TxDOT contract A00197420 bid tabulation
Rehabilitate Existing Roadway, FM 2790 (FM 471 to Medina/Atascosa C/L). Let by Texas DOT on March 4, 2026, Medina, San Antonio District. 9 bids received; low bid $11,778,114 by Dean Word Company, LTD., -27% against the engineer's estimate of $16,198,822.
- Owner
- Texas DOT
- Letting
- 04 MAR 2026
- Pay items
- 150
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Dean Word Company, LTD. | $11,778,114 | Low | -27% |
| 2 | Hunter Industries, LTD. | $11,904,134 | +1.0% | -27% |
| 3 | Salinas Construction Technologies, LTD. | $11,999,615 | +2.0% | -26% |
| 4 | D & D Contractors, Inc. | $13,272,109 | +13% | -18% |
| 5 | Texas Materials Group, Inc. | $13,360,412 | +13% | -18% |
| 6 | E-Z Bel Construction, LLC | $13,986,481 | +19% | -14% |
| 7 | 3LW Civil LLC | $14,280,198 | +21% | -12% |
| 8 | J3 Company, LLC | $14,542,659 | +23% | -10% |
| 9 | Anderson Columbia Co., Inc. | $17,197,678 | +46% | +6.0% |
Engineer's estimate: $16,198,822.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Dean Word Company, LTD. | 2. Hunter Industries, LTD. | 3. Salinas Construction Technologies, LTD. | 4. D & D Contractors, Inc. | 5. Texas Materials Group, Inc. | 6. E-Z Bel Construction, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 308 | $4,500.00 | $800.00 | $388.08 | $202.15 | $139.15 | $140.00 | $2,400.00 |
| 2 | Removing concrete (riprap) (104-7006) | SY | 152 | $18.00 | $56.05 | $13.08 | $27.08 | $14.69 | $35.00 | $21.00 |
| 3 | Removing concrete (driveways) (104-7011) | SY | 2,266 | $19.00 | $25.60 | $16.35 | $22.10 | $14.69 | $30.00 | $18.00 |
| 4 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 571 | $20.00 | $30.70 | $13.08 | $13.92 | $14.69 | $29.00 | $21.00 |
| 5 | Removing concrete (curb) (104-7016) | LF | 293 | $6.00 | $12.30 | $9.81 | $3.83 | $14.69 | $13.00 | $12.50 |
| 6 | Remove (2"-6") TRT/untrt base & asphalt pavement (105-7002) | SY | 7,882 | $7.00 | $4.35 | $2.77 | $3.21 | $9.56 | $7.60 | $7.25 |
| 7 | Remove (7"-11") TRT/untrt base & asphalt pavement (105-7007) | SY | 59,324 | $10.00 | $2.70 | $5.39 | $7.17 | $7.14 | $8.60 | $6.25 |
| 8 | Excavation (roadway) (110-7001) | CY | 2,172 | $17.00 | $22.55 | $16.35 | $16.51 | $27.76 | $23.00 | $24.00 |
| 9 | Subgr widen (OC) (112-7001) | STA | 59 | $450.00 | $1,612.10 | $725.94 | $791.67 | $1,147.70 | $1,540.00 | $1,150.00 |
| 10 | Embankment (final)(OC)(type C) (132-7005) | CY | 3,625 | $22.00 | $25.00 | $16.35 | $14.23 | $16.52 | $13.00 | $22.00 |
| 11 | Broadcast seed (permanent_rural_clay) (164-7002) | SY | 209,280 | $0.75 | $0.25 | $0.20 | $0.19 | $0.26 | $0.21 | $0.20 |
| 12 | Broadcast seed (temporary_warm_cool) (164-7007) | SY | 209,280 | $0.25 | $0.25 | $0.32 | $0.16 | $0.26 | $0.21 | $0.20 |
| 13 | Vegetative watering (168-7001) | TGL | 3,431 | $25.00 | $1.50 | $20.72 | $21.93 | $15.73 | $30.00 | $59.00 |
| 14 | FL BS (roadway del)(type A GR 1-2)(final pos) (247-7259) | CY | 16,268 | $65.00 | $61.25 | $61.91 | $50.93 | $90.93 | $62.75 | $75.75 |
| 15 | Lime (com or QK)(slurry) or QK(dry) (260-7001) | TON | 1,853 | $308.49 | $355.35 | $326.35 | $349.39 | $413.41 | $330.00 | $365.00 |
| 16 | Lime TRT (subgrade) (8") (260-7020) | SY | 93,122 | $2.00 | $4.25 | $2.86 | $2.73 | $2.88 | $5.22 | $3.25 |
| 17 | Emulsion (high yield) (290-7005) | TON | 684 | $775.00 | $1,346.50 | $1,309.68 | $1,500.07 | $1,597.87 | $1,295.00 | $1,575.00 |
| 18 | Emul TRT (new base) (6") (290-7021) | SY | 89,283 | $4.30 | $4.50 | $3.30 | $3.77 | $4.38 | $4.22 | $6.35 |
| 19 | Cement (291-7001) | TON | 283 | $242.60 | $215.00 | $197.95 | $225.87 | $231.14 | $183.00 | $255.00 |
| 20 | Prime coat(MC-30 or AE-P) (310-7013) | GAL | 1,647 | $3.93 | $5.50 | $4.51 | $6.06 | $4.50 | $4.35 | $3.50 |
| 21 | Asphalt (RC-250) (316-7016) | GAL | 17,860 | $6.00 | $4.55 | $4.52 | $5.89 | $5.20 | $4.40 | $3.50 |
| 22 | Aggregate (type-B, GR-5)(sac-B) (316-7175) | CY | 653 | $93.96 | $117.40 | $81.58 | $140.17 | $225.00 | $137.50 | $175.00 |
| 23 | D-GR HMA type-B PG64-22 (341-7001) | TON | 6,719 | $105.00 | $86.05 | $82.96 | $77.91 | $83.00 | $80.50 | $97.00 |
| 24 | SP mixes SP-C sac-B PG76-22 (344-7031) | TON | 13,308 | $92.00 | $95.40 | $91.52 | $89.58 | $94.50 | $95.00 | $66.50 |
| 25 | Planing asphalt concrete pavement(4" to 6") (354-7040) | SY | 18,458 | $7.00 | $2.20 | $2.36 | $4.13 | $4.10 | $3.50 | $3.75 |
| 26 | Planing asphalt concrete pavement(2") (354-7051) | SY | 2,121 | $5.00 | $5.65 | $1.83 | $7.65 | $3.60 | $1.60 | $2.00 |
| 27 | Cut and restore pavement (flex base) (400-7009) | SY | 26 | $209.74 | $167.85 | $85.00 | $130.36 | $32.00 | $75.00 | $40.00 |
| 28 | Flowable backfill (401-7001) | CY | 15 | $220.00 | $416.25 | $376.90 | $242.07 | $206.67 | $157.00 | $255.00 |
| 29 | Temporary special shoring (403-7001) | SF | 288 | $3.00 | $5.20 | $63.78 | $86.63 | $40.34 | $66.00 | $21.00 |
| 30 | Class C concrete (collar) (420-7061) | EACH | 12 | $1,256.50 | $813.90 | $695.82 | $1,767.23 | $1,331.25 | $4,000.00 | $1,050.00 |
| 31 | Riprap (concrete)(5 in) (432-7002) | CY | 9 | $609.22 | $566.10 | $638.66 | $1,064.49 | $673.44 | $600.00 | $550.00 |
| 32 | Riprap (concrete)(6 in) (432-7003) | CY | 35 | $13.13 | $565.90 | $685.11 | $682.76 | $722.41 | $600.00 | $550.00 |
| 33 | Riprap (concrete)(CL A) (432-7004) | CY | 6 | $527.57 | $1,075.35 | $632.85 | $1,068.80 | $667.31 | $750.00 | $1,200.00 |
| 34 | Riprap (mow strip)(4 in) (432-7013) | CY | 152 | $650.58 | $616.35 | $679.30 | $686.81 | $716.28 | $560.00 | $725.00 |
| 35 | Riprap (stone protection)(12 in) (432-7041) | CY | 14 | $280.00 | $529.55 | $400.00 | $493.26 | $257.13 | $230.00 | $269.00 |
| 36 | CMP (gal steel 24 in) (460-7005) | LF | 27 | $233.08 | $139.85 | $98.57 | $93.31 | $79.59 | $97.00 | $164.00 |
| 37 | CMP AR (gal steel des 2) (460-7016) | LF | 119 | $233.00 | $62.35 | $69.58 | $66.80 | $73.46 | $80.30 | $129.00 |
| 38 | CMP AR (gal steel des 3) (460-7018) | LF | 39 | $112.91 | $132.10 | $86.98 | $134.61 | $91.84 | $101.00 | $391.00 |
| 39 | Concrete box culvert (7 FT X 4 FT) (462-7016) | LF | 74 | $834.14 | $1,248.40 | $985.74 | $958.37 | $1,040.76 | $1,154.00 | $1,175.00 |
| 40 | RC pipe (CL III)(12 in) (464-7001) | LF | 1,380 | $85.00 | $67.20 | $60.30 | $74.88 | $63.67 | $72.75 | $59.00 |
| 41 | RC pipe (CL III)(18 in) (464-7003) | LF | 237 | $95.00 | $73.05 | $75.38 | $131.01 | $79.59 | $75.10 | $64.00 |
| 42 | RC pipe (CL III)(24 in) (464-7005) | LF | 647 | $102.74 | $90.25 | $98.57 | $102.56 | $104.08 | $98.25 | $110.00 |
| 43 | Wingwall (FW - 0) (HW=5 FT) (466-7147) | EACH | 4 | $18,394 | $27,967 | $8,593.36 | $17,903 | $9,073.00 | $9,963.00 | $19,500 |
| 44 | Wingwall (FW - S) (HW=6 FT) (466-7162) | EACH | 1 | $20,725 | $34,434 | $10,321 | $17,467 | $10,897 | $12,460 | $38,000 |
| 45 | Wingwall (PW - 2) (HW=4 FT) (466-7188) | EACH | 2 | $15,000 | $25,195 | $16,816 | $14,191 | $17,754 | $11,562 | $34,000 |
| 46 | Set (type II) (12 in) (RCP) (6: 1) (P) (467-7292) | EACH | 86 | $800.00 | $1,434.35 | $746.85 | $1,118.50 | $788.53 | $1,259.00 | $1,200.00 |
| 47 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 20 | $2,200.00 | $1,472.85 | $1,449.62 | $1,263.71 | $1,530.54 | $1,554.00 | $1,350.00 |
| 48 | Set (type II) (24 in) (CMP) (3: 1) (C) (467-7321) | EACH | 4 | $2,399.78 | $1,244.30 | $2,087.46 | $1,214.96 | $2,203.97 | $2,101.00 | $1,150.00 |
| 49 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 40 | $2,137.58 | $2,806.15 | $2,087.46 | $1,647.46 | $2,203.97 | $2,060.00 | $1,850.00 |
| 50 | Set (type II) (30 in) (CMP) (3: 1) (C) (467-7341) | EACH | 2 | $2,500.00 | $688.80 | $2,783.27 | $2,011.18 | $2,938.63 | $1,913.00 | $1,350.00 |
| 51 | Set (type II) (30 in) (CMP) (4: 1) (C) (467-7342) | EACH | 1 | $2,500.00 | $741.60 | $3,247.15 | $2,299.93 | $3,428.39 | $2,018.00 | $1,800.00 |
| 52 | Set (type II) (des 2) (CMP) (4: 1) (C) (467-7420) | EACH | 4 | $2,500.00 | $1,280.70 | $1,391.64 | $1,526.50 | $1,469.32 | $1,290.00 | $1,150.00 |
| 53 | Set (type II) (des 3) (CMP) (3: 1) (C) (467-7427) | EACH | 4 | $2,500.00 | $1,298.70 | $1,507.61 | $1,399.34 | $1,591.76 | $1,377.00 | $1,250.00 |
| 54 | Adjusting manholes (water valve box) (479-7007) | EACH | 2 | $862.43 | $1,539.10 | $3,000.00 | $2,028.03 | $1,887.45 | $1,000.00 | $450.00 |
| 55 | Clean existing culverts (480-7001) | EACH | 37 | $3,913.55 | $1,214.10 | $1,043.73 | $2,205.90 | $2,209.73 | $2,500.00 | $1,635.00 |
| 56 | Removing structure (set) (496-7004) | EACH | 108 | $400.00 | $518.90 | $52.19 | $487.08 | $618.99 | $902.00 | $450.00 |
| 57 | Removing structure (wingwall) (496-7005) | EACH | 19 | $2,224.25 | $1,603.75 | $1,043.73 | $2,306.67 | $1,563.77 | $839.00 | $1,150.00 |
| 58 | Removing structure (headwall) (496-7006) | EACH | 15 | $2,824.80 | $1,603.90 | $1,043.73 | $1,753.24 | $1,980.77 | $902.00 | $1,050.00 |
| 59 | Removing structure (pipe) (496-7007) | LF | 1,770 | $18.75 | $23.20 | $9.28 | $13.18 | $20.55 | $9.00 | $8.50 |
| 60 | Removing structure (small) (496-7036) | EACH | 1 | $2,346.09 | $1,554.80 | $2,899.24 | $2,398.34 | $557.09 | $1,060.00 | $1,695.00 |
| 61 | Mobilization (500-7001) | LS | 1 | $1,530,829 | $650,000 | $834,428 | $585,714 | $827,262 | $985,654 | $1,330,000 |
| 62 | Barricades, signs and traffic handling (502-7001) | MO | 14 | $11,047 | $5,601.00 | $10,841 | $4,243.23 | $4,369.97 | $8,650.00 | $4,250.00 |
| 63 | Portable changeable message sign (503-7001) | DAY | 146 | $53.76 | $116.45 | $77.31 | $57.51 | $56.57 | $85.00 | $225.00 |
| 64 | Portable changeable message sign (503-7002) | EACH | 2 | $6,914.00 | $24,787 | $5,154.01 | $21,031 | $1,697.05 | $11,500 | $8,300.00 |
| 65 | TMA (stationary) (505-7001) | DAY | 74 | $208.02 | $416.75 | $128.85 | $356.90 | $303.74 | $100.00 | $275.00 |
| 66 | TMA (mobile operation) (505-7003) | DAY | 34 | $139.42 | $796.45 | $309.24 | $548.10 | $1,133.82 | $400.00 | $475.00 |
| 67 | Rock filter dams (install) (type 3) (506-7003) | LF | 651 | $82.00 | $88.00 | $50.57 | $47.54 | $97.95 | $80.00 | $67.00 |
| 68 | Rock filter dams (remove) (506-7011) | LF | 651 | $13.50 | $6.60 | $17.54 | $8.16 | $7.35 | $6.00 | $45.25 |
| 69 | Construction exits (install) (type 1) (506-7020) | SY | 1,089 | $17.60 | $31.22 | $21.34 | $19.59 | $16.00 | $37.00 | |
| 70 | Construction exits (remove) (506-7024) | SY | 1,089 | $6.60 | $8.77 | $5.42 | $7.35 | $6.00 | $24.50 | |
| 71 | Temporary sediment control fence (install) (506-7039) | LF | 6,662 | $3.97 | $3.30 | $4.49 | $3.76 | $3.68 | $3.00 | $2.75 |
| 72 | Temporary sediment control fence (remove) (506-7041) | LF | 6,662 | $0.98 | $1.00 | $1.70 | $0.87 | $1.11 | $0.90 | $1.50 |
| 73 | Constructing detours (508-7001) | SY | 15,089 | $72.28 | $94.90 | $85.97 | $77.21 | $83.00 | $79.00 | $62.00 |
| 74 | One-way traffic control (pilot car) (510-7002) | HR | 240 | $117.54 | $376.90 | $99.00 | $124.61 | $94.29 | $148.00 | $367.00 |
| 75 | One-way traffic control (port traffic signal) (510-7003) | MO | 12 | $4,158.09 | $10,022 | $12,473 | $12,500 | $14,290 | $15,300 | $16,500 |
| 76 | Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009) | LF | 6,460 | $36.22 | $10.75 | $35.00 | $58.69 | $61.85 | $63.00 | $24.00 |
| 77 | Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010) | LF | 680 | $58.23 | $14.80 | $50.00 | $69.45 | $61.44 | $63.00 | $35.00 |
| 78 | Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033) | LF | 37,260 | $12.01 | $3.15 | $11.00 | $6.24 | $9.85 | $9.00 | $7.00 |
| 79 | Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034) | LF | 3,240 | $70.51 | $3.55 | $19.00 | $6.26 | $8.45 | $9.00 | $15.00 |
| 80 | Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057) | LF | 6,460 | $12.91 | $7.70 | $13.00 | $11.26 | $18.05 | $15.00 | $15.00 |
| 81 | Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058) | LF | 680 | $21.10 | $32.15 | $18.00 | $11.04 | $37.92 | $15.00 | $33.25 |
| 82 | Concrete curb (type II) (529-7002) | LF | 322 | $13.00 | $49.50 | $52.25 | $33.27 | $55.10 | $34.00 | $31.25 |
| 83 | Intersections (ACP) (530-7002) | SY | 5,686 | $115.42 | $25.90 | $39.06 | $39.62 | $30.00 | $50.75 | $49.75 |
| 84 | Driveways (concrete) (530-7006) | SY | 2,026 | $135.00 | $103.25 | $104.51 | $101.62 | $110.20 | $114.00 | $204.00 |
| 85 | Driveways (ACP) (530-7010) | SY | 7,314 | $45.00 | $23.95 | $39.06 | $55.77 | $14.00 | $59.25 | $37.50 |
| 86 | Turnouts (ACP) (530-7018) | SY | 1,292 | $53.73 | $18.40 | $39.06 | $73.06 | $22.00 | $64.25 | $35.25 |
| 87 | Concrete sidewalks (4") (531-7001) | SY | 35 | $70.00 | $94.30 | $63.87 | $183.45 | $67.35 | $85.00 | $89.00 |
| 88 | Concrete sidewalks (6") (531-7003) | SY | 397 | $115.00 | $109.65 | $75.48 | $113.64 | $79.59 | $90.00 | $131.00 |
| 89 | Curb ramps (type 5) (531-7008) | EACH | 15 | $3,100.00 | $2,853.65 | $2,902.99 | $1,428.15 | $3,061.07 | $3,800.00 | $1,900.00 |
| 90 | Curb ramps (type 7) (531-7010) | EACH | 6 | $3,015.00 | $2,917.75 | $1,683.73 | $2,002.72 | $1,775.42 | $2,500.00 | $1,891.00 |
| 91 | Curb ramps (type 21) (531-7023) | SY | 9 | $230.00 | $3,120.60 | $522.54 | $2,180.94 | $550.99 | $4,000.00 | $241.00 |
| 92 | Metal W-beam guard fence (timber post) (540-7001) | LF | 1,026 | $24.66 | $26.30 | $23.00 | $23.68 | $24.49 | $29.00 | $22.50 |
| 93 | Short radius (28") (540-7013) | LF | 50 | $60.00 | $41.35 | $32.00 | $35.68 | $55.10 | $40.00 | $32.25 |
| 94 | Driveway terminal anchor section (540-7014) | EACH | 2 | $1,520.14 | $1,518.15 | $1,300.00 | $1,369.66 | $795.88 | $1,500.00 | $1,260.00 |
| 95 | Metal W-beam guard fence (special) (540-7017) | LF | 25 | $66.29 | $35.00 | $35.00 | $33.53 | $61.22 | $75.00 | $28.50 |
| 96 | Metal W - beam guard fence (low fill culvert) (540-7018) | LF | 263 | $80.78 | $103.50 | $79.00 | $132.46 | $91.84 | $110.00 | $126.00 |
| 97 | Metal beam guard fence trans (31"-28")(25') (540-7031) | EACH | 2 | $650.00 | $680.65 | $800.00 | $982.21 | $979.54 | $1,000.00 | $891.00 |
| 98 | Remove metal beam guard fence (542-7001) | LF | 175 | $5.00 | $2.75 | $2.50 | $2.90 | $1.83 | $3.00 | $2.25 |
| 99 | Remove terminal anchor section (542-7002) | EACH | 4 | $220.00 | $275.05 | $250.00 | $233.33 | $183.66 | $500.00 | $200.00 |
| 100 | Guardrail end treatment (install) (544-7001) | EACH | 18 | $3,002.25 | $3,625.65 | $3,050.00 | $3,628.47 | $3,367.17 | $3,300.00 | $3,431.00 |
| 101 | Mailbox install-S (WC-post) type 3 (560-7004) | EACH | 18 | $300.00 | $271.85 | $150.00 | $219.33 | $244.88 | $150.00 | $275.00 |
| 102 | Mailbox install-D (WC-post) type 3 (560-7005) | EACH | 1 | $216.97 | $326.90 | $200.00 | $245.58 | $275.50 | $200.00 | $289.00 |
| 103 | Mailbox install-M (TWW-post) type 4 (560-7010) | EACH | 10 | $216.97 | $766.90 | $600.00 | $586.83 | $673.44 | $600.00 | $854.00 |
| 104 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 80 | $720.00 | $671.05 | $610.00 | $613.08 | $704.04 | $610.00 | $768.00 |
| 105 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 3 | $795.00 | $693.05 | $630.00 | $744.33 | $857.10 | $630.00 | $853.00 |
| 106 | Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007) | EACH | 3 | $1,000.00 | $759.05 | $690.00 | $849.33 | $979.54 | $690.00 | $960.00 |
| 107 | Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025) | EACH | 6 | $950.00 | $814.05 | $470.00 | $691.83 | $61.22 | $740.00 | $940.00 |
| 108 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 6 | $1,015.00 | $880.10 | $800.00 | $796.83 | $918.32 | $800.00 | $1,095.00 |
| 109 | Install small roadside sign support and assembly TYS80(1)SA(T-2EXT) (644-7029) | EACH | 6 | $2,100.00 | $990.10 | $900.00 | $849.33 | $979.54 | $900.00 | $1,230.00 |
| 110 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 4 | $1,175.00 | $1,023.10 | $930.00 | $954.33 | $1,101.98 | $930.00 | $1,315.00 |
| 111 | Install small roadside sign support and assembly TYS80(1)SA(U-2EXT) (644-7033) | EACH | 1 | $1,034.10 | $940.00 | $1,059.33 | $1,224.42 | $940.00 | $1,250.00 | |
| 112 | Remove SM RD SN sup&AM (644-7073) | EACH | 111 | $121.00 | $110.00 | $100.00 | $97.66 | $104.08 | $100.00 | $200.00 |
| 113 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 49 | $40.00 | $13.20 | $12.00 | $35.77 | $30.62 | $12.00 | $75.00 |
| 114 | Install object marker assembly (OM-2Z)(WFLX)GND(BI) (658-7059) | EACH | 49 | $85.00 | $66.00 | $60.00 | $104.02 | $110.20 | $60.00 | $102.00 |
| 115 | Remove delin & object marker assms (658-7078) | EACH | 11 | $22.00 | $11.00 | $10.00 | $13.73 | $6.12 | $10.00 | $125.00 |
| 116 | Install delineator assembly (D-SR)SZ 2(WC)GNDLL (658-7137) | EACH | 118 | $95.00 | $71.50 | $65.00 | $124.99 | $134.68 | $65.00 | $105.00 |
| 117 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 110,183 | $0.78 | $0.75 | $0.52 | $0.94 | $1.08 | $0.45 | $0.70 |
| 118 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 411 | $6.83 | $8.80 | $3.48 | $8.63 | $9.80 | $3.00 | $8.00 |
| 119 | Work zone pavement marking removing (W)(RR crossing) (662-7088) | EACH | 1 | $435.71 | $660.05 | $174.17 | $1,059.33 | $1,224.42 | $150.00 | $600.00 |
| 120 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 50,000 | $0.83 | $0.75 | $0.52 | $0.93 | $1.08 | $0.45 | $0.70 |
| 121 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 6,460 | $0.91 | $1.60 | $1.60 | $1.25 | $1.30 | $1.50 | $1.00 |
| 122 | Work zone pavement marking SHT terminal (tab)type Y (662-7113) | EACH | 12,920 | $1.97 | $1.50 | $1.60 | $1.25 | $1.32 | $1.50 | $1.00 |
| 123 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 2,452 | $0.97 | $1.00 | $0.99 | $0.98 | $1.11 | $0.85 | $0.90 |
| 124 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 30 | $3.60 | $4.15 | $4.06 | $6.52 | $3.97 | $3.50 | $3.75 |
| 125 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 605 | $7.00 | $8.25 | $7.26 | $6.98 | $7.96 | $6.25 | $7.50 |
| 126 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 15 | $145.00 | $143.00 | $168.36 | $202.41 | $214.28 | $145.00 | $130.00 |
| 127 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 14 | $165.00 | $176.00 | $179.97 | $223.33 | $244.88 | $155.00 | $160.00 |
| 128 | Reflectorized pavement marking type I (W)(RR crossing)(100MIL) (666-7081) | EACH | 1 | $632.55 | $348.33 | $586.83 | $673.44 | $300.00 | $575.00 | |
| 129 | Reflectorized pavement marking type I (Y)12"(solid)(100MIL) (666-7117) | LF | 58 | $3.66 | $4.15 | $4.64 | $5.02 | $3.97 | $4.00 | $3.75 |
| 130 | Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266) | LF | 59,160 | $0.63 | $0.90 | $0.82 | $0.85 | $0.98 | $0.71 | $0.80 |
| 131 | Reflectorized profile pavement marking type I(Y)6"(solid)(100MIL) (666-7270) | LF | 42,093 | $0.69 | $0.90 | $0.82 | $0.85 | $0.98 | $0.71 | $0.80 |
| 132 | Reflectorized profile pavement marking type I(Y)6"(broken)(100MIL) (666-7274) | LF | 3,730 | $0.71 | $1.10 | $0.93 | $0.87 | $0.98 | $0.80 | $1.00 |
| 133 | Pavement sler 6" (666-7347) | LF | 105,514 | $0.20 | $0.25 | $0.22 | $0.22 | $0.25 | $0.19 | $0.25 |
| 134 | Pavement sler 8" (666-7348) | LF | 2,477 | $0.36 | $0.40 | $0.35 | $0.30 | $0.31 | $0.30 | $0.35 |
| 135 | Pavement sler 12" (666-7350) | LF | 88 | $0.80 | $1.40 | $0.87 | $2.11 | $1.23 | $0.75 | $1.25 |
| 136 | Pavement sler 24" (666-7352) | LF | 605 | $1.50 | $2.75 | $1.16 | $2.25 | $2.45 | $1.00 | $2.50 |
| 137 | Pavement sler (arrow) (666-7353) | EACH | 15 | $50.00 | $82.50 | $11.61 | $84.97 | $91.84 | $10.00 | $75.00 |
| 138 | Pavement sler (word) (666-7354) | EACH | 14 | $45.00 | $110.00 | $11.61 | $85.42 | $91.84 | $10.00 | $100.00 |
| 139 | Pavement sler (RR crossing) (666-7364) | EACH | 1 | $275.05 | $87.08 | $250.81 | $183.66 | $75.00 | $250.00 | |
| 140 | Reflectorized pavement marker type I-C (672-7002) | EACH | 128 | $6.00 | $4.40 | $4.53 | $4.40 | $4.28 | $3.90 | $4.00 |
| 141 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 1,620 | $3.50 | $4.40 | $4.18 | $3.79 | $4.28 | $3.60 | $4.00 |
| 142 | Eliminating existing PM & markers (6") (677-7002) | LF | 49,330 | $0.19 | $0.40 | $0.70 | $0.54 | $0.62 | $0.60 | $0.35 |
| 143 | Eliminating existing PM & markers (24") (677-7008) | LF | 156 | $2.00 | $2.75 | $2.32 | $5.85 | $6.12 | $2.00 | $2.50 |
| 144 | Full - width mowing (730-7019) | CYC | 4 | $5,653.80 | $4,000.00 | $4,428.12 | $660.41 | $5,500.00 | $6,750.00 | |
| 145 | Litter removal (734-7002) | CYC | 14 | $868.95 | $2,000.00 | $2,292.13 | $2,694.25 | $1,500.00 | $1,200.00 | |
| 146 | Debris removing-CNTR med/MN LNS/ramps (735-7001) | MI | 23 | $174.10 | $1,000.00 | $948.45 | $1,040.22 | $600.00 | $1,600.00 | |
| 147 | Clean / sweep - center median - area(1) (738-7005) | CYC | 14 | $696.20 | $5,000.00 | $2,414.31 | $2,557.73 | $1,500.00 | $1,600.00 | |
| 148 | Bonding course (3007-7001) | GAL | 4,471 | $305.00 | $3.70 | $2.79 | $7.31 | $4.90 | $5.00 | $3.50 |
| 149 | Install bridge identification numbers (4019-7001) | EACH | 1 | $478.04 | $347.55 | $2,500.00 | $1,244.64 | $170.26 | $500.00 | $350.00 |
| 150 | Residential driveway temporary signal system (6089-7001) | MO | 12 | $4,158.09 | $4,987.30 | $16,074 | $16,103 | $18,134 | $32,000 | $20,228 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of March 4, 2026. Compiled by Mirage Metrics.