TxDOT contract A00207389 bid tabulation
Bridge Replacement, FM 1547 (@ Buck Creek to .). Let by Texas DOT on September 3, 2026, Collingsworth, Childress District. 7 bids received; low bid $3,017,334 by Coppell Construction Co., Inc., -8.2% against the engineer's estimate of $3,287,111.
- Owner
- Texas DOT
- Letting
- 03 SEP 2026
- Pay items
- 52
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Coppell Construction Co., Inc. | $3,017,334 | Low | -8.0% |
| 2 | Earth Builders, L.P. | $3,434,175 | +14% | +4.0% |
| 3 | Scott Tucker Construction Company, LLC | $3,790,406 | +26% | +15% |
| 4 | Tucan Contracting, LLC | $3,835,569 | +27% | +17% |
| 5 | Hodges and Son Construction Company, Inc. | $4,089,657 | +36% | +24% |
| 6 | Gilvin-Terrill, LTD. | $4,428,835 | +47% | +35% |
| 7 | J. Lee Milligan, Inc. | $5,691,985 | +89% | +73% |
Engineer's estimate: $3,287,111.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Coppell Construction Co., Inc. | 2. Earth Builders, L.P. | 3. Scott Tucker Construction Company, LLC | 4. Tucan Contracting, LLC | 5. Hodges and Son Construction Company, Inc. | 6. Gilvin-Terrill, LTD. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (riprap) (104-7006) | SY | 466 | $15.00 | $20.00 | $10.00 | $20.00 | $11.00 | $10.00 | $25.00 |
| 2 | Remove (8") TRT/untrt base & asphalt pavement (105-7028) | SY | 1,434 | $15.00 | $10.50 | $10.00 | $15.00 | $6.60 | $8.00 | $20.00 |
| 3 | Excavation (roadway) (110-7001) | CY | 380 | $35.00 | $25.00 | $40.00 | $36.00 | $27.50 | $30.00 | $25.00 |
| 4 | Excavation (channel) (110-7002) | CY | 25 | $55.00 | $40.00 | $80.00 | $22.00 | $50.00 | $60.00 | |
| 5 | Subgr widen (OC) (112-7001) | STA | 8 | $860.00 | $1,500.00 | $2,740.00 | $440.00 | $750.00 | $2,000.00 | |
| 6 | Embankment (final)(OC)(type B) (132-7003) | CY | 167 | $22.00 | $23.00 | $50.00 | $66.00 | $88.00 | $35.00 | $25.00 |
| 7 | Embankment (org)(DC)(type A) (132-7022) | CY | 160 | $23.00 | $50.00 | $67.00 | $88.00 | $35.00 | $60.00 | |
| 8 | Backfill (type A or B) (134-7004) | STA | 8 | $800.00 | $2,000.00 | $779.00 | $330.00 | $1,300.00 | $1,000.00 | |
| 9 | Blading (150-7002) | HR | 4 | $270.00 | $55.00 | $150.00 | $1,263.00 | $220.00 | $20.00 | $310.00 |
| 10 | Broadcast seed (permanent_rural_sand) (164-7033) | ACRE | 0.75 | $3,800.00 | $2,000.00 | $3,021.00 | $4,020.50 | $6,800.00 | $4,000.00 | |
| 11 | Drill seed (permanent_rural_sand) (164-7041) | ACRE | 0.75 | $620.00 | $3,800.00 | $2,000.00 | $5,533.00 | $1,860.19 | $2,600.00 | $4,000.00 |
| 12 | Vegetative watering (168-7001) | TGL | 33 | $25.00 | $50.00 | $100.00 | $735.00 | $30.53 | $1.00 | $70.00 |
| 13 | Proof rolling (216-7001) | HR | 4 | $165.00 | $60.00 | $100.00 | $1,088.00 | $159.50 | $20.00 | $165.00 |
| 14 | FL BS (compacted in place)(type A GR 1-2) (8") (247-7067) | SY | 1,442 | $27.00 | $40.00 | $40.00 | $34.00 | $66.00 | $50.00 | $45.00 |
| 15 | Prime coat (MC-30) (310-7004) | GAL | 1,065 | $6.00 | $18.00 | $10.00 | $20.00 | $19.80 | $15.00 | $10.00 |
| 16 | Asphalt (CRS-2P) (316-7012) | GAL | 3,258 | $8.00 | $16.25 | $10.00 | $18.00 | $19.80 | $15.00 | $10.00 |
| 17 | Aggregate (type-B, GR-4)(sac-A) (316-7099) | CY | 64 | $110.00 | $1,900.00 | $200.00 | $1,988.00 | $2,310.00 | $1,500.00 | $300.00 |
| 18 | Cem stabil BKFL (400-7010) | CY | 72 | $250.00 | $301.00 | $400.00 | $220.00 | $275.00 | $300.00 | $500.00 |
| 19 | Temporary special shoring (403-7001) | SF | 120 | $40.00 | $50.00 | $53.00 | $22.00 | $5.00 | $100.00 | |
| 20 | Drilled shaft (36 in) (416-7006) | LF | 1,615 | $300.00 | $295.00 | $275.00 | $353.00 | $495.00 | $375.00 | $400.00 |
| 21 | Class C concrete (abutment) (420-7012) | CY | 40.90 | $1,600.00 | $1,350.00 | $1,800.00 | $1,523.00 | $1,430.00 | $2,200.00 | $2,500.00 |
| 22 | Class C concrete (cap) (420-7022) | CY | 105 | $2,000.00 | $1,275.00 | $1,800.00 | $1,576.00 | $1,760.00 | $2,200.00 | $2,500.00 |
| 23 | Class C concrete (column) (420-7038) | CY | 22.60 | $2,500.00 | $2,100.00 | $1,800.00 | $1,898.00 | $1,980.00 | $2,200.00 | $2,500.00 |
| 24 | Reinforced concrete slab (422-7001) | SF | 17,340 | $28.19 | $28.50 | $40.00 | $32.00 | $30.80 | $40.00 | $40.00 |
| 25 | Approach slab (422-7013) | CY | 61.20 | $850.00 | $1,005.00 | $1,000.00 | $889.00 | $990.00 | $1,200.00 | $2,000.00 |
| 26 | Prestressed concrete girder (TX34) (425-7002) | LF | 2,024 | $234.26 | $250.00 | $250.00 | $280.00 | $269.50 | $255.00 | $300.00 |
| 27 | Penetrating concrete surface treatment (428-7001) | SY | 121 | $70.70 | $80.00 | $21.00 | $11.00 | $16.00 | $75.00 | |
| 28 | Riprap (mow strip)(4 in) (432-7013) | CY | 40 | $750.00 | $720.00 | $800.00 | $847.00 | $825.00 | $780.00 | $750.00 |
| 29 | Riprap (stone protection)(24 in) (432-7045) | CY | 594 | $210.00 | $210.00 | $200.00 | $220.00 | $440.00 | $230.00 | $300.00 |
| 30 | Rail (type T631) (450-7020) | LF | 80 | $84.00 | $100.00 | $112.00 | $165.00 | $95.00 | $110.00 | |
| 31 | Rail (type SSTR) (450-7024) | LF | 1,056 | $75.83 | $117.00 | $140.00 | $106.00 | $132.00 | $150.00 | $135.00 |
| 32 | Sealed expansion joint (4 in) (SEJ - M) (454-7004) | LF | 99 | $275.00 | $250.00 | $230.00 | $225.00 | $242.00 | $175.00 | $280.00 |
| 33 | Concrete box culvert (10 FT X 6 FT) (462-7034) | LF | 102 | $1,200.00 | $900.00 | $1,047.00 | $1,320.00 | $1,700.00 | $800.00 | |
| 34 | Wingwall (FW - 0) (HW=7 FT) (466-7149) | EACH | 2 | $17,500 | $25,000 | $14,390 | $22,000 | $25,000 | $10,000 | |
| 35 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 1 | $17,000 | $20,000 | $13,667 | $11,000 | $35,000 | $3,500.00 | |
| 36 | Removing structure (bridge 100 - 499 FT length) (496-7010) | EACH | 1 | $400,000 | $40,000 | $190,000 | $44,477 | $55,000 | $360,000 | $435,400 |
| 37 | Mobilization (500-7001) | LS | 1 | $246,646 | $130,000 | $325,000 | $379,000 | $300,000 | $360,000 | $415,000 |
| 38 | Barricades, signs and traffic handling (502-7001) | MO | 13 | $3,500.00 | $8,200.00 | $2,500.00 | $1,748.00 | $2,200.00 | $2,500.00 | $6,000.00 |
| 39 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 388 | $5.50 | $11.00 | $15.00 | $5.00 | $7.70 | $5.00 | $15.00 |
| 40 | Biodegradable erosion control logs (remove) (506-7046) | LF | 388 | $1.00 | $3.00 | $2.00 | $2.00 | $1.10 | $1.00 | $3.00 |
| 41 | Constructing detours (508-7001) | SY | 978 | $55.00 | $55.50 | $50.00 | $371.00 | $55.00 | $80.00 | $155.00 |
| 42 | Metal W-beam guard fence (steel post) (540-7002) | LF | 275 | $30.00 | $40.00 | $42.00 | $55.00 | $30.00 | $37.00 | |
| 43 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 4 | $3,100.00 | $2,175.00 | $2,500.00 | $3,717.00 | $2,530.00 | $2,300.00 | $2,300.00 |
| 44 | Guardrail end treatment (install) (544-7001) | EACH | 8 | $3,750.00 | $3,275.00 | $3,700.00 | $3,550.00 | $3,520.00 | $3,300.00 | $3,200.00 |
| 45 | Guardrail end treatment (remove) (544-7003) | EACH | 4 | $238.00 | $100.00 | $250.00 | $100.00 | $110.00 | $500.00 | $100.00 |
| 46 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 34 | $37.94 | $15.00 | $50.00 | $25.00 | $27.50 | $15.00 | $25.00 |
| 47 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 8 | $46.00 | $25.00 | $50.00 | $31.00 | $34.10 | $25.00 | $31.00 |
| 48 | Pavement sler 6" (666-7347) | LF | 2,200 | $0.79 | $3.00 | $3.50 | $2.00 | $3.30 | $1.00 | $3.00 |
| 49 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 1,882 | $0.45 | $4.00 | $4.50 | $6.00 | $4.40 | $4.00 | $4.00 |
| 50 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 408 | $0.45 | $4.00 | $4.50 | $6.00 | $4.40 | $4.00 | $4.00 |
| 51 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 1,622 | $0.43 | $4.00 | $4.50 | $6.00 | $4.40 | $4.00 | $4.00 |
| 52 | Pavement surface preparation for marking (6") (678-7002) | LF | 2,200 | $0.69 | $3.00 | $3.50 | $1.50 | $3.30 | $1.00 | $3.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of September 3, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.