TxDOT contract A00188271 bid tabulation
Bridge Replacement, US 70 (US 70 to at FM 1763). Let by Texas DOT on October 9, 2025, Wilbarger, Wichita Falls District. 5 bids received; low bid $3,176,311 by Altus Construction LLC, -1.0% against the engineer's estimate of $3,208,474.
- Owner
- Texas DOT
- Letting
- 09 OCT 2025
- Pay items
- 99
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Altus Construction LLC | $3,176,311 | Low | -1.0% |
| 2 | Coppell Construction Co., Inc. | $3,637,907 | +15% | +13% |
| 3 | Skyline Bridge LLC | $4,154,672 | +31% | +29% |
| 4 | Gilvin-Terrill, LTD. | $4,169,931 | +31% | +30% |
| 5 | Hodges and Son Construction Company, Inc. | $4,688,569 | +48% | +46% |
Engineer's estimate: $3,208,474.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Altus Construction LLC | 2. Coppell Construction Co., Inc. | 3. Skyline Bridge LLC | 4. Gilvin-Terrill, LTD. | 5. Hodges and Son Construction Company, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (mowstrip) (104-7003) | SY | 90 | $12.00 | $29.91 | $70.00 | $50.00 | $10.00 | $45.00 |
| 2 | Removing concrete (riprap) (104-7006) | SY | 870 | $12.00 | $39.01 | $16.00 | $5.00 | $10.00 | $45.00 |
| 3 | Removing concrete (rail) (104-7036) | LF | 56 | $17.00 | $61.35 | $180.00 | $170.00 | $150.00 | $8,000.00 |
| 4 | Remove (12") TRT/untrt base & asphalt pavement (105-7091) | CY | 2,690 | $18.00 | $20.90 | $12.00 | $40.00 | $25.00 | $40.00 |
| 5 | Excavation (roadway) (110-7001) | CY | 143 | $40.00 | $23.89 | $45.00 | $18.00 | $80.00 | $50.00 |
| 6 | Embankment (final)(DC)(type B) (132-7004) | CY | 611 | $40.00 | $18.56 | $36.00 | $35.00 | $80.00 | $60.00 |
| 7 | Backfill (type A) (134-7001) | STA | 9.80 | $240.00 | $177.78 | $1,950.00 | $1,000.00 | $500.00 | $100.00 |
| 8 | Drill seed (permanent_rural_clay) (164-7010) | SY | 10,550 | $2.50 | $0.33 | $0.40 | $0.75 | $0.50 | $1.00 |
| 9 | Drill seed (temporary_warm_cool) (164-7015) | SY | 9,490 | $0.50 | $0.33 | $0.40 | $0.75 | $0.50 | $1.00 |
| 10 | Soil ret BLKT(SL_mod_clay_long) (169-7002) | SY | 5,155 | $3.00 | $4.15 | $1.50 | $2.50 | $2.00 | $2.50 |
| 11 | Cement (275-7001) | TON | 34 | $460.00 | $273.08 | $325.00 | $400.00 | $200.00 | $380.00 |
| 12 | Cement TRT (existing material)(8") (275-7003) | SY | 2,993 | $20.00 | $5.56 | $10.00 | $42.00 | $10.00 | $12.00 |
| 13 | Prime coat (MC-30) (310-7004) | GAL | 797 | $10.00 | $22.70 | $12.00 | $22.00 | $10.00 | $20.00 |
| 14 | Emuls asphalt (erosion control)(SS-1) (314-7008) | GAL | 184 | $5.00 | $27.74 | $25.00 | $27.00 | $12.50 | $25.00 |
| 15 | SP mixes SP-B PG70-22 (344-7004) | TON | 810 | $180.00 | $398.43 | $160.00 | $325.00 | $200.00 | $320.00 |
| 16 | SP mixes SP-C sac-B PG70-22 (344-7021) | TON | 407 | $200.00 | $408.52 | $175.00 | $350.00 | $200.00 | $325.00 |
| 17 | Planing asphalt concrete pavement(0" to 2") (354-7032) | SY | 195 | $17.00 | $23.33 | $40.00 | $30.00 | $40.00 | $70.00 |
| 18 | Cem stabil BKFL (400-7010) | CY | 320 | $220.00 | $229.08 | $275.00 | $275.00 | $500.00 | $250.00 |
| 19 | Drilled shaft (18 in) (416-7002) | LF | 360 | $200.00 | $114.02 | $106.00 | $250.00 | $200.00 | $135.00 |
| 20 | Drilled shaft (36 in) (416-7006) | LF | 405 | $325.00 | $208.25 | $350.00 | $350.00 | $350.00 | $350.00 |
| 21 | Class C concrete (abutment)(HPC) (420-7013) | CY | 134.90 | $1,500.00 | $896.21 | $1,000.00 | $1,300.00 | $1,000.00 | $1,300.00 |
| 22 | Class C concrete (cap)(HPC) (420-7023) | CY | 51.30 | $1,750.00 | $2,358.55 | $995.00 | $1,900.00 | $1,000.00 | $2,000.00 |
| 23 | Class C concrete (column)(HPC) (420-7039) | CY | 44 | $2,000.00 | $1,558.61 | $1,100.00 | $2,500.00 | $1,000.00 | $1,800.00 |
| 24 | Class C concrete (rail foundation) (420-7052) | CY | 150 | $1,000.00 | $539.23 | $610.00 | $1,200.00 | $700.00 | $700.00 |
| 25 | Reinforced concrete slab (box beam)(HPC) (422-7006) | SF | 7,000 | $30.00 | $21.65 | $20.00 | $30.00 | $30.00 | $32.00 |
| 26 | Approach slab (HPC) (422-7014) | CY | 82 | $950.00 | $785.87 | $700.00 | $900.00 | $1,200.00 | $1,200.00 |
| 27 | Shear key (422-7020) | CY | 32 | $500.00 | $740.44 | $500.00 | $850.00 | $1,000.00 | $900.00 |
| 28 | Prestressed concrete box beam (5B20) (425-7027) | LF | 1,386 | $301.00 | $293.93 | $332.06 | $335.00 | $400.00 | $360.00 |
| 29 | Penetrating concrete surface treatment (428-7001) | SY | 777 | $28.00 | $28.37 | $21.00 | $20.00 | $20.00 | $20.00 |
| 30 | Riprap (concrete)(4 in) (432-7001) | CY | 100 | $550.00 | $1,052.72 | $650.00 | $1,000.00 | $750.00 | $750.00 |
| 31 | Riprap (mow strip)(4 in) (432-7013) | CY | 61 | $575.00 | $774.02 | $725.00 | $750.00 | $750.00 | $750.00 |
| 32 | Rail (type SSTR)(HPC) (450-7025) | LF | 530 | $180.00 | $143.02 | $110.00 | $190.00 | $125.00 | $150.00 |
| 33 | Rail (type T80PP) (450-7051) | LF | 840 | $228.00 | $94.09 | $450.00 | $225.00 | $275.00 | $200.00 |
| 34 | Sealed expansion joint (4 in) (SEJ - M) (454-7004) | LF | 68 | $240.00 | $269.51 | $330.00 | $275.00 | $300.00 | $200.00 |
| 35 | Removing structure (bridge 100 - 499 FT length) (496-7010) | EACH | 1 | $75,000 | $95,342 | $135,000 | $125,000 | $385,000 | $350,000 |
| 36 | Mobilization (500-7001) | LS | 1 | $290,000 | $316,047 | $340,000 | $350,000 | $400,000 | $410,000 |
| 37 | Barricades, signs and traffic handling (502-7001) | MO | 11 | $3,500.00 | $3,782.56 | $20,000 | $4,000.00 | $9,000.00 | $15,000 |
| 38 | Portable changeable message sign (503-7002) | EACH | 2 | $12,000 | $7,021.37 | $15,000 | $18,500 | $18,500 | $25,000 |
| 39 | TMA (stationary) (505-7001) | DAY | 108 | $200.00 | $189.13 | $650.00 | $900.00 | $510.00 | $300.00 |
| 40 | TMA (mobile operation) (505-7003) | DAY | 8 | $250.00 | $160.58 | $1,750.00 | $100.00 | $510.00 | $300.00 |
| 41 | Rock filter dams (install) (type 2) (506-7002) | LF | 115 | $53.00 | $50.64 | $50.00 | $45.00 | $54.00 | $1.00 |
| 42 | Rock filter dams (remove) (506-7011) | LF | 115 | $15.00 | $17.59 | $15.00 | $10.00 | $15.00 | $1.00 |
| 43 | Construction exits (install) (type 1) (506-7020) | SY | 448 | $40.00 | $35.81 | $42.00 | $10.00 | $50.00 | $1.00 |
| 44 | Construction exits (remove) (506-7024) | SY | 448 | $12.00 | $14.18 | $12.00 | $1.00 | $15.00 | $1.00 |
| 45 | Temporary sediment control fence (install) (506-7039) | LF | 1,850 | $6.00 | $4.52 | $6.00 | $3.90 | $6.00 | $1.00 |
| 46 | Temporary sediment control fence (remove) (506-7041) | LF | 1,850 | $2.00 | $1.13 | $1.00 | $1.00 | $1.00 | $1.00 |
| 47 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 595 | $6.50 | $6.95 | $7.00 | $12.00 | $10.00 | $1.00 |
| 48 | Biodegradable erosion control logs (remove) (506-7046) | LF | 595 | $2.00 | $1.89 | $1.25 | $6.00 | $2.00 | $1.00 |
| 49 | Constructing detours (508-7001) | SY | 516 | $138.00 | $209.83 | $362.00 | $350.00 | $500.00 | $350.00 |
| 50 | Constructing detours (ebss) (508-7002) | SY | 296 | $138.00 | $150.36 | $362.00 | $350.00 | $500.00 | $325.00 |
| 51 | One-way traffic control (flagger cont) (510-7001) | HR | 36 | $65.00 | $40.19 | $480.00 | $1,000.00 | $80.00 | $700.00 |
| 52 | One-way traffic control (port traffic signal) (510-7003) | MO | 4 | $5,900.00 | $5,811.36 | $7,800.00 | $7,500.00 | $4,400.00 | $5,000.00 |
| 53 | Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009) | LF | 80 | $100.00 | $75.65 | $150.00 | $150.00 | $60.00 | $80.00 |
| 54 | Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057) | LF | 80 | $22.00 | $26.48 | $150.00 | $50.00 | $60.00 | $80.00 |
| 55 | Metal W-beam guard fence (timber post) (540-7001) | LF | 700 | $28.00 | $28.09 | $26.00 | $29.00 | $25.00 | $25.00 |
| 56 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 8 | $2,514.00 | $2,127.22 | $1,525.00 | $2,000.00 | $1,650.00 | $1,600.00 |
| 57 | Downstream anchor terminal section (540-7015) | EACH | 1 | $2,000.00 | $1,385.83 | $1,275.00 | $1,750.00 | $1,500.00 | $1,400.00 |
| 58 | Metal beam guard fence trans (31"-28") (540-7028) | EACH | 1 | $615.00 | $472.82 | $550.00 | $800.00 | $800.00 | $600.00 |
| 59 | Remove metal beam guard fence (542-7001) | LF | 1,425 | $3.40 | $2.96 | $2.50 | $5.00 | $2.00 | $2.00 |
| 60 | Remove terminal anchor section (542-7002) | EACH | 5 | $225.00 | $212.42 | $200.00 | $500.00 | $300.00 | $500.00 |
| 61 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 6 | $220.00 | $260.05 | $150.00 | $500.00 | $300.00 | $500.00 |
| 62 | Guardrail end treatment (install) (544-7001) | EACH | 6 | $3,500.00 | $3,167.89 | $3,050.00 | $3,600.00 | $3,000.00 | $3,200.00 |
| 63 | Mailbox install-S (TWG-post) type 2 (560-7002) | EACH | 1 | $400.00 | $333.91 | $500.00 | $500.00 | $500.00 | $800.00 |
| 64 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 4 | $650.00 | $728.14 | $925.00 | $1,000.00 | $750.00 | $2,000.00 |
| 65 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 2 | $1,040.00 | $803.79 | $975.00 | $1,200.00 | $950.00 | $2,000.00 |
| 66 | Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007) | EACH | 1 | $1,000.00 | $1,885.08 | $1,200.00 | $1,500.00 | $1,250.00 | $2,000.00 |
| 67 | Install small roadside sign support and assembly type 10BWG(2)SA(P) (644-7017) | EACH | 1 | $1,400.00 | $1,487.02 | $1,500.00 | $1,500.00 | $1,500.00 | $2,000.00 |
| 68 | Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025) | EACH | 1 | $1,100.00 | $945.64 | $1,000.00 | $1,500.00 | $1,000.00 | $2,500.00 |
| 69 | Install small roadside sign support and assembly TYS80(1)SA(U-1EXT) (644-7032) | EACH | 1 | $1,100.00 | $1,407.81 | $1,250.00 | $1,500.00 | $1,250.00 | $2,500.00 |
| 70 | In bridge MNT clearance sign assembly(type N) (644-7061) | EACH | 2 | $2,800.00 | $4,586.35 | $4,000.00 | $5,000.00 | $3,000.00 | $8,000.00 |
| 71 | Install small roadside sign support and assembly (rail mount) (644-7063) | EACH | 4 | $4,900.00 | $5,285.21 | $7,500.00 | $7,500.00 | $4,500.00 | $2,000.00 |
| 72 | Remove SM RD SN sup&AM (644-7073) | EACH | 8 | $150.00 | $126.92 | $150.00 | $400.00 | $150.00 | $50.00 |
| 73 | Install delineator assembly (D-SW)SZ 1(WFLX)GF2 (658-7001) | EACH | 2 | $50.00 | $46.81 | $25.00 | $75.00 | $38.00 | $50.00 |
| 74 | Install delineator assembly (D-SW)SZ 1(WFLX)GF2(BI) (658-7002) | EACH | 7 | $40.00 | $47.28 | $25.00 | $75.00 | $38.00 | $40.00 |
| 75 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012) | EACH | 4 | $26.00 | $20.80 | $18.00 | $75.00 | $33.00 | $40.00 |
| 76 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 6 | $36.00 | $24.59 | $18.00 | $75.00 | $33.00 | $40.00 |
| 77 | Install delineator assembly (D-SY)SZ 1(yflx)GF2 (658-7021) | EACH | 9 | $54.00 | $20.80 | $25.00 | $75.00 | $38.00 | $100.00 |
| 78 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (658-7031) | EACH | 8 | $32.00 | $21.75 | $18.00 | $75.00 | $33.00 | $40.00 |
| 79 | Work zone pavement marking removing (reflectorized) type II-A-A (662-7051) | EACH | 145 | $4.00 | $8.26 | $7.00 | $10.00 | $6.55 | $8.00 |
| 80 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 2,125 | $1.00 | $1.89 | $1.50 | $2.00 | $1.50 | $2.00 |
| 81 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 22 | $30.00 | $18.91 | $16.00 | $20.00 | $15.50 | $20.00 |
| 82 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 5,645 | $1.00 | $1.89 | $1.50 | $2.00 | $1.50 | $2.00 |
| 83 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 120 | $1.10 | $1.89 | $1.50 | $2.00 | $1.50 | $2.00 |
| 84 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 54 | $9.00 | $11.35 | $9.00 | $12.00 | $9.00 | $10.00 |
| 85 | Reflectorized pavement marking type I (W)(RR crossing)(100MIL) (666-7081) | EACH | 1 | $1,000.00 | $1,260.85 | $1,100.00 | $1,500.00 | $1,100.00 | $1,200.00 |
| 86 | Type I high perf PM (W)6"(solid)(100MIL) (666-7293) | LF | 212 | $1.00 | $9.14 | $7.25 | $9.00 | $7.25 | $10.00 |
| 87 | Pavement sler 6" (666-7347) | LF | 4,542 | $0.50 | $0.32 | $0.25 | $0.50 | $0.25 | $1.00 |
| 88 | Pavement sler 8" (666-7348) | LF | 120 | $0.80 | $0.63 | $0.50 | $1.00 | $0.50 | $1.00 |
| 89 | Pavement sler 24" (666-7352) | LF | 54 | $2.00 | $3.15 | $2.50 | $3.00 | $2.50 | $10.00 |
| 90 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 1,975 | $0.90 | $2.08 | $1.65 | $2.00 | $1.65 | $2.00 |
| 91 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 240 | $0.90 | $2.08 | $1.65 | $2.00 | $1.65 | $2.00 |
| 92 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 2,115 | $0.90 | $2.08 | $1.65 | $2.00 | $1.65 | $2.00 |
| 93 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 24 | $10.00 | $10.40 | $8.25 | $10.00 | $8.25 | $15.00 |
| 94 | Eliminating existing PM & markers (4") (677-7001) | LF | 680 | $2.50 | $2.84 | $2.25 | $2.50 | $2.25 | $4.00 |
| 95 | Pavement surface preparation for marking (6") (678-7002) | LF | 1,010 | $2.50 | $0.13 | $0.10 | $0.25 | $0.10 | $1.00 |
| 96 | Pavement surface preparation for marking (24") (678-7008) | LF | 30 | $10.00 | $0.63 | $0.50 | $0.75 | $0.50 | $5.00 |
| 97 | Bonding course (3007-7001) | GAL | 384 | $5.15 | $2.52 | $3.00 | $5.00 | $15.00 | $8.00 |
| 98 | Rem lead-containing coating (4" strip) (5011-7004) | EACH | 105 | $230.00 | $301.34 | $239.00 | $300.00 | $300.00 | $400.00 |
| 99 | Rem lead-contatining coating (6" strip) (5011-7005) | EACH | 24 | $300.00 | $603.95 | $479.00 | $600.00 | $500.00 | $600.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of October 9, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.