TxDOT contract A00207502 bid tabulation

Bridge Replacement, FM 1107 (At Ecleto Creek to .). Let by Texas DOT on May 7, 2026, Wilson, San Antonio District. 17 bids received; low bid $948,875 by D&S Concrete Contractors LLC, -21% against the engineer's estimate of $1,202,996.

Owner
Texas DOT
Letting
07 MAY 2026
Pay items
42
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1D&S Concrete Contractors LLC$948,875Low-21%
2Presidio Contracting, LLC$1,007,380+6.0%-16%
3E-Z Bel Construction, LLC$1,022,050+8.0%-15%
4R Construction Civil, LLC$1,098,822+16%-9.0%
5Hunter Industries, LTD.$1,111,509+17%-8.0%
6Acme Bridge Company, Inc.$1,138,652+20%-5.0%
7STX Civil$1,154,699+22%-4.0%
8Texas Steel Industrial Placing, LLC$1,171,456+23%-3.0%
9Skyline Bridge LLC$1,190,954+26%-1.0%
10Joe Bland Construction LLC$1,239,732+31%+3.0%
11Dean Word Company, LTD.$1,367,333+44%+14%
12CK Newberry, LLC$1,380,458+45%+15%
13Icos Management, LLC$1,382,348+46%+15%
14J. Carroll Weaver, Inc.$1,388,823+46%+15%
15Delgado'S Contractors, LLC$1,585,539+67%+32%
16Hodges and Son Construction Company, Inc.$1,636,689+72%+36%
17Rucoba & Maya Construction, LLC$1,659,957+75%+38%
TxDOT contract A00207502: bids by rank

Engineer's estimate: $1,202,996.

Bid tabulation

LinePay itemUnitQuantityEstimate1. D&S Concrete Contractors LLC2. Presidio Contracting, LLC3. E-Z Bel Construction, LLC4. R Construction Civil, LLC5. Hunter Industries, LTD.6. Acme Bridge Company, Inc.
1Removing concrete (riprap) (104-7006)SY200$6.46$40.00$14.70$33.00$9.00$21.00$16.20
2Removing stab base and asphalt pavement(0"-16") (105-7129)SY2,625$12.26$10.00$6.75$6.50$5.00$8.51$6.80
3Excavation (roadway) (110-7001)CY1,437$17.70$28.00$19.30$18.00$27.00$21.10$16.10
4Excavation (channel) (110-7002)CY616$148.40$28.00$20.30$18.00$27.00$21.10$21.00
5Embankment (final)(DC)(type C1) (132-7008)CY942$24.41$30.00$75.00$63.00$22.00$33.38$52.50
6Embankment (final)(OC)(type C2) (132-7009)CY166$22.00$40.00$80.00$11.00$27.00$20.80$69.90
7Compost manuf topsoil (4") (161-7002)SY4,776$1.36$1.00$3.85$2.40$4.00$2.30$3.15
8Drill seed (permanent_rural_sand) (164-7009)SY4,776$1.25$2.00$0.50$0.40$0.50$0.35$0.37
9Drill seed (temporary_warm_cool) (164-7015)SY4,776$2.00$1.00$0.35$0.20$0.50$0.20$0.21
10Vegetative watering (168-7001)TGL74$36.28$5.00$70.00$55.00$250.00$28.00$71.20
11Soil ret BLKT(SL_mod_sand_short_spry) (169-7019)SY4,776$1.00$2.00$1.60$1.25$1.60$1.25$1.35
12FL BS(cip)(type D, GR 1-2 or 5)(final pos) (247-7192)CY1,014$60.00$2.00$79.30$93.00$58.00$69.93$101.00
13Prime coat(MC-30 or AE-P) (310-7013)GAL812$3.19$7.00$6.30$12.50$21.00$7.90$9.40
14Asphalt (AC-20-5TR) (316-7007)GAL50$12.00$22.00$1.00$25.00$11.00$25.80$19.80
15Asphalt (AC-15P, CHFRS2P or CRS2P) (316-7072)GAL3,260$4.89$5.00$7.50$8.00$11.00$8.00$7.70
16Aggregate (type-PB, GR-3)(sac-B) (316-7208)CY55$175.00$500.00$441.55$425.00$530.00$252.80$308.00
17Aggregate (type-PB, GR-4)(sac-B) (316-7211)CY53$119.91$490.00$441.55$450.00$530.00$245.94$325.00
18D-GR HMA type D PG76-22 (341-7056)TON21$115.90$200.00$1.00$180.00$320.00$481.00$532.00
19Riprap (mow strip)(4 in) (432-7013)CY22$575.00$700.00$825.00$680.00$650.00$640.50$941.00
20Rail (type T223) (450-7008)LF444$156.72$175.00$113.00$219.00$230.00$120.75$129.00
21Concrete box culvert (10 FT X 10 FT) (462-7038)LF240$1,500.00$1,400.00$900.00$830.00$900.00$1,286.25$1,150.00
22Wingwall (PW - 1) (HW=11 FT) (466-7181)EACH2$66,011$40,000$86,000$77,000$125,000$116,209$114,000
23Removing structure (headwall) (496-7006)EACH2$5,140.90$5,000.00$1,450.00$2,500.00$1,185.00$1,890.00$1,270.00
24Removing structure (bridge 0 - 99 FT length) (496-7009)EACH1$40,000$20,000$5,900.00$34,000$20,500$18,375$15,600
25Mobilization (500-7001)LS1$109,618$90,000$100,000$95,000$25,000$108,210$105,000
26Barricades, signs and traffic handling (502-7001)MO6$15,000$3,000.00$3,550.00$1,425.00$7,700.00$1,795.82$784.00
27Portable changeable message sign (503-7001)DAY170$76.44$25.00$43.30$105.00$80.00$152.29$83.00
28Portable changeable message sign (503-7002)EACH2$4,500.00$1,300.00$7,360.00$5,850.00$13,500$5,076.48$13,600
29Rock filter dams (install) (type 1) (506-7001)LF100$30.66$50.00$45.20$40.00$45.00$40.00$42.60
30Rock filter dams (remove) (506-7011)LF100$15.74$10.00$8.80$8.00$9.00$8.00$8.50
31Temporary sediment control fence (install) (506-7039)LF2,185$3.45$5.00$3.70$3.25$4.00$3.25$3.45
32Temporary sediment control fence (remove) (506-7041)LF2,185$0.90$0.50$0.50$0.75$0.50$0.75$0.80
33Metal W-beam guard fence (timber post) (540-7001)LF500$28.50$25.00$26.60$25.25$28.00$25.32$27.00
34Metal beam guard fence trans (thrie-beam) (540-7005)EACH4$2,500.00$1,500.00$2,625.00$1,885.00$1,850.00$2,384.80$2,010.00
35Downstream anchor terminal section (540-7015)EACH2$1,200.00$2,000.00$1,330.00$1,264.00$1,500.00$1,264.14$1,350.00
36Guardrail end treatment (install) (544-7001)EACH2$3,200.00$1,250.00$3,740.00$3,555.00$3,700.00$3,554.65$3,790.00
37Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266)LF2,240$0.74$1.50$2.10$2.00$2.00$2.00$2.15
38Reflectorized profile pavement marking type I(Y)6"(solid)(100MIL) (666-7270)LF1,120$0.74$1.50$2.10$2.00$2.00$2.00$2.15
39Reflectorized profile pavement marking type I(Y)6"(broken)(100MIL) (666-7274)LF290$0.70$2.00$2.10$2.00$2.00$2.00$2.15
40Pavement sler 6" (666-7347)LF3,650$0.19$2.00$1.05$1.00$1.00$1.00$1.05
41Reflectorized pavement marker type II-A-A (672-7004)EACH29$15.00$5.00$8.00$7.50$8.00$7.50$8.00
42Install bridge identification numbers (4019-7001)EACH2$500.00$200.00$400.00$550.00$850.00$409.81$82.50
TxDOT contract A00207502: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of May 7, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy