TxDOT contract A00193092 bid tabulation
Hazard Elimination & Safety, FM 1990 (0.1 mi N of Gum Cr to CR 2137). Let by Texas DOT on July 1, 2025, Anderson, Tyler District. 10 bids received; low bid $1,639,418 by THK Construction LLC, -31% against the engineer's estimate of $2,383,206.
- Owner
- Texas DOT
- Letting
- 01 JUL 2025
- Pay items
- 66
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | THK Construction LLC | $1,639,418 | Low | -31% |
| 2 | 3LW Civil LLC | $1,941,518 | +18% | -19% |
| 3 | Highway 19 Construction LLC | $1,989,245 | +21% | -17% |
| 4 | Cross Plus Construction, LLC | $2,054,544 | +25% | -14% |
| 5 | Garret Shields Infrastructure | $2,067,898 | +26% | -13% |
| 6 | Baker & Company Construction, LLC | $2,369,901 | +45% | -1.0% |
| 7 | True Roads Construction, LLC | $2,380,503 | +45% | 0.0% |
| 8 | Xit Paving and Construction Inc. | $2,381,996 | +45% | 0.0% |
| 9 | Grey Sky Construction LLC | $2,823,203 | +72% | +18% |
| 10 | Reynolds & Kay, LTD. | $3,125,834 | +91% | +31% |
Engineer's estimate: $2,383,206.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. THK Construction LLC | 2. 3LW Civil LLC | 3. Highway 19 Construction LLC | 4. Cross Plus Construction, LLC | 5. Garret Shields Infrastructure | 6. Baker & Company Construction, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 81 | $4,000.00 | $1,000.00 | $350.00 | $1,500.00 | $3,199.00 | $2,000.00 | $5,850.00 |
| 2 | Removing concrete (mowstrip) (104-7005) | LF | 700 | $10.00 | $25.00 | $10.00 | $10.00 | $20.00 | $21.00 | |
| 3 | Removing concrete (driveways) (104-7011) | SY | 426 | $35.00 | $20.00 | $30.00 | $25.00 | $25.00 | $40.00 | $10.00 |
| 4 | Remove (2"-6") TRT/untrt base & asphalt pavement (105-7002) | SY | 1,546 | $10.00 | $10.00 | $35.00 | $15.00 | $55.00 | $20.00 | $4.40 |
| 5 | Embankment (vehicle)(OC)(type C) (132-7017) | CY | 1,330 | $45.00 | $20.00 | $45.00 | $55.00 | $45.00 | $40.00 | $28.50 |
| 6 | Backfill (type A) (134-7001) | STA | 25 | $300.00 | $200.00 | $350.00 | $500.00 | $65.00 | $400.00 | $405.00 |
| 7 | Blading (150-7001) | STA | 75 | $400.00 | $200.00 | $275.00 | $350.00 | $250.00 | $100.00 | $241.00 |
| 8 | Furn & place topsoil (4") (160-7002) | SY | 23,525 | $4.00 | $3.50 | $4.00 | $3.00 | $6.00 | $5.00 | $1.85 |
| 9 | Broadcast seed (permanent_rural_sand) (164-7001) | SY | 23,525 | $1.00 | $0.14 | $0.16 | $0.75 | $1.00 | $1.00 | $0.15 |
| 10 | Bond fiber MTRX seed (permanent)(rural)(sand) (164-7076) | SY | 23,525 | $0.92 | $0.67 | $0.74 | $0.75 | $1.00 | $1.00 | $1.05 |
| 11 | Bond fiber MTRX seed (temporary)(warm) (164-7077) | SY | 11,764 | $0.53 | $0.59 | $0.66 | $0.35 | $1.00 | $1.00 | $0.75 |
| 12 | Bond fiber MTRX seed (temporary)(cool) (164-7078) | SY | 11,764 | $0.53 | $0.62 | $0.70 | $0.35 | $1.00 | $1.00 | $0.75 |
| 13 | Vegetative watering (168-7001) | TGL | 260 | $15.00 | $10.00 | $0.01 | $50.00 | $25.00 | $50.00 | $10.00 |
| 14 | Temporary special shoring (403-7001) | SF | 1,748 | $75.00 | $30.00 | $40.00 | $55.00 | $50.00 | $40.00 | $40.00 |
| 15 | Temporary special shoring (cofferdam) (403-7002) | SF | 195 | $34.07 | $100.00 | $22.00 | $350.00 | $50.00 | $40.00 | $190.00 |
| 16 | Class C concrete (collar) (420-7061) | EACH | 11 | $1,000.00 | $1,000.00 | $728.00 | $1,500.00 | $1,500.00 | $1,000.00 | $2,200.00 |
| 17 | Riprap (mow strip)(4 in) (432-7013) | CY | 88 | $700.00 | $625.14 | $550.00 | $750.00 | $700.00 | $660.00 | |
| 18 | Riprap (stone common)(dry)(18 in) (432-7033) | CY | 160 | $225.00 | $200.00 | $210.00 | $200.00 | $325.00 | $250.00 | $192.00 |
| 19 | Riprap (stone common)(dry)(24 in) (432-7034) | CY | 125 | $200.00 | $200.00 | $210.00 | $200.00 | $300.00 | $250.00 | $180.00 |
| 20 | Cleaning and sealing existing joints (CL7) (438-7007) | LF | 184 | $30.00 | $54.00 | $75.00 | $99.00 | $50.00 | $192.00 | |
| 21 | Concrete box culvert (3 FT X 2 FT)(extend) (462-7056) | LF | 7 | $850.00 | $1,000.00 | $595.03 | $600.00 | $1,236.00 | $700.00 | $412.00 |
| 22 | Concrete box culvert (6 FT X 6 FT)(extend) (462-7069) | LF | 28 | $1,500.00 | $1,200.00 | $1,122.93 | $1,000.00 | $1,514.00 | $800.00 | $875.00 |
| 23 | Concrete box culvert (7 FT X 3 FT)(extend) (462-7070) | LF | 10 | $1,200.00 | $1,500.00 | $1,055.54 | $1,100.00 | $1,566.00 | $1,000.00 | $770.00 |
| 24 | Concrete box culvert (8 FT X 8 FT)(extend) (462-7080) | LF | 12 | $2,400.00 | $1,500.00 | $2,675.93 | $1,200.00 | $2,500.00 | $1,200.00 | $1,045.00 |
| 25 | RC pipe (CL III)(18 in) (464-7003) | LF | 1,346 | $65.00 | $65.00 | $78.49 | $55.00 | $88.00 | $80.00 | $60.00 |
| 26 | RC pipe (CL III)(24 in) (464-7005) | LF | 304 | $165.00 | $95.00 | $106.57 | $93.00 | $121.00 | $90.00 | $96.00 |
| 27 | RC pipe (CL III)(30 in) (464-7007) | LF | 132 | $200.00 | $150.00 | $148.56 | $102.00 | $200.00 | $150.00 | $111.00 |
| 28 | Inlet(complete)(pazd)(FG)(4FTX4FT-4FTX4FT) (465-7160) | EACH | 1 | $6,000.00 | $10,000 | $10,140 | $7,500.00 | $7,589.00 | $6,000.00 | $6,685.00 |
| 29 | Wingwall (PW - 1) (HW=5 FT) (466-7175) | EACH | 2 | $17,000 | $20,000 | $24,208 | $15,000 | $6,000.00 | $10,000 | $12,650 |
| 30 | Wingwall (PW - 1) (HW=8 FT) (466-7178) | EACH | 4 | $35,000 | $30,000 | $57,850 | $24,000 | $9,000.00 | $12,000 | $27,225 |
| 31 | Wingwall (PW - 1) (HW=9 FT) (466-7179) | EACH | 1 | $30,000 | $37,380 | $36,000 | $12,355 | $20,000 | $28,300 | |
| 32 | Wingwall (PW - 1) (HW=10 FT) (466-7180) | EACH | 1 | $50,000 | $50,000 | $47,348 | $45,000 | $12,555 | $25,000 | $31,350 |
| 33 | Wingwall (PW - 2) (HW=4 FT) (466-7188) | EACH | 1 | $15,000 | $20,000 | $6,764.00 | $16,000 | $5,213.00 | $8,000.00 | $9,900.00 |
| 34 | Set (type II) (18 in) (RCP) (4: 1) (C) (467-7306) | EACH | 3 | $1,200.00 | $1,000.00 | $1,176.16 | $585.00 | $1,500.00 | $1,000.00 | $1,895.00 |
| 35 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 80 | $1,000.00 | $900.00 | $1,329.56 | $795.00 | $1,100.00 | $1,000.00 | $937.00 |
| 36 | Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326) | EACH | 8 | $2,500.00 | $1,500.00 | $1,624.66 | $960.00 | $1,841.00 | $2,000.00 | $1,885.00 |
| 37 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 14 | $1,400.00 | $1,200.00 | $1,854.76 | $1,325.00 | $1,999.00 | $2,500.00 | $1,940.00 |
| 38 | Set (type II) (30 in) (RCP) (6: 1) (P) (467-7348) | EACH | 4 | $2,000.00 | $2,500.00 | $2,730.96 | $2,430.00 | $3,255.00 | $3,000.00 | $2,848.00 |
| 39 | Clean existing culverts (480-7001) | EACH | 1 | $5,000.00 | $2,000.00 | $4,500.00 | $5,000.00 | $1,500.00 | $5,000.00 | $4,245.00 |
| 40 | Removing structure (pipe) (496-7037) | EACH | 51 | $535.00 | $10.00 | $750.00 | $500.00 | $99.00 | $500.00 | $832.00 |
| 41 | Mobilization (500-7001) | LS | 1 | $216,000 | $150,000 | $118,828 | $250,000 | $125,000 | $200,000 | $201,000 |
| 42 | Barricades, signs and traffic handling (502-7001) | MO | 9 | $7,500.00 | $1,632.47 | $3,497.47 | $5,000.00 | $5,000.00 | $5,000.00 | $7,396.00 |
| 43 | Portable changeable message sign (503-7001) | DAY | 42 | $175.00 | $100.00 | $115.00 | $100.00 | $50.00 | $100.00 | $150.00 |
| 44 | TMA (stationary) (505-7001) | DAY | 100 | $250.00 | $250.00 | $150.00 | $250.00 | $200.00 | $300.00 | $363.00 |
| 45 | Rock filter dams (install) (type 2) (506-7002) | LF | 700 | $40.00 | $37.45 | $56.40 | $60.00 | $20.00 | $30.00 | $66.00 |
| 46 | Rock filter dams (install) (type 3) (506-7003) | LF | 75 | $80.00 | $53.50 | $75.60 | $100.00 | $20.00 | $30.00 | $88.00 |
| 47 | Rock filter dams (remove) (506-7011) | LF | 775 | $11.00 | $10.70 | $16.80 | $10.00 | $10.00 | $10.00 | $22.00 |
| 48 | Earthwork (erosion & sediment control, in vehicle) (506-7029) | CY | 50 | $55.00 | $40.00 | $75.00 | $50.00 | $100.00 | $50.00 | $43.00 |
| 49 | Backhoe work (erosion & sediment control) (506-7030) | HR | 20 | $180.00 | $150.00 | $135.00 | $50.00 | $99.00 | $100.00 | $147.00 |
| 50 | Temporary sediment control fence (install) (506-7039) | LF | 3,800 | $4.00 | $3.75 | $6.00 | $4.00 | $2.00 | $6.00 | $4.00 |
| 51 | Temporary sediment control fence (remove) (506-7041) | LF | 3,800 | $1.00 | $0.81 | $1.20 | $1.00 | $1.00 | $1.00 | $1.00 |
| 52 | Trackhoe work (erosion & sediment control) (506-7051) | HR | 20 | $200.00 | $200.00 | $185.00 | $100.00 | $99.00 | $100.00 | $147.00 |
| 53 | Driveways (concrete) (hes) (530-7007) | SY | 682 | $150.00 | $100.00 | $102.00 | $110.00 | $125.00 | $150.00 | $247.50 |
| 54 | Driveways (ACP) (530-7010) | SY | 2,405 | $75.00 | $50.00 | $66.38 | $75.00 | $75.00 | $120.00 | $80.00 |
| 55 | Metal W-beam guard fence (steel post) (540-7002) | LF | 550 | $30.06 | $27.61 | $31.00 | $42.00 | $40.00 | $32.00 | |
| 56 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 4 | $2,059.75 | $2,344.00 | $2,188.00 | $1,599.00 | $2,500.00 | $2,420.00 | |
| 57 | Metal W - beam guard fence (low fill culvert) (540-7018) | LF | 100 | $98.44 | $119.20 | $122.00 | $55.00 | $100.00 | $88.00 | |
| 58 | Remove metal beam guard fence (542-7001) | LF | 400 | $2.68 | $2.50 | $5.00 | $1.00 | $5.00 | $3.00 | |
| 59 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 4 | $160.50 | $250.00 | $300.00 | $1,566.00 | $500.00 | $275.00 | |
| 60 | Guardrail end treatment (install) (544-7001) | EACH | 8 | $3,210.00 | $2,770.00 | $2,950.00 | $4,200.00 | $3,500.00 | $3,245.00 | |
| 61 | Guardrail end treatment (remove) (544-7003) | EACH | 4 | $214.00 | $250.00 | $300.00 | $100.00 | $500.00 | $275.00 | |
| 62 | Relocate existing mailbox (560-7012) | EACH | 3 | $400.00 | $250.00 | $375.00 | $250.00 | $200.00 | $500.00 | $550.00 |
| 63 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 25 | $26.75 | $29.80 | $45.00 | $55.00 | $12.00 | $28.00 | |
| 64 | Install object marker assembly (OM-2Z)(WFLX)GND(BI) (658-7059) | EACH | 35 | $65.00 | $85.60 | $52.00 | $55.00 | $55.00 | $35.00 | $50.00 |
| 65 | Full - width mowing (730-7019) | CYC | 3 | $5,000.00 | $10,000 | $3,500.00 | $5,000.00 | $1,200.00 | $4,000.00 | $5,500.00 |
| 66 | Litter removal (734-7002) | CYC | 3 | $3,750.00 | $5,000.00 | $3,500.00 | $2,000.00 | $1,200.00 | $2,000.00 | $5,500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of July 1, 2025. Compiled by Mirage Metrics.