TxDOT contract A00058519 bid tabulation
Widen Road - Add Lanes, SL 485 (US 271, IN S GLADEWATER, NORTHERLY to US 80 IN EAST GLADEWATER). Let by Texas DOT on July 2, 2025, Gregg, Tyler District. 6 bids received; low bid $31,901,003 by Highway 19 Construction LLC, -14% against the engineer's estimate of $37,001,247.
- Owner
- Texas DOT
- Letting
- 02 JUL 2025
- Pay items
- 238
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Highway 19 Construction LLC | $31,901,003 | Low | -14% |
| 2 | Longview Bridge and Road, LTD. | $32,222,162 | +1.0% | -13% |
| 3 | True Roads Construction, LLC | $32,718,172 | +3.0% | -12% |
| 4 | East Texas Bridge, Inc. | $33,763,520 | +6.0% | -9.0% |
| 5 | James Construction Group, LLC | $37,841,563 | +19% | +2.0% |
| 6 | Copasa Inc | $48,433,712 | +52% | +31% |
Engineer's estimate: $37,001,247.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Highway 19 Construction LLC | 2. Longview Bridge and Road, LTD. | 3. True Roads Construction, LLC | 4. East Texas Bridge, Inc. | 5. James Construction Group, LLC | 6. Copasa Inc |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 137 | $6,000.00 | $4,000.00 | $10,000 | $5,000.00 | $10,000 | $24,472 | $37,000 |
| 2 | Removing concrete (riprap) (104-7006) | SY | 295 | $62.28 | $25.00 | $30.00 | $13.00 | $20.00 | $5.10 | $20.00 |
| 3 | Removing concrete (medians) (104-7008) | SY | 146 | $35.00 | $35.00 | $26.00 | $28.00 | $20.00 | $8.31 | $20.00 |
| 4 | Removing concrete (driveways) (104-7011) | SY | 2,619 | $38.40 | $25.00 | $20.00 | $13.00 | $18.00 | $10.51 | $25.00 |
| 5 | Removing concrete (curb & gutter) (104-7017) | LF | 1,031 | $29.29 | $10.00 | $6.30 | $8.25 | $10.00 | $7.61 | $45.00 |
| 6 | Remove (4"-8") TRT/untrt base & asphalt pavement (105-7004) | SY | 3,114 | $5.00 | $5.00 | $8.50 | $6.50 | $8.00 | $4.06 | $6.00 |
| 7 | Remove (12"-16") TRT/untrt base & asphalt pavement (105-7012) | SY | 44,303 | $16.00 | $8.70 | $13.00 | $6.50 | $13.00 | $8.64 | $12.00 |
| 8 | Excavation (roadway) (110-7001) | CY | 70,614 | $12.00 | $6.00 | $12.00 | $12.00 | $12.00 | $12.09 | $10.04 |
| 9 | Embankment (final)(OC)(type C) (132-7005) | CY | 289,989 | $18.00 | $10.66 | $15.50 | $16.50 | $16.00 | $20.00 | $26.84 |
| 10 | Furn & place topsoil (4") (160-7002) | SY | 292,436 | $2.50 | $1.83 | $3.00 | $2.00 | $2.25 | $0.71 | $3.00 |
| 11 | Broadcast seed (permanent_rural_sand) (164-7001) | SY | 146,219 | $0.30 | $0.25 | $0.13 | $0.12 | $0.15 | $0.14 | $0.85 |
| 12 | Bond fiber MTRX seed (permanent)(rural)(sand) (164-7076) | SY | 292,436 | $0.99 | $0.65 | $0.64 | $0.57 | $0.65 | $0.58 | $0.60 |
| 13 | Bond fiber MTRX seed (temporary)(warm) (164-7077) | SY | 146,219 | $0.70 | $0.65 | $0.57 | $0.56 | $0.62 | $0.57 | $0.54 |
| 14 | Bond fiber MTRX seed (temporary)(cool) (164-7078) | SY | 146,219 | $0.80 | $0.25 | $0.61 | $0.56 | $0.62 | $0.57 | $0.54 |
| 15 | Vegetative watering (168-7001) | TGL | 8,043 | $40.00 | $1.00 | $14.50 | $14.00 | $4.00 | $30.00 | $32.00 |
| 16 | FL BS (compacted in place)(type A GR 1-2) (8") (247-7067) | SY | 88,574 | $24.00 | $34.90 | $28.00 | $29.00 | $33.00 | $40.00 | $25.00 |
| 17 | Lime (quicklime (dry)) (260-7002) | TON | 813 | $325.00 | $360.00 | $395.00 | $425.00 | $385.00 | $394.46 | $370.00 |
| 18 | Lime TRT (existing material)(8") (260-7007) | SY | 45,151 | $8.46 | $8.00 | $3.50 | $5.50 | $4.50 | $5.95 | $10.00 |
| 19 | Cement (275-7001) | TON | 813 | $325.00 | $250.00 | $300.00 | $345.00 | $300.00 | $306.39 | $250.00 |
| 20 | Cement TRT (existing material)(8") (275-7003) | SY | 45,151 | $7.78 | $4.50 | $3.50 | $4.50 | $3.75 | $2.33 | $10.00 |
| 21 | Prime coat & blotter (MC-30) (310-7010) | GAL | 26,200 | $8.00 | $7.00 | $5.50 | $7.25 | $6.50 | $7.00 | $8.50 |
| 22 | Emuls asphalt (erosion control)(CSS-1) (314-7010) | GAL | 1,031 | $6.00 | $8.00 | $5.00 | $10.00 | $8.00 | $8.00 | $8.50 |
| 23 | Asphalt (AC-20XP, AC-10-2TR, or AC-20-5TR) (316-7068) | GAL | 31,195 | $5.37 | $6.00 | $4.75 | $5.55 | $6.00 | $6.00 | $5.00 |
| 24 | Aggregate (type-PD or PL, GR-4) (316-7258) | CY | 722 | $170.00 | $180.00 | $265.00 | $250.00 | $200.00 | $180.00 | $230.00 |
| 25 | SP mixes SP-B PG64-22 (344-7001) | TON | 22,216.80 | $165.00 | $177.00 | $162.50 | $174.00 | $172.00 | $174.20 | $160.00 |
| 26 | SP mixes SP-C sac-A PG70-22 (344-7020) | TON | 12,691 | $170.00 | $188.00 | $178.00 | $185.00 | $180.00 | $185.02 | $185.00 |
| 27 | SP mixes SP-D PG64-22 (level-UP) (344-7044) | TON | 3,425 | $190.00 | $180.00 | $180.00 | $195.00 | $178.00 | $177.15 | $205.00 |
| 28 | Tack coat (344-7077) | GAL | 1,387 | $5.70 | $2.00 | $5.00 | $5.25 | $7.00 | $2.00 | $5.00 |
| 29 | Cut & restoring pavement (400-7006) | SY | 263 | $308.75 | $350.00 | $295.00 | $135.00 | $125.00 | $104.14 | $185.00 |
| 30 | Cem stabil BKFL (400-7010) | CY | 426 | $295.00 | $350.00 | $225.00 | $325.00 | $315.00 | $248.42 | $180.00 |
| 31 | Flowable backfill (401-7001) | CY | 80 | $512.85 | $350.00 | $250.00 | $275.00 | $375.00 | $420.63 | $400.00 |
| 32 | Trench excavation protection (402-7001) | LF | 2,099 | $28.43 | $10.00 | $11.00 | $13.00 | $10.00 | $1.17 | $10.00 |
| 33 | Temporary special shoring (403-7001) | SF | 5,752 | $48.00 | $55.00 | $55.00 | $62.00 | $75.00 | $78.05 | $35.00 |
| 34 | Drilled shaft (18 in) (416-7002) | LF | 135 | $200.00 | $180.00 | $200.00 | $146.00 | $100.00 | $84.63 | $231.33 |
| 35 | Drilled shaft (36 in) (416-7006) | LF | 2,048 | $367.50 | $324.00 | $350.00 | $375.00 | $375.00 | $335.07 | $800.00 |
| 36 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 8 | $505.00 | $300.00 | $330.00 | $330.00 | $325.00 | $300.00 | $300.00 |
| 37 | Drilled shaft (traffic signal pole) (36 in) (416-7044) | LF | 16 | $375.00 | $345.00 | $380.00 | $380.00 | $375.00 | $345.00 | $345.00 |
| 38 | Drilled shaft (traffic signal pole) (48 in) (416-7046) | LF | 66 | $550.00 | $1,575.00 | $1,750.00 | $1,750.00 | $1,700.00 | $1,575.00 | $1,575.00 |
| 39 | Class C concrete (abutment) (420-7012) | CY | 125.40 | $1,573.55 | $1,471.00 | $1,050.00 | $1,500.00 | $1,150.00 | $1,162.68 | $3,500.00 |
| 40 | Class C concrete (cap) (420-7022) | CY | 85 | $2,000.00 | $1,750.00 | $1,100.00 | $1,575.00 | $1,200.00 | $1,695.12 | $4,000.00 |
| 41 | Class C concrete (column) (420-7038) | CY | 96.50 | $1,822.92 | $1,350.00 | $1,000.00 | $2,250.00 | $1,200.00 | $2,071.99 | $4,500.00 |
| 42 | Class C concrete (crashwall) (420-7050) | CY | 100.40 | $1,500.00 | $1,462.00 | $1,300.00 | $1,750.00 | $1,250.00 | $2,226.77 | $4,500.00 |
| 43 | Class C concrete (collar) (420-7061) | EACH | 8 | $2,671.73 | $3,500.00 | $2,000.00 | $550.00 | $1,500.00 | $4,978.81 | $3,000.00 |
| 44 | CL E concrete (seal slab)(non-reinforced) (420-7070) | CY | 47 | $900.00 | $350.00 | $425.00 | $600.00 | $600.00 | $989.25 | $2,000.00 |
| 45 | Reinforced concrete slab (422-7001) | SF | 20,460 | $34.50 | $37.00 | $29.00 | $36.00 | $34.00 | $35.00 | $50.00 |
| 46 | Approach slab (422-7013) | CY | 217 | $980.00 | $700.00 | $950.00 | $715.00 | $925.00 | $595.02 | $2,800.00 |
| 47 | Prestressed concrete girder (TX54) (425-7005) | LF | 2,622 | $258.03 | $297.00 | $285.00 | $280.00 | $268.00 | $289.56 | $250.00 |
| 48 | Riprap (concrete)(4 in) (432-7001) | CY | 503.80 | $1,121.58 | $750.00 | $500.00 | $715.00 | $900.00 | $599.10 | $726.00 |
| 49 | Riprap (concrete)(5 in) (432-7002) | CY | 47 | $800.77 | $750.00 | $700.00 | $715.00 | $900.00 | $672.03 | $850.00 |
| 50 | Riprap (concrete)(flume) (432-7012) | CY | 8 | $450.00 | $1,000.00 | $1,000.00 | $715.00 | $1,100.00 | $729.34 | $1,000.00 |
| 51 | Riprap (stone common)(dry)(12 in) (432-7031) | CY | 293 | $274.69 | $180.00 | $205.00 | $235.00 | $210.00 | $211.17 | $267.50 |
| 52 | STR steel (miscellaneous non-bridge) (442-7007) | LB | 616 | $26.00 | $35.00 | $60.00 | $18.00 | $28.00 | $21.23 | $28.00 |
| 53 | Rail (type C221) (450-7032) | LF | 492 | $200.00 | $250.00 | $180.00 | $170.00 | $155.00 | $132.80 | $202.50 |
| 54 | Rail (type C402) (450-7036) | LF | 558.40 | $140.00 | $240.00 | $270.00 | $205.00 | $215.00 | $193.81 | $223.00 |
| 55 | Rail (CLF-RO) (450-7049) | LF | 405 | $200.00 | $180.00 | $170.00 | $120.00 | $175.00 | $108.65 | $168.00 |
| 56 | Sealed expansion joint (4 in) (SEJ - M) (454-7004) | LF | 190 | $239.53 | $180.00 | $265.00 | $250.00 | $250.00 | $226.66 | $240.00 |
| 57 | Concrete box culvert (4 FT X 2 FT) (462-7003) | LF | 296 | $600.00 | $250.00 | $250.00 | $330.00 | $275.00 | $230.35 | $220.91 |
| 58 | Concrete box culvert (5 FT X 3 FT) (462-7007) | LF | 152 | $685.00 | $468.00 | $400.00 | $550.00 | $500.00 | $405.17 | $399.69 |
| 59 | Concrete box culvert (6 FT X 5 FT) (462-7013) | LF | 100 | $970.00 | $650.00 | $650.00 | $800.00 | $740.00 | $662.45 | $603.36 |
| 60 | RC pipe (CL III)(18 in) (464-7003) | LF | 1,150 | $106.92 | $52.00 | $65.00 | $60.00 | $60.00 | $90.90 | $100.00 |
| 61 | RC pipe (CL III)(24 in) (464-7005) | LF | 2,520 | $164.18 | $66.00 | $80.00 | $93.00 | $80.00 | $116.87 | $110.00 |
| 62 | RC pipe (CL III)(30 in) (464-7007) | LF | 286 | $227.00 | $90.00 | $115.00 | $132.00 | $115.00 | $239.63 | $150.00 |
| 63 | RC pipe (CL III)(36 in) (464-7009) | LF | 600 | $225.27 | $135.00 | $150.00 | $192.00 | $155.00 | $153.15 | $170.00 |
| 64 | RC pipe (CL III)(42 in) (464-7010) | LF | 88 | $338.40 | $2,111.00 | $200.00 | $240.00 | $215.00 | $290.12 | $250.00 |
| 65 | RC pipe (CL III)(60 in) (464-7013) | LF | 396 | $500.00 | $360.00 | $330.00 | $605.00 | $370.00 | $428.95 | $340.00 |
| 66 | RC pipe (CL III)(72 in) (464-7015) | LF | 318 | $715.00 | $505.00 | $500.00 | $660.00 | $500.00 | $399.99 | $550.00 |
| 67 | Manh (complete)(PRM)(48IN) (465-7002) | EACH | 1 | $7,282.72 | $5,000.00 | $6,500.00 | $6,050.00 | $6,000.00 | $7,577.89 | $6,484.75 |
| 68 | Inlet (complete)(PSL)(RC)(4FTX4FT) (465-7071) | EACH | 1 | $6,525.00 | $7,500.00 | $8,750.00 | $8,800.00 | $9,000.00 | $9,914.96 | $10,000 |
| 69 | Inlet (complete)(PSL)(RC)(8FTX8FT) (465-7077) | EACH | 1 | $24,000 | $16,900 | $22,500 | $23,100 | $23,000 | $25,917 | $15,000 |
| 70 | Inlet (complete)(PSL)(FG)(3FTX3FT-3FTX3FT) (465-7126) | EACH | 1 | $6,000.00 | $6,800.00 | $7,500.00 | $7,700.00 | $7,500.00 | $8,619.78 | $10,000 |
| 71 | Inlet (complete)(pazd)(RC)(3FTX3FT) (465-7152) | EACH | 1 | $6,000.00 | $5,950.00 | $7,000.00 | $6,600.00 | $7,000.00 | $9,211.66 | $10,000 |
| 72 | Inlet(complete)(pazd)(FG)(4FTX4FT-4FTX4FT) (465-7160) | EACH | 2 | $8,800.00 | $6,400.00 | $8,500.00 | $8,800.00 | $9,000.00 | $8,771.46 | $10,000 |
| 73 | Inlet (complete)(cco)(3FT)(none) (465-7168) | EACH | 2 | $9,405.00 | $7,700.00 | $7,000.00 | $6,050.00 | $6,500.00 | $8,048.86 | $10,000 |
| 74 | Inlet (complete)(cco)(3FT)(left) (465-7169) | EACH | 2 | $8,565.00 | $7,700.00 | $7,000.00 | $6,050.00 | $6,500.00 | $8,323.53 | $10,000 |
| 75 | Inlet (complete)(cco)(3FT)(right) (465-7170) | EACH | 4 | $7,450.00 | $7,700.00 | $7,000.00 | $6,050.00 | $6,500.00 | $8,702.31 | $10,000 |
| 76 | Inlet (complete)(cco)(3FT)(both) (465-7171) | EACH | 3 | $9,460.16 | $7,700.00 | $7,500.00 | $6,050.00 | $7,500.00 | $10,025 | $10,000 |
| 77 | Headwall (CH - FW - 0) (diameter= 42 in) (466-7010) | EACH | 2 | $11,000 | $8,000.00 | $12,500 | $15,400 | $13,000 | $16,470 | $45,000 |
| 78 | Headwall (CH - FW - 15) (diameter= 60 in) (466-7028) | EACH | 2 | $14,000 | $15,000 | $16,200 | $17,600 | $20,000 | $15,921 | $50,000 |
| 79 | Headwall (CH - FW - 30) (diameter= 72 in) (466-7045) | EACH | 1 | $16,000 | $16,000 | $17,500 | $16,500 | $24,000 | $17,809 | $55,000 |
| 80 | Headwall (CH - FW - 45) (diameter= 36 in) (466-7054) | EACH | 2 | $14,000 | $9,000.00 | $12,750 | $11,000 | $20,000 | $19,532 | $60,000 |
| 81 | Headwall (CH - FW - 45) (diameter= 60 in) (466-7058) | EACH | 1 | $14,000 | $12,000 | $19,000 | $16,500 | $30,000 | $19,532 | $65,000 |
| 82 | Headwall (CH - PW - S) (diameter= 60 in) (466-7124) | EACH | 1 | $16,000 | $12,000 | $17,000 | $19,800 | $23,000 | $17,809 | $40,000 |
| 83 | Headwall (CH - PW - S) (diameter= 72 in) (466-7126) | EACH | 1 | $16,000 | $15,000 | $21,000 | $22,000 | $25,000 | $17,809 | $40,000 |
| 84 | Wingwall (FW - 0) (HW=3 FT) (466-7145) | EACH | 2 | $13,000 | $9,000.00 | $12,750 | $7,700.00 | $8,000.00 | $9,724.01 | $45,000 |
| 85 | Wingwall (FW - 0) (HW=4 FT) (466-7146) | EACH | 2 | $16,000 | $12,000 | $13,500 | $8,800.00 | $11,000 | $6,405.38 | $47,000 |
| 86 | Wingwall (SW - 0) (HW=5 FT) (466-7204) | EACH | 1 | $16,000 | $15,000 | $16,500 | $7,700.00 | $16,000 | $11,285 | $20,000 |
| 87 | Set (type II) (18 in) (RCP) (3: 1) (C) (467-7305) | EACH | 2 | $1,646.04 | $685.00 | $1,250.00 | $770.00 | $750.00 | $5,412.04 | $1,667.06 |
| 88 | Set (type II) (18 in) (RCP) (4: 1) (C) (467-7306) | EACH | 3 | $1,568.36 | $712.00 | $1,100.00 | $825.00 | $800.00 | $5,828.95 | $2,112.92 |
| 89 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 29 | $1,708.50 | $795.00 | $1,100.00 | $990.00 | $900.00 | $2,131.73 | $1,820.24 |
| 90 | Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326) | EACH | 4 | $2,335.95 | $960.00 | $1,500.00 | $1,320.00 | $1,200.00 | $2,052.17 | $2,350.19 |
| 91 | Set (type II) (24 in) (RCP) (6: 1) (C) (467-7327) | EACH | 5 | $2,671.26 | $1,325.00 | $1,750.00 | $1,760.00 | $1,400.00 | $2,052.17 | $2,912.23 |
| 92 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 10 | $2,463.51 | $1,325.00 | $1,750.00 | $1,760.00 | $1,400.00 | $2,781.92 | $2,840.19 |
| 93 | Set (type II) (30 in) (RCP) (4: 1) (C) (467-7346) | EACH | 2 | $3,832.50 | $2,100.00 | $2,200.00 | $2,200.00 | $2,000.00 | $2,243.27 | $2,750.00 |
| 94 | Clean existing culverts (480-7001) | EACH | 6 | $5,999.30 | $5,000.00 | $5,500.00 | $1,320.00 | $3,000.00 | $6,264.54 | $5,000.00 |
| 95 | Removing structure (inlet) (496-7002) | EACH | 6 | $3,200.00 | $1,000.00 | $1,550.00 | $880.00 | $500.00 | $720.86 | $1,250.00 |
| 96 | Removing structure (set) (496-7004) | EACH | 11 | $852.00 | $500.00 | $850.00 | $165.00 | $500.00 | $609.12 | $540.00 |
| 97 | Removing structure (pipe) (496-7007) | LF | 364 | $25.00 | $50.00 | $45.00 | $11.00 | $15.00 | $12.39 | $25.00 |
| 98 | Removing structure (bridge 100 - 499 FT length) (496-7010) | EACH | 1 | $250,000 | $100,000 | $65,000 | $225,000 | $85,000 | $250,000 | $800,000 |
| 99 | Removing structure (pipe) (496-7037) | EACH | 9 | $1,564.78 | $1,500.00 | $1,500.00 | $275.00 | $700.00 | $1,257.30 | $550.00 |
| 100 | Remove STR (driveway culvert) (496-7038) | EACH | 16 | $2,000.00 | $600.00 | $2,000.00 | $350.00 | $500.00 | $727.63 | $550.00 |
| 101 | Mobilization (500-7001) | LS | 1 | $3,400,000 | $3,700,000 | $2,800,000 | $3,200,000 | $3,090,000 | $3,600,000 | $5,000,000 |
| 102 | Barricades, signs and traffic handling (502-7001) | MO | 34 | $11,702 | $5,000.00 | $5,000.00 | $10,000 | $10,000 | $10,000 | $35,000 |
| 103 | Portable changeable message sign (503-7001) | DAY | 126 | $177.31 | $100.00 | $150.00 | $110.00 | $150.00 | $71.20 | $100.00 |
| 104 | TMA (stationary) (505-7001) | DAY | 1,502 | $300.00 | $250.00 | $240.00 | $50.00 | $250.00 | $222.48 | $250.00 |
| 105 | TMA (mobile operation) (505-7002) | HR | 1,500 | $150.00 | $100.00 | $75.00 | $5.00 | $45.00 | $60.37 | $70.00 |
| 106 | Rock filter dams (install) (type 2) (506-7002) | LF | 1,350 | $51.04 | $55.00 | $38.50 | $37.00 | $38.00 | $55.58 | $47.50 |
| 107 | Rock filter dams (remove) (506-7011) | LF | 1,350 | $17.32 | $10.00 | $11.00 | $9.00 | $11.00 | $21.62 | $14.11 |
| 108 | Construction exits (install) (type 1) (506-7020) | SY | 2,672 | $36.50 | $35.00 | $38.50 | $30.00 | $38.00 | $49.80 | $34.00 |
| 109 | Construction exits (remove) (506-7024) | SY | 2,672 | $11.58 | $10.00 | $11.00 | $11.00 | $11.00 | $13.75 | $11.40 |
| 110 | Excavation (erosion & sediment control, in vehicle) (506-7027) | CY | 2,120 | $65.00 | $50.00 | $45.00 | $10.00 | $20.00 | $20.00 | $40.00 |
| 111 | Embankment (erosion & sediment control, in vehicle) (506-7028) | CY | 2,120 | $65.00 | $50.00 | $50.00 | $10.00 | $23.00 | $20.00 | $40.00 |
| 112 | Earthwork (erosion & sediment control, in vehicle) (506-7029) | CY | 2,000 | $69.00 | $50.00 | $50.00 | $22.00 | $20.00 | $25.14 | $65.00 |
| 113 | Backhoe work (erosion & sediment control) (506-7030) | HR | 600 | $175.00 | $50.00 | $185.00 | $50.00 | $75.00 | $46.38 | $150.00 |
| 114 | Bulldozer work (erosion & sediment control) (506-7033) | HR | 500 | $200.00 | $100.00 | $195.00 | $50.00 | $75.00 | $161.19 | $200.00 |
| 115 | Temporary sediment control fence (install) (506-7039) | LF | 2,062 | $5.24 | $4.00 | $3.75 | $10.00 | $3.65 | $5.74 | $4.64 |
| 116 | Temporary sediment control fence (remove) (506-7041) | LF | 2,062 | $1.64 | $1.00 | $1.00 | $0.55 | $0.75 | $1.42 | $1.15 |
| 117 | Biodegradable erosion control logs (install) (6") (506-7042) | LF | 240 | $4.00 | $10.00 | $5.50 | $5.00 | $5.50 | $9.44 | $5.37 |
| 118 | Biodegradable erosion control logs (remove) (506-7046) | LF | 240 | $2.59 | $1.00 | $2.50 | $2.00 | $1.10 | $2.07 | $1.55 |
| 119 | Trackhoe work (erosion & sediment control) (506-7051) | HR | 600 | $151.63 | $100.00 | $225.00 | $50.00 | $100.00 | $132.31 | $187.50 |
| 120 | Constructing detours (508-7001) | SY | 3,409 | $150.00 | $175.00 | $150.00 | $150.00 | $170.00 | $164.63 | $180.00 |
| 121 | Portable concrete traffic barrier (des source)(F-shape)(type 1) (512-7017) | LF | 1,290 | $53.00 | $75.00 | $20.00 | $25.00 | $20.00 | $11.24 | $45.00 |
| 122 | Portable concrete traffic barrier (move)(F-shape)(type 1) (512-7029) | LF | 570 | $21.00 | $25.00 | $13.00 | $22.00 | $10.00 | $15.64 | $16.00 |
| 123 | Portable concrete traffic barrier (stockpile)(F-shape)(type 1) (512-7041) | LF | 1,290 | $30.00 | $25.00 | $13.00 | $20.00 | $20.00 | $10.02 | $21.00 |
| 124 | Concrete curb & gutter (type II) (529-7009) | LF | 5,586 | $55.00 | $35.00 | $28.00 | $42.00 | $32.00 | $34.23 | $60.00 |
| 125 | Driveways (concrete) (hes) (530-7007) | SY | 1,945 | $169.84 | $110.00 | $100.00 | $120.00 | $120.00 | $109.40 | $132.00 |
| 126 | Driveways (ACP) (530-7010) | SY | 3,338 | $80.10 | $60.00 | $50.00 | $54.00 | $55.00 | $71.68 | $110.00 |
| 127 | Concrete sidewalks (4") (531-7001) | SY | 13,028 | $127.99 | $75.00 | $53.00 | $65.00 | $78.00 | $69.81 | $100.00 |
| 128 | Curb ramps (type 1) (531-7005) | EACH | 12 | $4,500.00 | $1,500.00 | $2,700.00 | $2,150.00 | $3,000.00 | $2,656.87 | $2,925.00 |
| 129 | Curb ramps (type 10) (531-7011) | EACH | 2 | $3,500.00 | $1,800.00 | $3,600.00 | $2,500.00 | $3,000.00 | $2,656.87 | $3,097.50 |
| 130 | Concrete directional island (536-7004) | SY | 523 | $330.00 | $180.00 | $140.00 | $130.00 | $130.00 | $114.61 | $145.00 |
| 131 | Metal W-beam guard fence (steel post) (540-7002) | LF | 250 | $38.00 | $35.00 | $31.00 | $31.00 | $31.00 | $28.00 | $32.00 |
| 132 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 4 | $2,337.18 | $3,250.00 | $2,200.00 | $2,175.00 | $2,200.00 | $1,975.00 | $2,200.00 |
| 133 | Remove metal beam guard fence (542-7001) | LF | 1,516.50 | $5.12 | $5.00 | $2.50 | $10.00 | $2.25 | $2.00 | $2.00 |
| 134 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $3,422.77 | $3,150.00 | $3,300.00 | $3,300.00 | $3,300.00 | $3,000.00 | $3,050.00 |
| 135 | Guardrail end treatment (remove) (544-7003) | EACH | 4 | $385.13 | $250.00 | $220.00 | $220.00 | $220.00 | $200.00 | $480.00 |
| 136 | Crash cushion attenuator (remove) (545-7004) | EACH | 6 | $1,421.89 | $1,000.00 | $900.00 | $880.00 | $880.00 | $800.00 | $810.00 |
| 137 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 6 | $11,000 | $9,500.00 | $9,050.00 | $9,000.00 | $9,000.00 | $8,200.00 | $7,900.00 |
| 138 | Mailbox install-S (TWG-post) type 2 (560-7002) | EACH | 1 | $329.59 | $350.00 | $475.00 | $550.00 | $500.00 | $431.00 | $330.00 |
| 139 | In RD IL (U/P) (type 1) (150W EQ) LED (610-7014) | EACH | 4 | $1,660.00 | $2,370.00 | $2,700.00 | $2,600.00 | $2,600.00 | $2,370.00 | $2,370.00 |
| 140 | In RD IL (type SA) 40T-8 (250W EQ) LED (610-7124) | EACH | 1 | $6,600.00 | $7,200.00 | $7,950.00 | $8,000.00 | $7,800.00 | $7,200.00 | $7,200.00 |
| 141 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 355 | $20.17 | $11.50 | $12.75 | $12.65 | $12.50 | $11.50 | $11.50 |
| 142 | Conduit (PVC) (schedule 40) (3") (618-7036) | LF | 185 | $65.00 | $19.00 | $21.00 | $20.90 | $20.50 | $19.00 | $19.00 |
| 143 | Conduit (PVC) (schedule 40) (4") (618-7040) | LF | 45 | $25.00 | $29.00 | $32.00 | $31.90 | $31.50 | $29.00 | $29.00 |
| 144 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 700 | $20.47 | $14.65 | $16.25 | $16.00 | $16.00 | $14.65 | $14.65 |
| 145 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 135 | $35.32 | $32.50 | $36.00 | $35.75 | $35.00 | $32.50 | $32.50 |
| 146 | Conduit (PVC) (schedule 80) (3") (bore) (618-7061) | LF | 150 | $30.00 | $36.00 | $40.00 | $39.60 | $39.00 | $36.00 | $36.00 |
| 147 | Conduit (PVC) (schedule 80) (4") (bore) (618-7065) | LF | 465 | $37.00 | $40.00 | $44.00 | $44.00 | $43.00 | $40.00 | $40.00 |
| 148 | Conduit (RM) (3/4") (618-7070) | LF | 260 | $35.00 | $23.50 | $26.00 | $25.85 | $25.50 | $23.50 | $23.50 |
| 149 | Conduit (RM) (2") (618-7078) | LF | 30 | $57.00 | $50.00 | $55.00 | $55.00 | $54.00 | $50.00 | $50.00 |
| 150 | Electrical conductor (no.12) bare (620-7003) | LF | 260 | $2.15 | $2.10 | $2.35 | $2.30 | $2.30 | $2.10 | $2.10 |
| 151 | Electrical conductor (no.12) insulated (620-7004) | LF | 520 | $2.15 | $2.25 | $2.50 | $2.45 | $2.45 | $2.25 | $2.25 |
| 152 | Electrical conductor (no.8) bare (620-7007) | LF | 100 | $2.85 | $2.35 | $2.60 | $2.60 | $2.55 | $2.35 | $2.35 |
| 153 | Electrical conductor (no.8) insulated (620-7008) | LF | 200 | $3.50 | $2.50 | $2.75 | $2.75 | $2.70 | $2.50 | $2.50 |
| 154 | Electrical conductor (no.6) bare (620-7009) | LF | 1,790 | $6.00 | $3.00 | $3.30 | $3.30 | $3.25 | $3.00 | $3.00 |
| 155 | Electrical conductor (no.6) insulated (620-7010) | LF | 1,640 | $3.50 | $3.25 | $3.60 | $3.60 | $3.50 | $3.25 | $3.25 |
| 156 | Electrical conductor (no.4) bare (620-7011) | LF | 20 | $4.00 | $4.50 | $5.00 | $4.95 | $4.90 | $4.50 | $4.50 |
| 157 | Electrical conductor (no.4) insulated (620-7012) | LF | 35 | $4.00 | $5.20 | $5.75 | $5.75 | $5.65 | $5.20 | $5.20 |
| 158 | Tray cable (4 conductor) (12 AWG) (621-7006) | LF | 1,135 | $3.50 | $3.25 | $3.60 | $3.60 | $3.50 | $3.25 | $3.25 |
| 159 | Ground box type D (162922)W/apron (624-7008) | EACH | 9 | $1,750.00 | $1,825.00 | $2,010.00 | $2,000.00 | $1,975.00 | $1,825.00 | $1,825.00 |
| 160 | Elc SRV type A 120/240 060(NS)SS(E)SP(O) (628-7009) | EACH | 1 | $9,000.00 | $9,090.00 | $10,000 | $10,000 | $9,850.00 | $9,090.00 | $9,090.00 |
| 161 | Elc SRV type D 120/240 100(NS)SS(E)SP(O) (628-7248) | EACH | 1 | $9,000.00 | $8,450.00 | $9,300.00 | $9,200.00 | $9,200.00 | $8,450.00 | $8,450.00 |
| 162 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 25 | $839.73 | $750.00 | $645.00 | $740.00 | $645.00 | $583.00 | $633.00 |
| 163 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 24 | $937.76 | $820.00 | $750.00 | $910.00 | $750.00 | $679.00 | $790.00 |
| 164 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 4 | $1,044.09 | $1,150.00 | $1,200.00 | $1,380.00 | $1,200.00 | $1,081.00 | $1,105.00 |
| 165 | Remove SM RD SN sup&AM (644-7073) | EACH | 62 | $156.97 | $100.00 | $110.00 | $86.00 | $125.00 | $99.00 | $100.00 |
| 166 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012) | EACH | 12 | $29.10 | $25.00 | $28.00 | $38.00 | $30.00 | $25.00 | $28.00 |
| 167 | Install object marker assembly (OM-2X)(WC)GND (658-7055) | EACH | 7 | $170.00 | $95.00 | $90.00 | $61.00 | $100.00 | $80.00 | $118.00 |
| 168 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 11,834 | $0.66 | $0.50 | $0.55 | $0.55 | $0.55 | $0.50 | $0.33 |
| 169 | Work zone pavement marking non-removing (W)8"(solid) (662-7012) | LF | 462 | $2.18 | $0.65 | $0.75 | $0.72 | $0.72 | $0.65 | $0.73 |
| 170 | Work zone pavement marking non-removing (W)24"(solid) (662-7017) | LF | 44 | $11.69 | $5.00 | $5.50 | $5.50 | $5.50 | $5.00 | $7.25 |
| 171 | Work zone pavement marking non-removing (W)(arrow) (662-7018) | EACH | 4 | $90.00 | $175.00 | $195.00 | $190.00 | $195.00 | $175.00 | $150.00 |
| 172 | Work zone pavement marking non-removing(W)(word) (662-7030) | EACH | 4 | $95.00 | $175.00 | $195.00 | $190.00 | $195.00 | $175.00 | $215.00 |
| 173 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 12,058 | $0.66 | $0.50 | $0.55 | $0.55 | $0.55 | $0.50 | $0.33 |
| 174 | Work zone pavement marking removing (reflectorized) type I-C (662-7049) | EACH | 30 | $7.15 | $6.00 | $6.75 | $6.60 | $6.60 | $6.00 | $4.75 |
| 175 | Work zone pavement marking removing (reflectorized) type II-A-A (662-7051) | EACH | 30 | $5.50 | $6.00 | $6.75 | $6.60 | $6.60 | $6.00 | $4.75 |
| 176 | Work zone pavement marking removing (traffic BTN) type W (662-7057) | EACH | 434 | $6.00 | $5.00 | $5.50 | $5.50 | $5.50 | $5.00 | $4.20 |
| 177 | Work zone pavement marking removing (traffic BTN) type Y (662-7059) | EACH | 84 | $6.50 | $5.00 | $5.50 | $5.50 | $5.50 | $5.00 | $4.20 |
| 178 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 29,929 | $1.00 | $1.10 | $1.25 | $1.20 | $1.20 | $1.10 | $1.25 |
| 179 | Work zone pavement marking removing (W)8"(solid) (662-7072) | LF | 6,716 | $1.77 | $2.00 | $2.20 | $2.20 | $2.20 | $2.00 | $2.45 |
| 180 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 132 | $10.00 | $10.00 | $11.00 | $11.00 | $11.00 | $10.00 | $13.25 |
| 181 | Work zone pavement marking removing (W)(arrow) (662-7082) | EACH | 12 | $267.41 | $200.00 | $220.00 | $220.00 | $220.00 | $200.00 | $253.00 |
| 182 | Work zone pavement marking removing (W)(word) (662-7092) | EACH | 10 | $280.00 | $200.00 | $220.00 | $220.00 | $220.00 | $200.00 | $335.00 |
| 183 | Work zone pavement marking removing (W)36"(yld tri) (662-7094) | EACH | 22 | $100.00 | $75.00 | $85.00 | $82.50 | $85.00 | $75.00 | $109.00 |
| 184 | Work zone pavement marking removing (Y)6"(DOT) (662-7099) | LF | 227 | $1.00 | $1.10 | $1.25 | $1.20 | $1.20 | $1.10 | $3.35 |
| 185 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 39,517 | $1.01 | $1.10 | $1.25 | $1.20 | $1.20 | $1.10 | $1.25 |
| 186 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 2,155 | $2.21 | $3.00 | $2.00 | $1.40 | $1.75 | $1.50 | $3.00 |
| 187 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 2,048 | $2.41 | $3.00 | $2.00 | $1.40 | $1.75 | $1.20 | $1.47 |
| 188 | Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018) | LF | 275 | $2.32 | $1.50 | $1.65 | $1.65 | $1.65 | $6.50 | $3.00 |
| 189 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 4,788 | $1.74 | $1.20 | $1.35 | $1.30 | $1.35 | $1.00 | $1.47 |
| 190 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 1,480 | $10.87 | $6.50 | $7.15 | $7.15 | $7.15 | $1.00 | $11.20 |
| 191 | Pavement sler 6" (666-7347) | LF | 1,308 | $0.66 | $1.00 | $1.10 | $1.10 | $1.10 | $0.85 | $0.50 |
| 192 | Pavement sler 8" (666-7348) | LF | 75 | $1.28 | $1.00 | $1.10 | $1.10 | $1.10 | $0.70 | $1.00 |
| 193 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 6,726 | $1.39 | $0.85 | $0.95 | $0.94 | $0.95 | $0.85 | $0.97 |
| 194 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 28,143 | $0.75 | $0.70 | $0.80 | $0.77 | $0.77 | $0.70 | $0.95 |
| 195 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 6,053 | $1.17 | $0.85 | $0.95 | $0.94 | $0.95 | $0.85 | $0.95 |
| 196 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 35,565 | $1.30 | $0.70 | $0.80 | $0.77 | $0.77 | $0.70 | $0.97 |
| 197 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 34 | $500.00 | $220.00 | $250.00 | $240.00 | $245.00 | $220.00 | $325.00 |
| 198 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 18 | $500.00 | $265.00 | $295.00 | $290.00 | $300.00 | $265.00 | $375.00 |
| 199 | Prefabricated PM type C (W)(36")(yld tri) (668-7111) | EACH | 9 | $95.00 | $100.00 | $110.00 | $110.00 | $110.00 | $100.00 | $95.00 |
| 200 | Reflectorized pavement marker type I-C (672-7002) | EACH | 588 | $6.91 | $5.00 | $5.50 | $5.50 | $5.50 | $5.00 | $5.85 |
| 201 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 1,321 | $10.44 | $5.00 | $5.50 | $5.50 | $5.50 | $5.00 | $5.85 |
| 202 | Eliminating existing PM & markers (4") (677-7001) | LF | 30,070 | $1.00 | $1.00 | $0.55 | $2.20 | $1.00 | $2.50 | $0.67 |
| 203 | Eliminating existing PM & markers (6") (677-7002) | LF | 2,293 | $1.10 | $4.00 | $1.00 | $2.20 | $2.00 | $0.56 | $0.67 |
| 204 | Eliminating existing PM & markers (8") (677-7004) | LF | 560 | $2.12 | $10.00 | $1.00 | $2.20 | $4.00 | $0.56 | $2.00 |
| 205 | Eliminating existing PM & markers (12") (677-7006) | LF | 200 | $2.49 | $10.00 | $2.20 | $3.30 | $5.00 | $2.00 | $3.00 |
| 206 | Eliminating existing PM & markers (24") (677-7008) | LF | 194 | $6.05 | $10.00 | $4.50 | $5.50 | $10.00 | $2.20 | $6.00 |
| 207 | Pavement surface preparation for marking (6") (678-7002) | LF | 1,308 | $0.90 | $1.00 | $1.10 | $1.10 | $1.10 | $1.00 | $1.00 |
| 208 | Pavement surface preparation for marking (8") (678-7004) | LF | 75 | $1.00 | $1.00 | $1.10 | $1.10 | $1.10 | $1.00 | $2.00 |
| 209 | Install highway traffic signal (isolated) (680-7002) | EACH | 1 | $32,000 | $34,950 | $39,000 | $38,500 | $38,000 | $34,950 | $34,950 |
| 210 | Removing traffic signals (680-7004) | EACH | 2 | $7,893.32 | $7,500.00 | $8,500.00 | $8,250.00 | $8,100.00 | $7,500.00 | $7,500.00 |
| 211 | Temporary traffic signals (681-7001) | EACH | 1 | $46,000 | $128,012 | $141,000 | $140,000 | $138,500 | $128,012 | $128,012 |
| 212 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 10 | $350.51 | $313.00 | $350.00 | $345.00 | $340.00 | $313.00 | $313.00 |
| 213 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 4 | $359.43 | $335.00 | $375.00 | $370.00 | $365.00 | $335.00 | $335.00 |
| 214 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 10 | $364.52 | $313.00 | $350.00 | $345.00 | $340.00 | $313.00 | $313.00 |
| 215 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 4 | $353.60 | $335.00 | $375.00 | $370.00 | $365.00 | $335.00 | $335.00 |
| 216 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 10 | $427.70 | $313.00 | $350.00 | $345.00 | $340.00 | $313.00 | $313.00 |
| 217 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 8 | $356.19 | $335.00 | $375.00 | $370.00 | $365.00 | $335.00 | $335.00 |
| 218 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 8 | $912.88 | $733.00 | $805.00 | $800.00 | $800.00 | $733.00 | $733.00 |
| 219 | Backplate W/reflectorized border(4 sec) (682-7037) | EACH | 4 | $231.00 | $275.00 | $305.00 | $300.00 | $300.00 | $275.00 | $275.00 |
| 220 | Backplate W/reflectorized border(3 sec)aluminum (682-7039) | EACH | 10 | $220.00 | $205.00 | $225.00 | $225.00 | $225.00 | $205.00 | $205.00 |
| 221 | Traffic signal CBL (type A)(12 AWG)(2 conductor) (684-7007) | LF | 1,755 | $2.45 | $2.25 | $2.50 | $2.50 | $2.50 | $2.25 | $2.25 |
| 222 | Traffic signal CBL (type A)(12 AWG)(4 conductor) (684-7009) | LF | 1,800 | $2.45 | $2.85 | $3.20 | $3.15 | $3.10 | $2.85 | $2.85 |
| 223 | Traffic signal CBL (type A)(12 AWG)(7 conductor) (684-7012) | LF | 2,600 | $5.50 | $3.50 | $3.85 | $3.85 | $3.80 | $3.50 | $3.50 |
| 224 | Install RDSD FLSH BCN assembly (solar PWRD) (685-7004) | EACH | 2 | $8,000.00 | $13,400 | $14,500 | $14,750 | $14,500 | $13,400 | $13,400 |
| 225 | Ins traffic signal PL AM(S)1 arm(44')lum (686-7047) | EACH | 1 | $16,500 | $21,000 | $23,100 | $23,000 | $22,700 | $21,000 | $21,000 |
| 226 | Ins traffic signal PL AM(S)1 arm(50')lum (686-7055) | EACH | 1 | $31,000 | $43,001 | $47,500 | $47,000 | $46,500 | $43,001 | $43,001 |
| 227 | Ins traffic signal PL AM(S)1 arm(60')lum (686-7063) | EACH | 1 | $38,500 | $46,200 | $51,000 | $51,000 | $50,000 | $46,200 | $46,200 |
| 228 | Ins traffic signal PL AM(S)1 arm(65')lum (686-7067) | EACH | 1 | $40,000 | $47,475 | $52,500 | $52,000 | $51,500 | $47,475 | $47,475 |
| 229 | Pedestrian pole assembly (687-7001) | EACH | 8 | $3,273.33 | $6,074.00 | $6,750.00 | $6,600.00 | $6,600.00 | $6,074.00 | $6,074.00 |
| 230 | Pedestrian detect push button (APS) (688-7001) | EACH | 8 | $2,800.00 | $1,020.00 | $1,150.00 | $1,125.00 | $1,100.00 | $1,020.00 | $1,020.00 |
| 231 | Pedestrian detector controller unit (688-7003) | EACH | 1 | $4,056.75 | $4,500.00 | $5,000.00 | $4,950.00 | $4,900.00 | $4,500.00 | $4,500.00 |
| 232 | Install vid image vehicle det sys (VIVDS) (690-7084) | EACH | 1 | $24,500 | $13,450 | $15,000 | $14,800 | $14,600 | $13,450 | $13,450 |
| 233 | Install bbu system (690-7131) | EACH | 1 | $6,600.00 | $10,300 | $11,500 | $11,300 | $11,500 | $10,300 | $10,300 |
| 234 | VIVDS cable (install) (690-7137) | LF | 1,175 | $0.50 | $2.35 | $2.75 | $2.60 | $2.55 | $2.35 | $2.35 |
| 235 | VIVDS camera (install) (690-7138) | EACH | 4 | $10,500 | $3,190.00 | $3,500.00 | $3,500.00 | $3,500.00 | $3,190.00 | $3,120.00 |
| 236 | Full - width mowing (730-7019) | CYC | 9 | $3,500.00 | $5,000.00 | $4,500.00 | $4,950.00 | $5,000.00 | $2,500.00 | $4,100.00 |
| 237 | Litter removal (734-7002) | CYC | 9 | $1,000.00 | $2,500.00 | $5,700.00 | $3,300.00 | $3,000.00 | $884.91 | $2,500.00 |
| 238 | Retrofit det warn surface (surface applied) (5031-7001) | SF | 356 | $260.00 | $25.00 | $25.00 | $27.50 | $100.00 | $47.52 | $300.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of July 2, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.