TxDOT contract A00191470 bid tabulation

Construct Frontage Roads, SH 99 (Fry Road to Westheimer Parkway). Let by Texas DOT on August 6, 2026, Fort Bend, Houston District. 9 bids received; low bid $32,673,736 by James Construction Group, LLC, -23% against the engineer's estimate of $42,352,206.

Owner
Texas DOT
Letting
06 AUG 2026
Pay items
225
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1James Construction Group, LLC$32,673,736Low-23%
2MC2 Civil, LLC$33,824,290+4.0%-20%
3R Construction Civil, LLC$33,897,764+4.0%-20%
4Ser Construction Partners, LLC$34,596,007+6.0%-18%
5Harper Brothers Construction LLC$34,996,279+7.0%-17%
6Granite Construction Company$36,972,259+13%-13%
7Ragle Construction, Inc.$38,464,170+18%-9.0%
8Pulice Construction, Inc.$38,957,868+19%-8.0%
9Isi Contracting, Inc.$48,421,877+48%+14%
TxDOT contract A00191470: bids by rank

Engineer's estimate: $42,352,206.

Bid tabulation

LinePay itemUnitQuantityEstimate1. James Construction Group, LLC2. MC2 Civil, LLC3. R Construction Civil, LLC4. Ser Construction Partners, LLC5. Harper Brothers Construction LLC6. Granite Construction Company
1Preparing row (100-7002)STA68$10,000$18,370$40,000$1,400.00$4,300.00$3,000.00$40,000
2Removing concrete (pavement) (104-7001)SY8,196$10.00$8.87$10.00$15.00$14.70$9.36$10.00
3Removing concrete (riprap) (104-7006)SY312$13.00$4.80$10.00$5.00$6.70$4.94$10.00
4Removing concrete (sidewalk, ramp or shared use path) (104-7013)SY1,144$22.00$5.63$10.00$12.50$6.70$3.27$5.00
5Removing concrete (curb) (104-7016)LF1,459$2.02$2.00$6.25$1.50$2.50$9.00
6Removing concrete (curb or curb & gutter) (104-7018)LF1,999$10.00$2.12$2.00$6.40$2.80$2.75$2.75
7Remove (7"-13") TRT/untrt base & asphalt pavement (105-7058)SY7,977$8.00$3.46$5.00$3.75$6.00$3.54$5.00
8Excavation (roadway) (110-7001)CY25,252$18.00$10.90$10.00$16.00$11.90$8.00$9.00
9Excavation (channel) (110-7002)CY1,599$10.61$20.00$16.00$21.20$8.00$20.00
10Embankment (final)(DC)(type C) (132-7006)CY36,345$30.00$19.43$5.00$14.00$16.10$8.50$21.00
11Embankment (final)(DC)(type E)(csbe) (132-7036)CY2,894$55.00$55.97$70.00$43.00$57.80$69.00$70.00
12Embankment (final)(DC)(type E)(csbe_FND impr) (132-7037)CY1,567$55.00$55.52$70.00$54.00$57.80$69.00$75.00
13Embankment (final)(DC)(type E)(csbe_rwall impr) (132-7038)CY2,049$55.63$70.00$51.00$57.80$69.00$75.00
14Block sodding (162-7002)SY30,866$5.00$3.39$3.50$4.75$4.00$3.39$3.41
15Straw or hay mulch (162-7003)SY29,323$0.50$0.10$0.10$0.35$0.30$0.10$0.10
16Broadcast seed (temporary_warm) (164-7005)SY1,544$0.50$0.18$0.20$0.15$0.20$0.18$0.18
17Drill seed (temporary_warm_cool) (164-7015)SY29,323$0.25$0.20$0.20$0.19$0.10$0.20$0.20
18Fertilizer (166-7001)ACRE8.91$1,000.00$625.00$650.00$925.00$587.50$625.00$628.93
19Vegetative watering (168-7001)TGL1,069.70$20.00$28.00$15.00$40.00$29.20$22.00$9.00
20Lime (com or QK)(slurry) or QK(dry) (260-7001)TON404$350.00$348.06$325.00$345.00$354.30$380.00$330.00
21Lime TRT (existing material)(6") (260-7006)SY28,054$4.00$5.92$4.00$2.85$4.80$5.00$5.00
22Cement (275-7001)TON191$220.00$172.28$175.00$183.00$154.50$195.00$163.75
23Cement TRT (existing material)(6") (275-7002)SY12,306$3.00$2.92$4.00$3.95$7.10$4.00$3.00
24Cem TRT(PLNT MX)(CL N)(type E)(GR 4)(6") (276-7343)SY41,147$20.00$18.75$18.00$20.00$12.40$20.00$18.00
25Asphalt TRT base (GR 4)(PG 64) (292-7014)TON2,126$130.00$145.00$130.00$153.00$130.70$145.00$147.96
26Concrete pavement (CRCP) (10") (360-7004)SY38,518$100.00$80.19$60.00$90.00$76.40$79.00$78.00
27Struct excavation (400-7001)CY3,616$10.00$7.83$20.00$21.00$21.20$13.00$15.00
28Cem stabil BKFL (400-7010)CY8,254$65.00$58.94$55.00$63.00$65.00$69.00$58.00
29Cement stab backfill (inlet or MH) (400-7011)CY365$65.00$57.31$55.00$76.00$90.00$69.00$58.00
30Trench excavation protection (402-7001)LF7,013$5.00$1.05$5.00$5.25$0.20$1.00$1.30
31Temporary special shoring (403-7001)SF1,078$50.00$22.02$20.00$30.00$4.30$13.00$50.00
32Sheet piling (PZC - 18) (407-7005)SF1,650$65.53$50.00$78.00$51.60$90.00$43.49
33Prestressed concrete pil (16 in SQ) (409-7001)LF272$239.75$250.00$285.00$178.80$184.00$260.00
34Prestressed concrete pil (20 in SQ) (409-7003)LF4,085$170.00$192.08$165.00$270.00$233.30$240.00$346.00
35Prestressed concrete pil (24 in SQ) (409-7004)LF2,163$187.22$200.00$337.00$289.00$300.00$446.00
36Drilled shaft (30 in) (416-7005)LF9,825$300.00$185.21$190.00$214.00$210.60$185.00$200.00
37Drilled shaft (non - reinforced) (12 in) (416-7024)LF7$100.00$100.00$104.00$75.60$215.14$25.00
38Drilled shaft (sign mounts) (42 in) (416-7031)LF194$520.00$596.70$650.00$536.00$525.90$506.67$518.38
39Drilled shaft (roadway illumination pole) (30 in) (416-7040)LF112$275.00$255.66$260.00$168.00$165.50$159.42$258.24
40Sound wall (419-7001)SF154,220$50.00$32.81$25.00$39.00$36.10$32.35$29.00
41Class C concrete (abutment) (420-7012)CY260.40$1,620.00$827.15$1,300.00$615.00$1,129.30$1,300.00$1,200.00
42Class C concrete (cap) (420-7022)CY285$1,500.00$1,072.75$1,200.00$910.00$1,246.60$1,300.00$1,500.00
43Class C concrete (footing) (420-7044)CY20$700.81$1,600.00$1,150.00$1,323.30$1,800.00$1,300.00
44Class C concrete (sign column) (420-7057)CY102$2,000.00$1,654.18$1,600.00$980.00$1,366.10$2,100.00$1,500.00
45Class C concrete (sign footing) (420-7151)CY20$2,000.00$806.42$1,400.00$1,020.00$1,337.70$1,800.00$1,200.00
46Reinforced concrete slab (422-7001)SF44,915$26.00$21.00$25.00$28.00$23.20$23.00$28.00
47Ret wall (MSE) (horizontal scheme) (423-7004)SF23,866$50.00$52.44$50.00$63.00$51.40$70.00$65.00
48Prestressed concrete girder (TX34) (425-7002)LF2,075.90$216.00$185.96$186.00$238.00$205.10$316.30$200.00
49Prestressed concrete girder (TX46) (425-7004)LF3,580.52$242.00$201.89$190.00$229.00$218.50$288.91$270.00
50Riprap (concrete)(4 in) (432-7001)CY326.70$550.00$409.23$700.00$445.00$480.10$518.10$370.00
51Riprap (concrete)(5 in) (432-7002)CY56$456.78$800.00$530.00$412.10$536.81$405.00
52Riprap (concrete) (CL B) (4 in) (432-7007)CY380.80$600.00$401.85$900.00$645.00$578.00$559.27$645.00
53Riprap (concrete)(CL B)(5 in) (432-7008)CY394$389.51$750.00$520.00$412.10$528.97$610.00
54Riprap (mow strip)(4 in) (432-7013)CY132$600.00$582.24$850.00$620.00$532.90$527.61$585.00
55Riprap (mow strip)(5 in) (432-7014)CY12$832.62$675.00$675.00$741.80$636.95$530.00
56Riprap (stone common)(dry)(18 in) (432-7033)CY29.40$317.71$225.00$239.00$221.20$300.00$300.00
57Riprap (stone protection)(12 in) (432-7041)CY235$250.00$230.59$200.00$272.00$217.10$205.00$250.00
58Riprap (concrete)(CL B)(RR8&RR9) (432-7055)CY193$700.00$462.37$725.00$529.00$518.20$533.30$555.60
59STR steel (miscellaneous non-bridge) (442-7007)LB1,033$40.00$19.19$20.00$31.00$29.40$12.37$21.36
60Rail (type SSTR) (450-7024)LF5,312.30$85.00$56.51$67.00$80.00$56.60$58.00$61.44
61Rail (type C221) (450-7032)LF7,146.80$145.00$74.32$105.00$132.00$84.30$100.00$101.79
62Rail (type PR11) (450-7044)LF586$105.51$105.00$175.00$117.30$140.00$126.78
63Rail (handrail)(type F) (450-7063)LF476$200.00$127.33$120.00$200.00$144.60$195.00$123.96
64Sealed expansion joint (4 in) (SEJ - M) (454-7004)LF456$220.00$212.30$240.00$200.00$203.90$250.00$264.00
65Concrete box culvert (3 FT X 3 FT) (462-7002)LF837$350.00$235.69$350.00$245.00$293.70$280.00$250.00
66Concrete box culvert (4 FT X 2 FT) (462-7003)LF86$262.15$400.00$307.00$298.80$320.00$275.00
67Concrete box culvert (5 FT X 2 FT) (462-7006)LF42$500.00$345.33$450.00$380.00$438.70$500.00$350.00
68Concrete box culvert (5 FT X 3 FT) (462-7007)LF3,644$430.00$323.56$425.00$344.00$406.90$375.00$350.00
69Concrete box culvert (6 FT X 3 FT) (462-7011)LF4,042.50$525.00$397.84$500.00$409.00$496.70$440.00$400.00
70RC pipe (CL III)(24 in) (464-7005)LF2,236$100.00$72.42$130.00$74.00$106.70$150.00$90.00
71RC pipe (CL III)(30 in) (464-7007)LF556$150.00$84.85$150.00$92.00$125.00$150.00$125.00
72RC pipe (CL III)(36 in) (464-7009)LF129$180.00$134.72$210.00$133.00$163.00$220.00$150.00
73Junction box(complete)(PJB)(5FTX5FT) (465-7009)EACH1$3,772.35$10,000$6,400.00$7,684.70$4,400.00$5,000.00
74Junction box(complete)(PJB)(8FTX8FT) (465-7012)EACH4$6,727.61$13,000$14,300$16,234$8,500.00$7,000.00
75Inlet (complete)(PSL)(RC)(4FTX4FT) (465-7071)EACH1$5,159.86$7,000.00$3,200.00$4,305.80$5,500.00$6,000.00
76Inlet (complete)(PSL)(FG)(8FTX8FT-3FTX3FT) (465-7143)EACH1$5,539.37$12,000$11,200$17,002$7,000.00$6,000.00
77Inlet (complete)(curb)(type C1)(left)(hou) (465-7310)EACH5$7,500.00$7,923.75$12,000$4,800.00$8,821.40$10,500$10,000
78Inlet (complete)(curb)(type C1)(right)(hou) (465-7311)EACH4$7,500.00$5,008.86$8,000.00$3,950.00$8,263.00$8,000.00$6,500.00
79Inlet (complete)(curb)(type C1)(both)(hou) (465-7312)EACH25$8,000.00$6,948.54$10,000$4,450.00$7,495.20$9,500.00$8,500.00
80Inlet (complete)(type AD)(hou) (465-7314)EACH9$10,000$3,807.40$5,000.00$3,550.00$3,381.10$5,000.00$5,000.00
81Inlet (complete)(type aad)(hou) (465-7315)EACH26$9,000.00$5,778.38$7,000.00$4,700.00$6,348.30$7,000.00$7,000.00
82Inlet (complete)(type AZ2G)(hou) (465-7317)EACH4$12,000$6,408.43$8,000.00$6,300.00$8,231.90$9,000.00$8,000.00
83Inlet (complete)(type azr)(hou) (465-7318)EACH3$3,567.59$11,000$5,600.00$6,836.30$7,167.07$5,500.00
84Inlet (complete)(type AZR2G)(hou) (465-7319)EACH3$12,000$7,132.04$15,000$7,200.00$11,416$11,410$9,000.00
85Manh(comp)(junct box) (465-7347)EACH7$20,000$15,352$15,000$11,100$15,563$15,224$12,000
86Set (type I)(S= 4 FT)(HW= 2 FT)(4:1)(C) (467-7064)EACH1$6,376.56$8,250.00$8,750.00$6,550.70$9,779.26$25,000
87Set (type I)(S= 6 FT)(HW= 3 FT)(4:1)(C) (467-7125)EACH1$7,350.95$9,250.00$15,900$11,748$10,840$35,000
88Adjusting inlets (479-7002)EACH1$1,651.33$2,500.00$500.00$612.60$1,319.33$2,500.00
89Removing structure (inlet) (496-7002)EACH15$1,000.00$895.38$500.00$760.00$288.30$567.69$1,000.00
90Removing structure (manhole) (496-7003)EACH3$1,500.00$895.38$500.00$760.00$576.60$614.28$1,000.00
91Removing structure (set) (496-7004)EACH2$600.00$596.90$500.00$2,250.00$160.90$460.71$1,500.00
92Removing structure (wingwall) (496-7005)EACH3$2,916.51$750.00$3,400.00$2,127.00$855.20$2,000.00
93Removing structure (headwall) (496-7006)EACH2$2,000.00$1,269.72$1,000.00$2,700.00$4,253.90$1,000.00$2,000.00
94Removing structure (pipe) (496-7007)LF1,658$50.00$12.00$10.00$35.00$17.20$15.00$30.00
95Removing structure (box culvert) (496-7008)LF395$37.06$40.00$98.00$34.70$35.00$30.00
96Remove STR (rail) (496-7017)LF484$70.00$22.94$9.00$90.00$10.10$56.11$40.00
97Removing structure (ret wall) (496-7019)LF236$53.25$10.00$52.00$35.60$60.00$15.00
98Mobilization (500-7001)LS1$4,000,000$3,000,000$3,000,000$1,100,000$3,200,000$3,000,000$2,700,000
99Barricades, signs and traffic handling (502-7001)MO18$8,000.00$8,278.69$10,000$8,300.00$13,279$19,500$7,000.00
100Portable changeable message sign (503-7001)DAY600$100.00$1.00$60.00$250.00$46.40$50.00$55.00
101TMA (stationary) (505-7001)DAY20$220.00$232.81$470.00$735.00$309.00$260.00$430.00
102TMA (mobile operation) (505-7003)DAY80$200.00$595.60$1,100.00$1,130.00$689.30$900.00$1,045.00
103Construction exits (install) (type 1) (506-7020)SY312$28.00$32.00$25.00$29.00$30.80$32.00$32.35
104Construction exits (remove) (506-7024)SY312$9.00$20.00$10.00$10.00$12.40$20.00$20.22
105Temporary sediment control fence (install) (506-7039)LF7,958$4.00$2.95$2.25$1.80$3.70$2.90$2.98
106Temporary sediment control fence (remove) (506-7041)LF7,958$1.20$1.00$0.60$0.60$1.00$1.00$1.01
107Biodegradable erosion control logs (install) (8") (506-7043)LF440$8.00$7.00$6.00$6.80$8.00$8.09
108Biodegradable erosion control logs (install) (12") (506-7044)LF1,622$6.00$8.50$7.00$7.00$7.60$8.50$8.59
109Biodegradable erosion control logs (remove) (506-7046)LF2,062$1.25$2.00$2.00$2.00$1.00$2.00$2.02
110Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001)LF4,770$78.91$50.00$76.00$73.70$85.00$80.00
111Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009)LF880$39.82$25.00$72.00$20.30$85.00$70.00
112Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010)LF40$40.00$25.00$83.00$20.30$95.00$75.09
113Portable concrete traffic barrier (des source)(single slope)(type 1) (512-7013)LF4,160$17.00$9.84$25.00$6.75$15.90$9.00$8.99
114Portable concrete traffic barrier (des source)(low prof)(type 1) (512-7021)LF1,820$30.00$8.83$15.00$6.00$14.40$9.00$8.64
115Portable concrete traffic barrier (des source)(low prof)(type 2) (512-7022)LF40$30.00$12.84$15.00$34.00$19.00$25.00$28.23
116Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025)LF2,031$10.00$6.13$8.00$8.50$11.00$9.50$5.32
117Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033)LF2,440$10.00$4.98$8.00$7.00$11.20$9.50$4.58
118Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034)LF60$15.00$5.37$8.00$11.00$11.30$13.00$10.33
119Portable concrete traffic barrier (stockpile)(single slope)(type 1) (512-7037)LF8,276$13.00$10.05$10.00$6.75$15.90$8.00$7.98
120Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057)LF2,580$9.00$7.45$10.00$4.60$14.40$8.00$7.29
121Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058)LF80$18.00$36.39$10.00$5.70$14.30$10.00$24.43
122Portable concrete traffic barrier (connection hardware) (512-7070)EACH179$35.00$105.86$100.00$174.00$102.00$50.00$99.00
123Concrete curb (mono) (type I) (529-7006)LF604$4.43$4.00$11.50$3.70$6.00$6.00
124Concrete curb (mono) (type II) (529-7007)LF17,965$8.00$3.39$4.00$10.50$3.70$5.10$5.00
125Concrete sidewalks (5") (531-7002)SY15,994$75.00$56.29$50.00$66.00$62.00$75.00$52.00
126Concrete sidewalks (6") (531-7003)SY1,287$90.00$70.61$55.00$73.00$72.00$78.00$65.00
127Metal W-beam guard fence (timber post) (540-7001)LF412.50$30.00$24.00$28.50$30.00$30.90$28.50$24.00
128Metal beam guard fence trans (thrie-beam) (540-7005)EACH4$2,200.00$1,675.00$2,450.00$2,500.00$2,266.00$2,450.00$1,675.00
129Downstream anchor terminal section (540-7015)EACH2$1,650.00$1,350.00$1,650.00$1,250.00$1,236.00$1,650.00$1,350.00
130Remove metal beam guard fence (542-7001)LF110$10.00$3.00$5.00$3.00$4.00$5.00$3.00
131Remove terminal anchor section (542-7002)EACH1$150.00$500.00$220.00$246.20$500.00$150.00
132Guardrail end treatment (install) (544-7001)EACH6$3,400.00$3,050.00$3,650.00$3,500.00$3,605.00$3,650.00$3,050.00
133Guardrail end treatment (remove) (544-7003)EACH2$300.00$200.00$300.00$335.00$329.10$300.00$200.00
134Crash cushion attenuator (move & reset) (545-7002)EACH1$2,500.00$2,500.00$2,850.00$3,150.00$3,012.80$2,850.00$766.35
135Crash cushion attenuator (remove) (545-7004)EACH4$1,500.00$1,000.00$1,200.00$1,100.00$1,003.20$1,200.00$1,149.54
136Crash cushion attenuator (install)(L)(N)(TL3) (545-7006)EACH1$24,500$25,850$28,200$23,873$25,850$23,491
137Cca (install)(N)(TL3)(work zone) (545-7018)EACH5$10,000$8,300.00$8,650.00$28,200$23,873$8,650.00$8,523.16
138Chain link fence (remove) (550-7007)LF1,699$11.00$8.00$11.50$4.90$2.68$11.78
139Remove RD IL asm (trans-base) (610-7009)EACH15$500.00$252.20$255.00$970.00$953.00$919.00$254.75
140In RD IL (U/P) (type 1) (150W EQ) LED (610-7014)EACH2$1,694.85$1,700.00$1,770.00$1,737.60$1,675.00$1,711.97
141In RD IL (U/P) (type 1) (250W EQ) LED (610-7015)EACH4$2,400.00$1,694.85$1,700.00$2,300.00$2,334.90$2,250.00$1,711.97
142In RD IL (type AL) 40S-8 (250W EQ) LED (610-7132)EACH11$6,000.00$6,121.06$6,100.00$5,900.00$6,001.00$5,781.36$6,182.89
143In RD IL (type ST) 40T-8 (250W EQ) LED (610-7164)EACH3$5,331.96$5,300.00$6,200.00$6,108.30$5,885.00$5,385.82
144Conduit (HDPE) (2") (618-7009)LF3,313$17.00$8.13$8.00$7.50$7.60$9.35$8.21
145Conduit (HDPE) (2") bore (618-7010)LF252$50.00$18.05$18.00$8.00$8.30$7.95$18.23
146Conduit (PVC) (schedule 40) (3") (618-7036)LF11,380$18.00$8.87$9.00$10.25$10.50$10.16$8.96
147Conduit (PVC) (schedule 40) (3") (bore) (618-7037)LF350$34.00$56.48$56.00$39.50$40.40$38.93$57.05
148Conduit (PVC) (schedule 80) (2") (618-7054)LF3,004$8.46$8.00$8.75$9.00$8.66$8.55
149Conduit (RM) (2") (618-7078)LF223$30.00$5.00$30.00$34.00$34.80$33.50$35.35
150ITS multi-duct CND (PVC-40)(concrete encse) (619-7003)LF11,730$35.00$20.83$20.00$19.00$19.40$18.64$21.04
151ITS multi-duct CND (PVC-80)(bore) (619-7006)LF300$28.00$63.93$64.00$65.00$66.20$63.75$64.58
152Electrical conductor (no.14) insulated (620-7002)LF5,865$1.00$1.58$1.60$0.55$0.60$0.53$1.60
153Electrical conductor (no.8) bare (620-7007)LF6,627$2.00$2.05$2.00$1.20$1.20$1.17$2.07
154Electrical conductor (no.8) insulated (620-7008)LF12,088$2.00$2.31$2.50$1.50$1.50$1.46$2.33
155Electrical conductor (no.6) bare (620-7009)LF150$1.75$2.51$2.50$2.40$2.40$2.34$2.54
156Electrical conductor (no.6) insulated (620-7010)LF150$2.00$2.83$3.00$2.80$2.90$2.76$2.86
157Electrical conductor (no.4) bare (620-7011)LF150$3.00$3.21$3.25$3.25$3.30$3.20$3.24
158Electrical conductor (no.4) insulated (620-7012)LF150$3.50$3.61$3.50$3.70$3.80$3.63$3.65
159Ground box type A (122311) (624-7001)EACH8$1,250.00$1,093.64$1,100.00$750.00$764.40$736.45$1,104.69
160Ground box type A (122311)W/apron (624-7002)EACH11$1,226.17$1,225.00$1,000.00$1,018.50$1,050.00$1,238.56
161Remove ground box (624-7013)EACH5$400.00$189.16$190.00$450.00$458.70$441.91$191.07
162Elc SRV type A 240/480 060(NS)SS(E)SP(U) (628-7049)EACH2$7,704.16$7,700.00$9,500.00$9,653.90$9,300.55$7,781.98
163Elc SRV type A 240/480 060(SS)SS(E)SP(O) (628-7057)EACH2$8,800.00$9,364.52$9,350.00$11,000$11,314$10,900$9,459.11
164Aluminum signs (type G) (636-7002)SF60$35.00$42.00$42.00$41.00$41.50$40.00$40.72
165Aluminum signs (type O) (636-7003)SF312.50$45.00$38.46$38.00$30.00$30.30$56.00$29.68
166Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH6$660.00$668.00$670.00$720.00$736.50$720.88$253.00
167Install small roadside sign support and assembly type 10BWG(1)SA(P-BM) (644-7002)EACH1$800.00$965.00$965.00$1,025.00$1,014.60$1,027.24$253.00
168Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH16$800.00$759.00$760.00$1,050.00$1,014.60$914.15$253.00
169Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028)EACH1$1,050.00$1,050.00$1,200.00$2,575.00$1,183.60$253.00
170Remove SM RD SN sup&AM (644-7073)EACH14$90.00$85.00$85.00$115.00$154.50$130.00$150.00
171Install LRSS (struct steel) (647-7001)LB389.20$10.00$8.68$8.00$8.00$7.40$7.11$7.23
172Install overhead sign support(20 FT cant)(span only) (650-7020)EACH2$20,801$20,800$20,000$20,278$19,535$19,886
173Install overhead sign support(35 FT cant) (650-7038)EACH1$20,000$29,033$29,000$30,000$30,290$29,182$29,705
174Remove overhd sign sup (650-7193)EACH2$10,000$315.26$315.00$8,500.00$8,700.00$8,381.54$8,531.91
175Work zone pavement marking removing (W)4"(solid) (662-7064)LF5,541$0.75$2.00$1.20$1.50$2.10$1.17$1.18
176Work zone pavement marking removing (Y)4"(solid) (662-7097)LF2,826$0.75$2.00$1.20$1.50$2.10$1.17$1.18
177Reflectorized pavement marking type II (W) (entr gore) (666-7195)EACH1$200.00$289.00$100.00$128.00$297.78$100.00$101.01
178Reflectorized pavement marking type II (W) (exit gore) (666-7196)EACH1$200.00$289.00$100.00$130.00$297.70$100.00$101.01
179Reflectorized pavement marking type III (W)(6")(solid) (666-7236)LF8,686$1.00$1.00$1.00$1.20$1.00$0.92$0.93
180Reflectorized pavement marking type III (W)(6")(broken) (666-7237)LF10,320$0.80$1.00$1.00$1.20$1.00$0.92$0.93
181Reflectorized pavement marking type III (W)(6")(DOT) (666-7238)LF808$3.00$1.00$1.00$1.30$1.00$3.50$0.50
182Reflectorized pavement marking type III (W)(8")(solid) (666-7239)LF2,420$2.00$2.00$2.00$2.80$2.10$2.15$2.17
183Reflectorized pavement marking type III (W)(12")(solid) (666-7242)LF2,635$2.50$5.00$4.50$6.00$5.20$4.50$4.55
184Reflectorized pavement marking type III (W)(24")(solid) (666-7244)LF950$8.00$10.00$10.00$13.00$10.30$10.00$10.10
185Reflectorized pavement marking type III (Y)(6")(solid) (666-7248)LF3,426$1.00$1.00$1.00$1.20$1.00$0.92$0.93
186Reflectorized pavement marking type III (BLK)(6")(shadow) (666-7262)LF10,320$0.80$1.00$1.00$1.20$1.00$0.92$0.93
187Pavement sler (arrow) (666-7353)EACH8$35.00$20.00$5.00$6.50$20.60$5.00$5.05
188Pavement sler (word) (666-7354)EACH8$40.00$20.00$5.00$6.50$20.60$5.00$5.05
189Pavement sler (double arrow) (666-7356)EACH2$40.00$20.00$5.00$6.50$20.60$5.00$5.05
190Pavement sler (uturn arrow) (666-7358)EACH2$40.00$20.00$5.00$6.50$20.60$5.00$5.05
191Pavement sler (entr gore) (666-7361)EACH1$250.00$20.00$50.00$64.00$20.60$50.00$50.51
192Prefabricated PM type C (W)(arrow) (668-7091)EACH8$200.00$250.00$270.00$340.00$257.50$267.42$270.12
193Prefabricated PM type C (W)(double arrow) (668-7093)EACH2$300.00$250.00$360.00$460.00$257.50$362.34$366.00
194Prefabricated PM type C (W)(uturn arrow) (668-7096)EACH2$320.00$250.00$375.00$475.00$257.50$373.98$377.76
195Prefabricated PM type C (W)(word) (668-7103)EACH8$275.00$250.00$320.00$405.00$257.50$318.12$321.33
196Reflectorized pavement marker type II-C-R (672-7006)EACH871$5.00$7.00$6.00$8.00$7.20$6.00$6.06
197Eliminating existing PM & markers (6") (677-7002)LF3,423$0.45$0.35$0.50$0.65$0.40$0.49$0.49
198Eliminating existing PM & markers (8") (677-7004)LF1,157$0.80$0.45$1.00$1.25$0.50$0.96$1.27
199Eliminating existing PM & markers (24") (677-7008)LF100$3.00$2.00$2.50$3.40$2.10$2.65$2.68
200Eliminating existing PM & markers (arrow) (677-7009)EACH8$50.00$25.00$70.00$90.00$25.80$70.00$70.71
201Eliminating existing PM & markers (word) (677-7015)EACH6$55.00$25.00$75.00$95.00$25.80$75.00$75.76
202Pavement surface preparation for marking (6") (678-7002)LF4,725$0.05$0.03$0.05$0.08$0.10$0.06$0.06
203Pavement surface preparation for marking (8") (678-7004)LF3,620$0.12$0.05$0.10$0.11$0.10$0.08$0.08
204Pavement surface preparation for marking (24") (678-7008)LF100$0.50$0.25$0.25$0.32$0.30$0.24$0.24
205Pavement surface preparation for marking (arrow) (678-7009)EACH6$20.00$10.00$5.00$6.40$10.30$5.00$5.05
206Pavement surface preparation for marking (word) (678-7016)EACH5$25.00$10.00$5.00$6.40$10.30$5.00$5.05
207VIVDS cable (install) (690-7137)LF200$2.50$1.27$1.25$1.25$1.30$1.21$1.28
208Full - width mowing (730-7019)CYC6$4,000.00$1,137.42$2,500.00$1,300.00$3,927.20$4,000.00$2,510.00
209Litter removal (734-7002)CYC6$2,800.00$867.76$900.00$3,200.00$3,848.20$1,433.58$502.00
210Debris removing-CNTR med/MN LNS/ramps (735-7002)CYC6$1,000.00$1,315.74$900.00$400.00$3,848.20$1,433.58$1,000.00
211Cleaning / sweeping (frontage road) (738-7050)CYC16$3,000.00$2,031.36$2,500.00$900.00$1,527.40$1,500.00$1,667.20
212Wide flange pavement terminals (3003-7001)LF250$640.00$805.38$840.00$220.00$716.90$950.00$1,800.00
213Install bridge identification numbers (4019-7001)EACH1$500.00$500.00$500.00$500.00$103.03$500.00$500.00
214Ground box (install) (6013-7004)EACH12$900.00$4,406.24$4,400.00$1,100.00$5,526.50$5,321.23$4,450.75
215FO CBL (12 SMF)(pigtail) (6027-7020)LF1,720$3.00$3.56$3.50$7.70$7.90$7.58$3.60
216FO CBL (96 SMF) (6027-7029)LF11,730$3.00$5.05$5.00$3.20$3.30$3.14$5.10
217Wireless WWD system (6028-7001)EACH1$70,000$13,871$14,000$57,000$58,214$56,083$14,011
218Water main pipe (PVC)(C900)(6 in) (7004-7004)LF392$75.00$68.00$46.00$28.00$60.30$80.00$125.00
219Water main pipe (PVC)(C900)(12 in) (7004-7007)LF773$150.00$189.50$90.00$46.00$169.40$140.00$200.00
220Casing steel (18 in) (7004-7022)LF89$300.00$330.00$350.00$115.00$169.70$200.00$2,000.00
221Cut and plug water main (6 in) (7004-7025)EACH1$2,000.00$581.00$1,300.00$1,950.00$1,173.90$750.00$2,500.00
222Cut and plug water main (12 in) (7004-7027)EACH1$2,000.00$802.50$1,450.00$1,950.00$1,441.70$1,100.00$5,000.00
223Wet connection (12 in) (7004-7047)EACH2$2,000.00$2,627.00$1,900.00$3,500.00$2,864.50$4,500.00$5,000.00
224Remove existing water pipe (12 in) (7004-7052)LF193$20.00$14.50$10.00$36.00$26.10$14.00$50.00
225Wet connection (6 in) (7004-7059)EACH1$1,000.00$1,427.50$2,500.00$3,500.00$1,351.90$2,000.00$4,000.00
TxDOT contract A00191470: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of August 6, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy