TxDOT letting results, June 6, 2024
57 contracts let by Texas DOT on June 6, 2024, $792,545,630 in low bids, a median of 4 bidders per contract. On the 57 with an engineer's estimate, the low bid came in under it 37 times; median low bid -5.0% against the estimate.
- Owner
- Texas DOT
- Contracts
- 57
- Low bids, total
- $792,545,630
- Data through
- 19 NOV 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 06243201 | SL 1604 Widen road - add lanes from REDLAND RD. to JUDSON RD. | San Antonio District | 5 | Webber, LLC | $155,959,723 | $162,529,306 | +4.0% | -2.0% | TxDOT |
| 06243202 | IH 69 Drainage improvements from NORTH OF IH 45 to BUFFALO BAYOU | Houston District | 3 | Harper Brothers Construction LLC | $121,889,279 | $124,090,195 | +2.0% | +20% | TxDOT |
| 06243203 | FM 646 Widen road - add lanes from FM 1266 to EAST OF EDMUNDS WAY | Houston District | 2 | James Construction Group, LLC | $115,893,024 | $127,159,993 | +10% | +34% | TxDOT |
| 06243204 | IH 20 Construct rest area from FROM 0.7 MILES EAST OF CR 226 to 1.9 MILES EAST OF CR 226 | Abilene District | 2 | Webber, LLC | $74,808,808 | $79,817,932 | +7.0% | +43% | TxDOT |
| 06243205 | US 82 Widen road - add lanes from CLAY COUNTY LINE to APPROX 0.5 MI. E OF US 81 (RINGGOLD | Wichita Falls District | 3 | A. L. Helmcamp, Inc. | $38,961,339 | $39,515,512 | +1.0% | +21% | TxDOT |
| 06243208 | FM 1314 Rehabilitate existing roadway from 0.1 MILE SOUTH OF SH 242 to 1.08 MILE SOUTH OF SH 242 | Houston District | 6 | R Construction Civil, LLC | $31,355,905 | $31,898,180 | +2.0% | +5.0% | TxDOT |
| 06243206 | US 287 Bridge replacement from @ BNSF RR & LP 285 | Childress District | 4 | Mortmara Construction, Inc. | $28,987,860 | $32,210,206 | +11% | +14% | TxDOT |
| 06243207 | FM 846 Highway improvement from SH 137 to HOWARD COUNTY LINE | Odessa District | 4 | Jones Bros. Dirt & Paving Contractors, Inc. | $26,967,769 | $28,365,169 | +5.0% | -21% | TxDOT |
| 06243213 | SH 34 Repair roadway from US 77 to BI 45-G | Dallas District | 3 | Big Creek Construction, LTD. | $12,687,858 | $15,066,607 | +19% | -1.0% | TxDOT |
| 06243216 | SH 30 Bridge replacement from AT GIBBONS CREEK | Bryan District | 6 | Big Creek Construction, LTD. | $12,337,845 | $12,700,647 | +3.0% | +31% | TxDOT |
| 06243211 | IH 40 Install illumination from EAST OF HOPE ROAD to US 287 INTERCHANGE | Amarillo District | 3 | Highway Intelligent Traffic Solutions, Inc. | $11,497,987 | $11,857,877 | +3.0% | -4.0% | TxDOT |
| 06243217 | BS 21-P Resurface roadway from US 59 to 0.338 MI W OF FM 225 | Lufkin District | 2 | Texas Materials Group, Inc. | $10,814,631 | $10,874,698 | +1.0% | +14% | TxDOT |
| 06243219 | US 82 Preventive maintenance from 1.3 MI W OF FM 1417 to GRAYSON/FANNIN COUNTY LINE | Paris District | 4 | Overland Corporation | $10,591,400 | $11,317,569 | +7.0% | +37% | TxDOT |
| 06243210 | US 84 Resurface roadway from HERMLEIGH to NEAR FM 1613 | Abilene District | 3 | RK Hall, LLC | $9,325,297 | $10,427,824 | +12% | -4.0% | TxDOT |
| 06243214 | VA Bridge maintenance from VARIOUS LOCATIONS DISTRICTWIDE | San Antonio District | 5 | Relmco, Inc. | $9,168,264 | $11,534,339 | +26% | -11% | TxDOT |
| 06243222 | US 75 Traffic signal improvements from VARIOUS LOCATIONS to IN THE CITY OF DALLAS/RICHARDSON | Dallas District | 4 | Durable Specialties, Inc. | $8,247,830 | $8,301,064 | +1.0% | -2.0% | TxDOT |
| 06243209 | SH 183 Reconstruct existing roadway from AMERICAN BLVD to DALLAS C/L | Fort Worth District | 4 | Jagoe-Public Company | $8,095,510 | $8,559,356 | +6.0% | -8.0% | TxDOT |
| 06243227 | IH 35E Drainage improvements from HI LINE DR to REGAL ROW | Dallas District | 2 | FNH Construction, LLC | $8,080,872 | $8,388,213 | +4.0% | +21% | TxDOT |
| 06243212 | US 377 Preventive maintenance from SH 183 to STARLIGHT DR | Fort Worth District | 2 | Jagoe-Public Company | $7,770,211 | $8,825,040 | +14% | -8.0% | TxDOT |
| 06243220 | US 287 Surfacing/roadway restoration from BELL ROAD to IH 44 | Wichita Falls District | 3 | Zack Burkett Co. | $7,338,061 | $8,781,730 | +20% | +13% | TxDOT |
| 06243215 | FM 462 Rehabilitate existing roadway from BENTLEY CROSSING to CR 433 | San Antonio District | 8 | Salinas Construction Technologies, LTD. | $6,964,197 | $7,223,627 | +4.0% | -29% | TxDOT |
| 06243218 | FM 219 Replace bridge and approaches from @ BOSQUE RIVER RELIEF to (STR #016) | Waco District | 4 | Knife River Corporation - South | $6,464,517 | $7,453,895 | +15% | -15% | TxDOT |
| 06243226 | US 385 Construct pedestrian infrastructure from 16TH STREET to DENVER STREET | Amarillo District | 4 | Ti-Zack Concrete, LLC | $5,281,885 | $5,825,000 | +10% | -14% | TxDOT |
| 06243224 | SH 21 Preventive maintenance from 0.05 MILES WEST OF SH 21 to 0.03 MILES EAST OF SH 304 | Austin District | 4 | Lone Star Paving Company | $4,578,078 | $4,776,204 | +4.0% | 0.0% | TxDOT |
| 06243234 | IH 10 Landscape development from YARBROUGH DR to FM 659 (ZARAGOZA RD) | El Paso District | 6 | El Paso A.R.C. Electric, Inc. | $4,052,804 | $5,424,816 | +34% | -1.0% | TxDOT |
| 06243233 | FM 3124 Hazard elimination & safety from FM 2109 to 2.302 MI E OF FM 2109 | Lufkin District | 2 | Pinto Construction Co., Inc. | $3,926,437 | $4,276,586 | +9.0% | +15% | TxDOT |
| 06243229 | US 80 Resurface roadway from FM 134 to LOUISIANA S/L | Atlanta District | 3 | Madden Contracting Company, LLC. | $3,801,386 | $4,315,732 | +14% | -9.0% | TxDOT |
| 06243221 | VA Preventive maintenance from VARIOUS LOCATIONS DISTRICTWIDE | San Antonio District | 7 | Stripe-A-Zone, LLC | $3,699,237 | $3,889,919 | +5.0% | -31% | TxDOT |
| 06243231 | FM 519 Construct pedestrian infrastructure from IH 45 to SH 3 | Houston District | 6 | Ser Construction Partners, LLC | $3,290,125 | $3,436,562 | +4.0% | -9.0% | TxDOT |
| 06243228 | CS Rehabilitate bridge from RIVERSIDE DR (SB) AT W FORK OF TRIN to IN FT WORTH | Fort Worth District | 2 | Ragle Construction, Inc. | $3,188,000 | $4,999,315 | +57% | +21% | TxDOT |
| 06243232 | SH 20 Hazard elimination & safety from IH 10 to SUNLAND PARK | El Paso District | 2 | Tri State Electric, LTD. | $2,966,194 | $3,179,286 | +7.0% | -18% | TxDOT |
| 06243225 | VA Construct pedestrian infrastructure from DISTRICT WIDE | San Angelo District | 3 | Relmco, Inc. | $2,856,079 | $3,286,184 | +15% | -8.0% | TxDOT |
| 06243240 | BS 289C Rehabilitate existing roadway from SH 289S to ASH STREET | Dallas District | 3 | Jagoe-Public Company | $2,843,505 | $3,227,197 | +13% | +22% | TxDOT |
| 06243237 | SH 176 Bridge replacement from AT SULPHUR SPRINGS DRAW | Abilene District | 5 | Talbert Companies LLC | $2,389,848 | $2,562,182 | +7.0% | -9.0% | TxDOT |
| 06243259 | VA Install/replace signs from POTTER CO LINE to WHEELER CO LINE | Amarillo District | 4 | HJC Farms, Inc. | $2,357,140 | $2,637,252 | +12% | -29% | TxDOT |
| 06243223 | US 77 Hazard elimination & safety from MELON CREEK to 0.75 MI N OF SAN PATRICIO (C/L) | Corpus Christi District | 4 | SCR Civil Construction, LLC | $2,270,268 | $2,276,337 | 0.0% | -36% | TxDOT |
| 06243241 | BU 83-S Hazard elimination & safety from 0.1 MILES N. OF MILE 1 E. RD. to 0.1 MILES S. OF MILE 1 E. RD. | Pharr District | 3 | Traf-Tex, Inc. | $2,248,364 | $2,279,966 | +1.0% | -3.0% | TxDOT |
| 06243239 | BU 54-A Hazard elimination & safety from AT RUSHING RD/WILL RUTH AVE | El Paso District | 2 | Tri State Electric, LTD. | $2,059,372 | $2,353,461 | +14% | -17% | TxDOT |
| 06243246 | FM 738 Widen road - add shoulders from ON FM738 FROM .8 MI S OF CR303 to SOYARS AVE. | Corpus Christi District | 7 | Clark Construction of Texas, Inc. | $1,993,022 | $2,333,941 | +17% | -33% | TxDOT |
| 06243238 | CS Intersection improvements with right and/or left from 0.1 MI N OF WESTERN CENTER BLVD to 0.1 MI S OF WESTERN CENTER BLVD | Fort Worth District | 4 | Ragle Construction, Inc. | $1,933,735 | $2,138,505 | +11% | +12% | TxDOT |
| 06243242 | VA Install/replace signs from VARIOUS LOCATION to DISTRICT WIDE | Abilene District | 3 | HJC Farms, Inc. | $1,794,698 | $1,903,053 | +6.0% | -19% | TxDOT |
| 06243244 | FM 734 Highway improvement from CASSANDRA DRIVE to COLONIAL PARKWAY | Austin District | 7 | Dan Williams Company | $1,681,925 | $1,967,074 | +17% | -4.0% | TxDOT |
| 06243260 | VA Install/replace signs from AT VARIOUS LOCATIONS to IN NUECES, SAN PATRICIO, ARANSAS CO | Corpus Christi District | 7 | Maldonado-Burkett, LLP | $1,347,670 | $1,499,546 | +11% | -13% | TxDOT |
| 06243243 | US 190 Intersection improvement from 1 MI N OF OSR to OSR | Bryan District | 4 | Brazos Paving, Inc. | $1,275,457 | $1,360,386 | +7.0% | -5.0% | TxDOT |
| 06243247 | US 83 Hazard elimination & safety from 0.1 NORTH OF CIELITO LINDO BLVD to 0.1 SOUTH OF ESPEJO MOLINA RD | Laredo District | 4 | HJC Farms, Inc. | $1,040,125 | $1,075,228 | +3.0% | -17% | TxDOT |
| 06243248 | VA Advanced traffic management system from VARIOUS LOCATIONS AT ORANGE COUNTY to AND CHAMBERS COUNTY | Beaumont District | 5 | Traf-Tex, Inc. | $794,508 | $921,742 | +16% | -22% | TxDOT |
| 06243245 | SH 359 Construct pedestrian infrastructure from 1,000 FEET WEST OF WENDT ST to 600 FEET EAST OF W MENDOZA AVE | Corpus Christi District | 6 | Mako Contracting, LLC | $656,398 | $678,583 | +3.0% | -16% | TxDOT |
| 06243251 | US 281 Hazard elimination & safety from BROOKS/JIM WELLS COUNTY LINE to FM 1418 | Maintenance Division District | 2 | The Levy Company, Inc. | $614,388 | $659,720 | +7.0% | +9.0% | TxDOT |
| 06243249 | CR Bridge replacement from CR 2545 AT BAYOU SIEPE | Lufkin District | 6 | THK Construction LLC | $584,995 | $687,267 | +17% | -17% | TxDOT |
| 06243252 | SH 107 Hazard elimination & safety from 0.39 MILES W. OF MILE 2 W. RD. to 0.45 MILES E. OF FM 491 | Pharr District | 3 | Massana Construction Inc. | $554,000 | $592,034 | +7.0% | +3.0% | TxDOT |
| 06243253 | VA Bridge maintenance from DISTRICTWIDE to ALL COUNTIES | Yoakum District | 4 | Garret Shields Infrastructure | $538,360 | $553,695 | +3.0% | -10% | TxDOT |
| 06243250 | VA Advanced traffic management system from VARIOUS LOCATIONS AT COLORADO COUN | Yoakum District | 7 | Third Coast Services LLC | $523,697 | $571,500 | +9.0% | -26% | TxDOT |
| 06243254 | CS Hazard elimination & safety from SL 463 to FM 1315 | Yoakum District | 5 | STX Civil | $503,945 | $547,563 | +9.0% | +5.0% | TxDOT |
| 06243255 | US 84 Install raised median from 6TH ST to 8TH ST | Waco District | 3 | Encino Landscape, Inc. | $299,986 | $464,740 | +55% | +12% | TxDOT |
| 06243257 | VA Landscape development from VARIOUS LOCATIONS to VARIOUS LOCATIONS | Atlanta District | 4 | Texas Road Construction, LLC | $134,759 | $142,060 | +5.0% | -25% | TxDOT |
| 06243256 | FM 1459 Hazard elimination & safety from RURAL LANE to EARLEY STREET | Houston District | 8 | Marcom'S Mowing Service, LLC | $134,455 | $159,871 | +19% | -47% | TxDOT |
| 06243258 | VA Install/replace signs from DISTRICT WIDE to DISTRICT WIDE | Childress District | 5 | Synergy Signs & Services LLC | $122,600 | $143,805 | +17% | -15% | TxDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than TxDOT received, the others did not match their published totals and are left out.