Dean Word Company, LTD.: TxDOT bid record
Dean Word Company, LTD. submitted 119 bids on Texas DOT contracts in the data, from 09 JAN 2020 to 04 NOV 2026, and was the low bidder on 13 of them (11%). When it was not low, its total sat a median +21% above the low bid.
- Owner
- Texas DOT
- Low bid volume
- $52,780,697
- Latest bid
- 04 NOV 2026
- Data through
- 19 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2020 | 20 | 0 | 0% |
| 2021 | 24 | 1 | 4% |
| 2024 | 22 | 3 | 14% |
| 2025 | 31 | 6 | 19% |
| 2026 | 22 | 3 | 14% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| San Antonio District | 48 | 4 | 8% |
| Austin District | 40 | 9 | 23% |
| Yoakum District | 23 | 0 | 0% |
| Corpus Christi District | 7 | 0 | 0% |
| Laredo District | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Temporary sediment control fence (remove) | 506-7041 | LF | 94 | 14 (15%) | $0.85 | $1.00 |
| Excavation (roadway) | 110-7001 | CY | 71 | 12 (17%) | $18.63 | $20.00 |
| Barricades, signs and traffic handling | 502-7001 | MO | 119 | 11 (9%) | $5,772.79 | $5,000.00 |
| Reflectorized pavement marker type II-A-A | 672-7004 | EACH | 93 | 10 (11%) | $4.70 | $5.00 |
| Reflectorized pavement marking type I (W)24"(solid)(100MIL) | 666-7036 | LF | 57 | 9 (16%) | $7.75 | $8.00 |
| Temporary special shoring | 403-7001 | SF | 36 | 9 (25%) | $28.80 | $35.73 |
| Flexible pavement structure repair(6") | 351-7005 | SY | 29 | 9 (31%) | $44.00 | $60.00 |
| Temporary sediment control fence (install) | 506-7039 | LF | 94 | 8 (9%) | $3.90 | $4.00 |
| RC pipe (CL III)(24 in) | 464-7005 | LF | 34 | 8 (24%) | $101.44 | $108.13 |
| Crash cushion attenuator (remove) | 545-7004 | EACH | 26 | 8 (31%) | $598.30 | $1,000.00 |
| Riprap (mow strip)(4 in) | 432-7013 | CY | 51 | 7 (14%) | $669.50 | $643.00 |
| Removing concrete (riprap) | 104-7006 | SY | 31 | 7 (23%) | $20.09 | $25.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Hunter Industries, LTD. | 85 | 57 of 85 |
| Texas Materials Group, Inc. | 52 | 26 of 52 |
| Clark Construction of Texas, Inc. | 38 | 18 of 38 |
| Lone Star Paving Company | 37 | 24 of 37 |
| Acme Bridge Company, Inc. | 36 | 26 of 36 |
| Angel Brothers Holdings Corp. | 27 | 13 of 27 |
| CK Newberry, LLC | 25 | 11 of 25 |
| Allen Keller Company | 23 | 13 of 23 |
| E-Z Bel Construction, LLC | 20 | 11 of 20 |
| STX Civil | 18 | 13 of 18 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 04 NOV 2026 | A00188206 | Austin District | Resurface Roadway, IH 35 (0.73 MI N of Posey Rd to 0.19 MI S of SH 123) | 3 of 6 | $3,495,937 | +25% |
| 03 SEP 2026 | A00206794 | San Antonio District | Hazard Elimination & Safety, SL 1604 (Trumbo Rd. to Pleasanton Rd.) | 3 of 6 | $3,752,497 | +9.0% |
| 02 SEP 2026 | A00184856 | San Antonio District | Bridge Replacement, CR 33 (On Waring-Welfare Road to at Joshua Creek) | 7 of 8 | $840,360 | +28% |
| 06 AUG 2026 | A00136986 | San Antonio District | Bridge Replacement, IH 10 (At SH 80 to .) | 5 of 8 | $6,832,789 | +19% |
| 05 AUG 2026 | A00206283 | Yoakum District | Bridge Replacement, FREYBURG ENGLE RD (@ ROCKY CREEK to STR# AA02-75-002 (FREYBURG-ENGLE RD)) | 7 of 9 | $2,094,924 | +30% |
| 01 JUL 2026 | A00209381 | San Antonio District | Resurface Roadway, US 87 (Rosillo Creek to FM 1516) | 5 of 8 | $2,725,640 | +18% |
| 03 JUN 2026 | A00193431 | San Antonio District | Hazard Elimination & Safety, US 281 (SH 97 to FM 1334) | 9 of 10 | $1,270,124 | +23% |
| 02 JUN 2026 | A00193151 | Austin District | Hazard Elimination & Safety, CR 1397 (0.4 mi W of Cottonmouth School Rd to 0.277 mi W of Cottonmouth School Rd.) | 2 of 7 | $392,946 | +1.0% |
| 07 MAY 2026 | A00207502 | San Antonio District | Bridge Replacement, FM 1107 (At Ecleto Creek to .) | 11 of 17 | $1,367,333 | +44% |
| 07 MAY 2026 | A00214229 | San Antonio District | Surfacing/Roadway Restoration, SS 536 (Ashley Rd. to IH 410) | 6 of 7 | $1,499,609 | +36% |
| 06 MAY 2026 | A00214597 | San Antonio District | Widen Road - Add Shoulders, RM 473 (FM 1376 to FM 474) | 7 of 7 | $6,085,396 | +49% |
| 08 APR 2026 | A00197374 | Austin District | Preventive Maintenance, RM 12 (Travis County Line to US 290) | 1 of 6 | $10,020,820 | Low, 4.0% under the second |
| 07 APR 2026 | A00197417 | San Antonio District | Resurface Roadway, SL 368 (IH 410 to New Braunfels Ave) | 6 of 6 | $5,691,168 | +44% |
| 05 MAR 2026 | A00135150 | San Antonio District | Resurface Roadway, SH 211 (FM 1957 to US 90) | 4 of 8 | $2,834,030 | +13% |
| 05 MAR 2026 | A00209819 | Austin District | Preventive Maintenance, FM 110 (IH 35 to SH 123) | 1 of 7 | $1,570,963 | Low, 7.0% under the second |
| 04 MAR 2026 | A00197433 | San Antonio District | Resurface Roadway, US 281 (Bulverde Crossing to Bexar/Comal County Line) | 6 of 6 | $7,144,012 | +23% |
| 04 MAR 2026 | A00197420 | San Antonio District | Rehabilitate Existing Roadway, FM 2790 (FM 471 to Medina/Atascosa C/L) | 1 of 9 | $11,778,114 | Low, 1.0% under the second |
| 04 MAR 2026 | A00197378 | Austin District | Preventive Maintenance, FM 2001 (SH 21 to 0.37 MI N of Satterwhite Rd) | 5 of 7 | $2,299,184 | +29% |
| 04 MAR 2026 | A00189338 | San Antonio District | Resurface Roadway, SH 173 (SH 132 to CR 7711) | 8 of 11 | $2,002,381 | +31% |
| 05 FEB 2026 | A00188227 | San Antonio District | Resurface Roadway, SH 123 (Hays/Guadalupe County Line to FM 758) | 4 of 7 | $4,571,938 | +6.0% |
| 07 JAN 2026 | A00130902 | Austin District | Hazard Elimination & Safety, RM 150 (AT Onion Creek Double Crossings to .) | 10 of 10 | $1,698,660 | +70% |
| 06 JAN 2026 | A00206284 | Yoakum District | Bridge Replacement, COUNTY ROAD 281 (@ PONTON CREEK to STR# AA01-72-001) | 9 of 10 | $1,554,384 | +35% |
| 03 DEC 2025 | A00197215 | Austin District | Resurface Roadway, SH 95 (US 290 to 0.1 MI S. of FM 2336) | 6 of 6 | $2,992,297 | +46% |
| 03 DEC 2025 | A00206306 | Austin District | Highway Improvement, US 183 (0.12 miles north of County Road 309 to 0.92 miles north of County Road 309) | 6 of 7 | $1,849,970 | +20% |
| 03 DEC 2025 | A00206784 | San Antonio District | Hazard Elimination & Safety, US 181 (At Shannon Ridge Drive to .) | 3 of 4 | $257,701 | +40% |
How this record was read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Every bid counted here matched its published total to within one dollar; TxDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.