TxDOT contract A00200563 bid tabulation
Hazard Elimination & Safety, DELIA ST (Page Road to 0.1 Mi. S. of Page Road). Let by Texas DOT on May 1, 2025, Harrison, Atlanta District. 6 bids received; low bid $829,830 by THK Construction LLC, -32% against the engineer's estimate of $1,224,209.
- Owner
- Texas DOT
- Letting
- 01 MAY 2025
- Pay items
- 56
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | THK Construction LLC | $829,830 | Low | -32% |
| 2 | Longview Bridge and Road, LTD. | $964,568 | +16% | -21% |
| 3 | True Roads Construction, LLC | $1,046,208 | +26% | -15% |
| 4 | East Texas Bridge, Inc. | $1,074,742 | +30% | -12% |
| 5 | Grey Sky Construction LLC | $1,546,052 | +86% | +26% |
| 6 | O. Trevino Construction, LLC | $1,608,776 | +94% | +31% |
Engineer's estimate: $1,224,209.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. THK Construction LLC | 2. Longview Bridge and Road, LTD. | 3. True Roads Construction, LLC | 4. East Texas Bridge, Inc. | 5. Grey Sky Construction LLC | 6. O. Trevino Construction, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 5 | $3,500.00 | $1,000.00 | $7,000.00 | $2,400.00 | $5,000.00 | $20,000 | $5,000.00 |
| 2 | Removing concrete (pavement) (104-7001) | SY | 329 | $50.00 | $20.00 | $25.00 | $80.00 | $30.00 | $30.00 | $35.00 |
| 3 | Removing concrete (curb) (104-7016) | LF | 135 | $40.00 | $10.00 | $15.00 | $27.50 | $17.00 | $30.00 | $48.00 |
| 4 | Removing concrete (curb & gutter) (104-7017) | LF | 921 | $26.00 | $10.00 | $20.00 | $38.50 | $15.00 | $20.00 | $18.00 |
| 5 | Remove (8"-19") TRT/untrt base & asphalt pavement (105-7119) | SY | 1,155 | $31.00 | $15.00 | $16.00 | $12.00 | $20.00 | $30.00 | $25.00 |
| 6 | Excavation (roadway) (110-7001) | CY | 3,033 | $22.00 | $12.00 | $27.00 | $14.50 | $20.00 | $20.00 | $15.00 |
| 7 | Embankment (final)(DC)(type C) (132-7006) | CY | 217 | $30.00 | $12.00 | $40.00 | $33.50 | $40.00 | $50.00 | $180.00 |
| 8 | Embankment (final)(OC)(type D) (132-7011) | CY | 775 | $30.00 | $12.00 | $32.00 | $24.50 | $25.00 | $50.00 | $67.00 |
| 9 | Furn & place topsoil (4") (160-7002) | SY | 3,888 | $5.00 | $4.00 | $6.00 | $3.50 | $4.00 | $10.00 | $3.00 |
| 10 | Hydro mulch seed (permanent_rural_sandy) (164-7017) | SY | 3,888 | $1.00 | $0.55 | $1.00 | $0.55 | $0.80 | $2.00 | $0.65 |
| 11 | Vegetative watering (168-7001) | TGL | 60 | $25.00 | $20.00 | $25.00 | $50.00 | $20.00 | $50.00 | $130.00 |
| 12 | Proof rolling (216-7001) | HR | 4 | $230.00 | $100.00 | $250.00 | $150.00 | $25.00 | $150.00 | $230.00 |
| 13 | Lime (quicklime (slurry)) (260-7003) | TON | 78.90 | $500.00 | $400.00 | $450.00 | $550.00 | $450.00 | $400.00 | $530.00 |
| 14 | Lime TRT (subgrade) (8") (260-7020) | SY | 2,283 | $9.00 | $5.00 | $4.50 | $10.00 | $10.00 | $15.00 | $25.00 |
| 15 | Concrete pavement (CPCD) (8") (360-7018) | SY | 2,046 | $150.00 | $141.00 | $120.00 | $165.00 | $130.00 | $165.00 | $130.00 |
| 16 | Cut & restore concrete paving (400-7007) | SY | 32 | $500.00 | $150.00 | $450.00 | $325.00 | $275.00 | $200.00 | $380.00 |
| 17 | Riprap (stone common)(dry)(12 in) (432-7031) | CY | 4 | $400.00 | $250.00 | $350.00 | $400.00 | $300.00 | $185.00 | $1,100.00 |
| 18 | RC pipe (CL III)(18 in) (464-7003) | LF | 115 | $105.00 | $60.00 | $75.00 | $80.00 | $70.00 | $100.00 | $305.00 |
| 19 | RC pipe (CL III)(24 in) (464-7005) | LF | 65 | $135.00 | $75.00 | $100.00 | $100.00 | $90.00 | $250.00 | $380.00 |
| 20 | Junction box(complete)(PJB)(3FTX3FT) (465-7005) | EACH | 5 | $8,000.00 | $6,000.00 | $6,500.00 | $5,500.00 | $8,500.00 | $10,000 | $10,000 |
| 21 | Junction box(complete)(PJB)(4FTX4FT) (465-7006) | EACH | 1 | $9,000.00 | $6,000.00 | $7,500.00 | $7,000.00 | $10,000 | $10,000 | $11,300 |
| 22 | Junction box(complete)(PJB)(5FTX5FT) (465-7009) | EACH | 1 | $10,000 | $7,000.00 | $8,750.00 | $8,000.00 | $12,000 | $12,500 | $13,800 |
| 23 | Inlet (complete)(pco)(5FT)(none) (465-7021) | EACH | 2 | $10,500 | $7,000.00 | $9,000.00 | $8,000.00 | $12,500 | $12,500 | $14,900 |
| 24 | Inlet (complete)(pco)(5FT)(left) (465-7022) | EACH | 3 | $12,000 | $8,000.00 | $10,000 | $9,000.00 | $15,000 | $12,500 | $15,500 |
| 25 | Inlet (complete)(pco)(5FT)(right) (465-7023) | EACH | 2 | $12,000 | $8,000.00 | $10,000 | $9,000.00 | $15,000 | $12,500 | $15,500 |
| 26 | Inlet (complete)(pazd)(RC)(4FTX4FT) (465-7153) | EACH | 1 | $11,000 | $6,500.00 | $8,000.00 | $7,000.00 | $10,000 | $12,500 | $13,000 |
| 27 | Set(type II)(24 in)(RCP)(4:1)(P) (467-7468) | EACH | 1 | $2,671.00 | $2,000.00 | $2,000.00 | $1,500.00 | $2,100.00 | $3,500.00 | $7,500.00 |
| 28 | Thermoplastic pipe (PP) (18") (468-7001) | LF | 441 | $85.00 | $45.00 | $70.00 | $80.00 | $70.00 | $250.00 | $180.00 |
| 29 | Thermoplastic pipe (PP) (24") (468-7002) | LF | 44 | $90.00 | $60.00 | $110.00 | $140.00 | $90.00 | $400.00 | $305.00 |
| 30 | Removing structure (inlet) (496-7002) | EACH | 5 | $2,000.00 | $500.00 | $1,300.00 | $1,800.00 | $715.00 | $2,500.00 | $4,200.00 |
| 31 | Removing structure (pipe) (496-7007) | LF | 459 | $20.00 | $10.00 | $18.00 | $25.00 | $25.00 | $100.00 | $60.00 |
| 32 | Mobilization (500-7001) | LS | 1 | $111,000 | $60,000 | $50,000 | $85,000 | $110,000 | $150,000 | $160,000 |
| 33 | Barricades, signs and traffic handling (502-7001) | MO | 6 | $11,500 | $1,225.51 | $5,000.00 | $3,000.00 | $8,000.00 | $8,500.00 | $30,000 |
| 34 | TMA (stationary) (505-7001) | DAY | 99 | $210.00 | $200.00 | $200.00 | $200.00 | $200.00 | $250.00 | $200.00 |
| 35 | TMA (mobile operation) (505-7003) | DAY | 8 | $300.00 | $300.00 | $300.00 | $200.00 | $200.00 | $550.00 | $715.00 |
| 36 | Construction exits (install) (type 1) (506-7020) | SY | 222 | $30.00 | $35.31 | $38.00 | $36.00 | $40.00 | $40.00 | $55.00 |
| 37 | Construction exits (remove) (506-7024) | SY | 222 | $15.00 | $12.84 | $14.00 | $13.00 | $12.00 | $20.00 | $20.00 |
| 38 | Temporary sediment control fence (install) (506-7039) | LF | 450 | $6.50 | $4.86 | $5.50 | $5.00 | $6.00 | $4.00 | $8.00 |
| 39 | Temporary SDMT cont fence (inlet protection) (506-7040) | LF | 450 | $20.00 | $8.56 | $11.00 | $8.00 | $11.00 | $6.00 | $13.00 |
| 40 | Temporary sediment control fence (remove) (506-7041) | LF | 900 | $2.51 | $1.07 | $2.00 | $1.10 | $2.00 | $2.00 | $2.00 |
| 41 | Constructing detours (508-7001) | SY | 140 | $50.00 | $100.00 | $85.00 | $115.00 | $85.00 | $45.00 | $120.00 |
| 42 | Concrete curb (mono) (type II) (529-7007) | LF | 935 | $30.00 | $30.00 | $13.00 | $15.00 | $15.00 | $65.00 | $44.00 |
| 43 | Concrete curb & gutter (type II) (529-7009) | LF | 133 | $70.00 | $65.00 | $50.00 | $65.00 | $50.00 | $85.00 | $88.00 |
| 44 | Driveways (concrete) (530-7006) | SY | 107 | $150.00 | $100.00 | $180.00 | $135.00 | $150.00 | $200.00 | $175.00 |
| 45 | Concrete sidewalks (4") (531-7001) | SY | 541 | $150.00 | $90.00 | $80.00 | $85.00 | $85.00 | $85.00 | $127.00 |
| 46 | Curb ramps (type 7) (531-7010) | EACH | 2 | $3,500.00 | $3,500.00 | $3,000.00 | $2,400.00 | $3,500.00 | $3,850.00 | $5,000.00 |
| 47 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 3 | $810.00 | $1,243.34 | $1,500.00 | $1,000.00 | $1,300.00 | $1,500.00 | $1,101.00 |
| 48 | Install small roadside sign support and assembly tytwt(1)WS(P) (644-7057) | EACH | 1 | $510.00 | $898.80 | $1,100.00 | $750.00 | $925.00 | $1,500.00 | $814.00 |
| 49 | All-wther PM type I (W)6"(solid)(100MIL) (666-7309) | LF | 75 | $2.00 | $10.70 | $11.00 | $11.00 | $11.00 | $5.00 | $12.00 |
| 50 | All-wther PM type I (Y)6"(solid)(100MIL) (666-7315) | LF | 959 | $2.00 | $5.35 | $5.50 | $5.50 | $6.00 | $5.00 | $6.00 |
| 51 | All-wther PM type I (W) 8"(solid)(100MIL) (666-7425) | LF | 203 | $3.00 | $10.70 | $11.00 | $11.00 | $11.00 | $10.00 | $12.00 |
| 52 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 35 | $20.00 | $17.66 | $20.00 | $18.00 | $18.00 | $20.00 | $20.00 |
| 53 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 2 | $250.00 | $240.75 | $250.00 | $250.00 | $250.00 | $250.00 | $266.00 |
| 54 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 1 | $280.00 | $321.00 | $350.00 | $330.00 | $330.00 | $250.00 | $354.01 |
| 55 | Reflectorized pavement marker type I-C (672-7002) | EACH | 9 | $10.00 | $8.56 | $9.00 | $8.80 | $9.00 | $6.00 | $9.55 |
| 56 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 12 | $10.00 | $8.56 | $9.00 | $8.80 | $9.00 | $6.00 | $9.57 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of May 1, 2025. Compiled by Mirage Metrics.