TxDOT contract A00214746 bid tabulation

METAL BEAM GUARD FENCE REPAIR, US0082 (Various locations in to Grayson and Fannin County). Let by Texas DOT on August 21, 2025, Grayson, Paris District. 4 bids received; low bid $562,174 by Ross Sa Enterprise LLC, -29% against the engineer's estimate of $795,860.

Owner
Texas DOT
Letting
21 AUG 2025
Pay items
61
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Ross Sa Enterprise LLC$562,174Low-29%
2Marcom'S Mowing Service, LLC$706,079+26%-11%
3Rhino Equity, LLC$838,377+49%+5.0%
4Southern Cross Contractors, LLC$1,293,239+130%+62%
TxDOT contract A00214746: bids by rank

Engineer's estimate: $795,860.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Ross Sa Enterprise LLC2. Marcom'S Mowing Service, LLC3. Rhino Equity, LLC4. Southern Cross Contractors, LLC
1Riprap (mow strip)(4 in) (432-7013)CY20$425.00$100.00$450.00$360.00$400.00
2Mobilization (callout) (500-7002)EACH12$600.00$1.00$1.00$1.00$1.00
3TMA (stationary) (505-7001)DAY60$250.00$1.00$1.00$2,500.00$100.00
4Portable concrete traffic barrier (move)(safety SH)(type 2) (512-7063)LF200$50.00$1.00$20.00$2.00$15.00
5Metal W-beam guard fence (steel post) (540-7002)LF200$45.00$48.00$60.00$20.00$40.00
6Metal beam guard fence trans (thrie-beam) (540-7005)EACH2$2,300.00$1,500.00$1,980.00$500.00$2,200.00
7Metal beam guard fence trans (T101) (540-7007)EACH2$1,250.00$100.00$1,500.00$250.00$1,500.00
8Short radius (28") (540-7013)LF100$43.00$45.00$30.00$30.00$30.00
9Downstream anchor terminal section (540-7015)EACH2$1,400.00$2,500.00$2,000.00$300.00$1,300.00
10Metal W - beam guard fence (low fill culvert) (540-7018)LF200$61.00$10.00$1.00$30.00$79.00
11Metal beam guard fence (long span system) (540-7027)EACH100$55.00$10.00$1.00$50.00$1,200.00
12Metal beam guard fence trans (31"-28") (540-7028)EACH20$1,350.00$500.00$600.00$100.00$925.00
13Connector plate for thrie beam (540-7030)EACH4$800.00$350.00$920.00$150.00$800.00
14Remove metal beam guard fence (542-7001)LF1,000$10.00$1.00$1.00$1.00$2.00
15Remove terminal anchor section (542-7002)EACH10$2,500.00$1.00$1,000.00$50.00$100.00
16Remove downstream anchor terminal (542-7003)EACH2$200.00$1.00$1.00$50.00$1.00
17Guardrail end treatment (install) (544-7001)EACH30$3,000.00$1,800.00$500.00$2,000.00$2,950.00
18Guardrail end treatment (remove) (544-7003)EACH20$1,000.00$1.00$1.00$50.00$100.00
19Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012)EACH30$5.00$1.00$30.00$15.00$15.00
20Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013)EACH30$5.00$1.00$30.00$15.00$15.00
21Install delineator assembly (D-SW)SZ 1(BRF)GF1 (658-7015)EACH30$30.00$1.00$30.00$15.00$15.00
22Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018)EACH30$30.00$1.00$100.00$15.00$30.00
23Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019)EACH100$50.00$1.00$50.00$15.00$30.00
24Install delineator assembly (D-SY)SZ 1(BRF)CTB (658-7031)EACH30$5.00$1.00$30.00$15.00$10.00
25Install delineator assembly (D-SY)SZ 1(BRF)CTB (BI) (658-7032)EACH30$5.00$1.00$30.00$15.00$10.00
26Replace rail element (W-beam) (770-7001)LF2,500$22.00$30.00$30.00$10.00$23.00
27Replace rail element (thrie-beam) (770-7002)LF50$80.00$50.00$80.00$10.00$69.00
28Repl rail elmnt(thrie-BM trans to W-BM) (770-7003)EACH25$76.00$50.00$70.00$120.00$169.00
29Replace timber post W/O concrete FND (770-7006)EACH100$70.00$25.00$300.00$30.00$75.00
30Replace steel post W/O concrete FND (770-7007)EACH200$75.00$100.00$65.00$75.00$85.00
31Realign posts (770-7010)EACH300$15.00$15.00$1.00$5.00$1.00
32Replace terminal anchor posts (770-7012)EACH2$5.00$1.00$1.00$100.00$300.00
33Rem obsolete get & repl W/ SGT (770-7013)EACH50$3,500.00$3,500.00$2,980.00$2,200.00$3,200.00
34Repl single gdrail terminal impact head (770-7015)EACH5$1,400.00$1,000.00$1,200.00$500.00$1,200.00
35Replace single gdrail terminal rail (770-7016)LF300$50.00$30.00$45.00$30.00$55.00
36Replace single gdrail terminal post (770-7017)EACH75$80.00$100.00$1.00$50.00$69.00
37Replace blockout (770-7018)EACH10$60.00$500.00$400.00$25.00$15.00
38Repair steel post with base plate (770-7019)EACH6$250.00$100.00$320.00$25.00$325.00
39Reset SGT impact head (770-7020)EACH5$100.00$100.00$1.00$120.00$200.00
40Replace SGT object marker (770-7021)EACH10$20.00$1.00$1.00$30.00$20.00
41Replace SGT cable anchor (770-7022)EACH5$200.00$1.00$1.00$100.00$78.00
42Replace SGT strut (770-7024)EACH3$200.00$1.00$1.00$100.00$70.00
43Replace downstream anchor terminal (770-7026)EACH4$1,100.00$1,250.00$1,280.00$500.00$1,000.00
44Repair rail element (curved rail) (770-7027)LF50$42.00$50.00$35.00$25.00$36.00
45Replace CRT post (wood) (770-7029)EACH5$100.00$1,000.00$100.00$75.00$90.00
46Replace hinged top SGT post (steel) (770-7032)EACH2$800.00$1,000.00$2,000.00$70.00$200.00
47Replace posts (TL-4)(NU-cable) (771-7006)EACH300$155.00$250.00$170.00$180.00$200.00
48Cable splice / turnbuckle (TL-4) (771-7010)EACH5$300.00$150.00$200.00$100.00$330.00
49Repair concrete foundation (TL-4) (771-7012)EACH5$200.00$150.00$1.00$50.00$75.00
50Repair or replace cable barrier terminal sec(TL-4) (771-7014)EACH10$500.00$1,000.00$4,500.00$1,500.00$3,000.00
51Replace cable (TL-4) (771-7016)LF200$5.00$5.00$8.00$2.00$4.00
52Check / RE-tension cable (TL-4) (771-7018)EACH20$200.00$1.00$250.00$100.00$300.00
53Replace (quad - elite) wide (774-7011)EACH2$25,000$5,000.00$10,000$40,000$46,000
54Repair (quad - elite) wide (774-7012)LF25$250.00$100.00$200.00$300.00$1,500.00
55Replace (react)(M) (774-7014)EACH4$10,000$500.00$10,000$33,000$33,000
56Repair (react)(M) (774-7015)LF40$250.00$500.00$1,000.00$200.00$1,500.00
57Replace (react) wide (774-7017)EACH2$25,000$500.00$35,000$45,000$86,000
58Repair (react) wide (774-7018)LF30$250.00$150.00$500.00$500.00$3,750.00
59Repair attenuator object marker (774-7083)EACH10$60.00$1,000.00$350.00$400.00$100.00
60Replace W beam (T631) (776-7004)LF100$25.00$50.00$30.00$30.00$25.00
61Repair steel post W/ base plate (T631) (776-7005)EACH10$200.00$250.00$250.00$30.00$125.00
TxDOT contract A00214746: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of August 21, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy