Construct Ramps, Various (Various Locations in to the Lubbock District). Let by Texas DOT on July 2, 2025, Lubbock, Lubbock District. 3 bids received; low bid $2,978,481 by STX Civil, -14% against the engineer's estimate of $3,454,533.

Owner
Texas DOT
Letting
02 JUL 2025
Pay items
63
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1STX Civil$2,978,481Low-14%
2Ti-Zack Concrete, LLC$3,063,718+3.0%-11%
3Gilvin-Terrill, LTD.$4,276,263+44%+24%
TxDOT contract A00195963: bids by rank

Engineer's estimate: $3,454,533.

Bid tabulation

LinePay itemUnitQuantityEstimate1. STX Civil2. Ti-Zack Concrete, LLC3. Gilvin-Terrill, LTD.
1Preparing row (100-7002)STA2$2,100.00$2,900.00$1,100.00$5,000.00
2Removing concrete (pavement) (104-7001)SY74$16.52$45.00$32.35$60.00
3Removing concrete (driveways) (104-7011)SY3,724$27.15$10.00$32.14$60.00
4Removing concrete (sidewalk, ramp or shared use path) (104-7013)SY240$39.67$20.00$33.25$60.00
5Removing concrete (curb & gutter) (104-7017)LF46$27.56$1.00$34.70$60.00
6Remove (6"-10") TRT/untrt base & asphalt pavement (105-7006)SY1,245$20.00$10.00$32.05$60.00
7Backfill (type A)(vehicle) (134-7005)CY250$32.00$50.00$31.92$100.00
8Block sodding (162-7002)SY5,200$11.32$6.50$6.60$20.00
9Fertilizer (166-7001)ACRE1.20$1,082.67$2,200.00$27.50$3,000.00
10Vegetative watering (168-7001)TGL128.50$163.27$10.00$27.50$60.00
11Rdside amenity (ADA parking sign) (194-7006)EACH2$250.00$500.00$495.00$900.00
12D-GR HMA type-B PG70-28 (341-7009)TON25$227.50$350.00$330.00$700.00
13Struct excavation (400-7001)CY59$35.00$50.00$88.00$100.00
14Cut & restore concrete paving (400-7007)SY494$285.00$160.00$119.47$250.00
15Cut & restore asphalt paving (400-7008)SY359$177.81$230.00$99.00$250.00
16Riprap (concrete)(5 in) (432-7002)CY143$487.50$600.00$818.24$1,000.00
17Rail (handrail)(type A) (450-7058)LF24$101.14$220.00$220.00$175.00
18Rail (handrail)(type E) (450-7062)LF202$144.00$200.00$220.00$175.00
19CMP (gal steel 36 in) (460-7009)LF42$300.00$550.00$267.63$150.00
20Concrete box culvert (5 FT X 4 FT)(extend) (462-7063)LF10$1,175.00$800.00$3,824.32$3,000.00
21Inlet (complete)(pco)(5FT)(none) (465-7021)EACH1$10,000$8,500.00$16,783$10,000
22Wingwall (PW - 1) (HW=7 FT) (466-7177)EACH1$23,500$28,000$63,496$37,000
23Set (type II) (36 in) (CMP) (6: 1) (P) (467-7364)EACH1$9,850.00$5,500.00$13,226$10,000
24Adjusting manholes (479-7001)EACH2$2,675.84$1,500.00$798.00$1,500.00
25Adjusting manholes & inlets (479-7003)EACH6$1,083.00$4,500.00$1,330.00$1,500.00
26Adjusting manholes (water valve box) (479-7007)EACH3$1,536.30$500.00$1,330.00$1,500.00
27Adjusting manholes (water meter) (479-7008)EACH5$997.01$500.00$798.00$1,500.00
28Clean existing culverts (480-7001)EACH2$4,000.00$2,800.00$2,750.00$2,500.00
29Removing structure (inlet) (496-7002)EACH1$1,500.00$2,000.00$893.20$2,000.00
30Removing structure (set) (496-7004)EACH1$950.00$500.00$9,221.30$2,000.00
31Removing structure (wingwall) (496-7005)EACH1$2,500.00$2,400.00$30,439$2,000.00
32Remove STR (rail) (496-7017)LF13$17.50$1.00$275.00$200.00
33Mobilization (500-7001)LS1$314,000$252,500$220,198$425,000
34Barricades, signs and traffic handling (502-7001)MO15$7,500.00$2,800.00$3,850.00$17,500
35Portable changeable message sign (503-7001)DAY632$100.00$70.00$0.01$60.00
36TMA (stationary) (505-7001)DAY632$200.00$260.00$0.01$350.00
37Construction exits (install) (type 1) (506-7020)SY444$39.10$40.00$0.01$50.00
38Construction exits (remove) (506-7024)SY222$14.41$10.00$0.01$20.00
39Sandbags for erosion control (506-7035)EACH40$14.00$5.00$0.01$20.00
40Temporary sediment control fence (install) (506-7039)LF3,675$5.26$4.00$0.01$4.50
41Temporary sediment control fence (remove) (506-7041)LF1,838$1.60$2.00$0.01$1.00
42Biodegradable erosion control logs (install) (18") (506-7045)LF60$12.50$8.00$0.01$10.00
43Biodegradable erosion control logs (remove) (506-7046)LF60$3.07$1.00$0.01$4.00
44Concrete curb (type II) (529-7002)LF409$43.86$10.00$50.88$50.00
45Concrete curb (mono) (type II) (529-7007)LF52$40.86$8.00$50.88$70.00
46Concrete curb & gutter (type II) (529-7009)LF742$71.26$55.00$50.88$50.00
47Driveways (concrete) (530-7006)SY6,801$145.00$107.00$119.47$135.00
48Concrete sidewalks (5") (531-7002)SY8,734$95.00$105.00$117.90$125.00
49Concrete sidewalk (steps) (531-7004)SY1$250.00$1,000.00$166.99$450.00
50Curb ramps (type 1) (531-7005)EACH5$2,870.25$2,000.00$2,408.67$1,700.00
51Curb ramps (type 6) (531-7009)EACH1$3,533.37$2,000.00$2,408.67$2,000.00
52Curb ramps (type 7) (531-7010)EACH15$2,954.19$2,000.00$2,408.67$2,000.00
53Curb ramps (type 10) (531-7011)EACH14$3,567.12$2,000.00$2,408.67$2,000.00
54Concrete sidewalks (special) (531-7025)SY121$225.00$350.00$171.44$200.00
55Right of way markers (538-7001)EACH12$2,560.00$1,000.00$165.00$600.00
56Mailbox install-S (TWW-post) type 4 (560-7008)EACH19$319.40$350.00$605.00$425.00
57Relocate existing mailbox (560-7012)EACH19$225.00$350.00$605.00$450.00
58Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH68$861.45$800.00$495.00$800.00
59Remove SM RD SN sup&AM (644-7073)EACH66$178.82$50.00$27.50$100.00
60Reflectorized pavement marking type II (W) 6" (solid) (666-7175)LF148$1.00$17.50$19.25$17.50
61Prefabricated PM type C (W)(12")(solid) (668-7087)LF91$17.08$22.50$24.75$22.50
62Prefabricated PM type C (W)(24")(solid) (668-7089)LF180$23.73$27.50$30.25$27.50
63Retrofit det warn surface (surface applied) (5031-7001)SF24$20.00$125.00$21.00$100.00
TxDOT contract A00195963: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of July 2, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy