TxDOT letting results, June 1, 2023
67 contracts let by Texas DOT on June 1, 2023, $606,339,669 in low bids, a median of 3 bidders per contract. On the 67 with an engineer's estimate, the low bid came in under it 36 times; median low bid -2.0% against the estimate.
- Owner
- Texas DOT
- Contracts
- 67
- Low bids, total
- $606,339,669
- Data through
- 19 NOV 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 06233002 | IH 10 Widen road - add lanes from FM 464 to SH 123 | San Antonio District | 3 | Webber, LLC | $245,194,039 | $264,440,865 | +8.0% | +12% | TxDOT |
| 06233001 | US 281 Convert non-freeway from BU 281 R N. OF ALICE to SH 44, ETC. | Corpus Christi District | 5 | Anderson Columbia Co., Inc. | $138,438,663 | $141,093,403 | +2.0% | +15% | TxDOT |
| 06233006 | US 277 Highway improvement from SH 158 WEST IN BRONTE to TOM GREEN COUNTY LINE | San Angelo District | 3 | J. H. Strain & Sons, Inc. | $41,866,305 | $45,333,300 | +8.0% | +14% | TxDOT |
| 06233003 | US 59 Construct grade separation from AT INTERSECTION OF FM 1794 | Atlanta District | 2 | Longview Bridge and Road, LTD. | $36,905,848 | $40,957,722 | +11% | +6.0% | TxDOT |
| 06233004 | IH 20 Rehabilitate existing roadway from IH 45 to IH 635 | Dallas District | 3 | FNH Construction, LLC | $20,222,498 | $20,304,431 | 0.0% | +17% | TxDOT |
| 06233005 | SH 315 Resurface roadway from US 259 to PANOLA CL | Tyler District | 3 | Madden Contracting Company, LLC. | $13,565,152 | $18,494,308 | +36% | -28% | TxDOT |
| 06233007 | SS 115 Preventive maintenance from UVALDE RD. to SARAH AVE. | Pharr District | 3 | Foremost Paving, Inc. | $8,569,909 | $9,618,990 | +12% | -24% | TxDOT |
| 06233009 | SH 148 Widen road - add shoulders from FM 174 to NEAR W PLEASANT VALLEY RD | Wichita Falls District | 3 | A. L. Helmcamp, Inc. | $6,879,610 | $7,130,195 | +4.0% | +12% | TxDOT |
| 06233008 | FM 1259 Bridge replacement from TIERRA BLANCA CREEK | Amarillo District | 1 | J. Lee Milligan, Inc. | $5,827,413 | +23% | TxDOT | ||
| 06234006 | SH0030 Mill and inlay from ~ 1.94 MI W. OF FM 244 to FM 2562 | Bryan District | 2 | Knife River Corporation - South | $5,669,016 | $5,837,661 | +3.0% | -4.0% | TxDOT |
| 06233016 | FM 1100 Resurface roadway from US 290 to BASTROP COUNTY LINE | Austin District | 2 | Aaron Concrete Contractors, LLC | $4,953,190 | $5,042,932 | +2.0% | -18% | TxDOT |
| 06233012 | IH 40 Install illumination from 0.715 MI WEST OF BI-40D to 0.690 MI EAST OF BI-40D | Amarillo District | 3 | Mica Corporation | $4,121,379 | $4,265,605 | +3.0% | +2.0% | TxDOT |
| 06233022 | FM 1497 Rehabilitate existing roadway from FM 1184 to FM 3426 | Paris District | 3 | A. K. Gillis & Sons, LLC | $3,887,747 | $3,890,953 | 0.0% | -3.0% | TxDOT |
| 06233010 | US 281 Resurface roadway from CR 112 to SH 29 | Austin District | 5 | Big Creek Construction, LTD. | $3,623,789 | $4,053,260 | +12% | -15% | TxDOT |
| 06233023 | FM 1563 Rehabilitate existing roadway from FM 2655 to SH 50 | Paris District | 5 | Sammy Gist Enterprises, Inc. | $3,579,052 | $3,611,881 | +1.0% | -4.0% | TxDOT |
| 06233013 | VA Hazard elimination & safety from US 67/FM 1776 to SH 349 | Odessa District | 3 | Willis Electric Co., LP | $3,569,918 | $3,656,484 | +2.0% | -11% | TxDOT |
| 06233019 | FM 1686 Bridge replacement from AT DRAW to STR#1132-01-002 | Yoakum District | 3 | E-Z Bel Construction, LLC | $3,399,017 | $4,149,436 | +22% | +8.0% | TxDOT |
| 06233020 | SH 73 Surfacing/roadway restoration from KCS RR CROSSING, EAST to 25TH STREET | Beaumont District | 1 | Texas Materials Group, Inc. | $3,316,497 | +25% | TxDOT | ||
| 06234005 | IH0045 Spot base repair from VARIOUS to VARIOUS | Bryan District | 2 | Texas Materials Group, Inc. | $3,254,250 | $3,589,170 | +10% | -1.0% | TxDOT |
| 06233011 | CR Bridge replacement from RAICES ROAD | Laredo District | 5 | Relmco, Inc. | $2,879,456 | $3,493,998 | +21% | -20% | TxDOT |
| 06233015 | FM 978 Bridge replacement from AT MUSTANG CREEK | Bryan District | 5 | R Construction Civil, LLC | $2,875,306 | $3,120,260 | +9.0% | -7.0% | TxDOT |
| 06233014 | FM 600 Widen road - add shoulders from FM 2976 to JONES COUNTY | Abilene District | 4 | A. L. Helmcamp, Inc. | $2,844,985 | $2,979,096 | +5.0% | -5.0% | TxDOT |
| 06233018 | FM 2644 Widen road - add shoulders from 5.0 MI EAST OF FM 1021 INTERSECTION to FM 1021 INTERSECTION | Laredo District | 3 | CK Newberry, LLC | $2,696,126 | $3,060,935 | +14% | +13% | TxDOT |
| 06233021 | CS Advanced traffic management system from VARIOUS LOCATIONS to IN THE CITY OF ALLEN | Dallas District | 2 | FNH Construction, LLC | $2,574,588 | $2,603,185 | +1.0% | +21% | TxDOT |
| 06233024 | US 59 Hazard elimination & safety from 0.50 MI S OF CR 357 to 0.50 MI N OF CR 357 | Yoakum District | 3 | Texas Materials Group, Inc. | $2,182,905 | $2,393,963 | +10% | +19% | TxDOT |
| 06234016 | SH0006 Traffic control services from VARIOUS to VARIOUS | Bryan District | 4 | Professional Traffic Control LLC | $2,053,200 | $2,193,751 | +7.0% | -1.0% | TxDOT |
| 06234017 | US0290 Traffic control services from VARIOUS to VARIOUS | Bryan District | 3 | Professional Traffic Control LLC | $2,044,500 | $3,417,180 | +67% | -2.0% | TxDOT |
| 06233028 | SL 285 Hazard elimination & safety from @ LP 285 | Childress District | 2 | Hodges and Son Construction Company, Inc. | $1,870,931 | $1,993,787 | +7.0% | +51% | TxDOT |
| 06233025 | SH 78 Repair roadway from COLLIN COUNTY LINE to SPRING CREEK PARKWAY IN WYLIE | Dallas District | 6 | Interstate Improvement, Inc. | $1,739,804 | $1,806,080 | +4.0% | +50% | TxDOT |
| 06233027 | CS Bridge replacement from AT LIVE OAK CREEK to ON WHITE SETTLEMENT ROAD | Fort Worth District | 4 | Sema Construction, Inc. | $1,644,915 | $1,698,573 | +3.0% | +22% | TxDOT |
| 06233041 | CR Bridge replacement from CR 26320 to AT MORRISON CREEK | Paris District | 2 | Highway 19 Construction LLC | $1,489,928 | $2,008,039 | +35% | +6.0% | TxDOT |
| 06233035 | CR Bridge replacement from @ DUCK CREEK | Childress District | 2 | Earth Builders, L.P. | $1,446,464 | $1,757,567 | +22% | +47% | TxDOT |
| 06234004 | SH0036 Mill and inlay from VARIOUS to VARIOUS | Bryan District | 4 | Cornerstone Paving and Construction, L.L.C. | $1,297,678 | $1,334,001 | +3.0% | +9.0% | TxDOT |
| 06233030 | IH 35 Resurface roadway from INDUSTRIAL FORK to 0.37 MI N OF POSEY | Austin District | 4 | Hunter Industries, LTD. | $1,002,855 | $1,029,166 | +3.0% | -6.0% | TxDOT |
| 06233033 | RM 1623 Seal coat from 1.801 MI EAST OF RM 1888 to US 281 | Austin District | 6 | Clark Construction of Texas, Inc. | $976,312 | $1,009,743 | +3.0% | +7.0% | TxDOT |
| 06233038 | CS Install traffic signal from 0.1 E OF GARDEN SPRINGS DR to 0.1 W OF GARDEN SPRINGS DR | Fort Worth District | 3 | FNH Construction, LLC | $938,539 | $1,169,419 | +25% | +13% | TxDOT |
| 06233031 | CS Hazard elimination & safety from N 14TH STREET to MAIN STREET | Beaumont District | 2 | Traf-Tex, Inc. | $917,230 | $942,200 | +3.0% | +12% | TxDOT |
| 06233032 | VA Install flashing beacon from AT VARIOUS LOCATIONS IN CORPUS DIST | Corpus Christi District | 5 | Maldonado-Burkett, LLP | $916,588 | $1,027,991 | +12% | -5.0% | TxDOT |
| 06233026 | FM 2220 Hazard elimination & safety from NEUHAUS DR. to AUGUSTA AVE. | Pharr District | 3 | Foremost Paving, Inc. | $809,835 | $925,757 | +14% | -35% | TxDOT |
| 06233017 | FM 2221 Hazard elimination & safety from 0.1 MILES W. OF QUEEN PALM DR. to 0.1 MILES E. OF QUEEN PALM DR. | Pharr District | 4 | Austin Traffic Signal Construction Co., Inc. | $802,714 | $823,689 | +3.0% | +3.0% | TxDOT |
| 06233042 | US 77 Hazard elimination & safety from @ FM 3148 to @FM 3148 | Waco District | 3 | E-Z Bel Construction, LLC | $796,945 | $889,391 | +12% | -10% | TxDOT |
| 06233040 | SH 110 Install traffic signal from AT LP 49 | Tyler District | 2 | L. S. Equipment Co., Inc. | $787,821 | $806,189 | +2.0% | +4.0% | TxDOT |
| 06233037 | CR Bridge replacement from ON CR 147 to AT BIG ELM CREEK | Bryan District | 6 | Knife River Corporation - South | $774,755 | $918,418 | +19% | -19% | TxDOT |
| 06233039 | CR Bridge replacement from CR 2615 @ MEDINA RIVER | San Antonio District | 4 | Acee Construction LLC. | $730,221 | $831,628 | +14% | +2.0% | TxDOT |
| 06233044 | CR Hazard elimination & safety from (ON ACENSION RD) KENTWOOD AVE to HORIZON BLVD | El Paso District | 6 | Lesna Construction, Inc. | $730,108 | $898,922 | +23% | -16% | TxDOT |
| 06233043 | CR Bridge replacement from ON CR 616 (412) to AT N FORK CHAMPION CREEK | Abilene District | 2 | Delgado'S Contractors, LLC | $711,084 | $780,511 | +10% | +16% | TxDOT |
| 06234003 | IH0010 Metal beam guard fence repair from VARIOUS LOCATIONS IN to JEFFERSON , HARDIN, AND TYLER COUNT | Beaumont District | 2 | Ross Sa Enterprise LLC | $706,468 | $1,048,580 | +48% | -41% | TxDOT |
| 06234013 | SH0036 Hot mix from VARIOUS to VARIOUS | Bryan District | 6 | Knife River Corporation - South | $677,300 | $681,250 | +1.0% | -6.0% | TxDOT |
| 06233036 | CS Bridge replacement from ON CR 325 (LOCAL - TRINITY STREET) to AT TOWN BRANCH | Bryan District | 5 | R Construction Civil, LLC | $649,994 | $809,715 | +25% | -16% | TxDOT |
| 06234012 | IH0045 Hot mix from VARIOUS to VARIOUS | Bryan District | 3 | Knife River Corporation - South | $645,500 | $692,000 | +7.0% | -4.0% | TxDOT |
| 06233048 | SS 135 Surfacing/roadway restoration from FM 692 to END OF MAINTENANCE | Beaumont District | 2 | Cornerstone Paving and Construction, L.L.C. | $626,274 | $708,715 | +13% | +24% | TxDOT |
| 06233046 | FM 700 Resurface roadway from CORONADO AVE to BU 87M | Abilene District | 2 | FNH Construction, LLC | $588,687 | $804,811 | +37% | +20% | TxDOT |
| 06234018 | US0181 Mowing highway right of way from VARIOUS to LOCATIONS | Corpus Christi District | 2 | R&M Incorporated | $480,669 | $519,312 | +8.0% | -6.0% | TxDOT |
| 06234015 | IH0045 Limestone rock asphalt from VARIOUS to VARIOUS | Bryan District | 2 | Vulcan Construction Materials, LLC | $443,910 | $447,720 | +1.0% | +2.0% | TxDOT |
| 06234007 | IH0045 Hot mix from VARIOUS to VARIOUS | Bryan District | 2 | Knife River Corporation - South | $425,450 | $483,000 | +14% | -6.0% | TxDOT |
| 06234019 | US0183 Mowing highway right of way from VARIOUS to LOCATIONS | Corpus Christi District | 2 | R&M Incorporated | $392,522 | $421,765 | +7.0% | -6.0% | TxDOT |
| 06234009 | IH0045 Hot mix from VARIOUS to VARIOUS | Bryan District | 4 | Knife River Corporation - South | $389,800 | $391,800 | +1.0% | -7.0% | TxDOT |
| 06234008 | SH0006 Hot mix from VARIOUS to VARIOUS | Bryan District | 5 | Knife River Corporation - South | $377,600 | $406,700 | +8.0% | -9.0% | TxDOT |
| 06234002 | IH0040 Traffic control services from VARIOUS LOCATIONS ~ SEE PLAN SHEETS to VARIOUS LOCATIONS ~ SEE PLAN SHEETS | Amarillo District | 2 | Barricades Unlimited | $350,850 | $397,940 | +13% | -29% | TxDOT |
| 06234001 | IH0020 Overhead sign bridge repair from MULTIPLE LOCATIONS ON to IH0020 AND US0083 | Abilene District | 3 | HJC Farms, Inc. | $344,118 | $354,829 | +3.0% | +10% | TxDOT |
| 06233045 | VA Preventive maintenance from DISTRICTWIDE | El Paso District | 3 | International Eagle Enterprises, Inc. | $338,675 | $350,158 | +3.0% | +3.0% | TxDOT |
| 06234014 | SH0006 Limestone rock asphalt from VARIOUS to VARIOUS | Bryan District | 2 | Vulcan Construction Materials, LLC | $305,280 | $315,495 | +3.0% | -3.0% | TxDOT |
| 06233029 | VA Bridge maintenance from VARIOUS ROADWAYS IN SAN ANGELO DIST | San Angelo District | 11 | 12Twelve Road and Bridge LLC | $298,966 | $313,290 | +5.0% | -24% | TxDOT |
| 06234010 | SH0030 Raised pavement markers from VARIOUS to VARIOUS | Bryan District | 3 | Brydl Contracting, LLC | $293,308 | $325,210 | +11% | -16% | TxDOT |
| 06233034 | VA Construct pedestrian infrastructure from TRAVIS ST AND MAIN ST to COLORADO ST AND JEFFERSON ST | Yoakum District | 4 | 3LW Civil LLC | $286,576 | $294,815 | +3.0% | -4.0% | TxDOT |
| 06233051 | IH 20 Landscape development from AT NORTH CEDAR RIDGE DRIVE | Dallas District | 4 | Central North Construction, LLC | $190,482 | $191,385 | 0.0% | -9.0% | TxDOT |
| 06233050 | UA 281 Traffic signal improvements from ON UA281 .5 MI N OF FM99 to .5 MI S OF FM99 | Corpus Christi District | 6 | Maldonado-Burkett, LLP | $148,157 | $152,232 | +3.0% | -21% | TxDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than TxDOT received, the others did not match their published totals and are left out.
Your own bid history, read the same way