Rehabilitate Existing Roadway, FM 3309 (SL 256 to SH 155). Let by Texas DOT on January 7, 2026, Anderson, Tyler District. 5 bids received; low bid $1,861,683 by Baker & Company Construction, LLC, -4.1% against the engineer's estimate of $1,940,375.
- Owner
- Texas DOT
- Letting
- 07 JAN 2026
- Pay items
- 61
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Baker & Company Construction, LLC | $1,861,683 | Low | -4.0% |
| 2 | Big Creek Construction, LTD. | $1,893,528 | +2.0% | -2.0% |
| 3 | A. L. Helmcamp, Inc. | $2,136,740 | +15% | +10% |
| 4 | Drewery Construction Company, Incorporated | $2,209,920 | +19% | +14% |
| 5 | Texas Materials Group, Inc. | $2,325,258 | +25% | +20% |
Engineer's estimate: $1,940,375.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Baker & Company Construction, LLC | 2. Big Creek Construction, LTD. | 3. A. L. Helmcamp, Inc. | 4. Drewery Construction Company, Incorporated | 5. Texas Materials Group, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7001) | ACRE | 0.55 | $15,000 | $16,500 | $25,000 | $20,000 | $5,500.00 | $20,000 |
| 2 | Preparing row (100-7002) | STA | 26 | $2,000.00 | $3,025.00 | $4,500.00 | $5,000.00 | $3,200.00 | $8,500.00 |
| 3 | Removing concrete (curb & gutter) (104-7017) | LF | 150 | $15.00 | $16.50 | $20.00 | $44.00 | $23.00 | $45.00 |
| 4 | Remove (2"-6") TRT/untrt base & asphalt pavement (105-7002) | SY | 360 | $15.00 | $3.40 | $9.00 | $7.00 | $13.50 | $12.00 |
| 5 | Remove (6") TRT/untrt base & asphalt pavement (105-7026) | SY | 13,938 | $7.00 | $4.30 | $5.00 | $7.75 | $8.00 | $8.00 |
| 6 | Excavation (channel) (110-7002) | CY | 623 | $20.00 | $17.30 | $30.00 | $30.00 | $27.00 | $75.00 |
| 7 | Furn & place topsoil (4") (160-7002) | SY | 14,079 | $2.00 | $0.80 | $1.00 | $0.50 | $2.00 | $3.25 |
| 8 | Broadcast seed (permanent_rural_sand) (164-7001) | SY | 7,040 | $0.25 | $0.25 | $0.17 | $0.16 | $0.13 | $0.17 |
| 9 | Bond fiber MTRX seed (permanent)(rural)(sand) (164-7076) | SY | 14,079 | $0.65 | $1.05 | $0.65 | $0.63 | $0.60 | $0.66 |
| 10 | Bond fiber MTRX seed (temporary)(warm) (164-7077) | SY | 7,040 | $0.65 | $0.80 | $0.55 | $0.55 | $0.60 | $0.57 |
| 11 | Bond fiber MTRX seed (temporary)(cool) (164-7078) | SY | 7,040 | $0.65 | $0.80 | $0.55 | $0.55 | $0.60 | $0.57 |
| 12 | Vegetative watering (168-7001) | TGL | 388 | $10.00 | $10.00 | $25.00 | $5.00 | $36.00 | $50.00 |
| 13 | Cement (275-7001) | TON | 197 | $275.00 | $275.00 | $250.00 | $270.00 | $278.00 | $245.00 |
| 14 | Cement TRT (existing material)(8") (275-7003) | SY | 10,934 | $4.50 | $9.20 | $3.00 | $4.51 | $7.20 | $3.00 |
| 15 | Prime coat (RC-250) (310-7006) | GAL | 4,182 | $4.25 | $7.70 | $5.00 | $4.00 | $6.65 | $4.90 |
| 16 | Aggregate (type-D, GR-5)(sac-B) (316-7187) | CY | 117 | $250.00 | $200.00 | $160.00 | $255.00 | $354.00 | $320.00 |
| 17 | SP mixes SP-B PG64-22 (344-7001) | TON | 3,067 | $140.00 | $148.00 | $132.00 | $165.00 | $145.00 | $150.00 |
| 18 | SP mixes SP-C sac-A PG70-22 (344-7020) | TON | 1,585 | $140.00 | $172.00 | $145.00 | $165.00 | $167.50 | $165.00 |
| 19 | Tack coat (344-7077) | GAL | 1,441 | $5.00 | $5.25 | $4.25 | $4.50 | $6.45 | $4.50 |
| 20 | Planing asphalt concrete pavement(2") (354-7051) | SY | 471 | $4.50 | $30.00 | $7.00 | $4.50 | $35.00 | $12.00 |
| 21 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 20 | $175.00 | $1,320.00 | $400.00 | $275.00 | $150.00 | $315.00 |
| 22 | Riprap (stone common)(dry)(18 in) (432-7033) | CY | 55 | $200.00 | $171.00 | $150.00 | $225.00 | $295.00 | $355.00 |
| 23 | Clean existing culverts (480-7001) | EACH | 1 | $10,000 | $4,475.00 | $4,500.00 | $2,000.00 | $3,200.00 | $4,500.00 |
| 24 | Mobilization (500-7001) | LS | 1 | $175,000 | $148,190 | $178,000 | $195,000 | $255,000 | $230,000 |
| 25 | Barricades, signs and traffic handling (502-7001) | MO | 5 | $5,000.00 | $3,655.00 | $5,000.00 | $12,500 | $4,600.00 | $10,909 |
| 26 | Portable changeable message sign (503-7001) | DAY | 35 | $150.00 | $188.00 | $225.00 | $250.00 | $360.00 | $115.00 |
| 27 | TMA (stationary) (505-7001) | DAY | 5 | $200.00 | $363.00 | $300.00 | $250.00 | $260.00 | $400.00 |
| 28 | TMA (mobile operation) (505-7003) | DAY | 5 | $225.00 | $656.00 | $1,000.00 | $350.00 | $260.00 | $275.00 |
| 29 | Backhoe work (erosion & sediment control) (506-7030) | HR | 25 | $65.00 | $147.00 | $100.00 | $90.00 | $275.00 | $105.00 |
| 30 | Temporary sediment control fence (install) (506-7039) | LF | 1,000 | $4.15 | $4.40 | $4.00 | $4.50 | $4.45 | $4.70 |
| 31 | Temporary sediment control fence (remove) (506-7041) | LF | 1,000 | $1.25 | $2.20 | $1.00 | $1.05 | $1.15 | $1.15 |
| 32 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 250 | $6.00 | $8.80 | $6.00 | $5.25 | $11.00 | $5.55 |
| 33 | Biodegradable erosion control logs (remove) (506-7046) | LF | 250 | $2.00 | $5.50 | $1.00 | $1.10 | $2.20 | $1.15 |
| 34 | Trackhoe work (erosion & sediment control) (506-7051) | HR | 25 | $100.00 | $130.00 | $100.00 | $95.00 | $334.00 | $105.00 |
| 35 | Concrete curb & gutter (type II) (529-7009) | LF | 150 | $35.00 | $71.50 | $85.00 | $90.00 | $80.00 | $80.00 |
| 36 | Driveways (ACP) (530-7010) | SY | 360 | $75.00 | $145.00 | $40.00 | $80.00 | $54.00 | $90.00 |
| 37 | Mailbox install-S (TWG-post) type 2 (560-7002) | EACH | 10 | $350.00 | $396.00 | $240.00 | $231.00 | $428.00 | $430.00 |
| 38 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 10 | $675.00 | $853.00 | $700.00 | $683.00 | $755.00 | $760.00 |
| 39 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 5 | $1,150.00 | $1,232.00 | $1,050.00 | $1,040.00 | $1,230.00 | $1,250.00 |
| 40 | Remove SM RD SN sup&AM (644-7073) | EACH | 15 | $110.00 | $149.00 | $110.00 | $105.00 | $112.00 | $115.00 |
| 41 | Install object marker assembly (OM-2Z)(WFLX)GND(BI) (658-7059) | EACH | 4 | $90.00 | $143.00 | $80.00 | $79.00 | $124.00 | $125.00 |
| 42 | Install OM SM RD sign (1-OM-con)Y (658-7079) | EACH | 2 | $345.00 | $102.00 | $25.00 | $21.00 | $103.00 | $103.00 |
| 43 | Install OM SM RD sign (1-OM-con)R (658-7080) | EACH | 1 | $290.00 | $242.00 | $25.00 | $21.00 | $232.00 | $235.00 |
| 44 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 5,806 | $0.50 | $0.85 | $0.28 | $0.26 | $0.45 | $0.27 |
| 45 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 6,444 | $0.50 | $0.78 | $0.28 | $0.26 | $0.45 | $0.27 |
| 46 | Work zone pavement marking removing (W)6"(broken) (662-7065) | LF | 100 | $2.00 | $4.90 | $1.10 | $1.05 | $3.40 | $1.08 |
| 47 | Work zone pavement marking removing (Y)6"(broken) (662-7098) | LF | 1,432 | $2.00 | $3.80 | $0.80 | $0.79 | $1.35 | $0.80 |
| 48 | Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018) | LF | 24 | $2.15 | $5.50 | $2.20 | $2.10 | $2.75 | $2.45 |
| 49 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 150 | $1.40 | $2.20 | $1.10 | $1.05 | $2.20 | $1.15 |
| 50 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 244 | $8.00 | $7.15 | $7.50 | $7.35 | $7.70 | $8.00 |
| 51 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 5,806 | $0.85 | $1.65 | $0.75 | $0.74 | $0.90 | $0.80 |
| 52 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 6,444 | $0.85 | $1.65 | $0.75 | $0.74 | $0.90 | $0.80 |
| 53 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 1 | $250.00 | $275.00 | $275.00 | $263.00 | $270.00 | $300.00 |
| 54 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 1 | $265.00 | $330.00 | $275.00 | $263.00 | $293.00 | $300.00 |
| 55 | Reflectorized pavement marker type I-A (672-7001) | EACH | 60 | $6.60 | $6.60 | $4.50 | $4.20 | $4.70 | $4.75 |
| 56 | Reflectorized pavement marker type I-C (672-7002) | EACH | 12 | $7.00 | $6.60 | $4.50 | $4.20 | $4.70 | $4.75 |
| 57 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 144 | $7.00 | $5.50 | $4.50 | $4.20 | $4.70 | $4.75 |
| 58 | Full - width mowing (730-7019) | CYC | 1 | $5,000.00 | $3,850.00 | $4,200.00 | $6,905.42 | $1,900.00 | $4,200.00 |
| 59 | Litter removal (734-7002) | CYC | 1 | $3,000.00 | $3,850.00 | $3,000.00 | $6,243.90 | $1,700.00 | $1,400.00 |
| 60 | Membrane underseal (3005-7001) | GAL | 2,788 | $5.50 | $2.10 | $4.00 | $5.00 | $4.60 | $4.50 |
| 61 | Permeable concrete edge drain (4021-7001) | LF | 5,310 | $105.00 | $61.00 | $100.00 | $95.00 | $105.00 | $100.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of January 7, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.