Metal beam guard fence trans (31"-28"), TxDOT 540-7028
Low bidders on TxDOT contracts carried a median of $500.00 per EACH for this item, over the 24 months to 19 NOV 2026, across 15 low bids. Half of all 86 bids fell between $500.00 and $1,200.00.
- Owner
- Texas DOT
- Item
- 540-7028
- Unit
- EACH
- Data through
- 19 NOV 2026
TxDOT prints this item as “MTL BM GD FEN TRANS (31"-28")”.
TxDOT has bid this work under more than one code: 5406035001 on lettings from 08 APR 2020 to 05 MAR 2024 (169 bids); 540-7028 on lettings from 14 JAN 2025 to 03 NOV 2026 (103 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 13 | 13 | $600.00 | 66 | $767.50 |
| 2021 | 12 | 12 | $590.08 | 59 | $748.05 |
| 2022 | 4 | 4 | $1,697.00 | 7 | $1,325.00 |
| 2023 | 9 | 9 | $900.00 | 29 | $819.62 |
| 2024 | 2 | 2 | $673.00 | 7 | $731.00 |
| 2025 | 12 | 8 | $476.41 | 44 | $525.50 |
| 2026 | 7 | 7 | $1,025.00 | 42 | $1,200.00 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 3 | $480.00 |
| 3 to 5 | 4 | $1,112.50 |
| 5 to 20 | 4 | $745.22 |
| 20 to 100 | 4 | $100.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Barricades Unlimited | 7 | 6 (86%) |
| Hunter Industries, LTD. | 10 | 5 (50%) |
| Texas Materials Group, Inc. | 14 | 3 (21%) |
| Ross Sa Enterprise LLC | 7 | 3 (43%) |
| FNH Construction, LLC | 11 | 1 (9%) |
| Dbi Services, LLC | 7 | 1 (14%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 03 NOV 2026 | A00184974 | Austin District | 3 | $1,025.00 | $1,025.00 | $900.00 | 6 | Austin Bridge & Road Services, LP | TxDOT |
| 07 OCT 2026 | A00064192 | San Antonio District | 5 | $1,192.55 | $1,260.00 | $400.00 | 8 | Hunter Industries, LTD. | TxDOT |
| 07 MAY 2026 | A00183655 | Lubbock District | 4 | $1,300.00 | $1,350.00 | $300.00 | 6 | A. L. Helmcamp, Inc. | TxDOT |
| 06 MAY 2026 | A00130695 | Houston District | 4 | $1,200.00 | $1,095.00 | $500.00 | 6 | Durwood Greene Construction Co. | TxDOT |
| 16 APR 2026 | A00212377 | San Angelo District | 30 | $100.00 | $100.00 | $500.00 | 3 | T&L Cleaning Services LLC | TxDOT |
| 04 MAR 2026 | A00197433 | San Antonio District | 8 | $590.44 | $605.47 | $200.00 | 6 | Texas Materials Group, Inc. | TxDOT |
| 05 FEB 2026 | A00188227 | San Antonio District | 5 | $500.00 | $1,580.00 | $473.00 | 7 | Clark Construction of Texas, Inc. | TxDOT |
| 04 DEC 2025 | A00217870 | Lubbock District | 10 | n/a | $750.00 | $100.00 | 3 | Austin Barricade Company, L.L.C. | TxDOT |
| 04 DEC 2025 | A00217871 | Lubbock District | 10 | n/a | $250.00 | $100.00 | 3 | BK Field Operations LLC | TxDOT |
| 04 DEC 2025 | A00217872 | Lubbock District | 25 | n/a | $1,408.15 | $500.00 | 2 | Ross Sa Enterprise LLC | TxDOT |
| 14 OCT 2025 | A00217600 | Lubbock District | 20 | $100.00 | $100.00 | $100.00 | 3 | Ross Sa Enterprise LLC | TxDOT |
| 09 OCT 2025 | A00188271 | Wichita Falls District | 1 | $472.82 | $600.00 | $615.00 | 5 | Altus Construction LLC | TxDOT |
| 21 AUG 2025 | A00214746 | Paris District | 20 | $500.00 | $550.00 | $1,350.00 | 4 | Ross Sa Enterprise LLC | TxDOT |
| 04 JUN 2025 | A00213969 | Beaumont District | 1 | $480.00 | $480.00 | $700.00 | 3 | Ross Sa Enterprise LLC | TxDOT |
| 01 MAY 2025 | A00063599 | San Antonio District | 9 | $900.00 | $957.04 | $1,000.00 | 6 | Texas Materials Group, Inc. | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the TxDOT letting of 19 NOV 2026 and was rebuilt on 26 NOV 2026.