TxDOT contract A00184830 bid tabulation
Bridge Replacement, IH 40 (IH 40 AT SH 207 to .). Let by Texas DOT on September 3, 2026, Carson, Amarillo District. 7 bids received; low bid $9,899,343 by Gilvin-Terrill, LTD., -7.5% against the engineer's estimate of $10,704,179.
- Owner
- Texas DOT
- Letting
- 03 SEP 2026
- Pay items
- 128
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Gilvin-Terrill, LTD. | $9,899,343 | Low | -8.0% |
| 2 | L A Fuller & Sons Construction, LTD. | $11,103,635 | +12% | +4.0% |
| 3 | Webber, LLC | $11,346,486 | +15% | +6.0% |
| 4 | Texas Steel Industrial Placing, LLC | $12,935,696 | +31% | +21% |
| 5 | J. Lee Milligan, Inc. | $12,984,816 | +31% | +21% |
| 6 | Ragle Construction, Inc. | $13,026,104 | +32% | +22% |
| 7 | Earth Builders, L.P. | $13,990,306 | +41% | +31% |
Engineer's estimate: $10,704,179.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Gilvin-Terrill, LTD. | 2. L A Fuller & Sons Construction, LTD. | 3. Webber, LLC | 4. Texas Steel Industrial Placing, LLC | 5. J. Lee Milligan, Inc. | 6. Ragle Construction, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (riprap) (104-7006) | SY | 1,142 | $15.00 | $30.00 | $29.95 | $8.50 | $20.00 | $35.00 | $13.00 |
| 2 | Removing concrete (driveways) (104-7011) | SY | 379 | $20.00 | $30.00 | $32.70 | $17.50 | $20.00 | $40.00 | $22.00 |
| 3 | Removing concrete (foundations) (104-7023) | SY | 86 | $30.00 | $30.00 | $54.20 | $64.00 | $35.00 | $205.00 | $108.00 |
| 4 | Remove (16"-20") TRT/untrt base & asphalt pavement (105-7016) | SY | 10,788 | $20.00 | $20.00 | $9.75 | $15.00 | $12.00 | $16.00 | $20.00 |
| 5 | Excavation (roadway) (110-7001) | CY | 5,520 | $14.00 | $25.00 | $10.65 | $29.50 | $20.00 | $27.00 | $60.00 |
| 6 | Excavation (channel) (110-7002) | CY | 14,726 | $14.00 | $25.00 | $6.70 | $10.00 | $20.00 | $20.00 | $25.00 |
| 7 | Embankment (final)(DC)(type B) (132-7004) | CY | 26,495 | $24.00 | $25.00 | $23.50 | $11.00 | $25.00 | $27.75 | $40.00 |
| 8 | Broadcast seed (permanent_rural_clay) (164-7034) | ACRE | 9.39 | $1,000.00 | $655.00 | $888.97 | $668.00 | $655.00 | $710.00 | $1,254.24 |
| 9 | Drill seed (temporary_warm_cool) (164-7047) | ACRE | 9.90 | $1,000.00 | $530.00 | $888.97 | $540.00 | $530.00 | $570.00 | $1,150.68 |
| 10 | FL BS(compacted in place)(type A,B or D GR4)(12") (247-7134) | SY | 17,579 | $38.00 | $35.00 | $23.50 | $35.00 | $32.00 | $38.98 | $25.00 |
| 11 | Cement (275-7001) | TON | 193 | $300.00 | $230.00 | $265.00 | $240.00 | $250.00 | $315.00 | $360.00 |
| 12 | Cement treat (subgrade) (8") (275-7017) | SY | 17,579 | $5.65 | $10.00 | $5.60 | $2.75 | $7.00 | $9.00 | $3.90 |
| 13 | Prime coat (MC-30) (310-7004) | GAL | 4,396 | $6.00 | $10.20 | $8.00 | $6.95 | $15.00 | $5.60 | $8.50 |
| 14 | Emuls asphalt (erosion control)(multi) (314-7018) | GAL | 542 | $8.00 | $10.20 | $10.35 | $3.90 | $21.50 | $11.50 | $12.30 |
| 15 | SP mixes SP-D sac-A PG70-28 (344-7057) | TON | 6,539 | $177.00 | $160.00 | $185.00 | $200.05 | $265.00 | $180.00 | $185.00 |
| 16 | SP mixes SP-D sac-B PG70-28 (level-UP) (344-7059) | TON | 460 | $300.00 | $160.00 | $230.00 | $200.05 | $295.00 | $220.00 | $202.00 |
| 17 | Tack coat (344-7077) | GAL | 9,235 | $7.00 | $6.00 | $9.90 | $8.75 | $12.00 | $6.00 | $6.12 |
| 18 | Planing asphalt concrete pavement(0" to 2") (354-7032) | SY | 3,789 | $3.50 | $6.00 | $6.10 | $6.25 | $7.00 | $15.00 | $6.30 |
| 19 | Cut & restoring pavement (400-7006) | SY | 92 | $150.00 | $150.00 | $176.55 | $315.00 | $175.00 | $140.00 | $185.00 |
| 20 | Cem stabil BKFL (400-7010) | CY | 323 | $240.00 | $250.00 | $255.30 | $280.20 | $250.00 | $365.00 | $129.00 |
| 21 | Trench excavation protection (402-7001) | LF | 75 | $30.00 | $50.00 | $9.95 | $62.50 | $150.00 | $270.00 | $15.00 |
| 22 | Temporary special shoring (403-7001) | SF | 3,427 | $50.00 | $50.00 | $43.50 | $17.00 | $70.00 | $20.00 | $33.00 |
| 23 | Drilled shaft (18 in) (416-7002) | LF | 174 | $80.00 | $100.00 | $117.00 | $140.00 | $200.00 | $290.00 | $136.00 |
| 24 | Drilled shaft (36 in) (416-7006) | LF | 897 | $325.00 | $250.00 | $325.00 | $275.00 | $400.00 | $325.00 | $277.00 |
| 25 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 40 | $275.00 | $300.00 | $316.25 | $305.00 | $400.00 | $320.00 | $275.00 |
| 26 | Class C concrete (abutment)(HPC) (420-7013) | CY | 81 | $1,750.00 | $1,750.00 | $2,490.00 | $1,975.00 | $2,000.00 | $1,600.00 | $1,165.00 |
| 27 | Class C concrete (cap)(HPC) (420-7023) | CY | 34.60 | $1,800.00 | $1,750.00 | $4,075.00 | $1,656.50 | $2,500.00 | $1,500.00 | $1,800.00 |
| 28 | Class C concrete (column)(HPC) (420-7039) | CY | 54.60 | $2,000.00 | $1,750.00 | $1,865.00 | $1,595.00 | $2,500.00 | $2,150.00 | $3,400.00 |
| 29 | Class C concrete (rail foundation) (420-7052) | CY | 98 | $840.00 | $600.00 | $1,035.00 | $610.00 | $550.00 | $1,025.00 | $788.00 |
| 30 | Reinforced concrete slab (422-7001) | SF | 11,880 | $40.50 | $35.00 | $42.00 | $35.00 | $33.00 | $56.00 | $33.00 |
| 31 | Approach slab (422-7013) | CY | 156 | $900.00 | $1,500.00 | $1,013.90 | $760.00 | $650.00 | $1,290.00 | $733.00 |
| 32 | Retaining wall (MSE) (423-7001) | SF | 6,260 | $104.00 | $100.00 | $79.95 | $172.00 | $135.00 | $165.00 | $130.00 |
| 33 | Prestressed concrete girder (TX34) (425-7002) | LF | 2,166.52 | $280.00 | $300.00 | $430.00 | $270.00 | $230.00 | $375.00 | $280.00 |
| 34 | Riprap (concrete)(4 in) (432-7001) | CY | 594 | $830.00 | $530.00 | $860.00 | $710.00 | $525.00 | $565.00 | $691.00 |
| 35 | Riprap (concrete)(5 in) (432-7002) | CY | 107 | $860.00 | $560.00 | $720.00 | $655.00 | $575.00 | $755.00 | $741.00 |
| 36 | Riprap (concrete)(flume) (432-7012) | CY | 36 | $860.00 | $800.00 | $1,380.25 | $890.00 | $650.00 | $1,140.00 | $713.00 |
| 37 | Riprap (mow strip)(4 in) (432-7013) | CY | 72 | $760.00 | $600.00 | $945.15 | $715.00 | $650.00 | $700.00 | $649.00 |
| 38 | Rail (type SSTR) (450-7024) | LF | 828 | $120.00 | $110.00 | $103.55 | $188.00 | $104.00 | $135.00 | $109.00 |
| 39 | Rail (type T80PP-TS) (450-7053) | LF | 140 | $300.00 | $365.00 | $833.55 | $350.00 | $430.00 | $710.00 | $477.00 |
| 40 | Header type expansion joint (454-7009) | CF | 6 | $4,000.00 | $1,500.00 | $742.10 | $2,995.00 | $600.00 | $3,765.00 | $480.00 |
| 41 | Concrete box culvert (6 FT X 2 FT) (462-7010) | LF | 370 | $500.00 | $600.00 | $592.00 | $650.00 | $700.00 | $600.00 | $512.00 |
| 42 | Concrete box culvert (6 FT X 2 FT)(extend) (462-7065) | LF | 3 | $1,500.00 | $4,000.00 | $5,408.45 | $4,960.00 | $1,500.00 | $3,300.00 | $5,200.00 |
| 43 | RC pipe (CL III)(18 in) (464-7003) | LF | 263 | $120.00 | $125.00 | $137.10 | $135.00 | $125.00 | $190.00 | $100.00 |
| 44 | Set (type I)(S= 6 FT)(HW= 3 FT)(6:1)(C) (467-7126) | EACH | 6 | $16,200 | $8,100.00 | $24,606 | $12,605 | $17,000 | $21,000 | $25,000 |
| 45 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 7 | $1,630.00 | $6,675.00 | $3,000.60 | $2,400.00 | $3,200.00 | $3,600.00 | $2,700.00 |
| 46 | Clean existing culverts (480-7001) | EACH | 1 | $2,500.00 | $5,175.00 | $4,703.65 | $2,655.00 | $11,000 | $13,000 | $5,000.00 |
| 47 | Removing structure (inlet) (496-7002) | EACH | 1 | $1,000.00 | $2,070.00 | $1,901.10 | $2,175.00 | $3,500.00 | $2,500.00 | $1,000.00 |
| 48 | Removing structure (wingwall) (496-7005) | EACH | 4 | $1,440.00 | $2,070.00 | $2,557.50 | $2,375.00 | $3,000.00 | $2,500.00 | $10,000 |
| 49 | Removing structure (pipe) (496-7007) | LF | 110 | $50.00 | $30.00 | $64.45 | $46.00 | $30.00 | $65.00 | $19.00 |
| 50 | Removing structure (box culvert) (496-7008) | LF | 36 | $160.00 | $30.00 | $71.05 | $101.00 | $500.00 | $355.00 | $108.00 |
| 51 | Removing structure (bridge 100 - 499 FT length) (496-7010) | EACH | 1 | $205,000 | $175,000 | $230,000 | $139,280 | $250,000 | $320,000 | $1,100,000 |
| 52 | Remove STR (rail) (496-7017) | LF | 36 | $60.00 | $30.00 | $133.85 | $102.00 | $200.00 | $83.50 | $42.00 |
| 53 | Mobilization (500-7001) | LS | 1 | $840,000 | $900,000 | $1,100,000 | $1,132,050 | $1,293,000 | $1,429,000 | $1,300,000 |
| 54 | Barricades, signs and traffic handling (502-7001) | MO | 17 | $17,500 | $10,000 | $3,367.00 | $66,615 | $20,650 | $45,000 | $51,500 |
| 55 | Portable changeable message sign (503-7002) | EACH | 6 | $12,000 | $18,500 | $20,750 | $16,900 | $30,000 | $22,000 | $15,000 |
| 56 | TMA (stationary) (505-7001) | DAY | 300 | $200.00 | $367.00 | $634.20 | $270.00 | $300.00 | $425.00 | $400.00 |
| 57 | TMA (mobile operation) (505-7002) | HR | 40 | $150.00 | $95.00 | $94.50 | $86.00 | $200.00 | $100.00 | $63.00 |
| 58 | Rock filter dams (install) (type 3) (506-7003) | LF | 257 | $70.00 | $37.00 | $86.25 | $160.00 | $156.00 | $135.00 | $190.52 |
| 59 | Rock filter dams (remove) (506-7011) | LF | 257 | $30.00 | $13.00 | $20.70 | $20.00 | $19.50 | $50.00 | $32.86 |
| 60 | Construction exits (install) (type 1) (506-7020) | SY | 156 | $40.00 | $39.00 | $36.25 | $38.00 | $36.00 | $315.00 | $69.62 |
| 61 | Construction exits (remove) (506-7024) | SY | 156 | $15.00 | $13.00 | $17.50 | $14.00 | $13.00 | $20.00 | $16.89 |
| 62 | Construction perimeter fence (506-7034) | LF | 420 | $5.00 | $25.00 | $8.05 | $7.15 | $10.00 | $15.00 | $30.00 |
| 63 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 5,391 | $7.00 | $3.75 | $6.90 | $5.60 | $3.75 | $6.50 | $8.94 |
| 64 | Biodegradable erosion control logs (remove) (506-7046) | LF | 5,391 | $3.00 | $1.00 | $1.15 | $1.05 | $1.00 | $3.70 | $1.72 |
| 65 | Constructing detours (type 1) (508-7003) | SY | 17,014 | $53.00 | $19.02 | $45.50 | $28.00 | $100.00 | $22.00 | $30.00 |
| 66 | Constructing detours (type 2) (508-7004) | SY | 2,772 | $70.00 | $64.98 | $89.70 | $97.00 | $60.00 | $110.00 | $98.00 |
| 67 | Portable concrete traffic barrier (des source)(single slope)(type 1) (512-7013) | LF | 2,370 | $25.00 | $7.55 | $12.50 | $15.00 | $20.00 | $9.60 | $9.00 |
| 68 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 660 | $10.00 | $14.76 | $10.60 | $7.25 | $20.00 | $9.90 | $9.40 |
| 69 | Portable concrete traffic barrier (stockpile)(single slope)(type 1) (512-7037) | LF | 2,370 | $18.00 | $7.55 | $11.10 | $11.25 | $20.00 | $9.60 | $8.40 |
| 70 | Portable concrete traffic barrier (connection hardware) (512-7070) | EACH | 80 | $1.00 | $50.00 | $63.60 | $139.00 | $50.00 | $75.00 | $100.00 |
| 71 | Driveways (concrete) (530-7006) | SY | 500 | $150.00 | $139.50 | $210.00 | $190.00 | $140.00 | $190.00 | $124.00 |
| 72 | Driveways (ACP) (530-7010) | SY | 201 | $85.00 | $71.67 | $118.70 | $92.50 | $100.00 | $170.00 | $142.00 |
| 73 | Metal W-beam guard fence (steel post) (540-7002) | LF | 100 | $40.00 | $47.00 | $54.05 | $48.00 | $40.00 | $41.00 | $47.00 |
| 74 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 4 | $2,500.00 | $2,675.00 | $3,231.50 | $2,725.00 | $3,000.00 | $3,765.00 | $2,675.00 |
| 75 | Remove metal beam guard fence (542-7001) | LF | 1,775 | $4.00 | $3.00 | $4.13 | $3.35 | $5.00 | $5.40 | $3.00 |
| 76 | Remove terminal anchor section (542-7002) | EACH | 1 | $175.00 | $300.00 | $345.00 | $306.00 | $500.00 | $540.00 | $300.00 |
| 77 | Remove downstream anchor terminal (542-7003) | EACH | 3 | $200.00 | $300.00 | $345.00 | $306.00 | $500.00 | $540.00 | $300.00 |
| 78 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $3,800.00 | $3,400.00 | $3,910.00 | $3,475.00 | $3,500.00 | $4,850.00 | $3,400.00 |
| 79 | Guardrail end treatment (remove) (544-7003) | EACH | 4 | $255.00 | $300.00 | $345.00 | $325.00 | $500.00 | $540.00 | $300.00 |
| 80 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 2 | $3,000.00 | $3,750.00 | $4,312.00 | $3,825.00 | $2,000.00 | $2,700.00 | $1,150.00 |
| 81 | Crash cushion attenuator (remove) (545-7004) | EACH | 8 | $1,500.00 | $2,500.00 | $2,875.00 | $2,550.00 | $1,600.00 | $2,150.00 | $920.00 |
| 82 | Crash cushion attenuator (install)(L)(N)(TL3) (545-7006) | EACH | 1 | $20,000 | $33,500 | $38,525 | $34,125 | $40,000 | $37,650 | $33,000 |
| 83 | Crash cushion attenuator (install)(L)(W)(TL3) (545-7008) | EACH | 1 | $29,000 | $52,500 | $60,375 | $53,500 | $40,000 | $60,250 | $55,000 |
| 84 | Cca (install)(N)(TL3)(work zone) (545-7018) | EACH | 6 | $10,000 | $6,750.00 | $12,075 | $10,695 | $10,000 | $9,700.00 | $10,000 |
| 85 | Wire fence (type C) (552-7003) | LF | 492 | $15.00 | $35.00 | $17.25 | $9.00 | $25.00 | $35.00 | $40.00 |
| 86 | Gate (type 1) (552-7006) | EACH | 1 | $1,000.00 | $500.00 | $2,587.50 | $1,959.00 | $1,500.00 | $9,800.00 | $3,500.00 |
| 87 | Wire fence (water gap) (552-7010) | LF | 33 | $150.00 | $150.00 | $97.75 | $66.00 | $75.00 | $65.00 | $60.00 |
| 88 | Pipe underdrains (type 6) (6") (556-7006) | LF | 485 | $25.00 | $10.00 | $28.00 | $26.00 | $50.00 | $50.00 | $41.00 |
| 89 | Relocate existing mailbox (560-7012) | EACH | 1 | $300.00 | $550.00 | $621.00 | $491.00 | $550.00 | $945.00 | $540.00 |
| 90 | Remove RD IL asm (trans-base) (610-7009) | EACH | 2 | $950.00 | $900.00 | $1,150.00 | $925.00 | $500.00 | $975.00 | $1,000.00 |
| 91 | In RD IL (type ST) 50T-8 (400W EQ) LED (610-7228) | EACH | 4 | $7,000.00 | $7,125.00 | $9,200.00 | $7,250.00 | $3,500.00 | $7,700.00 | $8,000.00 |
| 92 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 250 | $16.00 | $15.00 | $17.25 | $15.50 | $20.00 | $16.15 | $15.00 |
| 93 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 475 | $18.00 | $18.00 | $28.75 | $25.50 | $20.00 | $19.50 | $25.00 |
| 94 | Electrical conductor (no.8) bare (620-7007) | LF | 725 | $2.00 | $2.50 | $2.88 | $2.60 | $5.00 | $2.70 | $2.50 |
| 95 | Electrical conductor (no.8) insulated (620-7008) | LF | 1,450 | $2.50 | $3.00 | $3.16 | $3.05 | $5.00 | $3.25 | $2.75 |
| 96 | Ground box type A (122311)W/apron (624-7002) | EACH | 5 | $2,400.00 | $1,250.00 | $1,840.00 | $1,275.00 | $1,500.00 | $1,345.00 | $1,600.00 |
| 97 | Remove ground box (624-7013) | EACH | 1 | $350.00 | $200.00 | $690.00 | $205.00 | $500.00 | $215.00 | $600.00 |
| 98 | Remove electrical services (628-7002) | EACH | 1 | $750.00 | $200.00 | $747.50 | $205.00 | $12,500 | $215.00 | $650.00 |
| 99 | Elc SRV type A 240/480 060(NS)SS(E)SP(O) (628-7048) | EACH | 2 | $12,000 | $7,725.00 | $8,625.00 | $7,865.00 | $8,000.00 | $8,300.00 | $7,500.00 |
| 100 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 5 | $850.00 | $990.00 | $862.50 | $705.00 | $990.00 | $940.00 | $750.00 |
| 101 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 16 | $1,100.00 | $990.00 | $1,035.00 | $705.00 | $990.00 | $1,155.00 | $900.00 |
| 102 | Install small roadside sign support and assembly TYS80(1)SA(P-BM) (644-7026) | EACH | 1 | $1,500.00 | $990.00 | $1,380.00 | $705.00 | $990.00 | $1,325.00 | $1,200.00 |
| 103 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 4 | $1,400.00 | $990.00 | $1,380.00 | $1,075.00 | $990.00 | $1,375.00 | $1,200.00 |
| 104 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 1 | $1,400.00 | $1,500.00 | $1,495.00 | $615.00 | $1,500.00 | $1,490.00 | $1,300.00 |
| 105 | Install small roadside sign support and assembly TYS80(1)SA(U-1EXT) (644-7032) | EACH | 2 | $1,400.00 | $1,500.00 | $1,667.50 | $998.00 | $1,500.00 | $1,695.00 | $1,450.00 |
| 106 | Install small roadside sign support and assembly TYS80(1)SA(U-2EXT) (644-7033) | EACH | 2 | $1,600.00 | $1,500.00 | $1,840.00 | $998.00 | $1,500.00 | $1,885.00 | $1,600.00 |
| 107 | Remove SM RD SN sup&AM (644-7073) | EACH | 17 | $115.00 | $100.00 | $115.00 | $225.00 | $100.00 | $165.00 | $200.00 |
| 108 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012) | EACH | 16 | $40.00 | $45.00 | $55.20 | $102.00 | $50.00 | $54.00 | $45.00 |
| 109 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 12 | $45.00 | $45.00 | $55.20 | $102.00 | $50.00 | $54.00 | $45.00 |
| 110 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (658-7031) | EACH | 4 | $40.00 | $45.00 | $55.20 | $102.00 | $100.00 | $54.00 | $45.00 |
| 111 | Install object marker assembly (OM-2Z)(WFLX)GND (658-7058) | EACH | 8 | $100.00 | $80.00 | $138.00 | $102.00 | $80.00 | $130.00 | $120.00 |
| 112 | Install OM SM RD sign (1-OM-PW)R (658-7318) | EACH | 4 | $1.00 | $15.00 | $14.95 | $102.00 | $15.00 | $43.00 | $13.00 |
| 113 | Install OM SM RD sign (2-OM-PW)Y (658-7319) | EACH | 27 | $1.00 | $15.00 | $20.70 | $102.00 | $15.00 | $48.50 | $18.00 |
| 114 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 10,517 | $0.50 | $1.25 | $1.44 | $1.30 | $1.00 | $1.35 | $1.25 |
| 115 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 9,813 | $0.50 | $1.25 | $1.44 | $1.30 | $1.00 | $1.35 | $1.25 |
| 116 | Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018) | LF | 113 | $1.50 | $1.50 | $1.73 | $1.60 | $2.00 | $1.60 | $1.50 |
| 117 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 1,428 | $1.50 | $1.25 | $1.44 | $1.30 | $2.00 | $1.35 | $1.25 |
| 118 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 138 | $10.00 | $17.50 | $20.13 | $17.85 | $20.00 | $18.85 | $17.50 |
| 119 | Type I high perf PM (W)6"(solid)(100MIL) (666-7293) | LF | 17,705 | $0.70 | $0.85 | $0.98 | $0.95 | $1.00 | $0.90 | $0.85 |
| 120 | Type I high perf PM (Y)6"(broken)(100MIL) (666-7302) | LF | 330 | $0.70 | $1.00 | $1.15 | $1.05 | $2.00 | $1.10 | $1.00 |
| 121 | Type I high perf PM (Y)6"(solid)(100MIL) (666-7305) | LF | 17,587 | $0.70 | $0.85 | $0.98 | $0.90 | $1.00 | $0.90 | $0.85 |
| 122 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 6 | $250.00 | $275.00 | $316.25 | $280.00 | $320.00 | $295.00 | $275.00 |
| 123 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 6 | $250.00 | $375.00 | $431.25 | $382.00 | $420.00 | $400.00 | $375.00 |
| 124 | Reflectorized pavement marker type I-C (672-7002) | EACH | 70 | $9.00 | $7.00 | $8.05 | $7.15 | $15.00 | $7.55 | $7.00 |
| 125 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 470 | $9.00 | $7.00 | $8.05 | $7.15 | $15.00 | $7.55 | $7.00 |
| 126 | Eliminating existing PM & markers (4") (677-7001) | LF | 2,220 | $1.00 | $6.00 | $6.90 | $6.15 | $3.00 | $6.45 | $6.00 |
| 127 | Anti-graffiti coatng (permnent-type III) (740-7006) | SF | 6,260 | $2.50 | $1.79 | $2.06 | $1.85 | $1.79 | $2.15 | $2.50 |
| 128 | Install bridge identification numbers (4019-7001) | EACH | 2 | $500.00 | $500.00 | $575.00 | $510.00 | $900.00 | $540.00 | $750.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of September 3, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.