TxDOT contract A00127306 bid tabulation

Rehabilitate Existing Roadway, SH 44 (US 59 to 4 MI EAST OF US 59). Let by Texas DOT on March 4, 2026, Duval, Laredo District. 5 bids received; low bid $18,216,991 by Hunter Industries, LTD., -17% against the engineer's estimate of $21,994,703.

Owner
Texas DOT
Letting
04 MAR 2026
Pay items
126
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Hunter Industries, LTD.$18,216,991Low-17%
2Anderson Columbia Co., Inc.$18,582,416+2.0%-16%
3CK Newberry, LLC$19,019,467+4.0%-14%
4Texas Materials Group, Inc.$23,806,134+31%+8.0%
5Mako Contracting, LLC$27,009,857+48%+23%
TxDOT contract A00127306: bids by rank

Engineer's estimate: $21,994,703.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Hunter Industries, LTD.2. Anderson Columbia Co., Inc.3. CK Newberry, LLC4. Texas Materials Group, Inc.5. Mako Contracting, LLC
1Preparing row (100-7002)STA230$3,000.00$673.51$500.00$500.00$268.00$1,100.00
2Removing concrete (riprap) (104-7006)SY1,622$8.00$14.18$25.00$20.00$19.00$55.00
3Remove (10") TRT/untrt base & asphalt pavement (105-7030)SY120,504$10.00$4.77$2.40$4.75$10.00$7.00
4Excavation (roadway) (110-7001)CY13,707$14.00$16.35$10.00$15.00$19.00$14.00
5Subgr widen (DC) (112-7002)STA230$1,000.00$488.40$2,200.00$350.00$940.00$3,750.00
6Embankment (final)(DC)(type D) (132-7012)CY2,195$6.50$14.21$10.00$20.00$14.20$7.00
7Drill seed (permanent_rural_clay) (164-7042)ACRE42.20$800.00$1,250.00$1,350.00$1,250.00$1,250.00$5,500.00
8Drill seed (temporary_warm) (164-7045)ACRE42.20$500.00$500.00$540.00$500.00$500.00$2,500.00
9Proof rolling (216-7001)HR42$80.00$88.00$140.00$70.00$182.00$125.00
10FL BS (compacted in place)(tya GR1-2)(final pos) (247-7176)CY40,261$85.00$88.73$88.00$85.00$114.50$110.00
11Lime (quicklime (slurry)) (260-7003)TON1,938$350.00$326.35$375.00$315.00$398.00$492.49
12Lime TRT (existing material)(6") (260-7006)SY130,461$3.50$3.02$3.50$1.65$4.22$3.22
13Prime coat (RC-250) (310-7006)GAL25,133$5.00$4.41$5.00$4.50$4.60$6.13
14D-GR HMA type-B sac-B PG70-22 (341-7007)TON31,404$105.00$95.31$98.00$96.50$107.50$159.85
15D-GR HMA type-C sac-A PG76-22 (341-7031)TON14,972$120.00$116.22$108.00$112.50$138.00$204.70
16D-GR HMA type D sac-B PG64-22 (341-7045)TON2,293$140.00$98.56$110.00$105.00$128.00$194.35
17Planing asphalt concrete pavement(4") (354-7053)SY107,026$2.60$2.81$1.00$1.50$3.14$4.26
18Struct excavation (box) (400-7002)CY2,549$50.00$9.43$10.00$10.00$9.50$104.50
19Cem stabil BKFL (400-7010)CY641$250.00$90.57$150.00$140.00$138.00$280.00
20Trench excavation protection (402-7001)LF644$20.00$9.08$12.00$12.00$11.85$60.00
21Temporary special shoring (403-7001)SF27,002$25.00$0.95$12.00$10.75$31.00$14.00
22Drilled shaft (roadway illumination pole) (30 in) (416-7040)LF72$350.00$383.24$210.00$300.00$250.00$224.25
23Drilled shaft (traffic signal pole) (36 in) (416-7044)LF27$380.00$540.74$320.00$400.00$350.00$339.25
24Riprap (concrete)(5 in) (432-7002)CY11$600.00$783.23$600.00$575.00$550.00$750.00
25Riprap (concrete) (CL B) (4 in) (432-7007)CY203$550.00$726.06$550.00$525.00$505.00$700.00
26Riprap (concrete)(dissipater) (432-7011)CY7$1,200.00$1,301.55$700.00$650.00$632.00$5,000.00
27Riprap (mow strip)(4 in) (432-7013)CY182$825.00$743.21$550.00$550.00$510.00$600.00
28Concrete box culvert (3 FT X 2 FT) (462-7001)LF108$410.00$292.72$380.00$375.00$350.00$467.50
29Concrete box culvert (4 FT X 3 FT) (462-7004)LF60$450.00$346.90$460.00$450.00$426.00$555.50
30Concrete box culvert (5 FT X 2 FT) (462-7006)LF224$530.00$400.56$540.00$525.00$501.00$641.30
31Concrete box culvert (5 FT X 4 FT) (462-7008)LF152$550.00$453.15$620.00$625.00$575.00$716.10
32Concrete box culvert (6 FT X 2 FT) (462-7010)LF53$650.00$453.15$640.00$625.00$577.00$807.40
33Concrete box culvert (6 FT X 3 FT) (462-7011)LF249$785.00$504.15$700.00$675.00$652.00$880.00
34Concrete box culvert (6 FT X 5 FT) (462-7013)LF69$950.00$583.31$840.00$800.00$771.00$935.00
35Concrete box culvert (9 FT X 8 FT) (462-7030)LF92$1,550.00$1,027.96$1,700.00$1,600.00$1,575.00$3,600.00
36Wingwall (PW - 1) (HW=4 FT) (466-7174)EACH1$15,000$22,790$11,000$10,000$9,461.00$18,000
37Wingwall (PW - 1) (HW=5 FT) (466-7175)EACH2$17,780$28,204$20,000$20,000$18,405$25,000
38Wingwall (PW - 1) (HW=7 FT) (466-7177)EACH2$33,000$39,912$24,000$22,000$21,891$30,000
39Wingwall (PW - 1) (HW=9 FT) (466-7179)EACH2$45,000$50,952$38,000$36,000$35,000$40,000
40Wingwall (PW - 1) (HW=10 FT) (466-7180)EACH1$50,000$55,648$45,000$42,000$41,250$50,000
41Set (type I)(S= 3 FT)(HW= 3 FT)(4:1)(C) (467-7041)EACH6$8,000.00$2,217.74$7,000.00$7,000.00$6,550.00$12,000
42Set (type I)(S= 4 FT)(HW= 4 FT)(3:1)(C) (467-7071)EACH2$14,000$16,431$9,000.00$9,000.00$8,339.00$15,000
43Set (type I)(S= 5 FT)(HW= 3 FT)(4:1)(C) (467-7096)EACH4$14,000$2,806.04$11,000$10,000$9,739.00$15,000
44Set (type I)(S= 6 FT)(HW= 3 FT)(4:1)(C) (467-7125)EACH2$15,000$3,478.38$10,000$9,500.00$8,750.00$15,000
45Removing structure (box culvert) (496-7001)EACH14$9,000.00$132.81$1,800.00$2,500.00$1,609.00$32,450
46Removing structure (set) (496-7004)EACH16$800.00$531.25$1,500.00$1,500.00$1,375.00$3,850.00
47Removing structure (wingwall) (496-7005)EACH4$2,300.00$1,301.55$1,400.00$1,500.00$1,250.00$4,800.00
48Mobilization (500-7001)LS1$1,434,613$1,440,059$1,640,000$1,800,000$1,699,450$665,000
49Barricades, signs and traffic handling (502-7001)MO18$5,000.00$8,288.30$3,500.00$5,000.00$3,275.00$4,350.00
50Portable changeable message sign (503-7002)EACH4$12,000$2,500.00$20,000$20,000$15,000$5,000.00
51TMA (stationary) (505-7001)DAY698$250.00$150.00$300.00$200.00$175.00$200.00
52TMA (mobile operation) (505-7003)DAY500$250.00$250.00$20.00$25.00$400.00$250.00
53Rock filter dams (install) (type 3) (506-7003)LF273$73.00$90.00$100.00$90.00$90.00$25.00
54Rock filter dams (remove) (506-7011)LF273$14.50$18.00$20.00$18.00$18.00$5.00
55Construction exits (install) (type 1) (506-7020)SY56$40.00$55.00$60.00$25.00$55.00$40.00
56Construction exits (remove) (506-7024)SY56$10.00$20.00$22.00$20.00$20.00$18.00
57Backhoe work (erosion & sediment control) (506-7030)HR20$150.00$150.00$100.00$85.00$140.00$125.00
58Temporary sediment control fence (install) (506-7039)LF800$6.00$6.00$6.50$6.00$6.00$5.00
59Temporary sediment control fence (remove) (506-7041)LF800$1.00$2.00$2.10$2.00$2.00$1.00
60Constructing detours (508-7001)SY27,022$44.00$45.36$51.00$50.00$66.00$74.00
61One-way traffic control (flagger cont) (510-7001)HR200$75.00$82.50$80.00$50.00$75.00$30.00
62One-way traffic control (pilot car) (510-7002)HR1,000$40.00$93.50$185.00$110.00$150.00$125.00
63Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001)LF19,500$50.00$30.15$22.00$60.00$56.00$80.00
64Portable concrete traffic barrier (des source)(low prof)(type 1) (512-7021)LF4,040$20.00$17.42$16.00$12.00$30.00$20.00
65Portable concrete traffic barrier (des source)(low prof)(type 2) (512-7022)LF340$20.00$25.66$16.00$22.00$35.00$30.00
66Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025)LF19,500$10.00$6.34$1.70$8.00$7.00$7.00
67Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033)LF5,820$15.00$15.88$4.00$5.00$7.00$7.00
68Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034)LF500$16.00$26.64$4.00$15.00$7.00$7.00
69Portable concrete traffic barrier (stockpile)(low prof)(type 1) (512-7045)LF3,880$12.00$16.01$12.00$10.00$24.00$50.00
70Portable concrete traffic barrier (stockpile)(low prof)(type 2) (512-7046)LF340$20.00$22.24$12.00$22.00$24.00$50.00
71Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049)LF19,500$20.00$15.20$12.00$15.00$32.00$7.00
72Mill rumble strips (asphalt) (shoulder) (533-7001)LF42,240$0.27$0.18$0.17$0.15$0.18$0.16
73Mill rumble strips (asphalt) (centerline) (533-7002)LF21,120$0.27$0.20$0.17$0.20$0.20$0.30
74Metal W-beam guard fence (timber post) (540-7001)LF2,975$25.00$27.25$36.00$28.00$30.00$38.53
75Metal beam guard fence (long span system) (540-7027)EACH4$1,130.00$1,455.00$1,820.00$1,925.00$1,160.00$1,941.20
76Remove metal beam guard fence (542-7001)LF1,975$3.00$5.00$2.40$3.00$3.00$2.59
77Remove terminal anchor section (542-7002)EACH4$265.00$355.00$215.00$325.00$220.00$230.00
78Guardrail end treatment (install) (544-7001)EACH14$3,000.00$2,985.00$3,800.00$4,500.00$3,300.00$4,054.90
79Guardrail end treatment (remove) (544-7003)EACH8$1,415.00$455.00$215.00$325.00$330.00$230.00
80Crash cushion attenuator (move & reset) (545-7002)EACH70$1,300.00$1,250.00$975.00$650.00$1,180.00$948.75
81Crash cushion attenuator (remove) (545-7004)EACH70$1,000.00$555.00$740.00$650.00$825.00$948.75
82Cca (install)(N)(TL3)(work zone) (545-7018)EACH70$10,000$6,825.00$6,250.00$6,500.00$8,000.00$948.75
83Mailbox install-M (TWG-post) type 1 (560-7001)EACH8$250.00$656.27$600.00$550.00$550.00$660.00
84Mailbox install-M (TWW-post) type 4 (560-7010)EACH1$500.00$880.63$645.00$600.00$600.00$900.00
85Relocate existing mailbox (560-7012)EACH9$250.00$544.08$270.00$250.00$250.00$660.00
86In RD IL (type SA) 40T-8 (250W EQ) LED (610-7124)EACH9$11,914$4,674.00$5,270.00$5,250.00$4,500.00$5,629.25
87Conduit (PVC) (schedule 40) (2") (618-7030)LF2,075$15.34$13.30$11.00$20.00$12.00$11.50
88Conduit (PVC) (schedule 80) (2") (bore) (618-7055)LF93$28.71$35.75$40.00$51.00$30.00$42.55
89Electrical conductor (no.8) bare (620-7007)LF2,213$2.24$2.05$1.60$2.50$1.50$1.73
90Electrical conductor (no.8) insulated (620-7008)LF4,371$2.55$2.30$1.70$2.75$1.55$1.84
91Electrical conductor (no.6) bare (620-7009)LF10$3.62$2.23$3.40$3.75$1.75$3.68
92Electrical conductor (no.6) insulated (620-7010)LF10$2,015.59$2.55$3.70$4.25$1.95$3.68
93Tray cable (3 conductor) (12 AWG) (621-7002)LF286$3.62$3.35$3.00$2.75$3.00$3.22
94Ground box type C (162911)W/apron (624-7006)EACH2$2,015.59$1,241.00$1,360.00$2,000.00$1,000.00$1,449.00
95Zinc-coat steel wire strand (3/8") (625-7004)LF165$3.12$4.90$3.00$3.25$3.05$3.22
96Remove electrical services (628-7002)EACH1$812.94$1,890.00$400.00$4,000.00$365.00$419.75
97Elc SRV type T 120/240 000(NS)GS(L)SP(O) (628-7319)EACH1$4,000.00$7,227.00$6,330.00$5,500.00$5,500.00$6,762.00
98Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH39$1,000.00$768.45$740.00$700.00$690.00$930.00
99Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH7$1,100.00$824.54$1,030.00$800.00$790.00$1,380.00
100Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031)EACH11$1,700.00$992.81$1,034.92$1,000.00$960.00$1,680.00
101Remove SM RD SN sup&AM (644-7073)EACH57$135.00$95.35$107.00$100.00$100.00$102.00
102Install delineator assembly (D-SW)SZ 1(WFLX)GF2 (658-7001)EACH27$31.00$68.65$48.00$100.00$45.00$62.40
103Install delineator assembly (D-SW)SZ 1(WFLX)GF2(BI) (658-7002)EACH12$35.00$75.00$54.00$100.00$45.00$62.40
104Work zone pavement marking removing (reflectorized) type II-A-A (662-7051)EACH580$1.00$7.50$8.00$8.00$7.50$9.00
105Work zone pavement marking removing (traffic BTN) type W (662-7057)EACH18,957$1.00$1.10$1.20$1.25$1.10$1.32
106Work zone pavement marking removing (traffic BTN) type Y (662-7059)EACH18,957$1.00$1.10$1.20$1.25$1.10$1.32
107Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042)EACH8$250.00$275.00$300.00$300.00$275.00$330.00
108Pavement sler 6" (666-7347)LF87,601$0.30$0.28$0.30$0.30$0.28$0.34
109Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408)LF3,501$1.00$0.78$0.85$0.80$0.78$0.94
110Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF42,050$1.00$0.62$0.65$0.65$0.62$0.74
111Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF42,050$0.75$0.62$0.65$0.65$0.62$0.74
112Reflectorized pavement marker type I-C (672-7002)EACH176$5.50$7.50$8.00$8.00$7.50$9.00
113Reflectorized pavement marker type II-A-A (672-7004)EACH528$5.00$7.50$8.00$8.00$7.50$9.00
114Eliminating existing PM & markers (4") (677-7001)LF68,814$1.00$0.25$0.30$0.50$0.25$0.30
115Eliminating existing PM & markers (arrow) (677-7009)EACH6$110.00$70.00$75.00$75.00$70.00$84.00
116Eliminating existing PM & markers (word) (677-7015)EACH6$110.00$70.00$75.00$75.00$70.00$84.00
117Install highway traffic signal (flash beacon) (680-7001)EACH1$3,559.79$20,758$3,500.00$10,000$3,600.00$3,737.50
118Temporary traffic signals (681-7001)EACH3$5,000.00$12,459$7,000.00$10,000$7,000.00$7,475.00
119Vehicle signal section (12")LED(yel) (682-7003)EACH4$316.37$105.00$485.00$375.00$345.00$517.50
120Vehicle signal section (12")LED(red) (682-7005)EACH2$317.87$105.00$485.00$375.00$345.00$517.50
121Traffic signal CBL (type A)(12 AWG)(3 conductor) (684-7008)LF221$2.69$2.40$3.00$2.75$2.45$3.22
122Removal of conduit (690-7001)LF10$4.56$6.35$35.00$4.50$2.00$36.80
123Remove traffic signal (690-7100)EACH1$7,285.71$6,458.00$3,450.00$7,000.00$2,500.00$3,680.00
124Bonding course (3007-7001)GAL23,679$5.00$2.79$1.00$3.25$3.56$4.03
125Bird exclusion method (5029-7001)SF1,324$10.00$1.50$23.00$25.00$7.60$10.00
126Trail MNT sol PRD rad speed CNT monitor (6025-7002)EACH4$10,000$5,000.00$13,400$10,000$11,850$10,000
TxDOT contract A00127306: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of March 4, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy