-7267) | CY | 1,541 | $100.00 | $75.00 | $97.27 | $80.85 | $144.00 | $172.50 | $190.00 |
| 44 | SP mixes SP-D sac-A PG76-22 (344-7064) | TON | 31,509 | $115.00 | $113.00 | $100.57 | $119.00 | $125.00 | $139.11 | $165.00 |
| 45 | Plane & text asphalt concrete pavement(1.5") (354-7018) | SY | 10,498 | $5.00 | $1.00 | $3.01 | $2.15 | $6.00 | $6.90 | $4.00 |
| 46 | Struct excavation (special) (400-7005) | CY | 4,389 | $50.00 | $85.00 | $68.00 | $75.00 | $112.00 | $14.02 | $95.00 |
| 47 | Cut & restore asphalt paving (400-7008) | SY | 1,976 | $180.00 | $75.00 | $105.00 | $64.60 | $77.00 | $58.42 | $125.00 |
| 48 | Cut and restore pavement (flex base) (400-7009) | SY | 206 | $50.00 | $50.00 | $50.00 | $20.40 | $53.00 | $44.53 | $100.00 |
| 49 | Cem stabil BKFL (400-7010) | CY | 12,504 | $70.00 | $55.00 | $80.00 | $80.10 | $68.00 | $186.35 | $115.00 |
| 50 | Trench excavation protection (402-7001) | LF | 22,364 | $10.00 | $0.10 | $0.10 | $3.75 | $4.00 | $3.45 | $2.00 |
| 51 | Drilled shaft (traffic signal pole) (24 in) (416-7042) | LF | 108 | $219.00 | $248.71 | $230.00 | $254.00 | $249.00 | $124.17 | $250.00 |
| 52 | Drilled shaft (traffic signal pole) (36 in) (416-7044) | LF | 210 | $344.00 | $389.29 | $360.00 | $398.00 | $389.00 | $174.49 | $375.00 |
| 53 | Riprap (concrete)(CL B)(5 in) (432-7008) | CY | 882 | $650.00 | $550.00 | $1,375.00 | $457.00 | $594.00 | $477.25 | $450.00 |
| 54 | Concrete box culvert (5 FT X 5 FT) (462-7009) | LF | 931 | $700.00 | $575.00 | $780.00 | $645.00 | $752.00 | $864.25 | $800.00 |
| 55 | RC pipe (CL III)(15 in) (464-7002) | LF | 128 | $70.00 | $100.00 | $70.00 | $62.40 | $83.00 | $85.76 | $90.00 |
| 56 | RC pipe (CL III)(18 in) (464-7003) | LF | 6,065 | $100.00 | $80.00 | $105.00 | $67.85 | $83.00 | $59.92 | $100.00 |
| 57 | RC pipe (CL III)(24 in) (464-7005) | LF | 4,605 | $142.85 | $90.00 | $109.00 | $78.90 | $104.00 | $88.58 | $115.00 |
| 58 | RC pipe (CL III)(30 in) (464-7007) | LF | 2,599 | $199.76 | $120.00 | $120.00 | $103.00 | $121.00 | $101.53 | $150.00 |
| 59 | RC pipe (CL III)(36 in) (464-7009) | LF | 3,539 | $182.00 | $160.00 | $170.00 | $148.00 | $173.00 | $149.66 | $240.00 |
| 60 | RC pipe (CL III)(42 in) (464-7010) | LF | 2,366 | $215.87 | $208.00 | $220.00 | $199.00 | $229.00 | $197.92 | $275.00 |
| 61 | RC pipe (CL III)(48 in) (464-7011) | LF | 874 | $191.96 | $255.00 | $280.00 | $235.00 | $276.00 | $293.74 | $300.00 |
| 62 | RC pipe (CL III)(54 in) (464-7012) | LF | 417 | $230.28 | $285.00 | $310.00 | $266.00 | $427.00 | $292.72 | $350.00 |
| 63 | RC pipe (CL III)(60 in) (464-7013) | LF | 1,231 | $424.00 | $350.00 | $370.00 | $330.00 | $488.00 | $362.39 | $500.00 |
| 64 | RC pipe (CL IV)(24 in) (464-7021) | LF | 752 | $110.00 | $120.00 | $80.00 | $97.20 | $164.00 | $86.14 | $125.00 |
| 65 | RC pipe (CL IV)(36 in) (464-7024) | LF | 218 | $214.79 | $185.00 | $200.00 | $159.00 | $197.00 | $172.29 | $225.00 |
| 66 | RC pipe (CL IV)(42 in) (464-7025) | LF | 150 | $270.00 | $235.00 | $270.00 | $217.00 | $258.00 | $240.65 | $260.00 |
| 67 | RC pipe (CL IV)(48 in) (464-7026) | LF | 344 | $330.00 | $270.00 | $280.00 | $257.00 | $316.00 | $259.06 | $350.00 |
| 68 | RC pipe (CL IV)(60 in) (464-7028) | LF | 222 | $288.00 | $400.00 | $380.00 | $367.00 | $563.00 | $423.24 | $450.00 |
| 69 | Manh (complete)(PRM)(48IN) (465-7002) | EACH | 4 | $9,034.00 | $5,000.00 | $5,700.00 | $4,480.00 | $9,140.00 | $6,636.17 | $8,500.00 |
| 70 | Manh (complete)(PRM)(72IN) (465-7004) | EACH | 3 | $14,000 | $7,500.00 | $8,000.00 | $6,380.00 | $10,760 | $6,618.92 | $10,000 |
| 71 | Inlet (complete)(pco)(3FT)(left) (465-7014) | EACH | 18 | $4,773.00 | $5,500.00 | $7,000.00 | $4,950.00 | $5,250.00 | $6,935.17 | $10,500 |
| 72 | Inlet (complete)(pco)(3FT)(right) (465-7015) | EACH | 26 | $4,930.00 | $5,500.00 | $6,500.00 | $4,950.00 | $5,250.00 | $6,670.67 | $10,500 |
| 73 | Inlet (complete)(pco)(3FT)(both) (465-7016) | EACH | 8 | $5,356.00 | $6,500.00 | $8,500.00 | $5,820.00 | $6,130.00 | $8,095.83 | $11,000 |
| 74 | Inlet (complete)(pco)(4FT)(left) (465-7018) | EACH | 13 | $6,040.00 | $6,500.00 | $8,000.00 | $5,530.00 | $6,070.00 | $8,225.12 | $11,000 |
| 75 | Inlet (complete)(pco)(4FT)(right) (465-7019) | EACH | 7 | $5,720.00 | $6,700.00 | $8,300.00 | $5,940.00 | $6,500.00 | $9,497.16 | $11,500 |
| 76 | Inlet (complete)(pco)(4FT)(both) (465-7020) | EACH | 2 | $6,060.00 | $6,700.00 | $9,600.00 | $6,160.00 | $6,500.00 | $9,458.58 | $11,500 |
| 77 | Inlet (complete)(pco)(5FT)(left) (465-7022) | EACH | 4 | $9,110.00 | $8,300.00 | $10,400 | $7,130.00 | $7,630.00 | $11,098 | $12,500 |
| 78 | Inlet (complete)(pco)(5FT)(right) (465-7023) | EACH | 1 | $10,780 | $7,500.00 | $9,700.00 | $6,250.00 | $6,680.00 | $8,884.42 | $11,500 |
| 79 | Inlet (complete)(pco)(5FT)(both) (465-7024) | EACH | 2 | $9,360.00 | $9,000.00 | $11,000 | $8,210.00 | $8,390.00 | $10,850 | $13,000 |
| 80 | Inlet (complete)(pco)(6FT)(left) (465-7026) | EACH | 5 | $10,700 | $10,250 | $11,000 | $7,830.00 | $8,480.00 | $11,526 | $13,000 |
| 81 | Inlet (complete)(pco)(6FT)(right) (465-7027) | EACH | 4 | $10,700 | $10,250 | $11,200 | $7,910.00 | $8,580.00 | $13,266 | $13,000 |
| 82 | Inlet (complete)(pco)(6FT)(both) (465-7028) | EACH | 7 | $7,850.00 | $11,000 | $12,000 | $9,000.00 | $9,330.00 | $15,335 | $13,500 |
| 83 | Inlet (complete)(pcu)(3FT)(left) (465-7030) | EACH | 1 | $8,400.00 | $5,200.00 | $6,300.00 | $4,530.00 | $4,990.00 | $7,349.17 | $10,000 |
| 84 | Inlet (complete)(pcu)(3FT)(right) (465-7031) | EACH | 2 | $8,250.00 | $5,200.00 | $6,500.00 | $4,770.00 | $5,250.00 | $7,400.92 | $10,500 |
| 85 | Inlet (complete)(pcu)(3FT)(both) (465-7032) | EACH | 1 | $8,428.69 | $5,800.00 | $6,900.00 | $5,460.00 | $5,750.00 | $8,545.17 | $10,500 |
| 86 | Inlet (complete)(PSL)(RH)(5FTX5FT) (465-7066) | EACH | 7 | $11,509 | $8,000.00 | $10,200 | $6,860.00 | $7,560.00 | $8,872.92 | $12,000 |
| 87 | Inlet (complete)(PSL)(RH)(8FTX8FT) (465-7069) | EACH | 9 | $18,085 | $21,500 | $20,000 | $15,500 | $23,860 | $25,364 | $20,000 |
| 88 | Inlet (complete)(PSL)(FG)(3FTX3FT-3FTX3FT) (465-7126) | EACH | 8 | $7,000.00 | $4,400.00 | $9,200.00 | $3,470.00 | $4,160.00 | $6,514.44 | $8,500.00 |
| 89 | Inlet (complete)(PSL)(FG)(4FTX4FT-3FTX3FT) (465-7127) | EACH | 2 | $9,100.00 | $5,300.00 | $8,800.00 | $4,410.00 | $5,170.00 | $7,320.42 | $9,500.00 |
| 90 | Inlet (complete)(PSL)(FG)(3FTX5FT-3FTX3FT) (465-7129) | EACH | 2 | $8,000.00 | $4,800.00 | $9,000.00 | $4,050.00 | $4,610.00 | $6,250.92 | $9,000.00 |
| 91 | Wingwall (SW - 0) (HW=6 FT) (466-7205) | EACH | 1 | $16,000 | $24,000 | $23,800 | $9,830.00 | $28,230 | $9,987.42 | $15,800 |
| 92 | Set (type II) (15 in) (RCP) (6: 1) (P) (467-7300) | EACH | 8 | $2,013.00 | $1,250.00 | $1,100.00 | $1,070.00 | $1,320.00 | $1,872.04 | $2,800.00 |
| 93 | Set (type II) (18 in) (RCP) (4: 1) (C) (467-7306) | EACH | 2 | $1,400.00 | $1,500.00 | $1,200.00 | $944.00 | $1,190.00 | $2,470.59 | $3,500.00 |
| 94 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 44 | $1,200.00 | $1,200.00 | $1,500.00 | $1,220.00 | $1,320.00 | $2,317.75 | $2,800.00 |
| 95 | Jack bor or tun pipe(48 in)(RC)(CL IV) (476-7025) | LF | 216 | $1,500.00 | $1,200.00 | $1,620.00 | $1,390.00 | $1,310.00 | $1,501.02 | $1,050.00 |
| 96 | Adjusting manholes (479-7001) | EACH | 1 | $2,600.00 | $4,500.00 | $2,800.00 | $832.00 | $4,700.00 | $1,082.48 | $8,000.00 |
| 97 | Clean existing culverts (480-7001) | EACH | 1 | $2,500.00 | $1,500.00 | $2,600.00 | $2,700.00 | $3,260.00 | $3,835.44 | $7,500.00 |
| 98 | Pipe (PVC) (schedule 80) (14 in) (481-7031) | LF | 167 | $50.00 | $100.00 | $340.00 | $102.00 | $86.00 | $358.80 | $110.00 |
| 99 | Removing structure (inlet) (496-7002) | EACH | 25 | $1,200.00 | $750.00 | $950.00 | $679.00 | $734.00 | $465.37 | $1,500.00 |
| 100 | Removing structure (manhole) (496-7003) | EACH | 2 | $1,081.87 | $1,000.00 | $960.00 | $993.00 | $2,750.00 | $1,921.78 | $3,000.00 |
| 101 | Removing structure (set) (496-7004) | EACH | 101 | $280.00 | $300.00 | $700.00 | $253.00 | $362.00 | $796.34 | $750.00 |
| 102 | Removing structure (headwall) (496-7006) | EACH | 2 | $3,000.00 | $2,500.00 | $1,200.00 | $3,300.00 | $6,100.00 | $1,693.47 | $3,000.00 |
| 103 | Removing structure (pipe) (496-7007) | LF | 6,688 | $20.00 | $10.00 | $26.50 | $12.30 | $17.00 | $14.45 | $20.00 |
| 104 | Removing structure (pipe) (496-7037) | EACH | 1 | $640.00 | $2,500.00 | $850.00 | $1,230.00 | $5,130.00 | $1,483.14 | $3,000.00 |
| 105 | Mobilization (500-7001) | LS | 1 | $3,100,000 | $2,560,000 | $1,765,000 | $2,427,500 | $2,200,000 | $2,840,668 | $3,750,000 |
| 106 | Barricades, signs and traffic handling (502-7001) | MO | 40 | $5,000.00 | $2,000.00 | $4,700.00 | $1,750.00 | $850.00 | $6,392.09 | $10,000 |
| 107 | Portable changeable message sign (503-7002) | EACH | 6 | $10,024 | $100.00 | $6,869.72 | $5,760.00 | $65.00 | $5,175.00 | $35,000 |
| 108 | TMA (stationary) (505-7001) | DAY | 624 | $174.00 | $1.00 | $51.07 | $28.80 | $34.00 | $86.25 | $350.00 |
| 109 | TMA (mobile operation) (505-7003) | DAY | 1,248 | $230.00 | $1.00 | $0.01 | $57.60 | $64.00 | $201.25 | $100.00 |
| 110 | Rock filter dams (install) (type 2) (506-7002) | LF | 105 | $48.00 | $66.00 | $65.00 | $66.25 | $104.00 | $74.75 | $65.00 |
| 111 | Rock filter dams (remove) (506-7011) | LF | 105 | $20.00 | $64.50 | $40.00 | $22.70 | $46.00 | $23.00 | $17.00 |
| 112 | Construction exits (install) (type 2) (506-7021) | SY | 858 | $50.00 | $25.00 | $21.08 | $15.95 | $22.00 | $46.00 | $100.00 |
| 113 | Construction exits (remove) (506-7024) | SY | 858 | $10.50 | $1.00 | $13.97 | $9.00 | $8.00 | $17.25 | $20.00 |
| 114 | Sandbags for erosion control (6") (506-7036) | LF | 1,425 | $4.57 | $6.00 | $6.00 | $3.25 | $9.00 | $17.25 | $10.00 |
| 115 | Temporary sediment control fence (install) (506-7039) | LF | 15,002 | $4.00 | $3.00 | $3.85 | $2.90 | $5.00 | $5.18 | $5.25 |
| 116 | Temporary sediment control fence (remove) (506-7041) | LF | 15,002 | $1.20 | $0.50 | $1.25 | $1.05 | $1.00 | $1.50 | $1.00 |
| 117 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 2,045 | $6.00 | $3.00 | $5.85 | $3.25 | $8.00 | $9.20 | $10.00 |
| 118 | Biodegradable erosion control logs (remove) (506-7046) | LF | 3,470 | $1.30 | $0.10 | $1.25 | $1.00 | $1.00 | $1.15 | $1.00 |
| 119 | Constructing detours (508-7001) | SY | 3,522 | $80.00 | $35.00 | $37.19 | $42.30 | $46.00 | $69.00 | $65.00 |
| 120 | PCTB (fur&inst)(F-shape or SNGL SLP)type 1 (512-7089) | LF | 16,710 | $40.00 | $1.00 | $13.53 | $52.10 | $25.00 | $39.64 | $90.00 |
| 121 | PCTB (move)(F-shape or SNGL SLP)type 1 (512-7090) | LF | 12,270 | $6.00 | $1.00 | $7.31 | $4.30 | $9.00 | $6.80 | $9.00 |
| 122 | PCTB (remove)(F-shape or SNGL SLP)type 1 (512-7092) | LF | 16,710 | $12.00 | $1.00 | $8.15 | $6.00 | $12.00 | $10.41 | $30.00 |
| 123 | Landscape pavers (528-7001) | SY | 13,244 | $120.50 | $80.00 | $129.94 | $108.00 | $108.00 | $120.90 | $80.00 |
| 124 | Concrete C&G (valley gutter) (529-7019) | LF | 1,363 | $70.00 | $50.00 | $19.25 | $50.15 | $74.00 | $22.14 | $21.00 |
| 125 | Concrete curb & gutter (type B) (mountable) (529-7024) | LF | 27,693 | $17.00 | $15.00 | $16.75 | $17.30 | $18.00 | $19.26 | $18.50 |
| 126 | Concrete curb & gutter (type A) (barrier) (529-7025) | LF | 40 | $24.77 | $65.00 | $80.00 | $21.60 | $143.00 | $19.26 | $18.50 |
| 127 | Concrete curb (special) (529-7027) | LF | 27,246 | $20.00 | $8.00 | $9.93 | $14.35 | $17.00 | $29.04 | $30.00 |
| 128 | Driveways (concrete) (530-7006) | SY | 1,512 | $127.96 | $100.00 | $55.00 | $76.10 | $107.00 | $63.25 | $155.00 |
| 129 | Driveways (ACP) (530-7010) | SY | 1,757 | $60.00 | $60.00 | $79.07 | $39.65 | $37.00 | $109.25 | $60.00 |
| 130 | Concrete sidewalks (4") (531-7001) | SY | 17,128 | $69.89 | $35.00 | $46.38 | $46.05 | $58.00 | $53.34 | $50.00 |
| 131 | Curb ramps (type 1) (531-7005) | EACH | 14 | $3,000.00 | $1,800.00 | $2,650.00 | $1,620.00 | $2,000.00 | $3,047.50 | $3,000.00 |
| 132 | Curb ramps (type 2) (531-7006) | EACH | 12 | $2,500.00 | $1,800.00 | $2,650.00 | $1,790.00 | $1,979.00 | $3,047.50 | $3,000.00 |
| 133 | Curb ramps (type 5) (531-7008) | EACH | 3 | $3,500.00 | $2,250.00 | $3,100.00 | $1,990.00 | $3,050.00 | $3,565.00 | $3,500.00 |
| 134 | Curb ramps (type 7) (531-7010) | EACH | 28 | $2,000.00 | $1,800.00 | $2,450.00 | $1,880.00 | $1,950.00 | $2,817.50 | $2,500.00 |
| 135 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 57 | $1,509.00 | $500.00 | $1,525.00 | $1,200.00 | $1,620.00 | $794.75 | $685.00 |
| 136 | Crash cushion attenuator (remove) (545-7004) | EACH | 50 | $850.00 | $100.00 | $810.00 | $598.00 | $1,710.00 | $825.51 | $750.00 |
| 137 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 50 | $10,000 | $6,500.00 | $7,600.00 | $7,300.00 | $9,130.00 | $7,121.99 | $12,000 |
| 138 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 19 | $375.00 | $296.62 | $285.00 | $325.00 | $545.00 | $339.25 | $275.00 |
| 139 | Conduit (PVC) (schedule 40) (1") (618-7021) | LF | 25 | $17.26 | $6.00 | $5.55 | $6.15 | $6.00 | $11.50 | $6.00 |
| 140 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 250 | $8.00 | $19.46 | $18.00 | $19.85 | $19.00 | $12.65 | $20.00 |
| 141 | Conduit (PVC) (schedule 40) (4") (618-7040) | LF | 691 | $25.00 | $27.03 | $25.00 | $27.65 | $27.00 | $17.25 | $26.00 |
| 142 | Conduit (PVC) (schedule 80) (4") (bore) (618-7065) | LF | 1,503 | $40.00 | $35.69 | $33.00 | $36.45 | $36.00 | $34.50 | $36.00 |
| 143 | Electrical conductor (no.8) bare (620-7007) | LF | 2,173 | $1.74 | $1.95 | $1.80 | $2.00 | $2.00 | $3.52 | $2.00 |
| 144 | Electrical conductor (no.6) bare (620-7009) | LF | 120 | $2.00 | $2.16 | $2.00 | $2.20 | $2.00 | $3.68 | $2.20 |
| 145 | Electrical conductor (no.6) insulated (620-7010) | LF | 252 | $2.50 | $2.43 | $2.25 | $2.50 | $2.00 | $3.97 | $2.50 |
| 146 | Tray cable (4 conductor) (12 AWG) (621-7006) | LF | 3,585 | $3.50 | $2.92 | $2.70 | $3.00 | $3.00 | $4.31 | $3.00 |
| 147 | Ground box type A (122311)W/apron (624-7002) | EACH | 12 | $1,030.00 | $1,405.77 | $1,300.00 | $1,440.00 | $1,410.00 | $2,472.50 | $1,400.00 |
| 148 | Ground box type D (162922)W/apron (624-7008) | EACH | 2 | $1,500.00 | $1,838.32 | $1,700.00 | $1,880.00 | $1,840.00 | $2,472.50 | $1,800.00 |
| 149 | Zinc-coat steel wire strand (3/16") (625-7001) | LF | 2,170 | $4.00 | $3.03 | $2.80 | $3.10 | $3.00 | $4.07 | $3.00 |
| 150 | Zinc-coat steel wire strand (5/16") (625-7003) | LF | 6,492 | $5.00 | $3.03 | $2.80 | $3.10 | $3.00 | $4.31 | $3.00 |
| 151 | Zinc-coat steel wire strand (3/8") (625-7004) | LF | 590 | $3.40 | $4.22 | $3.90 | $4.30 | $4.00 | $4.53 | $4.25 |
| 152 | Remove electrical services (628-7002) | EACH | 3 | $1,000.00 | $454.17 | $420.00 | $464.00 | $454.00 | $2,300.00 | $450.00 |
| 153 | Elc SRV type T 120/240 000(NS)GS(L)TS(O) (628-7322) | EACH | 3 | $3,551.89 | $4,217.32 | $3,900.00 | $4,310.00 | $4,220.00 | $9,775.00 | $4,200.00 |
| 154 | Aluminum signs (type A) (636-7001) | SF | 187 | $35.00 | $25.13 | $65.15 | $33.15 | $18.00 | $50.03 | $45.00 |
| 155 | Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025) | EACH | 28 | $770.00 | $764.97 | $735.00 | $967.00 | $446.00 | $862.50 | $800.00 |
| 156 | Install small roadside sign support and assembly TYS80(1)SA(P-BM) (644-7026) | EACH | 27 | $950.00 | $733.74 | $705.00 | $1,135.00 | $535.00 | $977.50 | $900.00 |
| 157 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 10 | $957.00 | $889.86 | $855.00 | $1,050.00 | $446.00 | $1,150.00 | $900.00 |
| 158 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 5 | $1,114.00 | $1,150.05 | $1,105.00 | $1,437.00 | $554.00 | $1,437.50 | $1,000.00 |
| 159 | Remove SM RD SN sup&AM (644-7073) | EACH | 55 | $120.00 | $504.77 | $100.00 | $85.00 | $276.00 | $138.00 | $105.00 |
| 160 | Work zone pavement marking non-removing (W)6"(broken) (662-7005) | LF | 6,950 | $0.42 | $1.20 | $1.20 | $1.30 | $1.00 | $1.38 | $0.80 |
| 161 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 73,307 | $0.63 | $0.42 | $0.42 | $0.47 | $0.50 | $0.48 | $0.65 |
| 162 | Work zone pavement marking non-removing (W)8"(solid) (662-7012) | LF | 2,432 | $1.00 | $1.40 | $1.40 | $1.57 | $1.00 | $1.61 | $1.50 |
| 163 | Work zone pavement marking non-removing (W)24"(solid) (662-7017) | LF | 168 | $9.00 | $16.00 | $16.00 | $17.50 | $16.00 | $18.40 | $11.00 |
| 164 | Work zone pavement marking non-removing (W)(arrow) (662-7018) | EACH | 12 | $130.00 | $150.00 | $150.00 | $167.00 | $150.00 | $172.50 | $130.00 |
| 165 | Work zone pavement marking non-removing(W)(word) (662-7030) | EACH | 12 | $230.00 | $250.00 | $250.00 | $275.00 | $250.00 | $287.50 | $130.00 |
| 166 | Work zone pavement marking non-removing (Y)6"(broken) (662-7036) | LF | 4,020 | $0.32 | $0.78 | $0.78 | $0.87 | $0.75 | $0.90 | $0.80 |
| 167 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 82,141 | $0.50 | $0.42 | $0.42 | $0.45 | $0.50 | $0.48 | $0.70 |
| 168 | Work zone pavement marking removing (reflectorized) type I-C (662-7049) | EACH | 386 | $0.94 | $3.50 | $3.50 | $3.90 | $4.00 | $4.03 | $5.25 |
| 169 | Work zone pavement marking removing (reflectorized) type II-A-A (662-7051) | EACH | 1,975 | $3.50 | $3.50 | $3.50 | $3.90 | $4.00 | $4.03 | $5.25 |
| 170 | Work zone pavement marking removing (W)6"(DOT) (662-7066) | LF | 167 | $4.00 | $2.00 | $2.00 | $2.25 | $2.00 | $2.30 | $3.50 |
| 171 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 26 | $1.26 | $19.74 | $1.28 | $1.45 | $8.00 | $12.40 | $7.50 |
| 172 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 92 | $1.39 | $5.65 | $1.28 | $1.45 | $8.00 | $5.88 | $4.50 |
| 173 | Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009) | LF | 255 | $3.23 | $3.00 | $3.00 | $3.35 | $3.00 | $3.45 | $3.50 |
| 174 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 9,122 | $1.20 | $0.88 | $0.88 | $1.00 | $1.00 | $1.01 | $1.50 |
| 175 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 3,490 | $10.00 | $6.00 | $6.00 | $6.65 | $6.00 | $6.90 | $11.00 |
| 176 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 40 | $242.50 | $90.00 | $90.00 | $100.00 | $90.00 | $103.50 | $130.00 |
| 177 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 40 | $333.60 | $130.00 | $130.00 | $150.00 | $130.00 | $149.50 | $130.00 |
| 178 | Reflectorized pavement marking type I (Y)12"(solid)(100MIL) (666-7117) | LF | 2,351 | $4.00 | $1.20 | $1.20 | $1.35 | $1.00 | $1.38 | $5.25 |
| 179 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 13,122 | $0.91 | $0.84 | $0.84 | $0.95 | $0.75 | $0.97 | $0.80 |
| 180 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 31,773 | $1.50 | $0.72 | $0.72 | $0.83 | $0.75 | $0.83 | $0.75 |
| 181 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 43,790 | $0.63 | $0.72 | $0.72 | $0.83 | $0.75 | $0.83 | $0.75 |
| 182 | Reflectorized pavement marker type I-C (672-7002) | EACH | 459 | $6.00 | $7.50 | $7.50 | $8.30 | $8.00 | $8.63 | $5.00 |
| 183 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 1,500 | $6.00 | $5.00 | $5.00 | $5.55 | $5.00 | $5.75 | $5.00 |
| 184 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 657 | $6.00 | $5.00 | $5.00 | $5.55 | $5.00 | $5.75 | $5.00 |
| 185 | Eliminating existing PM & markers (4") (677-7001) | LF | 9,289 | $0.50 | $0.50 | $0.50 | $0.57 | $0.50 | $0.58 | $0.70 |
| 186 | Eliminating existing PM & markers (8") (677-7004) | LF | 100 | $1.00 | $0.85 | $0.85 | $1.00 | $0.75 | $0.98 | $2.00 |
| 187 | Eliminating existing PM & markers (12") (677-7006) | LF | 566 | $1.82 | $0.95 | $0.95 | $1.00 | $1.00 | $0.98 | $3.00 |
| 188 | Eliminating existing PM & markers (24") (677-7008) | LF | 102 | $4.25 | $3.00 | $3.00 | $3.35 | $3.00 | $3.45 | $8.00 |
| 189 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 1 | $100.00 | $50.00 | $50.00 | $100.00 | $50.00 | $57.50 | $105.00 |
| 190 | Eliminating existing PM & markers (word) (677-7015) | EACH | 1 | $200.00 | $50.00 | $50.00 | $100.00 | $50.00 | $57.50 | $105.00 |
| 191 | Install highway traffic signal (flash beacon) (680-7001) | EACH | 1 | $10,000 | $5,514.96 | $5,100.00 | $5,640.00 | $5,510.00 | $5,175.00 | $5,500.00 |
| 192 | Install highway traffic signal (isolated) (680-7002) | EACH | 3 | $30,000 | $24,655 | $22,800 | $25,200 | $24,660 | $25,530 | $25,000 |
| 193 | Removing traffic signals (680-7004) | EACH | 4 | $6,000.00 | $3,676.64 | $3,400.00 | $3,760.00 | $3,680.00 | $4,600.00 | $3,500.00 |
| 194 | Temporary traffic signals (681-7001) | EACH | 2 | $7,500.00 | $13,625 | $12,600 | $13,900 | $13,630 | $46,000 | $15,000 |
| 195 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 24 | $296.00 | $356.85 | $330.00 | $365.00 | $357.00 | $264.50 | $375.00 |
| 196 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 12 | $300.00 | $367.66 | $340.00 | $376.00 | $368.00 | $264.50 | $375.00 |
| 197 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 28 | $300.00 | $356.85 | $330.00 | $365.00 | $357.00 | $264.50 | $375.00 |
| 198 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 24 | $300.00 | $367.66 | $340.00 | $376.00 | $368.00 | $264.50 | $375.00 |
| 199 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 28 | $300.00 | $356.85 | $330.00 | $365.00 | $357.00 | $264.50 | $375.00 |
| 200 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 12 | $300.00 | $367.66 | $340.00 | $376.00 | $368.00 | $264.50 | $375.00 |
| 201 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 24 | $696.00 | $951.60 | $880.00 | $973.00 | $952.00 | $684.25 | $950.00 |
| 202 | Backplate W/reflectorized border(4 sec) (682-7037) | EACH | 12 | $320.00 | $140.58 | $130.00 | $144.00 | $141.00 | $231.92 | $150.00 |
| 203 | Backplate W/reflectorized border(3 sec) (682-7054) | EACH | 24 | $180.00 | $118.95 | $110.00 | $122.00 | $119.00 | $231.92 | $120.00 |
| 204 | Traffic signal CBL (type A)(12 AWG)(2 conductor) (684-7007) | LF | 4,745 | $2.11 | $1.95 | $1.80 | $2.00 | $2.00 | $2.89 | $2.00 |
| 205 | Traffic signal CBL (type A)(12 AWG)(5 conductor) (684-7010) | LF | 8,570 | $2.10 | $3.30 | $3.05 | $3.35 | $3.00 | $3.81 | $3.25 |
| 206 | Traffic signal CBL (type A)(12 AWG)(7 conductor) (684-7012) | LF | 3,225 | $3.30 | $4.38 | $4.05 | $4.50 | $4.00 | $4.55 | $4.25 |
| 207 | Ins traffic signal PL AM (S)STR(type D)lum (686-7020) | EACH | 14 | $11,000 | $10,273 | $9,500.00 | $10,500 | $10,270 | $8,943.71 | $10,500 |
| 208 | Pedestrian pole assembly (687-7001) | EACH | 18 | $2,635.00 | $1,297.64 | $1,200.00 | $1,330.00 | $1,300.00 | $1,150.00 | $1,300.00 |
| 209 | Pedestrian detect push button (APS) (688-7001) | EACH | 24 | $1,000.00 | $1,005.67 | $930.00 | $1,030.00 | $1,010.00 | $1,138.50 | $1,000.00 |
| 210 | Pedestrian detector controller unit (688-7003) | EACH | 3 | $3,500.00 | $3,784.77 | $3,500.00 | $3,870.00 | $3,780.00 | $7,072.50 | $3,800.00 |
| 211 | Removal of conduit (690-7001) | LF | 3,985 | $2.60 | $4.06 | $3.75 | $4.15 | $4.00 | $8.66 | $4.00 |
| 212 | Removal of ground boxes (690-7006) | EACH | 41 | $230.00 | $86.51 | $80.00 | $88.40 | $87.00 | $631.10 | $85.00 |
| 213 | Ditch cleaning and reshaping (foot) (760-7001) | LF | 3,190 | $10.00 | $7.50 | $10.00 | $12.45 | $7.00 | $9.20 | $8.00 |
| 214 | Bonding course (3007-7001) | GAL | 12,856 | $3.60 | $3.00 | $2.75 | $3.00 | $8.00 | $5.75 | $4.00 |
| 215 | Impermeable liner (5030-7001) | SY | 4,100 | $20.00 | $20.00 | $24.00 | $29.25 | $36.00 | $8.05 | $45.00 |
| 216 | RVDS (presence detection only) (6008-7001) | EACH | 12 | $7,900.00 | $4,866.14 | $4,500.00 | $4,970.00 | $4,870.00 | $10,710 | $5,000.00 |
| 217 | RVDS (advance detection only) (6008-7002) | EACH | 12 | $7,900.00 | $4,866.14 | $4,500.00 | $4,970.00 | $4,870.00 | $10,428 | $5,000.00 |
| 218 | Welded steel casing pipe (open cut)(24") (7003-7001) | LF | 140 | $173.00 | $325.00 | $78.00 | $179.00 | $418.00 | $312.40 | $300.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of May 6, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way