TxDOT contract A00136986 bid tabulation
Bridge Replacement, IH 10 (At SH 80 to .). Let by Texas DOT on August 6, 2026, Guadalupe, San Antonio District. 8 bids received; low bid $5,753,739 by Hunter Industries, LTD., +0.9% against the engineer's estimate of $5,699,899.
- Owner
- Texas DOT
- Letting
- 06 AUG 2026
- Pay items
- 110
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Hunter Industries, LTD. | $5,753,739 | Low | +1.0% |
| 2 | Texas Steel Industrial Placing, LLC | $5,956,399 | +4.0% | +5.0% |
| 3 | J3 Company, LLC | $6,294,204 | +9.0% | +10% |
| 4 | Capital Excavation Company | $6,596,524 | +15% | +16% |
| 5 | Dean Word Company, LTD. | $6,832,789 | +19% | +20% |
| 6 | E-Z Bel Construction, LLC | $6,896,186 | +20% | +21% |
| 7 | Joe Bland Construction LLC | $7,163,025 | +24% | +26% |
| 8 | Lucania Contractors LLC | $7,955,804 | +38% | +40% |
Engineer's estimate: $5,699,899.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Hunter Industries, LTD. | 2. Texas Steel Industrial Placing, LLC | 3. J3 Company, LLC | 4. Capital Excavation Company | 5. Dean Word Company, LTD. | 6. E-Z Bel Construction, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 23 | $5,000.00 | $889.65 | $5,500.00 | $7,500.00 | $1,200.00 | $3,771.50 | $4,400.00 |
| 2 | Removing concrete (riprap) (104-7006) | SY | 2,463 | $12.50 | $16.35 | $20.00 | $35.00 | $19.20 | $13.25 | $20.00 |
| 3 | Removing concrete (driveways) (104-7011) | SY | 775 | $10.00 | $16.35 | $20.00 | $25.00 | $29.25 | $15.50 | $20.00 |
| 4 | Removing concrete (sawcut) (104-7020) | LF | 1,452 | $50.00 | $12.04 | $8.00 | $5.00 | $3.85 | $4.00 | $15.00 |
| 5 | Remove (16"-20") TRT/untrt base & asphalt pavement (105-7016) | SY | 7,516 | $40.00 | $9.30 | $10.00 | $12.00 | $10.80 | $9.50 | $13.00 |
| 6 | Remove (0"-12") TRT/untrt base & asphalt pavement (105-7052) | SY | 513 | $25.00 | $8.31 | $10.00 | $12.00 | $13.05 | $11.50 | $25.00 |
| 7 | Excavation (roadway) (110-7001) | CY | 424 | $19.00 | $35.97 | $25.00 | $35.00 | $30.60 | $33.00 | $21.00 |
| 8 | Embankment (final)(OC)(type B) (132-7003) | CY | 1,307 | $30.00 | $35.97 | $25.00 | $35.00 | $24.25 | $29.00 | $21.50 |
| 9 | Broadcast seed (permanent_rural_clay) (164-7002) | SY | 6,460 | $1.00 | $0.35 | $0.23 | $0.30 | $0.25 | $0.50 | $0.40 |
| 10 | Broadcast seed (temporary_warm) (164-7005) | SY | 3,230 | $0.17 | $0.39 | $0.14 | $0.30 | $0.15 | $0.50 | $0.40 |
| 11 | Broadcast seed (temporary_cool) (164-7006) | SY | 3,230 | $0.20 | $0.39 | $0.13 | $0.30 | $0.15 | $0.50 | $0.40 |
| 12 | Vegetative watering (168-7001) | TGL | 101 | $28.00 | $22.96 | $50.00 | $65.00 | $62.85 | $76.75 | $80.00 |
| 13 | Proof rolling (216-7001) | HR | 232 | $120.00 | $110.00 | $120.00 | $90.00 | $89.15 | $140.00 | $125.00 |
| 14 | FL BS (compacted in place)(type D GR1-2 or 5)(8") (247-7089) | SY | 9,148 | $30.00 | $14.42 | $25.00 | $24.00 | $31.00 | $17.75 | $26.25 |
| 15 | Salvage, haul & stockpile reclaimed asphalt PV (0 to 2") (305-7002) | SY | 5,584 | $5.00 | $1.89 | $4.00 | $4.00 | $1.85 | $3.75 | $5.00 |
| 16 | Prime coat(MC-30 or AE-P) (310-7013) | GAL | 1,806 | $4.00 | $4.93 | $5.00 | $6.00 | $5.30 | $4.25 | $6.00 |
| 17 | D-GR HMA type-B PG64-22 (341-7001) | TON | 2,583 | $90.00 | $96.38 | $120.00 | $125.00 | $132.00 | $102.50 | $121.00 |
| 18 | D-GR HMA type-B PG64-22 (level-UP) (341-7004) | TON | 47 | $95.00 | $159.52 | $125.00 | $275.00 | $280.00 | $154.50 | $126.00 |
| 19 | D-GR HMA type-C PG64-22 (341-7015) | TON | 1,122 | $100.00 | $98.54 | $125.00 | $165.00 | $165.00 | $116.50 | $126.00 |
| 20 | D-GR HMA type-C PG64-22 (level-UP) (341-7018) | TON | 272 | $200.00 | $107.34 | $130.00 | $140.00 | $142.00 | $173.50 | $131.00 |
| 21 | D-GR HMA type-C sac-B PG70-22 (341-7024) | TON | 119 | $110.00 | $109.62 | $140.00 | $180.00 | $182.00 | $175.50 | $141.00 |
| 22 | SP mixes SP-C sac-A PG76-22 (344-7030) | TON | 1,590 | $150.00 | $117.27 | $160.00 | $145.00 | $152.00 | $139.75 | $161.00 |
| 23 | Flexible pavement structure repair(9") (351-7008) | SY | 1,375 | $95.00 | $87.43 | $80.00 | $75.00 | $62.35 | $73.75 | $81.00 |
| 24 | Planing asphalt concrete pavement(2") (354-7051) | SY | 1,277 | $2.00 | $3.21 | $6.00 | $8.00 | $7.15 | $4.25 | $6.00 |
| 25 | Cem stabil BKFL (400-7010) | CY | 340.30 | $120.00 | $125.00 | $185.00 | $200.00 | $240.00 | $232.25 | $240.00 |
| 26 | Temporary special shoring (403-7001) | SF | 103 | $25.00 | $75.00 | $50.00 | $220.00 | $134.00 | $34.50 | $28.00 |
| 27 | Drilled shaft (18 in) (416-7002) | LF | 132 | $150.00 | $70.46 | $90.00 | $120.00 | $166.00 | $97.00 | $79.00 |
| 28 | Drilled shaft (36 in) (416-7006) | LF | 462 | $250.00 | $260.79 | $260.00 | $180.00 | $320.00 | $293.00 | $275.00 |
| 29 | Drilled shaft (48 in) (416-7008) | LF | 580 | $350.00 | $477.53 | $460.00 | $220.00 | $470.00 | $526.00 | $460.00 |
| 30 | Class C concrete (abutment) (420-7012) | CY | 92.20 | $1,200.00 | $1,600.00 | $1,100.00 | $1,500.00 | $1,790.00 | $1,817.00 | $1,640.00 |
| 31 | Class C concrete (cap) (420-7022) | CY | 99.30 | $1,500.00 | $1,510.00 | $1,500.00 | $1,700.00 | $2,010.00 | $3,069.75 | $2,370.00 |
| 32 | Class C concrete (column) (420-7038) | CY | 148.90 | $1,550.00 | $1,900.00 | $1,400.00 | $1,700.00 | $2,480.00 | $3,630.25 | $3,530.00 |
| 33 | Class C concrete (crashwall) (420-7050) | CY | 62.50 | $750.00 | $1,900.00 | $1,200.00 | $1,200.00 | $1,220.00 | $2,021.50 | $2,330.00 |
| 34 | Reinforced concrete slab (422-7001) | SF | 22,400 | $20.00 | $30.50 | $22.00 | $26.00 | $27.70 | $37.75 | $32.50 |
| 35 | Approach slab (422-7013) | CY | 112.30 | $600.00 | $650.00 | $600.00 | $550.00 | $840.00 | $672.75 | $684.50 |
| 36 | Prestressed concrete girder (TX46) (425-7004) | LF | 2,883.89 | $250.00 | $200.00 | $220.00 | $235.00 | $230.00 | $272.25 | $250.00 |
| 37 | Riprap (concrete)(4 in) (432-7001) | CY | 520.90 | $590.00 | $467.50 | $450.00 | $500.00 | $770.00 | $648.25 | $460.00 |
| 38 | Riprap (mow strip)(4 in) (432-7013) | CY | 11 | $640.00 | $603.00 | $580.00 | $950.00 | $1,160.00 | $992.00 | $675.00 |
| 39 | Rail (type SSTR) (450-7024) | LF | 708 | $70.00 | $67.00 | $100.00 | $110.00 | $107.00 | $104.50 | $145.00 |
| 40 | Sealed expansion joint (4 in) (SEJ - M) (454-7004) | LF | 220.95 | $220.00 | $250.00 | $200.00 | $220.00 | $280.00 | $293.75 | $370.00 |
| 41 | RC pipe (arch)(CL III)(des 1) (464-7040) | LF | 74 | $200.00 | $211.95 | $200.00 | $300.00 | $310.00 | $222.25 | $190.00 |
| 42 | Set (type II)(18 in)(RCP)(3:1)(P) (467-7467) | EACH | 4 | $2,000.00 | $1,800.00 | $2,000.00 | $2,500.00 | $2,780.00 | $2,436.00 | $1,150.00 |
| 43 | Removing structure (bridge 100 - 499 FT length) (496-7010) | EACH | 1 | $100,000 | $189,808 | $300,000 | $300,000 | $242,000 | $279,227 | $258,000 |
| 44 | Mobilization (500-7001) | LS | 1 | $507,991 | $570,060 | $595,000 | $500,000 | $550,000 | $350,000 | $675,000 |
| 45 | Barricades, signs and traffic handling (502-7001) | MO | 14 | $8,000.00 | $25,000 | $12,000 | $17,500 | $5,800.00 | $4,143.00 | $2,400.00 |
| 46 | Portable changeable message sign (503-7001) | DAY | 360 | $85.00 | $61.66 | $75.00 | $100.00 | $70.50 | $83.75 | $130.00 |
| 47 | TMA (stationary) (505-7001) | DAY | 260 | $215.00 | $102.77 | $200.00 | $325.00 | $167.00 | $529.25 | $312.00 |
| 48 | TMA (mobile operation) (505-7003) | DAY | 58 | $140.00 | $256.92 | $200.00 | $1,200.00 | $700.00 | $974.50 | $521.00 |
| 49 | Construction exits (install) (type 1) (506-7020) | SY | 112 | $25.00 | $22.80 | $45.00 | $22.80 | $48.60 | $26.75 | $22.75 |
| 50 | Construction exits (remove) (506-7024) | SY | 112 | $10.00 | $11.50 | $16.00 | $11.50 | $17.30 | $13.50 | $11.50 |
| 51 | Temporary sediment control fence (install) (506-7039) | LF | 2,882 | $3.50 | $3.50 | $2.85 | $3.50 | $3.10 | $4.00 | $3.50 |
| 52 | Temporary sediment control fence (remove) (506-7041) | LF | 2,882 | $1.00 | $0.50 | $1.00 | $0.50 | $1.10 | $0.50 | $0.50 |
| 53 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 199 | $6.00 | $5.50 | $3.25 | $5.50 | $3.50 | $6.50 | $5.50 |
| 54 | Biodegradable erosion control logs (remove) (506-7046) | LF | 199 | $1.50 | $1.00 | $1.00 | $1.00 | $1.10 | $1.25 | $1.00 |
| 55 | Constructing detours (508-7001) | SY | 1,628 | $90.00 | $71.92 | $165.00 | $110.00 | $133.00 | $105.25 | $94.75 |
| 56 | One-way traffic control (flagger cont) (510-7001) | HR | 40 | $85.00 | $104.50 | $150.00 | $100.00 | $260.00 | $377.00 | $312.00 |
| 57 | Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001) | LF | 2,310 | $25.00 | $36.00 | $30.00 | $35.00 | $34.65 | $41.25 | $52.00 |
| 58 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 450 | $6.85 | $24.00 | $20.00 | $15.00 | $19.60 | $5.50 | $4.75 |
| 59 | Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049) | LF | 2,310 | $11.00 | $13.00 | $20.00 | $25.00 | $16.95 | $12.00 | $17.25 |
| 60 | Concrete curb (type II) (529-7002) | LF | 680 | $25.00 | $25.00 | $20.00 | $30.00 | $34.90 | $34.50 | $33.00 |
| 61 | Driveways (concrete) (530-7006) | SY | 824 | $100.00 | $106.89 | $98.00 | $120.00 | $160.00 | $135.25 | $115.00 |
| 62 | Driveways (ACP) (530-7010) | SY | 349 | $50.00 | $47.85 | $25.00 | $90.00 | $152.00 | $65.50 | $50.50 |
| 63 | Metal W-beam guard fence (timber post) (540-7001) | LF | 38 | $25.00 | $26.00 | $25.00 | $28.00 | $27.00 | $29.25 | $29.75 |
| 64 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 4 | $2,300.00 | $1,976.00 | $1,900.00 | $2,000.00 | $2,050.00 | $3,622.25 | $2,200.00 |
| 65 | Downstream anchor terminal section (540-7015) | EACH | 2 | $1,300.00 | $1,430.00 | $1,375.00 | $1,500.00 | $1,480.00 | $1,614.75 | $1,900.00 |
| 66 | Remove metal beam guard fence (542-7001) | LF | 858 | $2.75 | $1.56 | $1.50 | $2.00 | $1.60 | $1.75 | $3.50 |
| 67 | Cable barrier system (install)(TL-4) (543-7002) | LF | 250 | $12.00 | $33.28 | $32.00 | $40.00 | $34.55 | $37.50 | $38.00 |
| 68 | Cable barrier terminal sec (install)(TL-4) (543-7018) | EACH | 2 | $2,200.00 | $6,552.00 | $6,300.00 | $6,800.00 | $6,800.00 | $7,398.50 | $5,500.00 |
| 69 | Cable barrier (remove) (543-7037) | LF | 250 | $5.00 | $0.78 | $0.75 | $1.00 | $0.80 | $1.00 | $6.25 |
| 70 | Cable barrier terminal section (remove) (543-7038) | EACH | 2 | $1,050.00 | $364.00 | $350.00 | $400.00 | $380.00 | $411.00 | $2,500.00 |
| 71 | Guardrail end treatment (install) (544-7001) | EACH | 1 | $3,200.00 | $3,723.20 | $3,580.00 | $4,000.00 | $3,870.00 | $4,204.25 | $3,800.00 |
| 72 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 2 | $1,500.00 | $572.00 | $550.00 | $750.00 | $590.00 | $646.00 | $919.00 |
| 73 | Crash cushion attenuator (remove) (545-7004) | EACH | 8 | $1,000.00 | $468.00 | $450.00 | $750.00 | $490.00 | $528.50 | $918.00 |
| 74 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 8 | $8,400.00 | $6,760.00 | $6,500.00 | $7,000.00 | $7,000.00 | $7,633.50 | $7,800.00 |
| 75 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 13 | $500.00 | $550.00 | $725.00 | $550.00 | $590.00 | $646.00 | $550.00 |
| 76 | Relocate SM RD SN sup&AM type S80 (644-7067) | EACH | 13 | $820.00 | $550.00 | $900.00 | $550.00 | $590.00 | $646.00 | $550.00 |
| 77 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 1,202 | $0.30 | $0.35 | $0.35 | $0.35 | $0.35 | $0.50 | $0.35 |
| 78 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 1,122 | $0.30 | $0.35 | $0.35 | $0.35 | $0.35 | $0.50 | $0.35 |
| 79 | Work zone pavement marking removing (reflectorized) type II-A-A (662-7051) | EACH | 391 | $3.86 | $3.50 | $3.50 | $3.50 | $3.75 | $4.00 | $3.50 |
| 80 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 19,358 | $0.80 | $0.90 | $0.90 | $0.90 | $0.95 | $1.00 | $0.90 |
| 81 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 311 | $6.50 | $10.00 | $10.00 | $10.00 | $10.70 | $11.75 | $10.00 |
| 82 | Work zone pavement marking removing (W)18"(yld tri) (662-7093) | EACH | 47 | $40.00 | $50.00 | $50.00 | $50.00 | $53.45 | $58.75 | $50.00 |
| 83 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 14,635 | $0.80 | $0.90 | $0.90 | $0.90 | $0.95 | $1.00 | $0.90 |
| 84 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 1,053 | $1.00 | $1.00 | $1.00 | $1.00 | $1.05 | $1.25 | $1.00 |
| 85 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 69 | $8.00 | $8.00 | $8.00 | $8.00 | $8.55 | $9.50 | $8.00 |
| 86 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 8 | $160.00 | $175.00 | $175.00 | $175.00 | $187.00 | $205.50 | $175.00 |
| 87 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 4 | $190.00 | $200.00 | $200.00 | $200.00 | $214.00 | $234.75 | $200.00 |
| 88 | Ref pavement marking type I(W)36"(yld tri)(100MIL) (666-7090) | EACH | 28 | $50.00 | $35.00 | $35.00 | $35.00 | $37.40 | $41.00 | $35.00 |
| 89 | Reflectorized pavement marking type I(Y)(med nose)(100MIL) (666-7132) | EACH | 3 | $350.00 | $350.00 | $350.00 | $350.00 | $370.00 | $411.00 | $350.00 |
| 90 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 3,768 | $0.16 | $0.35 | $0.35 | $0.35 | $0.35 | $0.50 | $0.35 |
| 91 | Reflectorized pavement marking type II (W) 8" (solid) (666-7179) | LF | 1,053 | $0.30 | $0.45 | $0.45 | $0.45 | $0.50 | $0.50 | $0.45 |
| 92 | Reflectorized pavement marking type II (W) 24" (solid) (666-7184) | LF | 69 | $4.75 | $4.00 | $4.00 | $4.00 | $4.30 | $4.75 | $4.00 |
| 93 | Reflectorized pavement marking type II (W) (arrow) (666-7186) | EACH | 8 | $90.00 | $100.00 | $100.00 | $100.00 | $107.00 | $117.50 | $100.00 |
| 94 | Reflectorized pavement marking type II (W) (word) (666-7194) | EACH | 4 | $100.00 | $100.00 | $100.00 | $100.00 | $107.00 | $117.50 | $100.00 |
| 95 | Reflectorized pavement marking type II (W) 36" (yld tri) (666-7201) | EACH | 28 | $25.00 | $35.00 | $35.00 | $35.00 | $37.40 | $41.00 | $35.00 |
| 96 | Reflectorized pavement marking type II (Y) 6" (broken) (666-7211) | LF | 204 | $0.20 | $0.35 | $0.35 | $0.35 | $0.35 | $0.50 | $0.35 |
| 97 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 6,095 | $0.16 | $0.35 | $0.35 | $0.35 | $0.35 | $0.50 | $0.35 |
| 98 | Reflectorized pavement marking type II (Y) (med nose) (666-7220) | EACH | 3 | $250.00 | $250.00 | $250.00 | $250.00 | $270.00 | $293.50 | $250.00 |
| 99 | Type I high perf PM (W)6"(solid)(100MIL) (666-7293) | LF | 3,768 | $1.00 | $0.75 | $0.75 | $0.75 | $0.80 | $1.00 | $0.75 |
| 100 | Type I high perf PM (Y)6"(broken)(100MIL) (666-7302) | LF | 204 | $1.00 | $0.75 | $0.75 | $0.75 | $0.80 | $1.00 | $0.75 |
| 101 | Type I high perf PM (Y)6"(solid)(100MIL) (666-7305) | LF | 6,095 | $1.00 | $0.75 | $0.75 | $0.75 | $0.80 | $1.00 | $0.75 |
| 102 | Reflectorized pavement marker type I-C (672-7002) | EACH | 54 | $4.00 | $4.50 | $4.50 | $4.50 | $4.80 | $5.25 | $4.50 |
| 103 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 302 | $4.00 | $4.50 | $4.50 | $4.50 | $4.80 | $5.25 | $4.50 |
| 104 | Eliminating existing PM & markers (4") (677-7001) | LF | 8,200 | $0.25 | $0.45 | $0.45 | $0.45 | $0.50 | $0.50 | $0.45 |
| 105 | Eliminating existing PM & markers (24") (677-7008) | LF | 219 | $3.50 | $6.00 | $6.00 | $6.00 | $6.40 | $7.00 | $6.00 |
| 106 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 4 | $80.00 | $150.00 | $150.00 | $150.00 | $160.00 | $176.25 | $150.00 |
| 107 | Eliminating existing PM & markers (18")(yld tri) (677-7023) | EACH | 12 | $45.00 | $50.00 | $50.00 | $50.00 | $53.45 | $58.75 | $50.00 |
| 108 | Underseal course (3006-7001) | GAL | 241 | $3.00 | $4.54 | $4.50 | $6.00 | $6.35 | $5.00 | $4.50 |
| 109 | Bonding course (3007-7001) | GAL | 4,837 | $3.00 | $3.24 | $4.50 | $4.00 | $4.75 | $4.25 | $4.50 |
| 110 | Install bridge identification numbers (4019-7001) | EACH | 2 | $550.00 | $2,190.78 | $500.00 | $500.00 | $630.00 | $164.50 | $950.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of August 6, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.