TxDOT contract A00207367 bid tabulation
REHABILITATION OF EXISTING ROADWAY, MR0682 (US 80 to 2ND STREET). Let by Texas DOT on June 4, 2025, Kaufman, Dallas District. 3 bids received; low bid $4,164,553 by Granite Construction Company, -5.0% against the engineer's estimate of $4,381,737.
- Owner
- Texas DOT
- Letting
- 04 JUN 2025
- Pay items
- 101
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Granite Construction Company | $4,164,553 | Low | -5.0% |
| 2 | Ed Bell Construction Company | $4,424,423 | +6.0% | +1.0% |
| 3 | Grey Sky Construction LLC | $5,358,746 | +29% | +22% |
Engineer's estimate: $4,381,737.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Granite Construction Company | 2. Ed Bell Construction Company | 3. Grey Sky Construction LLC |
|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 21.81 | $13,500 | $19,000 | $14,000 | $20,000 |
| 2 | Removing concrete (pavement) (104-7001) | SY | 224 | $55.00 | $20.00 | $30.00 | $50.00 |
| 3 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 95 | $30.00 | $25.00 | $30.00 | $50.00 |
| 4 | Removing concrete (curb) (104-7016) | LF | 35 | $50.00 | $15.00 | $50.00 | $50.00 |
| 5 | Removing concrete (curb & gutter) (104-7017) | LF | 199 | $50.00 | $25.00 | $50.00 | $50.00 |
| 6 | Removing concrete (flume) (104-7041) | SY | 11 | $130.00 | $45.00 | $100.00 | $50.00 |
| 7 | Remove (2"-6") TRT/untrt base & asphalt pavement (105-7002) | SY | 29 | $20.00 | $15.00 | $35.00 | $20.00 |
| 8 | Remove (8"-12") TRT/untrt base & asphalt pavement (105-7008) | SY | 301 | $20.00 | $17.00 | $45.00 | $30.00 |
| 9 | Remove (14"-18") TRT/untrt base & asphalt pavement (105-7014) | SY | 1,097 | $20.00 | $24.00 | $25.00 | $40.00 |
| 10 | Excavation (roadway) (110-7001) | CY | 5,335 | $30.00 | $30.00 | $8.00 | $30.00 |
| 11 | Excavation (channel) (110-7002) | CY | 5,875 | $25.00 | $27.00 | $17.00 | $50.00 |
| 12 | Subgr widen (OC) (112-7001) | STA | 3.85 | $1,200.00 | $10,000 | $1,500.00 | $650.00 |
| 13 | Embankment (final)(OC)(type A) (132-7001) | CY | 204 | $25.00 | $40.00 | $75.00 | $80.00 |
| 14 | Embankment (final)(OC)(type C) (132-7005) | CY | 1,863 | $30.00 | $25.00 | $20.00 | $80.00 |
| 15 | Backfill (type A or B) (134-7004) | STA | 21.81 | $402.00 | $600.00 | $600.00 | $650.00 |
| 16 | Road grader work (ord comp) (152-7001) | STA | 21.81 | $200.00 | $350.00 | $100.00 | $450.00 |
| 17 | Furn & place topsoil (4") (160-7002) | SY | 10,327 | $4.50 | $2.00 | $4.00 | $10.00 |
| 18 | Block sodding (162-7002) | SY | 2,517 | $10.00 | $4.50 | $5.00 | $10.00 |
| 19 | Drill seed (temporary_warm_cool) (164-7015) | SY | 3,408 | $0.33 | $0.40 | $0.15 | $1.00 |
| 20 | Hydro mulch seed (permanent_urban_clay) (164-7020) | SY | 10,327 | $1.00 | $0.45 | $1.05 | $1.00 |
| 21 | Vegetative watering (168-7001) | TGL | 2,418 | $10.00 | $0.01 | $3.00 | $20.00 |
| 22 | FL BS (compacted in place)(type D GR 1-2) (10") (247-7102) | SY | 7,598 | $20.00 | $35.00 | $30.00 | $30.00 |
| 23 | Prime coat (MC-30) (310-7004) | GAL | 1,514 | $11.00 | $11.00 | $12.00 | $10.00 |
| 24 | SP mixes SP-B PG64-22 (344-7001) | TON | 2,914 | $160.00 | $143.00 | $143.50 | $180.00 |
| 25 | SP mixes SP-C sac-B PG64-22 (344-7011) | TON | 832 | $175.00 | $155.00 | $166.75 | $220.00 |
| 26 | Tack coat (344-7077) | GAL | 454 | $5.76 | $2.00 | $2.00 | $10.00 |
| 27 | Trench excavation protection (402-7001) | LF | 1,256 | $21.00 | $1.00 | $6.00 | $10.00 |
| 28 | Riprap (mow strip)(4 in) (432-7013) | CY | 45 | $800.00 | $600.00 | $900.00 | $550.00 |
| 29 | Riprap (stone protection)(18 in) (432-7043) | CY | 2,152 | $370.00 | $140.00 | $215.00 | $185.00 |
| 30 | Concrete box culvert (10 FT X 8 FT) (462-7036) | LF | 280 | $1,200.00 | $1,885.00 | $1,000.00 | $1,650.00 |
| 31 | RC pipe (CL III)(24 in) (464-7005) | LF | 108 | $150.00 | $200.00 | $150.00 | $120.00 |
| 32 | RC pipe (CL III)(36 in) (464-7009) | LF | 310 | $250.00 | $225.00 | $170.00 | $165.00 |
| 33 | RC pipe (CL III)(42 in) (464-7010) | LF | 141 | $420.00 | $275.00 | $220.00 | $250.00 |
| 34 | Junction box(complete)(PJB)(5FTX5FT) (465-7009) | EACH | 2 | $6,000.00 | $5,400.00 | $10,000 | $12,500 |
| 35 | Inlet (complete)(pco)(5FT)(none) (465-7021) | EACH | 1 | $6,000.00 | $5,400.00 | $12,000 | $12,500 |
| 36 | Inlet (complete)(pco)(5FT)(left) (465-7022) | EACH | 1 | $8,000.00 | $5,600.00 | $13,000 | $12,500 |
| 37 | Inl(CMP)(pazd-CZ)(FG)(3FTX3FT-3FTX3FT) (465-7163) | EACH | 2 | $8,000.00 | $6,000.00 | $10,000 | $12,500 |
| 38 | Wingwall (PW - 1) (HW=8 FT) (466-7178) | EACH | 1 | $35,000 | $45,000 | $55,000 | $65,000 |
| 39 | Wingwall (PW - 1) (HW=9 FT) (466-7179) | EACH | 2 | $42,500 | $55,000 | $75,000 | $75,000 |
| 40 | Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326) | EACH | 1 | $2,080.00 | $2,500.00 | $1,500.00 | $2,250.00 |
| 41 | Set (type II) (36 in) (RCP) (6: 1) (C) (467-7367) | EACH | 1 | $6,000.00 | $4,000.00 | $6,000.00 | $3,500.00 |
| 42 | Set (type II) (42 in) (RCP) (6: 1) (P) (467-7380) | EACH | 1 | $5,000.00 | $8,000.00 | $7,500.00 | $8,500.00 |
| 43 | Adjusting manholes (479-7001) | EACH | 1 | $1,500.00 | $1,500.00 | $3,000.00 | $2,500.00 |
| 44 | Removing structure (inlet) (496-7002) | EACH | 4 | $1,000.00 | $2,000.00 | $2,000.00 | $2,500.00 |
| 45 | Removing structure (manhole) (496-7003) | EACH | 3 | $1,500.00 | $2,000.00 | $3,000.00 | $2,500.00 |
| 46 | Removing structure (headwall) (496-7006) | EACH | 2 | $2,448.00 | $2,000.00 | $10,000 | $2,500.00 |
| 47 | Removing structure (pipe) (496-7007) | LF | 2,768 | $5.00 | $10.00 | $50.00 | $50.00 |
| 48 | Removing structure (box culvert) (496-7008) | LF | 228 | $322.00 | $100.00 | $125.00 | $200.00 |
| 49 | Remove STR (bollard) (496-7028) | EACH | 2 | $432.00 | $250.00 | $250.00 | $500.00 |
| 50 | Mobilization (500-7001) | LS | 1 | $398,340 | $415,000 | $450,000 | $500,000 |
| 51 | Barricades, signs and traffic handling (502-7001) | MO | 10 | $15,000 | $3,478.63 | $20,000 | $15,000 |
| 52 | Portable changeable message sign (503-7002) | EACH | 2 | $12,000 | $10,000 | $7,500.00 | $20,000 |
| 53 | TMA (stationary) (505-7001) | DAY | 60 | $450.00 | $183.33 | $150.00 | $250.00 |
| 54 | TMA (mobile operation) (505-7003) | DAY | 2 | $214.00 | $900.00 | $1,000.00 | $550.00 |
| 55 | Construction exits (install) (type 1) (506-7020) | SY | 28 | $30.00 | $50.00 | $60.00 | $50.00 |
| 56 | Construction exits (remove) (506-7024) | SY | 28 | $15.00 | $20.00 | $30.00 | $20.00 |
| 57 | Temporary sediment control fence (install) (506-7039) | LF | 5,153 | $5.00 | $3.60 | $3.00 | $4.00 |
| 58 | Temporary SDMT cont fence (inlet protection) (506-7040) | LF | 86 | $8.00 | $8.00 | $6.00 | $6.00 |
| 59 | Temporary sediment control fence (remove) (506-7041) | LF | 5,239.50 | $3.00 | $1.20 | $2.00 | $2.00 |
| 60 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 500 | $7.00 | $6.00 | $6.00 | $18.00 |
| 61 | Biodegradable erosion control logs (remove) (506-7046) | LF | 500 | $3.00 | $1.25 | $3.00 | $9.00 |
| 62 | Concrete curb & gutter (type II) (529-7009) | LF | 354 | $140.00 | $37.68 | $75.00 | $85.00 |
| 63 | Driveways (concrete) (530-7006) | SY | 252 | $140.00 | $107.25 | $175.00 | $100.00 |
| 64 | Concrete sidewalks (4") (531-7001) | SY | 43 | $90.00 | $92.09 | $175.00 | $72.00 |
| 65 | Curb ramps (type 7) (531-7010) | EACH | 2 | $3,000.00 | $2,625.83 | $3,750.00 | $3,850.00 |
| 66 | Metal W-beam guard fence (timber post) (540-7001) | LF | 236 | $30.00 | $39.00 | $32.25 | $50.00 |
| 67 | Short radius (28") (540-7013) | LF | 187 | $35.00 | $51.00 | $32.25 | $85.00 |
| 68 | Downstream anchor terminal section (540-7015) | EACH | 3 | $1,390.00 | $1,525.00 | $1,400.00 | $1,850.00 |
| 69 | Remove metal beam guard fence (542-7001) | LF | 26 | $30.00 | $4.00 | $35.00 | $5.00 |
| 70 | Guardrail end treatment (install) (544-7001) | EACH | 3 | $3,500.00 | $3,100.00 | $3,400.00 | $3,850.00 |
| 71 | Chain link fence (remove) (550-7007) | LF | 290 | $5.00 | $6.25 | $12.50 | $20.00 |
| 72 | Remove and install existing gate (550-7017) | EACH | 1 | $2,000.00 | $6,252.92 | $3,000.00 | $10,000 |
| 73 | Wire fence (remove) (552-7011) | LF | 583 | $20.00 | $2.25 | $2.75 | $3.00 |
| 74 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 14 | $1,200.00 | $775.00 | $850.00 | $1,500.00 |
| 75 | Install object marker assembly (OM-2Z)(WFLX)GND (658-7058) | EACH | 5 | $95.00 | $55.00 | $60.00 | $100.00 |
| 76 | Install object marker assembly (OM-3R)(WFLX)SRF(BI) (658-7068) | EACH | 19 | $300.00 | $450.00 | $485.00 | $100.00 |
| 77 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 456 | $2.00 | $3.00 | $2.15 | $6.00 |
| 78 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 124 | $10.00 | $26.00 | $16.70 | $20.00 |
| 79 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 4 | $175.00 | $750.00 | $215.00 | $250.00 |
| 80 | Reflectorized pavement marking type I(W)(double arrow)(100MIL) (666-7045) | EACH | 2 | $250.00 | $750.00 | $350.00 | $500.00 |
| 81 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 4 | $200.00 | $750.00 | $270.00 | $250.00 |
| 82 | Reflectorized pavement marking type I (Y)24"(solid)(100MIL) (666-7123) | LF | 46 | $10.00 | $26.00 | $14.00 | $20.00 |
| 83 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 3,299 | $1.00 | $1.50 | $1.35 | $3.00 |
| 84 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 3,567 | $1.00 | $1.50 | $1.35 | $3.00 |
| 85 | Reflectorized pavement marker type I-C (672-7002) | EACH | 18 | $6.00 | $10.00 | $27.00 | $6.00 |
| 86 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 63 | $6.00 | $10.00 | $27.00 | $6.00 |
| 87 | Full - width mowing (730-7019) | CYC | 3 | $2,000.00 | $550.00 | $2,500.00 | $5,000.00 |
| 88 | Water main pipe(PVC)(12IN)(DR 18)(C900) (7049-7002) | LF | 174 | $250.00 | $150.00 | $525.00 | $200.00 |
| 89 | Casing steel (30IN) (7049-7003) | LF | 47 | $400.00 | $600.00 | $945.00 | $850.00 |
| 90 | Casing steel (24IN) (7049-7004) | LF | 234 | $160.00 | $575.00 | $630.00 | $650.00 |
| 91 | Water main pipe (PVC)(18IN)(DR18)(C900) (7049-7005) | LF | 198 | $350.00 | $250.00 | $630.00 | $250.00 |
| 92 | 12" gate valve (7049-7006) | EACH | 1 | $6,000.00 | $15,000 | $7,350.00 | $12,500 |
| 93 | 18" gate valve (vertical) (7049-7007) | EACH | 1 | $25,000 | $35,000 | $36,750 | $30,000 |
| 94 | 5’ drop manhole (pre-cast) (7049-7008) | EACH | 3 | $4,000.00 | $15,000 | $21,000 | $15,000 |
| 95 | 18" X 18" cut-in-tee (7049-7009) | EACH | 1 | $20,000 | $25,000 | $21,000 | $20,000 |
| 96 | 18" horizontal bend (7049-7010) | EACH | 3 | $2,000.00 | $5,000.00 | $6,300.00 | $20,000 |
| 97 | 12" horizontal bend (7049-7011) | EACH | 2 | $2,000.00 | $4,000.00 | $3,675.00 | $12,500 |
| 98 | 18"X12" reducer (7049-7012) | EACH | 1 | $2,000.00 | $3,000.00 | $9,450.00 | $15,000 |
| 99 | 12" to 8" reducer (7049-7013) | EACH | 1 | $2,000.00 | $2,700.00 | $6,300.00 | $12,500 |
| 100 | Pipe (PVC)(SDR-26)(15IN) (7049-7014) | LF | 345 | $150.00 | $250.00 | $262.50 | $150.00 |
| 101 | Fire hydrant remove and replace (7049-7015) | EACH | 2 | $1,500.00 | $10,000 | $15,750 | $20,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of June 4, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.