TxDOT contract A00065051 bid tabulation
Highway Improvement, FM 466 (At Eastwood Dr. to .). Let by Texas DOT on June 2, 2026, Guadalupe, San Antonio District. 7 bids received; low bid $2,728,902 by Hunter Industries, LTD., -8.5% against the engineer's estimate of $2,982,000.
- Owner
- Texas DOT
- Letting
- 02 JUN 2026
- Pay items
- 133
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Hunter Industries, LTD. | $2,728,902 | Low | -8.0% |
| 2 | D&S Concrete Contractors LLC | $2,760,043 | +1.0% | -7.0% |
| 3 | J3 Company, LLC | $3,089,270 | +13% | +4.0% |
| 4 | Acme Bridge Company, Inc. | $3,149,442 | +15% | +6.0% |
| 5 | STX Civil | $3,240,842 | +19% | +9.0% |
| 6 | Texas Materials Group, Inc. | $3,362,927 | +23% | +13% |
| 7 | E-Z Bel Construction, LLC | $3,492,121 | +28% | +17% |
Engineer's estimate: $2,982,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Hunter Industries, LTD. | 2. D&S Concrete Contractors LLC | 3. J3 Company, LLC | 4. Acme Bridge Company, Inc. | 5. STX Civil | 6. Texas Materials Group, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 25.15 | $4,200.00 | $732.56 | $1,000.00 | $4,400.00 | $2,000.00 | $1,248.13 | $2,600.00 |
| 2 | Preparation row (tree remove) (0"-12" diameter) (100-7003) | EACH | 4 | $396.00 | $2,750.00 | $150.00 | $1,500.00 | $1,220.00 | $1,424.27 | $1,150.00 |
| 3 | Removing concrete (riprap) (104-7006) | SY | 2 | $10.00 | $108.90 | $50.00 | $350.00 | $32.80 | $20.91 | $219.00 |
| 4 | Removing concrete (driveways) (104-7011) | SY | 345 | $12.50 | $16.50 | $40.00 | $30.00 | $22.10 | $18.28 | $33.00 |
| 5 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 389 | $9.00 | $16.50 | $40.00 | $22.00 | $19.60 | $5.65 | $32.00 |
| 6 | Removing concrete (curb & gutter) (104-7017) | LF | 508 | $10.00 | $9.90 | $5.00 | $6.00 | $9.00 | $5.74 | $12.00 |
| 7 | Removing concrete (miscellaneous) (104-7046) | SY | 21 | $26.00 | $29.70 | $40.00 | $150.00 | $87.20 | $28.63 | $85.00 |
| 8 | Excavation (roadway) (110-7001) | CY | 14,205 | $19.00 | $18.70 | $20.00 | $18.00 | $18.20 | $23.14 | $25.00 |
| 9 | Embankment (final)(DC)(type C1) (132-7008) | CY | 282 | $15.00 | $22.00 | $30.00 | $50.00 | $14.00 | $47.38 | $85.00 |
| 10 | Compost manuf topsoil (4") (161-7002) | SY | 6,572 | $1.00 | $2.26 | $1.00 | $8.00 | $4.00 | $1.84 | $3.80 |
| 11 | Block sodding (162-7002) | SY | 677 | $5.80 | $9.88 | $10.00 | $10.00 | $8.50 | $10.39 | $7.00 |
| 12 | Broadcast seed (permanent_urban_clay) (164-7004) | SY | 5,895 | $1.00 | $0.27 | $0.50 | $0.50 | $0.37 | $0.28 | $0.40 |
| 13 | Broadcast seed (temporary_warm_cool) (164-7007) | SY | 5,895 | $0.13 | $0.16 | $0.50 | $0.25 | $0.37 | $0.17 | $0.35 |
| 14 | Vegetative watering (168-7001) | TGL | 105 | $24.20 | $29.70 | $8.50 | $60.00 | $61.30 | $75.63 | $48.00 |
| 15 | Soil ret BLKT(SL_mod_clay_long_roll) (169-7010) | SY | 6,572 | $3.00 | $1.36 | $1.50 | $2.50 | $2.90 | $1.42 | $2.60 |
| 16 | FL BS(cip)(type D, GR 1-2 or 5)(final pos) (247-7192) | CY | 2,315 | $60.00 | $53.13 | $20.00 | $60.00 | $80.00 | $60.14 | $90.00 |
| 17 | Geogrid base reinforcement (type 2) (250-7002) | SY | 10,785 | $2.00 | $1.76 | $1.00 | $2.50 | $3.00 | $3.35 | $2.20 |
| 18 | Lime (com or QK)(slurry) (260-7005) | TON | 263 | $300.00 | $385.00 | $300.00 | $300.00 | $457.00 | $352.51 | $330.00 |
| 19 | Lime TRT (subgrade) (8") (260-7020) | SY | 10,785 | $2.00 | $4.40 | $4.00 | $6.50 | $3.35 | $3.82 | $6.15 |
| 20 | Prime coat(MC-30 or AE-P) (310-7013) | GAL | 1,888 | $3.20 | $5.06 | $5.00 | $3.50 | $3.70 | $4.15 | $5.00 |
| 21 | D-GR HMA type-B PG64-22 (341-7001) | TON | 1,533 | $75.04 | $89.10 | $190.00 | $100.00 | $100.00 | $112.75 | $100.00 |
| 22 | D-GR HMA type D PG76-22 (341-7056) | TON | 1,086 | $96.88 | $97.90 | $190.00 | $120.00 | $124.00 | $138.87 | $115.00 |
| 23 | D-GR HMA type D PG76-22 (level-UP) (341-7059) | TON | 118 | $96.88 | $110.00 | $200.00 | $140.00 | $111.00 | $124.62 | $137.00 |
| 24 | Tom-C PG76-22 sac-A (347-7001) | TON | 537 | $144.17 | $124.30 | $200.00 | $165.00 | $173.00 | $194.65 | $225.00 |
| 25 | Planing asphalt concrete pavement (2.5") (354-7082) | SY | 1,364 | $2.57 | $7.70 | $9.00 | $8.00 | $7.40 | $2.61 | $2.50 |
| 26 | Concrete pavement (CRCP) (7") (360-7001) | SY | 518 | $108.20 | $97.15 | $125.00 | $120.00 | $125.00 | $114.82 | $105.00 |
| 27 | Cut & restoring pavement (400-7006) | SY | 444 | $211.68 | $82.80 | $35.00 | $100.00 | $185.00 | $123.64 | $46.00 |
| 28 | Flowable backfill (401-7001) | CY | 563 | $416.00 | $231.83 | $140.00 | $180.00 | $255.00 | $199.37 | $220.00 |
| 29 | Trench excavation protection (402-7001) | LF | 1,123 | $7.00 | $27.60 | $1.00 | $10.00 | $9.50 | $5.24 | $25.00 |
| 30 | Drilled shaft (24 in) (416-7004) | LF | 6 | $310.00 | $209.99 | $200.00 | $300.00 | $423.00 | $474.76 | $350.00 |
| 31 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 104 | $240.00 | $241.49 | $300.00 | $350.00 | $243.00 | $332.33 | $230.00 |
| 32 | Class A concrete (channel lining) (420-7150) | CY | 98 | $1,050.00 | $674.08 | $750.00 | $550.00 | $746.00 | $998.37 | $642.00 |
| 33 | Riprap (concrete)(4 in) (432-7001) | CY | 31.20 | $575.00 | $787.43 | $900.00 | $750.00 | $571.00 | $603.06 | $750.00 |
| 34 | RC pipe (CL III)(18 in) (464-7003) | LF | 42 | $82.00 | $152.34 | $120.00 | $180.00 | $95.20 | $67.26 | $200.00 |
| 35 | RC pipe (CL III)(36 in) (464-7009) | LF | 1,095 | $170.00 | $229.62 | $220.00 | $200.00 | $150.00 | $153.97 | $280.00 |
| 36 | Manh (complete)(PRM)(48IN) (465-7002) | EACH | 2 | $6,031.00 | $6,816.88 | $4,000.00 | $7,000.00 | $9,930.00 | $10,375 | $8,800.00 |
| 37 | Manh (complete)(PRM)(60IN) (465-7003) | EACH | 1 | $10,234 | $9,642.99 | $5,000.00 | $8,500.00 | $10,400 | $9,908.12 | $13,000 |
| 38 | Manh (complete)(PRM)(72IN) (465-7004) | EACH | 1 | $11,565 | $11,383 | $6,200.00 | $10,500 | $13,100 | $11,769 | $14,000 |
| 39 | Junction box(complete)(PJB)(5FTX5FT) (465-7009) | EACH | 1 | $6,601.00 | $8,847.88 | $4,000.00 | $10,000 | $10,400 | $10,885 | $12,750 |
| 40 | Inlet (complete)(pco)(3FT)(both) (465-7016) | EACH | 1 | $6,933.00 | $7,217.46 | $5,000.00 | $10,000 | $7,610.00 | $9,160.02 | $8,200.00 |
| 41 | Inlet (complete)(pco)(4FT)(both) (465-7020) | EACH | 4 | $5,286.00 | $11,260 | $7,000.00 | $10,500 | $10,400 | $10,545 | $8,900.00 |
| 42 | Inlet (complete)(PSL)(FG)(3FTX3FT-3FTX3FT) (465-7126) | EACH | 1 | $5,413.00 | $6,229.58 | $4,000.00 | $7,000.00 | $6,550.00 | $8,973.27 | $7,700.00 |
| 43 | Inlet (complete)(PSL)(FG)(4FTX4FT-4FTX4FT) (465-7128) | EACH | 3 | $5,922.00 | $8,058.83 | $5,500.00 | $8,000.00 | $8,210.00 | $9,288.35 | $8,600.00 |
| 44 | Inlet (complete)(armor curb slot) (465-7335) | EACH | 4 | $6,817.25 | $4,414.69 | $2,500.00 | $7,500.00 | $7,500.00 | $6,471.47 | $9,150.00 |
| 45 | Inlet (comp)(type sidewalk bridge) (465-7336) | EACH | 1 | $13,993 | $15,466 | $2,500.00 | $18,000 | $21,700 | $16,879 | $26,500 |
| 46 | Set (type II) (18 in) (RCP) (4: 1) (C) (467-7306) | EACH | 1 | $1,494.00 | $2,539.08 | $2,500.00 | $3,600.00 | $2,110.00 | $2,102.32 | $2,640.00 |
| 47 | Removing structure (inlet) (496-7002) | EACH | 3 | $466.00 | $1,324.74 | $300.00 | $2,000.00 | $625.00 | $1,398.37 | $1,100.00 |
| 48 | Removing structure (set) (496-7004) | EACH | 4 | $534.00 | $717.57 | $250.00 | $1,200.00 | $547.00 | $307.45 | $350.00 |
| 49 | Removing structure (pipe) (496-7007) | LF | 781 | $20.00 | $33.12 | $5.00 | $32.00 | $18.60 | $24.86 | $50.00 |
| 50 | Mobilization (500-7001) | LS | 1 | $271,091 | $109,131 | $200,000 | $275,000 | $284,000 | $253,891 | $334,000 |
| 51 | Barricades, signs and traffic handling (502-7001) | MO | 11 | $9,440.00 | $6,597.36 | $2,000.00 | $6,500.00 | $5,000.00 | $3,263.41 | $5,000.00 |
| 52 | Portable changeable message sign (503-7002) | EACH | 3 | $2,285.00 | $3,831.03 | $5,000.00 | $3,000.00 | $7,500.00 | $7,945.21 | $13,000 |
| 53 | TMA (stationary) (505-7001) | DAY | 64 | $139.00 | $136.82 | $100.00 | $140.00 | $2.50 | $165.03 | $50.00 |
| 54 | TMA (mobile operation) (505-7003) | DAY | 30 | $144.00 | $328.37 | $200.00 | $1,000.00 | $21.30 | $200.04 | $300.00 |
| 55 | Rock filter dams (install) (type 2) (506-7002) | LF | 22 | $40.27 | $53.09 | $50.00 | $50.00 | $68.70 | $55.78 | $95.00 |
| 56 | Rock filter dams (remove) (506-7011) | LF | 22 | $11.00 | $36.71 | $20.00 | $40.00 | $31.70 | $38.57 | $25.00 |
| 57 | Construction exits (install) (type 1) (506-7020) | SY | 312 | $25.00 | $44.75 | $40.00 | $25.00 | $26.40 | $47.02 | $25.00 |
| 58 | Construction exits (remove) (506-7024) | SY | 312 | $10.86 | $11.01 | $1.00 | $15.00 | $15.90 | $11.57 | $5.00 |
| 59 | FRNT end loader work (ersn & sedm cont) (506-7031) | HR | 80 | $100.00 | $110.00 | $20.00 | $120.00 | $121.00 | $65.02 | $126.00 |
| 60 | Temporary sediment control fence (install) (506-7039) | LF | 1,565 | $3.50 | $3.39 | $5.00 | $4.00 | $5.30 | $3.56 | $5.00 |
| 61 | Temporary sediment control fence (remove) (506-7041) | LF | 1,565 | $0.92 | $1.13 | $0.50 | $1.50 | $1.30 | $1.19 | $1.25 |
| 62 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 363 | $5.52 | $4.18 | $3.00 | $4.00 | $6.30 | $4.39 | $8.00 |
| 63 | Biodegradable erosion control logs (remove) (506-7046) | LF | 363 | $1.15 | $1.02 | $2.00 | $1.50 | $2.10 | $1.07 | $1.25 |
| 64 | One-way traffic control (flagger cont) (510-7001) | HR | 540 | $84.00 | $77.00 | $20.00 | $40.00 | $186.00 | $143.30 | $66.00 |
| 65 | Landscape pavers (528-7001) | SY | 762 | $128.74 | $94.50 | $112.00 | $95.00 | $125.00 | $59.34 | $90.00 |
| 66 | Concrete curb (type I) (529-7001) | LF | 3,966 | $14.00 | $14.70 | $25.00 | $16.00 | $15.90 | $47.48 | $14.00 |
| 67 | Concrete curb & gutter (type I) (529-7008) | LF | 331 | $25.06 | $46.20 | $25.00 | $28.00 | $31.70 | $47.48 | $44.00 |
| 68 | Concrete curb & gutter (type II) (529-7009) | LF | 450 | $29.46 | $46.20 | $25.00 | $32.00 | $33.80 | $53.41 | $44.00 |
| 69 | Intersections (concrete) (530-7001) | SY | 21 | $153.51 | $205.79 | $110.00 | $250.00 | $95.10 | $166.16 | $196.00 |
| 70 | Driveways (concrete) (530-7006) | SY | 668 | $101.00 | $120.75 | $100.00 | $90.00 | $95.10 | $77.15 | $115.00 |
| 71 | Concrete sidewalks (4") (531-7001) | SY | 505 | $65.00 | $82.95 | $100.00 | $60.00 | $84.50 | $77.74 | $79.00 |
| 72 | Concrete sidewalks (6") (531-7003) | SY | 704 | $44.11 | $95.55 | $110.00 | $70.00 | $105.00 | $91.98 | $91.00 |
| 73 | Curb ramps (type 2) (531-7006) | EACH | 3 | $2,500.00 | $2,263.74 | $1,200.00 | $1,500.00 | $2,320.00 | $2,789.20 | $2,156.00 |
| 74 | Curb ramps (type 10) (531-7011) | EACH | 2 | $3,100.00 | $2,263.74 | $1,200.00 | $1,500.00 | $2,320.00 | $4,450.84 | $2,156.00 |
| 75 | Curb ramps (type 21) (531-7013) | EACH | 2 | $3,098.00 | $2,551.43 | $1,200.00 | $1,800.00 | $2,320.00 | $4,462.71 | $2,430.00 |
| 76 | Curb ramps (type 7) (sup) (531-7032) | EACH | 1 | $3,100.00 | $2,673.23 | $1,200.00 | $1,500.00 | $2,430.00 | $4,617.01 | $2,546.00 |
| 77 | Curb ramps (type 1) (sup) (531-7033) | EACH | 2 | $2,500.00 | $2,468.48 | $1,200.00 | $1,500.00 | $2,430.00 | $2,967.23 | $2,351.00 |
| 78 | Curb ramps (type 2) (sup) (531-7034) | EACH | 1 | $3,100.00 | $2,673.23 | $1,200.00 | $1,500.00 | $2,430.00 | $3,323.28 | $2,546.00 |
| 79 | Remove metal beam guard fence (542-7001) | LF | 256 | $2.30 | $1.73 | $5.00 | $5.00 | $1.60 | $4.45 | $6.84 |
| 80 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 8 | $305.12 | $288.74 | $200.00 | $400.00 | $370.00 | $415.41 | $290.00 |
| 81 | In RD IL (type SA) 40T-8 (250W EQ) LED (610-7124) | EACH | 10 | $4,500.00 | $5,249.86 | $5,100.00 | $5,500.00 | $5,280.00 | $6,171.83 | $5,000.00 |
| 82 | In RD IL (type SA) 40T-8-8 (250W EQ) LED (610-7125) | EACH | 3 | $6,600.00 | $6,824.81 | $5,800.00 | $7,000.00 | $6,870.00 | $7,358.72 | $6,500.00 |
| 83 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 1,370 | $9.00 | $13.65 | $10.50 | $25.00 | $13.70 | $13.06 | $13.00 |
| 84 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 445 | $25.90 | $21.00 | $34.00 | $35.00 | $21.10 | $37.98 | $20.00 |
| 85 | Electrical conductor (no.8) bare (620-7007) | LF | 1,930 | $2.00 | $1.68 | $2.00 | $2.50 | $1.70 | $2.37 | $1.60 |
| 86 | Electrical conductor (no.8) insulated (620-7008) | LF | 4,160 | $2.00 | $1.84 | $1.80 | $2.50 | $1.85 | $2.37 | $1.75 |
| 87 | Ground box type A (122311) (624-7001) | EACH | 1 | $1,178.00 | $944.97 | $1,000.00 | $1,100.00 | $951.00 | $1,175.03 | $900.00 |
| 88 | Ground box type A (122311)W/apron (624-7002) | EACH | 5 | $1,442.00 | $1,023.72 | $1,250.00 | $1,400.00 | $1,030.00 | $1,542.96 | $975.00 |
| 89 | Elc SRV type A 120/240 060(NS)SS(E)SP(O) (628-7009) | EACH | 1 | $9,700.00 | $7,349.80 | $5,500.00 | $11,000 | $7,400.00 | $10,326 | $7,000.00 |
| 90 | Aluminum signs (type A) (636-7001) | SF | 11 | $48.00 | $26.25 | $25.00 | $110.00 | $103.00 | $59.35 | $50.00 |
| 91 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 24 | $597.00 | $701.12 | $130.00 | $840.00 | $793.00 | $890.17 | $675.00 |
| 92 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 11 | $790.00 | $787.48 | $130.00 | $1,100.00 | $1,010.00 | $1,139.42 | $740.00 |
| 93 | Install small roadside sign support and assembly type 10BWG(1)SA(T-2EXT) (644-7005) | EACH | 1 | $800.00 | $892.48 | $750.00 | $1,000.00 | $916.00 | $1,029.04 | $765.00 |
| 94 | Remove SM RD SN sup&AM (644-7073) | EACH | 28 | $132.00 | $52.50 | $50.00 | $50.00 | $79.30 | $89.02 | $100.00 |
| 95 | Remove SM RD SN sup&AM (sign only) (644-7075) | EACH | 2 | $130.00 | $26.25 | $25.00 | $25.00 | $40.20 | $45.11 | $50.00 |
| 96 | Remove delin & object marker assms (658-7078) | EACH | 10 | $25.00 | $5.25 | $25.00 | $5.00 | $23.30 | $21.02 | $15.00 |
| 97 | Install object marker assembly (OM-2Z)(WFLX)GNDLL (658-7248) | EACH | 5 | $130.00 | $94.50 | $110.00 | $90.00 | $116.00 | $130.56 | $45.00 |
| 98 | Install object marker assembly (OM-2Z)(WFLX)SRFLL (658-7256) | EACH | 5 | $130.00 | $94.50 | $97.00 | $90.00 | $100.00 | $112.75 | $50.00 |
| 99 | Install OM SM RD sign (1-OM-PW)Y (658-7317) | EACH | 30 | $11.00 | $52.50 | $400.00 | $50.00 | $33.80 | $37.98 | $15.00 |
| 100 | Install OM SM RD sign (1-OM-PW)R (658-7318) | EACH | 7 | $11.00 | $52.50 | $400.00 | $50.00 | $33.80 | $37.98 | $15.00 |
| 101 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 506 | $0.82 | $1.72 | $4.62 | $3.00 | $1.90 | $0.90 | $1.75 |
| 102 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 282 | $0.53 | $1.72 | $4.63 | $3.00 | $1.90 | $0.90 | $1.75 |
| 103 | Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009) | LF | 117 | $1.27 | $0.89 | $2.00 | $3.60 | $0.90 | $1.01 | $2.20 |
| 104 | Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018) | LF | 58 | $1.33 | $1.26 | $3.00 | $3.80 | $1.25 | $1.42 | $3.50 |
| 105 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 594 | $1.00 | $1.26 | $1.00 | $1.50 | $1.25 | $1.42 | $2.10 |
| 106 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 724 | $7.70 | $9.45 | $6.75 | $8.35 | $9.50 | $10.68 | $7.75 |
| 107 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 4 | $140.00 | $208.94 | $200.00 | $165.00 | $210.00 | $236.19 | $115.00 |
| 108 | Reflectorized pavement marking type I(W)(double arrow)(100MIL) (666-7045) | EACH | 6 | $250.00 | $288.74 | $300.00 | $205.00 | $291.00 | $326.40 | $140.00 |
| 109 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 4 | $175.00 | $225.74 | $200.00 | $205.00 | $227.00 | $255.18 | $130.00 |
| 110 | Ref pavement marking type I(W)18"(yld tri)(100MIL) (666-7087) | EACH | 25 | $40.00 | $52.50 | $35.00 | $62.00 | $52.80 | $59.34 | $35.00 |
| 111 | Reflectorized pavement marking type I (Y)24"(solid)(100MIL) (666-7123) | LF | 436 | $7.65 | $9.45 | $12.00 | $8.35 | $9.50 | $10.68 | $11.40 |
| 112 | Pavement sler 6" (666-7347) | LF | 8,722 | $0.20 | $0.37 | $0.50 | $0.33 | $0.37 | $0.42 | $0.61 |
| 113 | Pavement sler 8" (666-7348) | LF | 652 | $0.40 | $0.50 | $0.50 | $0.75 | $0.51 | $0.57 | $1.40 |
| 114 | Pavement sler 24" (666-7352) | LF | 1,160 | $2.00 | $1.26 | $3.00 | $5.22 | $1.25 | $1.42 | $1.60 |
| 115 | Pavement sler (arrow) (666-7353) | EACH | 6 | $80.00 | $26.25 | $100.00 | $90.00 | $26.40 | $29.67 | $50.00 |
| 116 | Pavement sler (word) (666-7354) | EACH | 4 | $76.00 | $26.25 | $100.00 | $105.00 | $26.40 | $29.67 | $60.00 |
| 117 | Pavement sler (double arrow) (666-7356) | EACH | 6 | $74.00 | $26.25 | $150.00 | $105.00 | $26.40 | $29.67 | $65.00 |
| 118 | Pavement sler (yld tri) (666-7365) | EACH | 25 | $32.00 | $26.25 | $25.00 | $40.00 | $26.40 | $29.67 | $15.00 |
| 119 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 3,981 | $0.50 | $0.84 | $1.00 | $0.85 | $0.85 | $0.95 | $1.00 |
| 120 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 4,624 | $0.55 | $0.84 | $1.00 | $0.85 | $0.85 | $0.95 | $1.00 |
| 121 | Prefabricated PM type B (W)(LN RDCT arrow) (668-7029) | EACH | 2 | $350.00 | $367.49 | $1,000.00 | $460.00 | $370.00 | $415.42 | $450.00 |
| 122 | Reflectorized pavement marker type I-C (672-7002) | EACH | 144 | $3.80 | $6.30 | $5.50 | $6.50 | $6.30 | $7.12 | $5.85 |
| 123 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 163 | $3.80 | $6.30 | $5.50 | $6.50 | $6.30 | $7.12 | $5.85 |
| 124 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 2 | $320.00 | $278.24 | $225.00 | $500.00 | $280.00 | $166.17 | $265.00 |
| 125 | Install RDSD FLSH BCN assembly (solar PWRD) (685-7004) | EACH | 1 | $7,900.00 | $7,349.80 | $4,900.00 | $7,500.00 | $7,400.00 | $9,020.36 | $7,000.00 |
| 126 | Removing RDSD FLSH BCN AM (solar PWRD) (685-7006) | EACH | 1 | $1,400.00 | $524.99 | $300.00 | $750.00 | $528.00 | $379.80 | $500.00 |
| 127 | Strip mowing (730-7018) | CYC | 4 | $4,350.00 | $850.00 | $200.00 | $1,250.00 | $1,740.00 | $4,226.74 | $1,500.00 |
| 128 | Litter removal (734-7002) | CYC | 11 | $3,000.00 | $1,250.00 | $50.00 | $1,700.00 | $1,910.00 | $2,206.74 | $500.00 |
| 129 | Litter removal (spot) (734-7003) | ACRE | 4.91 | $50.00 | $450.00 | $75.00 | $1,500.00 | $446.00 | $11.04 | $500.00 |
| 130 | Debris removing-CNTR med/MN LNS/ramps (735-7002) | CYC | 11 | $2,000.00 | $850.00 | $100.00 | $1,700.00 | $1,910.00 | $5,664.27 | $500.00 |
| 131 | Debris removal (spot debris) (735-7072) | MI | 0.15 | $1,387.30 | $5,000.00 | $3,000.00 | $5,000.00 | $14,801 | $155.87 | $5,000.00 |
| 132 | Underseal course (3006-7001) | GAL | 273 | $3.20 | $4.62 | $4.00 | $4.00 | $4.25 | $4.75 | $4.00 |
| 133 | Bonding course (3007-7001) | GAL | 3,647 | $3.20 | $3.30 | $3.00 | $5.00 | $3.15 | $3.56 | $4.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of June 2, 2026. Compiled by Mirage Metrics.