TxDOT contract A00183655 bid tabulation

Roadway Rehabilitation/Reconstruction With No Added Capacity, FM 179 (South of US 62 to LP 88 (FM 1585)). Let by Texas DOT on May 7, 2026, Lubbock, Lubbock District. 6 bids received; low bid $9,632,448 by A. L. Helmcamp, Inc., -6.2% against the engineer's estimate of $10,274,387.

Owner
Texas DOT
Letting
07 MAY 2026
Pay items
153
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1A. L. Helmcamp, Inc.$9,632,448Low-6.0%
2Webber, LLC$11,395,000+18%+11%
3Duininck, Inc.$12,239,305+27%+19%
4J. Lee Milligan, Inc.$12,730,908+32%+24%
5Lone Star Dirt & Paving, LTD.$12,828,101+33%+25%
6Gilvin-Terrill, LTD.$14,162,929+47%+38%
TxDOT contract A00183655: bids by rank

Engineer's estimate: $10,274,387.

Bid tabulation

LinePay itemUnitQuantityEstimate1. A. L. Helmcamp, Inc.2. Webber, LLC3. Duininck, Inc.4. J. Lee Milligan, Inc.5. Lone Star Dirt & Paving, LTD.6. Gilvin-Terrill, LTD.
1Preparing row (100-7002)STA13$3,720.00$4,000.00$77,000$8,000.00$10,000$12,500$2,500.00
2Removing concrete (driveways) (104-7011)SY1,717$40.00$40.00$36.50$22.00$30.00$50.00$20.00
3Remove (2"-6") TRT/untrt base & asphalt pavement (105-7002)SY27,360$7.50$3.00$5.85$7.30$5.95$16.00$5.00
4Excavation (special) (110-7003)CY17,468$12.00$21.00$16.70$18.00$16.00$16.00$30.00
5Subgr widen (DC) (112-7004)SY25,943$8.00$5.00$4.20$30.00$21.00$21.00$25.00
6Embankment (final)(DC)(type C) (132-7006)CY22$18.00$96.00$403.00$120.00$290.00$75.00$30.00
7Backfill (type A) (134-7001)STA91.20$950.00$350.00$649.00$160.00$630.00$1,600.00$500.00
8Blading (150-7001)STA91.20$500.00$350.00$559.00$145.00$300.00$3,000.00$150.00
9Drill seed (permanent_rural_sand) (164-7009)SY44,304$0.50$0.24$0.35$0.26$0.20$5.00$0.30
10Drill seed (temporary_warm_cool) (164-7015)SY44,304$0.50$0.22$0.30$0.24$0.20$5.00$0.30
11Vegetative watering (168-7001)TGL1,491$60.00$25.00$25.00$36.50$35.00$66.00$30.00
12Proof rolling (216-7001)HR50$200.00$210.00$87.50$225.00$140.00$450.00$150.00
13Prime coat (MC-30) (310-7004)GAL10,336$7.00$8.00$7.05$6.80$7.00$17.00$7.00
14Fog seal (CSS-1H) (315-7004)GAL8,208$7.00$5.50$5.15$4.80$5.00$9.00$6.00
15Tack coat (341-7082)GAL7,235$7.00$5.00$6.25$4.00$6.50$17.00$6.00
16D-GR HMA type-B sac-B PG70-28 (341-7083)TON20,801$150.00$150.00$167.00$175.00$185.00$160.00$230.00
17Stone-MTRX-asphalt SMA-D sac-A PG76-28 (346-7010)TON5,979$180.00$198.00$210.00$260.00$260.00$255.00$245.00
18Flexible pavement structure repair(2") (351-7001)SY527$60.00$47.00$67.50$65.00$60.00$65.00$100.00
19Flexible pavement structure repair(6") (351-7005)SY527$100.00$93.00$102.00$130.00$105.00$85.00$150.00
20Plane & text asphalt concrete pavement(2" to 4") (354-7010)SY26,347$3.75$3.30$3.40$2.40$4.50$16.00$5.00
21Cut & restore asphalt paving (400-7008)SY53$300.00$60.00$170.00$295.00$155.00$120.00$400.00
22Cem stabil BKFL (400-7010)CY316.70$154.00$300.00$204.00$315.00$350.00$108.00$300.00
23Trench excavation protection (402-7001)LF135$9.00$53.00$61.25$59.00$90.00$9.00$35.00
24Temporary special shoring (cofferdam) (403-7002)SF720$35.00$57.00$25.00$59.00$50.00$27.00$100.00
25Drilled shaft (42 in) (416-7007)LF21$700.00$450.00$420.00$495.00$465.00$600.00$420.00
26Drilled shaft (roadway illumination pole) (30 in) (416-7040)LF16$400.00$350.00$300.00$355.00$335.00$300.00$300.00
27Drilled shaft (traffic signal pole) (36 in) (416-7044)LF56$500.00$400.00$360.00$425.00$400.00$480.00$360.00
28Riprap (concrete)(5 in) (432-7002)CY368$570.00$800.00$486.00$890.00$1,030.00$700.00$1,000.00
29Riprap (concrete)(CL A) (432-7004)CY1.25$1,900.00$1,600.00$3,970.00$1,800.00$1,000.00$900.00$1,000.00
30Gabion mattresses (galvanized)(9 in) (459-7006)SY596$290.00$200.00$149.00$225.00$140.00$85.00$650.00
31RC pipe (CL III)(24 in) (464-7005)LF132$290.00$130.00$154.00$135.00$190.00$300.00$150.00
32RC pipe (arch)(CL IV)(des 1) (464-7046)LF800$250.00$330.00$271.00$365.00$310.00$250.00$300.00
33Headwall (CH - FW - 0) (diameter= 36 in) (466-7009)EACH2$10,700$12,000$12,930$12,500$13,000$7,000.00$15,000
34Headwall (CH - FW - 0) (diameter= 48 in) (466-7011)EACH2$12,000$12,000$12,210$12,500$17,000$6,500.00$17,000
35Set (type II) (24 in) (RCP) (6: 1) (C) (467-7327)EACH8$2,135.00$2,300.00$4,180.00$2,500.00$3,500.00$4,500.00$3,500.00
36Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH2$4,750.00$2,300.00$4,180.00$2,500.00$3,500.00$4,500.00$3,500.00
37Set (type II) (des 1) (RCP) (6: 1) (P) (467-7418)EACH36$2,000.00$1,700.00$4,320.00$1,900.00$3,000.00$4,000.00$3,000.00
38Thermoplastic pipe (PP) (36") (468-7004)LF106$190.00$160.00$169.00$180.00$400.00$250.00$175.00
39Thermoplastic pipe (PP) (48") (468-7006)LF72$290.00$300.00$294.00$335.00$650.00$250.00$250.00
40Adjusting manholes (479-7001)EACH7$1,400.00$1,900.00$2,450.00$3,600.00$1,200.00$3,500.00$1,000.00
41Adjusting manholes (water valve box) (479-7007)EACH13$750.00$1,900.00$2,450.00$1,800.00$1,000.00$3,000.00$1,000.00
42Clean existing culverts (480-7001)EACH1$2,850.00$5,900.00$18,771$4,700.00$7,000.00$4,000.00$7,000.00
43Removing structure (pipe) (496-7037)EACH8$2,900.00$270.00$6,550.00$295.00$2,200.00$3,500.00$3,500.00
44Mobilization (500-7001)LS1$997,000$815,000$1,100,000$1,175,000$1,400,000$700,000$1,400,000
45Barricades, signs and traffic handling (502-7001)MO13$38,000$23,600$43,600$30,000$35,000$11,000$50,000
46Portable changeable message sign (503-7001)DAY780$100.00$75.00$58.00$120.00$100.00$145.00$50.00
47TMA (stationary) (505-7001)DAY360$150.00$250.00$241.00$295.00$525.00$325.00$610.00
48TMA (mobile operation) (505-7003)DAY24$200.00$250.00$225.00$1,100.00$1,000.00$1,000.00$610.00
49Construction exits (install) (type 1) (506-7020)SY650$48.00$25.00$48.75$47.50$50.00$125.00$40.00
50Construction exits (remove) (506-7024)SY650$28.00$10.00$18.80$26.00$10.00$50.00$15.00
51Sandbags for erosion control (506-7035)EACH26$20.00$30.00$51.75$29.50$30.00$50.00$20.00
52Temporary sediment control fence (install) (506-7039)LF4,425$7.00$4.50$5.85$5.20$6.00$20.00$5.00
53Temporary sediment control fence (remove) (506-7041)LF1,475$4.00$1.10$1.60$1.20$3.00$9.00$1.00
54Biodegradable erosion control logs (install) (18") (506-7045)LF1,175$10.00$9.50$12.60$10.50$9.00$20.00$13.00
55Biodegradable erosion control logs (remove) (506-7046)LF540$5.00$1.10$1.60$1.20$7.00$9.00$1.50
56Constructing detours (508-7001)SY975$130.00$100.00$118.00$115.00$155.00$122.00$150.00
57PTB (fur&inst)(F shape)(type 1) or (steel) (512-7077)LF180$125.00$98.00$51.00$110.00$110.00$400.00$45.00
58PTB (move)(F shape)(type 1) or (steel) (512-7078)LF180$80.00$38.00$20.10$40.00$32.00$400.00$15.00
59PTB (remove)(F shape)(type 1) or (steel) (512-7080)LF180$38.00$40.00$22.70$40.00$32.00$400.00$45.00
60Intersections (concrete) (530-7001)SY684$150.00$190.00$108.00$215.00$235.00$115.00$150.00
61Intersections (ACP) (530-7002)SY877$100.00$82.00$68.25$165.00$180.00$110.00$100.00
62Driveways (concrete) (530-7006)SY1,229$140.00$170.00$119.00$190.00$180.00$115.00$150.00
63Driveways (ACP) (530-7010)SY1,004$140.00$92.00$68.25$165.00$185.00$75.00$100.00
64Mill rumble strips (asphalt) (shoulder) (533-7001)LF18,240$0.30$0.90$0.75$0.52$0.80$9.00$1.00
65Metal W-beam guard fence (steel post) (540-7002)LF1,925$50.00$33.00$31.00$36.50$39.00$66.00$31.00
66Short radius (28") (540-7013)LF96$100.00$36.00$34.00$40.50$45.00$63.00$34.00
67Downstream anchor terminal section (540-7015)EACH5$2,000.00$1,800.00$1,600.00$1,900.00$2,275.00$2,000.00$1,600.00
68Metal beam guard fence trans (non - sym) (540-7016)EACH1$1,330.00$1,200.00$1,100.00$1,300.00$1,330.00$1,400.00$1,100.00
69Metal beam guard fence trans (31"-28") (540-7028)EACH4$300.00$1,300.00$1,200.00$1,400.00$2,050.00$2,200.00$1,200.00
70Guardrail end treatment (install) (544-7001)EACH4$4,750.00$3,500.00$3,300.00$3,900.00$5,400.00$4,400.00$3,300.00
71Crash cushion attenuator (move & reset) (545-7002)EACH2$2,000.00$1,200.00$2,500.00$3,000.00$1,650.00$1,800.00$1,000.00
72Crash cushion attenuator (remove) (545-7004)EACH2$1,000.00$1,200.00$1,000.00$1,200.00$1,100.00$500.00$1,000.00
73Crash cushion attenuator (install)(S)(N)(TL3) (545-7014)EACH2$9,000.00$9,500.00$18,010$12,000$11,000$12,800$7,500.00
74Mailbox install-S (TWW-post) type 4 (560-7008)EACH7$290.00$230.00$220.00$260.00$1,450.00$1,500.00$375.00
75Mailbox install-M (TWW-post) type 4 (560-7010)EACH1$480.00$580.00$550.00$650.00$2,200.00$2,000.00$802.00
76In RD IL (type ST) 40T-12 (250W EQ) LED (610-7168)EACH2$7,600.00$5,100.00$4,830.00$5,700.00$5,350.00$5,100.00$4,825.00
77Conduit (PVC) (schedule 80) (2") (618-7054)LF205$44.00$16.00$15.00$18.00$17.00$12.00$15.00
78Conduit (PVC) (schedule 80) (2") (bore) (618-7055)LF380$48.00$24.00$22.50$26.50$25.00$23.00$22.50
79Conduit (PVC) (schedule 80) (4") (618-7064)LF200$44.00$19.00$18.00$21.50$20.00$16.00$18.00
80Conduit (PVC) (schedule 80) (4") (bore) (618-7065)LF885$48.00$37.00$35.00$41.50$39.00$35.00$35.00
81Electrical conductor (no.6) bare (620-7009)LF1,525$2.40$2.20$2.00$2.35$2.25$2.00$2.00
82Electrical conductor (no.6) insulated (620-7010)LF2,200$3.80$2.30$2.20$2.60$2.45$2.20$2.20
83Electrical conductor (no.2) insulated (620-7016)LF435$5.70$4.30$4.00$4.75$4.45$3.00$4.00
84Ground box type A (122311)W/apron (624-7002)EACH2$1,900.00$1,100.00$1,000.00$1,200.00$1,100.00$1,100.00$1,000.00
85Ground box type D (162922) (624-7007)EACH5$1,500.00$1,700.00$1,600.00$1,900.00$1,780.00$1,400.00$1,600.00
86Ground box type D (162922)W/apron (624-7008)EACH4$2,500.00$1,400.00$1,350.00$1,600.00$1,495.00$1,400.00$1,350.00
87Elc SRV type A 240/480 060(NS)SS(E)SP(O) (628-7048)EACH1$9,500.00$9,000.00$8,500.00$10,000$9,500.00$9,000.00$8,500.00
88Elc SRV type D 120/240 060(NS)SS(N)SP(O) (628-7156)EACH1$9,500.00$8,800.00$8,250.00$9,800.00$9,200.00$9,000.00$8,250.00
89Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH12$950.00$700.00$650.00$770.00$910.00$1,200.00$655.00
90Install small roadside sign support and assembly type 10BWG(1)SA(P-BM) (644-7002)EACH16$1,000.00$800.00$750.00$890.00$1,020.00$1,200.00$754.00
91Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH14$1,045.00$800.00$750.00$890.00$1,050.00$1,200.00$771.00
92Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007)EACH1$1,140.00$800.00$750.00$890.00$1,325.00$1,200.00$1,001.00
93Install small roadside sign support and assembly type 10BWG(1)SB(P) (644-7009)EACH2$650.00$740.00$700.00$830.00$1,020.00$1,200.00$733.00
94Install small roadside sign support and assembly type 10BWG(1)SB(T) (644-7012)EACH2$750.00$790.00$750.00$890.00$1,080.00$1,200.00$782.00
95Remove SM RD SN sup&AM (644-7073)EACH44$150.00$110.00$100.00$120.00$140.00$500.00$100.00
96Remove SM RD SN sup&AM (sign only) (644-7075)EACH1$133.00$100.00$100.00$120.00$55.00$500.00$250.00
97Install delineator assembly (D-SW)SZ 1(BRF)GF2(BR) (658-7020)EACH28$60.00$45.00$55.00$49.50$55.00$48.00$42.00
98Install object marker assembly (OM-2Z)(WFLX)GND(BI) (658-7059)EACH20$90.00$90.00$85.00$100.00$175.00$115.00$77.00
99Remove delin & object marker assms (658-7078)EACH18$20.00$16.00$15.00$18.00$30.00$70.00$120.00
100Install OM SM RD sign (1-OM-PW)Y (658-7317)EACH21$35.00$10.00$10.00$12.00$25.00$1,500.00$13.00
101Install OM SM RD sign (1-OM-PW)R (658-7318)EACH26$35.00$10.00$10.00$12.00$25.00$1,500.00$13.00
102Work zone pavement marking non-removing (W)6"(broken) (662-7005)LF100$0.30$1.15$1.00$1.20$1.10$1.20$1.00
103Work zone pavement marking non-removing (W)6"(solid) (662-7008)LF47,345$0.30$0.33$0.30$0.36$0.35$0.40$0.30
104Work zone pavement marking non-removing (W)24"(solid) (662-7017)LF48$4.75$22.00$20.00$23.50$22.15$24.00$20.00
105Work zone pavement marking non-removing (Y)6"(broken) (662-7036)LF13,680$0.30$0.33$0.30$0.37$0.35$0.40$0.31
106Work zone pavement marking non-removing (Y)6"(solid) (662-7038)LF89,572$0.30$0.32$0.30$0.36$0.35$0.40$0.30
107Work zone pavement marking removing (reflectorized) type I-C (662-7050)LF18$2.90$5.50$5.25$29.50$5.80$6.30$5.25
108Work zone pavement marking removing (reflectorized) type II-A-A (662-7051)EACH1,054$2.90$5.50$5.25$6.20$5.80$6.30$5.25
109Work zone pavement marking removing (W)6"(solid) (662-7068)LF3,160$1.00$1.30$1.25$1.50$1.40$1.50$1.25
110Work zone pavement marking removing (W)24"(solid) (662-7077)LF48$9.50$22.00$20.00$23.50$22.15$24.00$20.00
111Work zone pavement marking removing (Y)6"(solid) (662-7100)LF3,160$1.00$1.30$1.25$1.50$1.40$1.50$1.25
112Work zone pavement marking SHT terminal (tab)type W (662-7112)EACH1,824$1.00$0.75$0.95$1.80$1.60$5.00$1.00
113Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114)EACH4,560$1.00$0.75$0.70$1.80$1.60$5.00$1.00
114Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF260$1.40$1.00$0.90$1.05$1.00$1.10$0.90
115Type I high perf PM (W)6"(solid)(100MIL) (666-7293)LF15,677$0.80$0.75$0.70$0.83$0.80$0.90$0.70
116Type I high perf PM (Y)6"(broken)(100MIL) (666-7302)LF16,268$0.80$0.75$0.70$0.83$0.80$0.90$0.70
117Type I high perf PM (Y)6"(solid)(100MIL) (666-7305)LF16,480$0.80$0.75$0.70$0.83$0.80$0.90$0.70
118Prefabricated PM type B (W)(24")(solid) (668-7021)LF282$40.00$40.00$37.50$44.50$41.50$45.00$37.50
119Prefabricated PM type C (W)(24")(solid) (668-7089)LF312$20.00$16.50$15.50$18.50$17.25$19.00$15.50
120Prefabricated PM type C (W)(arrow) (668-7091)EACH8$400.00$300.00$280.00$330.00$310.00$336.00$280.00
121Prefabricated PM type C (W)(double arrow) (668-7093)EACH6$450.00$480.00$455.00$540.00$505.00$546.00$455.00
122Reflectorized pavement marker type I-C (672-7002)EACH13$5.00$11.00$10.00$12.00$11.10$12.00$10.00
123Reflectorized pavement marker type II-A-A (672-7004)EACH1,640$5.00$5.50$5.00$5.90$5.55$6.00$5.00
124Eliminating existing PM & markers (6") (677-7002)LF81,796$1.10$0.70$0.65$0.77$0.75$0.80$0.65
125Eliminating existing PM & markers (8") (677-7004)LF98$1.50$1.00$1.00$1.20$1.10$1.20$1.00
126Eliminating existing PM & markers (24") (677-7008)LF50$3.25$4.50$4.00$4.75$4.45$5.00$4.00
127Install highway traffic signal (isolated) (680-7002)EACH1$40,000$24,000$21,000$25,000$23,250$30,000$21,000
128Temporary traffic signals (681-7001)EACH1$25,000$8,600.00$13,000$29,500$8,620.00$6,500.00$60,000
129Vehicle signal section (12")LED(green) (682-7001)EACH12$330.00$320.00$300.00$355.00$335.00$390.00$300.00
130Vehicle signal section (12")LED(green arrow) (682-7002)EACH2$330.00$320.00$300.00$355.00$335.00$390.00$300.00
131Vehicle signal section (12")LED(yel) (682-7003)EACH12$330.00$320.00$300.00$355.00$335.00$390.00$300.00
132Vehicle signal section (12")LED(yel arrow) (682-7004)EACH4$330.00$320.00$300.00$355.00$335.00$390.00$300.00
133Vehicle signal section (12")LED(red) (682-7005)EACH12$330.00$320.00$300.00$355.00$335.00$390.00$300.00
134Vehicle signal section (12")LED(red arrow) (682-7006)EACH2$330.00$320.00$300.00$355.00$335.00$390.00$300.00
135Backplate W/ref border(3 sec)(vent)aluminum (682-7042)EACH12$380.00$270.00$250.00$295.00$275.00$300.00$250.00
136Backplate W/ref border(4 sec)(vent)aluminum (682-7043)EACH2$380.00$320.00$300.00$355.00$335.00$380.00$300.00
137Traffic signal CBL (type A)(12 AWG)(5 conductor) (684-7010)LF530$4.30$5.00$4.75$5.60$5.25$6.00$4.75
138Traffic signal CBL (type A)(12 AWG)(7 conductor) (684-7012)LF110$5.20$5.50$5.00$5.90$5.55$7.20$5.00
139Traffic signal CBL (type A)(12 AWG)(12 conductor) (684-7017)LF1,175$6.20$6.50$6.00$7.10$6.65$11.00$6.00
140Reloct RDSD FLSH BCN AM (solar PWRD) (685-7005)EACH2$3,500.00$3,400.00$3,250.00$3,800.00$3,600.00$2,100.00$3,250.00
141Ins traffic signal PL AM (S)1 arm(28') (686-7029)EACH1$16,000$13,000$12,230$14,500$13,600$16,800$12,225
142Ins traffic signal PL AM(S)1 arm(36') (686-7037)EACH1$17,000$14,000$13,000$15,500$14,500$17,700$13,000
143Ins traffic signal PL AM(S)2 arm(32-32') (686-7105)EACH1$22,000$20,000$18,500$22,000$20,500$25,200$18,500
144Ins traffic signal PL AM(S)2 arm(36-28') (686-7117)EACH1$25,000$19,000$18,000$21,500$20,000$25,800$18,000
145Install of cables (690-7011)LF1,505$3.00$2.70$2.50$2.95$2.80$2.50$2.50
146Full - width mowing (730-7019)CYC4$14,250$5,000.00$6,300.00$5,700.00$3,075.00$2,500.00$2,500.00
147Litter removal (734-7002)CYC4$3,800.00$2,500.00$2,200.00$4,800.00$4,620.00$2,500.00$2,000.00
148Reinforced fab for asphalt PVMNT overlays (3002-7001)SY50,667$6.50$6.80$7.00$8.10$6.90$6.50$12.00
149Asphalt for reinforced fab (PG76-28) (3002-7002)GAL7,600$5.00$6.80$4.90$5.10$8.00$12.00$5.50
150ITS pole(40 FT)(110 MPH)(W/stiff) (6011-7015)EACH1$25,000$16,000$14,750$17,500$16,350$16,500$14,750
151ITS pole MNTD cab (type 2)(conf 1) (6011-7028)EACH1$9,500.00$7,100.00$6,750.00$8,000.00$7,500.00$3,000.00$6,745.00
152Temporary speed monitor sys (6016-7001)EACH2$19,000$17,000$17,000$10,000$19,000$4,500.00$30,000
153CCTV field equip (digital) (install only) (6018-7001)EACH1$4,750.00$3,500.00$3,250.00$3,800.00$3,600.00$5,000.00$3,250.00
TxDOT contract A00183655: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of May 7, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy