TxDOT contract A00064408 bid tabulation

Roadway Rehabilitation/Reconstruction With No Added Capacity, US 79 (RUSK C/L, SW to .16 MI E OF SH110 IN NW SUMMERFIELD). Let by Texas DOT on February 7, 2025, Cherokee, Tyler District. 7 bids received; low bid $4,258,941 by Madden Contracting Company, LLC., -31% against the engineer's estimate of $6,215,435.

Owner
Texas DOT
Letting
07 FEB 2025
Pay items
71
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Madden Contracting Company, LLC.$4,258,941Low-31%
2Reynolds & Kay, LTD.$4,266,3450.0%-31%
3Big Creek Construction, LTD.$4,587,747+8.0%-26%
4Longview Bridge and Road, LTD.$4,977,741+17%-20%
5L. S. Equipment Co., Inc.$5,575,648+31%-10%
6Grey Sky Construction LLC$6,187,489+45%0.0%
7CDM Holdings$7,291,646+71%+17%
TxDOT contract A00064408: bids by rank

Engineer's estimate: $6,215,435.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Madden Contracting Company, LLC.2. Reynolds & Kay, LTD.3. Big Creek Construction, LTD.4. Longview Bridge and Road, LTD.5. L. S. Equipment Co., Inc.6. Grey Sky Construction LLC
1Preparing row (100-7002)STA12$4,773.22$2,680.00$2,000.00$4,000.00$10,000$3,000.00$52,000
2Embankment (vehicle)(OC)(type C) (132-7017)CY814$94.16$42.00$25.00$65.00$40.00$60.00$50.00
3Backfill (type A) (134-7001)STA132$526.80$286.00$420.00$200.00$320.00$450.00$250.00
4Backfill (type B) (134-7002)STA207$335.00$212.00$315.00$150.00$300.00$450.00$250.00
5Blading (150-7001)STA8$233.00$800.00$520.00$750.00$350.00$400.00$250.00
6Furn & place topsoil (4") (160-7002)SY7,601$8.45$4.75$5.00$2.50$4.00$4.00$10.00
7Bonded fiber MTRX seed (temporary)(warm) (164-7074)SY7,601$1.42$0.53$0.60$0.60$0.70$0.75$0.50
8Bonded fiber MTRX seed (temporary)(cool) (164-7075)SY7,601$1.47$0.55$0.60$0.60$0.73$0.75$0.50
9Bond fiber MTRX seed (permanent)(rural)(sand) (164-7076)SY32,572$0.74$0.59$0.65$0.60$0.75$0.80$0.50
10Vegetative watering (168-7001)TGL358$37.87$22.00$10.00$25.00$15.00$0.01$50.00
11Asphalt (AC-20XP, AC-10-2TR, or AC-20-5TR) (316-7068)GAL77,246$7.31$4.20$4.15$4.20$4.75$6.00$7.00
12Aggregate (type-PD or PL, GR-3) (316-7257)CY1,839$392.60$194.00$194.00$170.00$195.00$225.00$300.00
13PFC-C PG76-22 sac-A (342-7001)TON13,520$251.00$175.00$175.00$200.00$195.00$203.00$200.00
14Flexible pavement structure repair(8") (351-7007)SY1,000$72.76$115.00$95.00$100.00$85.00$95.00$80.00
15Planing asphalt concrete pavement(0" to 2") (354-7032)SY3,824$3.50$4.50$5.00$5.00$6.00$10.00$10.00
16Planing asphalt concrete pavement(2") (354-7051)SY2,400$4.89$4.50$5.00$5.00$6.00$10.00$10.00
17Planing asphalt concrete pavement (0" to 1.5") (354-7073)SY1,534$9.63$10.00$5.00$6.00$9.00$10.00$10.00
18Riprap (mow strip)(4 in) (432-7013)CY117$618.57$835.00$1,000.00$750.00$775.00$975.00$650.00
19Cleaning and sealing existing joints (438-7001)LF1,080$18.00$37.48$60.00$60.00$48.00$88.50$65.00
20RC pipe (CL III)(18 in) (464-7003)LF130$74.25$65.00$70.00$90.00$70.00$80.15$100.00
21RC pipe (CL III)(24 in) (464-7005)LF36$84.25$210.00$95.00$110.00$90.00$93.75$150.00
22Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308)EACH8$1,150.00$950.00$1,100.00$1,200.00$1,200.00$1,100.00$1,850.00
23Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH2$1,528.75$1,220.00$1,500.00$1,700.00$1,600.00$1,450.00$2,500.00
24Set (type II) (30 in) (RCP) (6: 1) (P) (467-7348)EACH6$2,496.51$1,895.00$2,400.00$2,500.00$2,400.00$3,500.00$3,000.00
25Removing structure (pipe) (496-7037)EACH5$533.50$750.00$450.00$650.00$1,000.00$1,000.00$500.00
26Mobilization (500-7001)LS1$276,833$242,500$205,000$201,000$475,000$550,000$600,000
27Barricades, signs and traffic handling (502-7001)MO6$8,318.88$2,000.00$5,000.00$3,000.00$12,000$10,000$15,000
28Portable changeable message sign (503-7001)DAY2$15,429$300.00$200.00$250.00$750.00$500.00$16,000
29TMA (stationary) (505-7001)DAY80$400.13$300.00$200.00$400.00$275.00$300.00$250.00
30TMA (mobile operation) (505-7003)DAY8$188.88$0.01$200.00$800.00$350.00$250.00$550.00
31Rock filter dams (install) (type 2) (506-7002)LF620$36.00$36.00$40.00$50.00$40.00$65.00$18.00
32Rock filter dams (remove) (506-7011)LF620$7.59$10.00$10.00$10.00$12.00$18.00$9.00
33Earthwork (erosion & sediment control, in vehicle) (506-7029)CY244$45.50$42.00$22.00$10.00$50.00$40.00$65.00
34Backhoe work (erosion & sediment control) (506-7030)HR20$141.50$125.00$55.00$75.00$200.00$100.00$150.00
35Temporary sediment control fence (install) (506-7039)LF4,106$3.81$3.30$3.75$4.00$4.00$6.00$4.00
36Temporary sediment control fence (remove) (506-7041)LF4,106$1.40$0.65$0.65$1.00$0.75$1.00$2.00
37Trackhoe work (erosion & sediment control) (506-7051)HR20$176.43$175.00$103.00$85.00$220.00$100.00$150.00
38Driveways (ACP) (530-7010)SY416$48.33$86.00$80.00$60.00$75.00$75.00$45.00
39Mill rumble strips (asphalt) (shoulder) (533-7001)LF66,401$0.27$0.26$0.17$0.25$0.21$0.75$0.15
40Mill rumble strips (asphalt) (centerline) (533-7002)LF33,200$0.27$0.26$0.17$0.25$0.21$0.75$0.15
41Metal W-beam guard fence (timber post) (540-7001)LF1,175$23.95$22.25$25.00$40.00$25.00$32.25$28.00
42Metal beam guard fence trans (thrie-beam) (540-7005)EACH8$1,600.00$1,600.00$1,800.00$2,500.00$1,750.00$3,200.00$1,850.00
43Remove metal beam guard fence (542-7001)LF800$2.39$2.00$2.25$10.00$2.50$8.00$3.00
44Remove terminal anchor section (542-7002)EACH8$205.00$200.00$230.00$1,000.00$220.00$500.00$500.00
45Guardrail end treatment (install) (544-7001)EACH12$3,012.75$2,750.00$3,200.00$3,200.00$3,050.00$4,250.00$3,250.00
46Guardrail end treatment (remove) (544-7003)EACH8$207.50$200.00$230.00$1,200.00$250.00$500.00$1,500.00
47Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013)EACH24$15.38$20.00$23.00$30.00$25.00$25.00$100.00
48Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019)EACH51$27.35$25.00$28.00$35.00$30.00$30.00$100.00
49Work zone pavement marking non-removing (W)6"(broken) (662-7005)LF3,940$0.48$0.22$0.25$0.30$0.25$0.32$0.75
50Work zone pavement marking non-removing (W)6"(solid) (662-7008)LF67,881$0.94$0.18$0.20$0.30$0.20$0.28$0.25
51Work zone pavement marking non-removing (Y)6"(broken) (662-7036)LF5,700$7.20$0.22$0.25$0.30$0.25$0.32$0.75
52Work zone pavement marking non-removing (Y)6"(solid) (662-7038)LF46,501$0.76$0.18$0.20$0.30$0.20$0.28$0.25
53Work zone pavement marking removing (W)6"(broken) (662-7065)LF1,773$1.72$1.85$1.50$1.60$1.30$3.00$5.00
54Work zone pavement marking removing (Y)6"(broken) (662-7098)LF2,566$1.81$1.85$1.50$1.60$1.30$3.00$5.00
55Work zone pavement marking removing (Y)6"(solid) (662-7100)LF10,463$1.31$1.85$1.50$1.60$1.30$3.00$0.75
56Work zone pavement marking SHT terminal (tab)type W (662-7112)EACH1,182$1.20$1.50$1.50$1.50$1.20$2.00$5.00
57Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114)EACH4,035$1.30$1.50$1.50$1.50$1.20$2.00$5.00
58Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF206$1.00$1.20$1.30$1.50$1.40$1.50$3.00
59Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266)LF1,480$0.87$4.00$4.40$3.50$4.50$6.00$0.80
60Reflectorized profile pavement marking type I(Y)6"(solid)(100MIL) (666-7270)LF1,480$0.97$4.00$4.40$3.50$4.50$6.00$0.80
61Reflectorized profile pavement marking type I(Y)6"(broken)(100MIL) (666-7274)LF230$3.45$4.00$4.40$3.50$4.50$6.00$0.80
62Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408)LF3,940$0.68$0.80$0.90$0.70$1.00$1.00$0.80
63Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF66,401$0.98$0.70$0.75$0.70$0.80$1.00$0.80
64Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420)LF5,470$0.73$0.80$0.90$0.70$0.90$1.00$0.80
65Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF45,021$0.98$0.70$0.75$0.70$0.80$1.00$0.80
66PRFB rumble strip (BLK)(1')(centerline) (668-7002)LF115$7.43$15.00$17.00$20.00$17.00$20.00$20.00
67Prefabricated PM type C (W)(arrow) (668-7091)EACH2$210.61$225.00$250.00$275.00$250.00$300.00$250.00
68Prefabricated PM type C (W)(LN reduct arrow) (668-7100)EACH8$354.74$285.00$320.00$600.00$320.00$325.00$250.00
69Prefabricated PM type C (W)(word) (668-7103)EACH2$241.84$265.00$300.00$350.00$295.00$285.00$250.00
70Reflectorized pavement marker type I-C (672-7002)EACH219$4.05$6.00$6.50$6.00$6.70$8.00$5.00
71Reflectorized pavement marker type II-A-A (672-7004)EACH1,142$5.59$4.60$5.50$6.00$5.00$5.00$5.00
TxDOT contract A00064408: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of February 7, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy