TxDOT letting results, February 2, 2024
54 contracts let by Texas DOT on February 2, 2024, $399,865,896 in low bids, a median of 4 bidders per contract. On the 54 with an engineer's estimate, the low bid came in under it 34 times; median low bid -4.0% against the estimate.
- Owner
- Texas DOT
- Contracts
- 54
- Low bids, total
- $399,865,896
- Data through
- 19 NOV 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 02243202 | SH 99 Widen road - add lanes from SH 249 to KUYKENDAHL ROAD | Houston District | 8 | Brice Construction and Design LLC | $55,689,700 | $56,592,682 | +2.0% | -3.0% | TxDOT |
| 02243201 | SL 363 Construct new road from INDUSTRIAL BLVD to LUCIUS MCCELVEY | Waco District | 3 | James Construction Group, LLC | $53,775,775 | $61,746,144 | +15% | -18% | TxDOT |
| 02243203 | FM 281 Rehabilitate existing roadway from HARTLEY COUNTY LINE to US 287 | Amarillo District | 3 | J. Lee Milligan, Inc. | $41,097,397 | $53,171,995 | +29% | +3.0% | TxDOT |
| 02243204 | SH 6 Surfacing/roadway restoration from SH 164 to FALLS COUNTY LINE | Waco District | 3 | Big Creek Construction, LTD. | $22,852,588 | $26,259,214 | +15% | -21% | TxDOT |
| 02243207 | IH 20 Rehabilitate existing roadway from TARRANT COUNTY LINE to WEST OF IH 35E | Dallas District | 4 | FNH Construction, LLC | $20,092,843 | $21,343,138 | +6.0% | +29% | TxDOT |
| 02243239 | CS Widen road - add lanes from UPLAND AVENUE, FROM 66TH STREET to 82ND STREET | Lubbock District | 3 | Lone Star Dirt & Paving, LTD. | $19,074,047 | $21,571,088 | +13% | +9.0% | TxDOT |
| 02243206 | US 380 Construct new roadway lanes from FM 1156 to WISE COUNTY LINE | Fort Worth District | 3 | A. L. Helmcamp, Inc. | $18,488,019 | $18,798,818 | +2.0% | +8.0% | TxDOT |
| 02243208 | FM 887 Rehabilitate existing roadway from US 181 to SH 123 | Corpus Christi District | 5 | CK Newberry, LLC | $15,967,612 | $17,931,713 | +12% | -10% | TxDOT |
| 02243212 | US 287 Rehabilitate existing roadway from 2100' W OF FM 164 NB & SB (RAMPS) E to CHILDRESS WCL | Childress District | 3 | Gilvin-Terrill, LTD. | $15,308,760 | $15,620,583 | +2.0% | +38% | TxDOT |
| 02243209 | IH 20 Resurface roadway from US 69 to .787 MI. EAST OF US 69 | Tyler District | 4 | Drewery Construction Company, Incorporated | $13,106,221 | $13,487,541 | +3.0% | +5.0% | TxDOT |
| 02243205 | FM 3351 Bridge replacement from AT CIBOLO CREEK | San Antonio District | 9 | Dan Williams Company | $12,558,078 | $12,867,778 | +2.0% | -20% | TxDOT |
| 02243215 | IH 369 Resurface roadway from US 59 to IH 30 | Atlanta District | 3 | East Texas Bridge, Inc. | $10,246,641 | $10,258,012 | 0.0% | +47% | TxDOT |
| 02243210 | US 59 Surfacing/roadway restoration from 0.1 MI S. OF FM 2791 to 0.1 MI S. OF LOUISE ST | Atlanta District | 3 | RK Hall, LLC | $9,573,841 | $10,201,215 | +7.0% | -3.0% | TxDOT |
| 02243214 | IH 69 Surfacing/roadway restoration from S OF BISSONNET to N OF SOUTH RICE AVE | Houston District | 4 | Vulcan Materials Asphalt and Construction, LLC | $7,540,358 | $8,641,824 | +15% | -4.0% | TxDOT |
| 02243213 | VA Fy 2024 striping from VARIOUS LOCATIONS IN to THE LUBBOCK DISTRICT | Lubbock District | 4 | L&L Company | $7,117,197 | $7,492,119 | +5.0% | -16% | TxDOT |
| 02243222 | SS 3 Resurface roadway from SH 358 to END OF STATE MAINTENANCE | Corpus Christi District | 1 | Anderson Columbia Co., Inc. | $6,716,238 | +21% | TxDOT | ||
| 02243220 | US 82 Preventive maintenance from COOKE COUNTY LINE to FM 901 | Paris District | 5 | RK Hall, LLC | $5,645,404 | $5,816,805 | +3.0% | -12% | TxDOT |
| 02243217 | FM 1391 Bridge replacement from FM 1391 AT CEDAR CREEK | Dallas District | 10 | Highway 19 Construction LLC | $5,443,324 | $5,656,473 | +4.0% | -8.0% | TxDOT |
| 02243216 | US 287 Resurface roadway from NEAR LONE STAR ROAD to MONTAGUE COUNTY LINE | Wichita Falls District | 2 | Jagoe-Public Company | $5,372,832 | $6,443,291 | +20% | -9.0% | TxDOT |
| 02243228 | FM 366 Surfacing/roadway restoration from 0.3 MILES NORTH OF HOGABOOM RD. , S to 0.04 MILES SOUTH OF 32ND ST. | Beaumont District | 3 | Texas Materials Group, Inc. | $5,074,279 | $5,207,179 | +3.0% | +30% | TxDOT |
| 02243224 | CS Traffic signal improvements from VARIOUS INTERSECTIONS to IN THE CITY OF DALLAS | Dallas District | 2 | FNH Construction, LLC | $4,872,333 | $5,148,443 | +6.0% | +14% | TxDOT |
| 02243218 | US 79 Resurface roadway from FM 1660 to FM 3349 | Austin District | 2 | Lone Star Paving Company | $3,840,828 | $5,042,158 | +31% | -36% | TxDOT |
| 02243227 | US 77 Rehabilitate existing roadway from EAGLE DR to MCKINNEY ST | Dallas District | 4 | Jagoe-Public Company | $3,803,760 | $3,867,400 | +2.0% | +8.0% | TxDOT |
| 02243221 | US 79 Installation of median cable barrier from 0.58 MI EAST OF FM 1460 to FM 685 | Austin District | 6 | Dan Williams Company | $3,597,980 | $3,968,164 | +10% | -27% | TxDOT |
| 02243226 | IH 45 Highway improvement from N OF FM 830 to S OF FM 1097 | Houston District | 9 | James Construction Group, LLC | $3,167,866 | $3,173,298 | 0.0% | +9.0% | TxDOT |
| 02244219 | SS0407 Base repair with seal coat and/or overlay from RAND MORGAN to CANTWELL LN | Corpus Christi District | 2 | CK Newberry, LLC | $3,090,451 | $3,157,120 | +2.0% | +15% | TxDOT |
| 02243229 | US 82 Rehabilitate bridge from US 82 WB (KELL) to AT KEMP BLVD | Wichita Falls District | 5 | Talbert Companies LLC | $2,856,132 | $2,981,747 | +4.0% | +1.0% | TxDOT |
| 02243223 | VA Highway improvement from VARIOUS LOCATIONS DISTRICTWIDE | Lufkin District | 7 | Stripe-A-Zone, LLC | $2,621,784 | $2,788,743 | +6.0% | -27% | TxDOT |
| 02243236 | SH 121 Bridge maintenance from AT US 69 to , ETC. | Paris District | 5 | DCC Construction and Services, L.L.C. | $2,050,081 | $2,146,355 | +5.0% | +5.0% | TxDOT |
| 02244221 | US0084 Mill and inlay from VARIOUS to VARIOUS | Brownwood District | 4 | Allen Keller Company | $1,840,800 | $1,997,624 | +9.0% | 0.0% | TxDOT |
| 02243242 | FM 46 Bridge replacement from AT CEDAR CREEK | Bryan District | 9 | Knife River Corporation - South | $1,750,130 | $1,864,485 | +7.0% | -7.0% | TxDOT |
| 02243230 | RM 2243 Resurface roadway from GAREY PARK to US 183 | Austin District | 2 | Texas Materials Group, Inc. | $1,696,964 | $2,035,554 | +20% | -11% | TxDOT |
| 02244230 | SH0007 Traffic control services from VARIOUS ROADWAYS IN HOUSTON, to TRINITY AND ANGELINA MAINT SECTIONS | Lufkin District | 3 | Professional Traffic Control LLC | $1,289,920 | $1,352,973 | +5.0% | -18% | TxDOT |
| 02243225 | VA Repair roadway from VARIOUS LOCATIONS DISTRICTWIDE ON I | Austin District | 1 | Roy Jorgensen Associates, Inc. | $1,284,795 | -17% | TxDOT | ||
| 02243231 | US 190 Intersection improvements with left turn lane from AT FM 2296 | Bryan District | 8 | Knife River Corporation - South | $1,036,981 | $1,057,150 | +2.0% | -7.0% | TxDOT |
| 02243234 | SH 80 Preventive maintenance from SL 82 to IH 35 | Austin District | 5 | Dean Word Company, LTD. | $1,035,073 | $1,066,165 | +3.0% | +10% | TxDOT |
| 02243233 | SL 212 Preventive maintenance from US 290 to WILBARGER CREEK | Austin District | 2 | Texas Materials Group, Inc. | $799,754 | $1,086,299 | +36% | -12% | TxDOT |
| 02243235 | VA Preventive maintenance from DISTRICTWIDE to DISTRICTWIDE | El Paso District | 2 | Tri State Electric, LTD. | $793,768 | $1,293,472 | +63% | +17% | TxDOT |
| 02243219 | VA Install/replace signs from DISTRICT WIDE | Beaumont District | 7 | Vaca Underground Utilities Inc | $721,370 | $723,459 | 0.0% | -13% | TxDOT |
| 02244228 | IH0030 Cable barrier repair from VARIOUS ROADWAYS to VARIOUS ROADWAYS | Atlanta District | 5 | Ross Sa Enterprise LLC | $667,815 | $694,500 | +4.0% | -4.0% | TxDOT |
| 02243238 | BU 82-J Bridge maintenance from AT EAST LANGFORD CREEK to , ETC. | Paris District | 8 | Aad Contracting Inc. | $627,372 | $644,635 | +3.0% | +4.0% | TxDOT |
| 02244220 | SH0036 Mill and inlay from VARIOUS to VARIOUS | Brownwood District | 3 | Blacksmith Ventures LLC | $601,942 | $649,781 | +8.0% | +21% | TxDOT |
| 02244223 | SH0035 Hot-mix cold-laid from MATAGORDA COUNTY | Yoakum District | 3 | Quality Hot Mix, Inc. | $594,000 | $600,000 | +1.0% | -3.0% | TxDOT |
| 02244222 | IH0010 Pavement markings graphics from VARIOUS HIGHWAYS IN WEST HARRIS CO. to VARIOUS HIGHWAYS IN WEST HARRIS CO. | Houston District | 5 | Professional Traffic Control LLC | $524,860 | $586,165 | +12% | -44% | TxDOT |
| 02243241 | VA Construct pedestrian infrastructure from ON CR 2160 W FROM RICARDO MS TO NIX to ON NIX ST FROM CR 2160 TO WAGER AV | Corpus Christi District | 2 | Lucania Contractors LLC | $520,422 | $562,613 | +8.0% | -2.0% | TxDOT |
| 02244229 | IH0020 Cable barrier repair from VARIOUS ROADWAYS to VARIOUS ROADWAYS | Atlanta District | 6 | Ross Sa Enterprise LLC | $478,435 | $527,950 | +10% | -6.0% | TxDOT |
| 02244224 | US0059 Hot mix from WHARTON COUNTY | Yoakum District | 5 | Quality Hot Mix, Inc. | $440,000 | $455,000 | +3.0% | -2.0% | TxDOT |
| 02244226 | US0059 Limestone rock asphalt from WHARTON, MATAGORDA, COLORADO, to AND AUSTIN COUNTIES | Yoakum District | 2 | Martin Marietta Materials, Inc. | $429,750 | $433,353 | +1.0% | -3.0% | TxDOT |
| 02244217 | SH0034 Bridge preventative maintenance from VARIOUS LOCATIONS IN to HUNT COUNTY | Paris District | 8 | DCC Construction and Services, L.L.C. | $416,470 | $426,204 | +2.0% | -4.0% | TxDOT |
| 02244216 | IH0020 Mowing highway right of way from VARIOUS LOCATIONS IN to CALLAHAN COUNTY | Abilene District | 5 | Jose Ernesto Salazar, LLC | $391,555 | $474,605 | +21% | -6.0% | TxDOT |
| 02244225 | SH0035 Hot mix from MATAGORDA COUNTY | Yoakum District | 4 | Quality Hot Mix, Inc. | $364,000 | $376,000 | +3.0% | -1.0% | TxDOT |
| 02243237 | BS 349C Install traffic signal from AT OCCIDENTAL PKWY | Odessa District | 2 | Willis Electric Co., LP | $353,315 | $506,418 | +43% | -49% | TxDOT |
| 02244227 | SH0036 Tree removal from VARIOUS to VARIOUS | Bryan District | 4 | Icos Management, LLC | $285,360 | $480,650 | +68% | -14% | TxDOT |
| 02244218 | IH0020 Mowing highway right of way from VARIOUS LOCATIONS IN to NOLAN COUNTY | Abilene District | 6 | Jose Ernesto Salazar, LLC | $278,679 | $303,453 | +9.0% | -9.0% | TxDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than TxDOT received, the others did not match their published totals and are left out.