TxDOT contract A00185350 bid tabulation
Construct Pedestrian Infrastructure, Various (Various Locations in Kingsville to .). Let by Texas DOT on May 7, 2026, Kleberg, Corpus Christi District. 8 bids received; low bid $1,171,489 by 3LW Civil LLC, -18% against the engineer's estimate of $1,426,805.
- Owner
- Texas DOT
- Letting
- 07 MAY 2026
- Pay items
- 39
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | 3LW Civil LLC | $1,171,489 | Low | -18% |
| 2 | Garret Shields Infrastructure | $1,185,319 | +1.0% | -17% |
| 3 | Lucania Contractors LLC | $1,271,429 | +9.0% | -11% |
| 4 | Ti-Zack Concrete, LLC | $1,301,352 | +11% | -9.0% |
| 5 | Icos Management, LLC | $1,392,339 | +19% | -2.0% |
| 6 | STX Civil | $1,433,105 | +22% | 0.0% |
| 7 | Artillery L.L.C. | $1,840,850 | +57% | +29% |
| 8 | O. Trevino Construction, LLC | $2,235,893 | +91% | +57% |
Engineer's estimate: $1,426,805.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. 3LW Civil LLC | 2. Garret Shields Infrastructure | 3. Lucania Contractors LLC | 4. Ti-Zack Concrete, LLC | 5. Icos Management, LLC | 6. STX Civil |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (driveways) (104-7011) | SY | 264 | $38.00 | $30.00 | $20.00 | $20.00 | $30.23 | $7.35 | $15.65 |
| 2 | Removing concrete (curb & gutter) (104-7017) | LF | 1,085 | $31.00 | $12.00 | $10.00 | $8.00 | $7.35 | $3.15 | $10.67 |
| 3 | Furn & place topsoil (4") (160-7002) | SY | 1,645 | $10.00 | $4.25 | $4.00 | $7.00 | $10.40 | $12.60 | $1.84 |
| 4 | Block sodding (162-7002) | SY | 1,645 | $7.00 | $8.50 | $8.00 | $13.75 | $5.00 | $7.35 | $6.54 |
| 5 | Vegetative watering (168-7001) | TGL | 27 | $300.00 | $150.00 | $20.00 | $10.00 | $1.00 | $42.00 | $44.87 |
| 6 | Trench excavation protection (402-7001) | LF | 659 | $25.00 | $20.00 | $1.00 | $5.00 | $10.00 | $5.25 | $5.06 |
| 7 | RC pipe (CL III)(24 in) (464-7005) | LF | 659 | $215.00 | $88.48 | $120.00 | $140.00 | $126.22 | $126.00 | $137.85 |
| 8 | Inlet (complete)(pco)(3FT)(both) (465-7016) | EACH | 5 | $6,000.00 | $8,659.30 | $5,000.00 | $8,000.00 | $5,985.00 | $7,350.00 | $9,971.87 |
| 9 | Mobilization (500-7001) | LS | 1 | $102,000 | $117,000 | $100,000 | $93,000 | $122,976 | $69,750 | $117,122 |
| 10 | Barricades, signs and traffic handling (502-7001) | MO | 8 | $3,000.00 | $8,282.07 | $5,000.00 | $1,700.00 | $3,200.00 | $1.00 | $4,987.03 |
| 11 | Portable changeable message sign (503-7001) | DAY | 56 | $200.00 | $0.10 | $1.00 | $300.00 | $1.00 | $262.50 | $87.32 |
| 12 | TMA (stationary) (505-7001) | DAY | 180 | $80.00 | $0.10 | $300.00 | $300.00 | $1.00 | $262.50 | $167.74 |
| 13 | Biodegradable erosion control logs (install) (6") (506-7042) | LF | 880 | $5.00 | $0.10 | $5.00 | $7.00 | $0.10 | $8.40 | $8.03 |
| 14 | Biodegradable erosion control logs (remove) (506-7046) | LF | 880 | $2.00 | $0.10 | $1.00 | $2.00 | $0.10 | $2.10 | $0.05 |
| 15 | Concrete curb & gutter (type II) (529-7009) | LF | 2,979 | $55.00 | $42.00 | $20.00 | $38.00 | $47.14 | $42.00 | $58.87 |
| 16 | Driveways (concrete) (530-7006) | SY | 514 | $130.00 | $110.34 | $100.00 | $90.00 | $104.87 | $210.00 | $132.87 |
| 17 | Concrete sidewalks (6") (531-7003) | SY | 5,876 | $80.00 | $76.27 | $80.00 | $85.00 | $90.40 | $78.75 | $99.80 |
| 18 | Curb ramps (type 2) (531-7006) | EACH | 3 | $3,000.00 | $1,720.31 | $2,500.00 | $2,000.00 | $2,365.18 | $3,990.00 | $2,107.52 |
| 19 | Curb ramps (type 3) (531-7007) | EACH | 11 | $2,800.00 | $1,720.31 | $2,500.00 | $2,000.00 | $2,365.18 | $3,990.00 | $2,107.52 |
| 20 | Curb ramps (type 5) (531-7008) | EACH | 1 | $3,500.00 | $1,720.31 | $2,500.00 | $2,000.00 | $2,365.18 | $3,990.00 | $2,107.52 |
| 21 | Curb ramps (type 6) (531-7009) | EACH | 1 | $3,500.00 | $1,720.31 | $2,500.00 | $2,000.00 | $2,365.18 | $3,990.00 | $2,107.52 |
| 22 | Curb ramps (type 7) (531-7010) | EACH | 49 | $2,500.00 | $1,577.04 | $2,500.00 | $2,000.00 | $2,365.18 | $3,675.00 | $2,107.52 |
| 23 | Curb ramps (type 10) (531-7011) | EACH | 3 | $3,000.00 | $1,720.31 | $2,500.00 | $2,000.00 | $2,365.18 | $4,200.00 | $2,107.52 |
| 24 | Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025) | EACH | 40 | $500.00 | $693.00 | $500.00 | $700.00 | $715.00 | $945.00 | $684.25 |
| 25 | Install small roadside sign support and assembly (inst sign only) (644-7064) | EACH | 56 | $250.00 | $115.50 | $300.00 | $130.00 | $80.00 | $157.50 | $126.87 |
| 26 | Relocate SM RD SN sup&AM type S80 (644-7067) | EACH | 16 | $400.00 | $693.00 | $300.00 | $750.00 | $350.00 | $840.00 | $697.14 |
| 27 | Remove SM RD SN sup&AM (644-7073) | EACH | 17 | $150.00 | $93.50 | $100.00 | $100.00 | $151.50 | $105.00 | $90.07 |
| 28 | Reflectorized pavement marking type I (W)6"(DOT)(090MIL) (666-7008) | LF | 923 | $1.00 | $2.20 | $2.50 | $2.50 | $0.75 | $0.97 | $2.00 |
| 29 | Reflectorized pavement marking type I (W)24"(solid)(090MIL) (666-7035) | LF | 1,495 | $5.00 | $8.25 | $8.00 | $9.50 | $9.50 | $10.80 | $7.50 |
| 30 | Reflectorized pavement marking type I (W)(bike arrow)(090MIL) (666-7092) | EACH | 15 | $240.00 | $82.50 | $90.00 | $94.00 | $150.00 | $172.80 | $75.00 |
| 31 | Reflectorized pavement marking type I(W)(bike syml)(090MIL) (666-7098) | EACH | 15 | $270.00 | $176.00 | $180.00 | $200.00 | $175.00 | $168.00 | $160.00 |
| 32 | Pavement sler 6" (666-7347) | LF | 20,439 | $2.00 | $0.35 | $0.50 | $0.40 | $0.45 | $0.63 | $0.32 |
| 33 | Pavement sler 24" (666-7352) | LF | 1,495 | $4.00 | $0.97 | $1.00 | $1.10 | $3.25 | $4.20 | $0.88 |
| 34 | Pavement sler (bike arrow) (666-7368) | EACH | 15 | $5.00 | $38.50 | $40.00 | $43.75 | $35.00 | $42.00 | $35.00 |
| 35 | Pavement sler (bike symbol) (666-7369) | EACH | 15 | $5.00 | $38.50 | $40.00 | $43.75 | $40.00 | $52.50 | $35.00 |
| 36 | Reflectorized pavement marking type I (W)6"(solid)(090MIL) (666-7410) | LF | 6,821 | $0.60 | $0.75 | $0.75 | $0.85 | $0.75 | $1.10 | $0.68 |
| 37 | Reflectorized pavement marking type I (Y)6"(solid)(090MIL) (666-7422) | LF | 12,695 | $0.50 | $0.28 | $0.60 | $0.65 | $0.75 | $1.05 | $0.52 |
| 38 | Eliminating existing PM & markers (24") (677-7008) | LF | 631 | $2.00 | $1.65 | $1.60 | $1.88 | $5.00 | $6.30 | $1.50 |
| 39 | Tree removal (4" - 12" diameter) (752-7005) | EACH | 11 | $400.00 | $250.00 | $500.00 | $1,000.00 | $1,000.00 | $650.00 | $82.67 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of May 7, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.