TxDOT contract A00193151 bid tabulation
Hazard Elimination & Safety, CR 1397 (0.4 mi W of Cottonmouth School Rd to 0.277 mi W of Cottonmouth School Rd.). Let by Texas DOT on June 2, 2026, Travis, Austin District. 7 bids received; low bid $388,598 by Garret Shields Infrastructure, -4.5% against the engineer's estimate of $406,871.
- Owner
- Texas DOT
- Letting
- 02 JUN 2026
- Pay items
- 30
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Garret Shields Infrastructure | $388,598 | Low | -4.0% |
| 2 | Dean Word Company, LTD. | $392,946 | +1.0% | -3.0% |
| 3 | Dan Williams Company | $399,100 | +3.0% | -2.0% |
| 4 | Icos Management, LLC | $451,740 | +16% | +11% |
| 5 | Digg Commercial, LLC | $489,923 | +26% | +20% |
| 6 | STX Civil | $543,440 | +40% | +34% |
| 7 | E-Z Bel Construction, LLC | $597,636 | +54% | +47% |
Engineer's estimate: $406,871.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Garret Shields Infrastructure | 2. Dean Word Company, LTD. | 3. Dan Williams Company | 4. Icos Management, LLC | 5. Digg Commercial, LLC | 6. STX Civil |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 10 | $3,250.00 | $1,000.00 | $3,150.00 | $2,000.00 | $1,050.00 | $3,323.00 | $2,075.19 |
| 2 | Removing concrete (riprap) (104-7006) | SY | 442 | $16.00 | $40.00 | $22.00 | $11.75 | $26.25 | $15.00 | $24.32 |
| 3 | Remove stab base and asphalt pavement (6"-20") (105-7123) | SY | 448 | $8.00 | $20.00 | $19.50 | $7.00 | $26.25 | $10.00 | $53.01 |
| 4 | Excavation (roadway) (110-7001) | CY | 47 | $14.00 | $50.00 | $123.50 | $65.00 | $210.00 | $75.00 | $38.89 |
| 5 | Embankment (final)(OC)(type A) (132-7001) | CY | 555 | $21.00 | $35.00 | $63.50 | $30.00 | $68.25 | $75.00 | $51.78 |
| 6 | Furn & place topsoil (4") (160-7002) | SY | 3,664 | $2.00 | $5.00 | $3.00 | $1.30 | $8.40 | $4.00 | $4.16 |
| 7 | Bond fiber MTRX seed (temporary)(warm) (164-7077) | SY | 1,832 | $1.00 | $0.50 | $1.50 | $2.50 | $1.10 | $1.00 | $1.52 |
| 8 | Bond fiber MTRX seed (temporary)(cool) (164-7078) | SY | 1,832 | $1.00 | $0.50 | $1.50 | $2.50 | $1.10 | $6.00 | $1.52 |
| 9 | Vegetative watering (168-7001) | TGL | 110 | $28.00 | $20.00 | $43.25 | $5.00 | $10.50 | $50.00 | $48.11 |
| 10 | Trench excavation protection (402-7001) | LF | 736 | $14.50 | $1.00 | $5.00 | $1.00 | $6.30 | $8.00 | $22.55 |
| 11 | RC pipe (CL III)(24 in) (464-7005) | LF | 1,019 | $110.00 | $120.00 | $78.00 | $95.00 | $105.00 | $108.00 | $159.45 |
| 12 | Inl(CMP)(pazd-CZ)(FG)(4FTX4FT-4FTX4FT) (465-7165) | EACH | 6 | $7,750.00 | $5,000.00 | $5,696.00 | $9,000.00 | $8,400.00 | $8,000.00 | $7,578.73 |
| 13 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 2 | $2,300.00 | $2,500.00 | $4,060.00 | $2,250.00 | $1,890.00 | $4,000.00 | $2,982.51 |
| 14 | Removing structure (set) (496-7004) | EACH | 14 | $575.00 | $500.00 | $492.50 | $200.00 | $420.00 | $454.00 | $343.48 |
| 15 | Removing structure (pipe) (496-7007) | LF | 364 | $21.00 | $10.00 | $34.25 | $20.00 | $12.60 | $20.00 | $27.78 |
| 16 | Mobilization (500-7001) | LS | 1 | $40,850 | $30,000 | $35,000 | $37,500 | $28,500 | $50,000 | $42,574 |
| 17 | Barricades, signs and traffic handling (502-7001) | MO | 2 | $7,500.00 | $5,000.00 | $11,069 | $15,000 | $1.10 | $15,000 | $2,286.69 |
| 18 | Portable changeable message sign (503-7002) | EACH | 2 | $8,500.00 | $1,000.00 | $4,310.25 | $7,000.00 | $5,250.00 | $8,802.00 | $7,846.78 |
| 19 | Rock filter dams (install) (type 2) (506-7002) | LF | 160 | $60.00 | $20.00 | $47.75 | $47.50 | $21.00 | $47.00 | $51.71 |
| 20 | Rock filter dams (remove) (506-7011) | LF | 160 | $21.00 | $5.00 | $17.75 | $21.50 | $10.50 | $13.00 | $19.56 |
| 21 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 120 | $6.00 | $5.00 | $4.50 | $8.75 | $10.50 | $50.00 | $4.97 |
| 22 | Biodegradable erosion control logs (remove) (506-7046) | LF | 120 | $1.30 | $1.00 | $1.25 | $3.75 | $5.25 | $1.00 | $1.33 |
| 23 | Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009) | LF | 240 | $40.00 | $80.00 | $13.00 | $20.00 | $105.00 | $60.00 | $89.06 |
| 24 | Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010) | LF | 120 | $45.00 | $80.00 | $22.00 | $25.00 | $105.00 | $60.00 | $89.06 |
| 25 | Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057) | LF | 240 | $13.00 | $20.00 | $8.00 | $15.00 | $21.00 | $15.00 | $50.07 |
| 26 | Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058) | LF | 120 | $20.00 | $20.00 | $12.00 | $15.00 | $21.00 | $15.00 | $48.98 |
| 27 | Driveways (ACP) (530-7010) | SY | 502 | $70.00 | $100.00 | $87.75 | $118.00 | $115.50 | $75.00 | $115.36 |
| 28 | Remove metal beam guard fence (542-7001) | LF | 451 | $4.00 | $5.00 | $7.25 | $5.00 | $4.20 | $5.00 | $1.99 |
| 29 | Remove terminal anchor section (542-7002) | EACH | 4 | $508.00 | $500.00 | $313.00 | $210.00 | $840.00 | $175.00 | $248.75 |
| 30 | Guardrail end treatment (remove) (544-7003) | EACH | 4 | $398.00 | $500.00 | $313.00 | $225.00 | $840.00 | $237.00 | $331.77 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of June 2, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.