TxDOT contract A00193132 bid tabulation
Rehabilitate Existing Roadway, SH 16 (Mills County Line to .4 Miles S. of CR 140). Let by Texas DOT on September 5, 2025, San Saba, Brownwood District. 4 bids received; low bid $11,074,629 by Allen Keller Company, -21% against the engineer's estimate of $13,990,091.
- Owner
- Texas DOT
- Letting
- 05 SEP 2025
- Pay items
- 131
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Allen Keller Company | $11,074,629 | Low | -21% |
| 2 | CK Newberry, LLC | $11,885,997 | +7.0% | -15% |
| 3 | Big Creek Construction, LTD. | $12,387,672 | +12% | -11% |
| 4 | Texas Materials Group, Inc. | $13,973,452 | +26% | 0.0% |
Engineer's estimate: $13,990,091.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Allen Keller Company | 2. CK Newberry, LLC | 3. Big Creek Construction, LTD. | 4. Texas Materials Group, Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 240 | $1,100.00 | $502.07 | $500.00 | $2,000.00 | $797.00 |
| 2 | Removing concrete (driveways) (104-7011) | SY | 25 | $30.00 | $73.64 | $50.00 | $50.00 | $71.00 |
| 3 | Excavation (roadway) (110-7001) | CY | 20,497 | $16.25 | $5.77 | $15.00 | $17.00 | $12.75 |
| 4 | Embankment (final)(DC)(type C) (132-7006) | CY | 24,553 | $18.00 | $3.32 | $18.00 | $17.00 | $10.30 |
| 5 | Blading (150-7002) | HR | 40 | $170.00 | $468.68 | $175.00 | $150.00 | $155.00 |
| 6 | Broadcast seed (temporary_warm) (164-7005) | SY | 26,295 | $0.20 | $0.17 | $0.20 | $0.20 | $0.18 |
| 7 | Broadcast seed (temporary_cool) (164-7006) | SY | 26,295 | $0.20 | $0.17 | $0.20 | $0.20 | $0.18 |
| 8 | Drill seed (permanent_rural_sand) (164-7009) | SY | 52,589 | $0.20 | $0.17 | $0.20 | $0.20 | $0.18 |
| 9 | Vegetative watering (168-7001) | TGL | 578.50 | $25.00 | $46.50 | $25.00 | $15.00 | $70.25 |
| 10 | Proof rolling (216-7001) | HR | 40 | $111.00 | $147.42 | $100.00 | $150.00 | $143.25 |
| 11 | FL BS (compacted in place)(type A GR 1-2) (10") (247-7090) | SY | 120,269 | $22.00 | $17.44 | $16.00 | $17.00 | $21.75 |
| 12 | FL BS (compacted in place)(tya GR1-2)(final pos) (247-7176) | CY | 11,151 | $83.00 | $43.47 | $50.00 | $50.00 | $64.50 |
| 13 | FL BS (compacted in place)(type D GR 4)(final pos) (247-7190) | CY | 2,500 | $75.00 | $55.27 | $95.00 | $125.00 | $87.40 |
| 14 | Rework BS metal (type C)(8")(density control) (251-7052) | SY | 121,502 | $2.75 | $0.56 | $1.00 | $1.00 | $1.85 |
| 15 | Cement (275-7001) | TON | 882 | $245.00 | $243.11 | $235.00 | $250.00 | $275.00 |
| 16 | Cement TRT (existing material)(8") (275-7003) | SY | 104,249 | $4.00 | $1.75 | $2.00 | $2.50 | $1.75 |
| 17 | Prime coat (MC-30) (310-7004) | GAL | 18,597 | $6.00 | $5.15 | $5.00 | $5.50 | $8.15 |
| 18 | Asphalt (RC-250) (316-7016) | GAL | 23,556 | $5.00 | $5.15 | $4.00 | $5.00 | $6.80 |
| 19 | Asphalt (AC-20-5TR or CRS-2P) (316-7086) | GAL | 66,453 | $4.75 | $4.68 | $4.25 | $4.00 | $5.05 |
| 20 | Aggregate (type-B, GR-4)(sac-B) (316-7173) | CY | 563 | $110.00 | $154.92 | $140.00 | $150.00 | $235.00 |
| 21 | Aggregate (type-PB, GR-4)(sac-B) (316-7211) | CY | 1,476 | $130.00 | $160.60 | $175.00 | $130.00 | $215.25 |
| 22 | D-GR HMA type-B PG64-22 (341-7001) | TON | 6,524 | $125.00 | $107.70 | $130.00 | $102.00 | $159.00 |
| 23 | SP mixes SP-D sac-B PG76-22 (344-7065) | TON | 535 | $140.00 | $126.47 | $165.00 | $150.00 | $245.00 |
| 24 | Plane & text asphalt concrete pavement(0" to 10") (354-7008) | SY | 8,813 | $7.50 | $8.99 | $5.00 | $12.00 | $17.70 |
| 25 | Planing asphalt concrete pavement(0" to 3") (354-7033) | SY | 802 | $3.00 | $5.39 | $5.00 | $7.00 | $26.50 |
| 26 | Planing asphalt concrete pavement(0" to 4") (354-7034) | SY | 802 | $3.50 | $5.60 | $5.00 | $8.00 | $26.00 |
| 27 | Cem stabil BKFL (400-7010) | CY | 400 | $220.00 | $199.43 | $250.00 | $180.00 | $275.00 |
| 28 | Flowable backfill (401-7001) | CY | 113 | $280.00 | $234.70 | $375.00 | $220.00 | $290.00 |
| 29 | Trench excavation protection (402-7001) | LF | 111 | $31.00 | $251.85 | $35.00 | $30.00 | $1.00 |
| 30 | Temporary special shoring (403-7001) | SF | 8,335 | $25.00 | $38.30 | $22.00 | $15.00 | $28.00 |
| 31 | Class C concrete (rail foundation) (420-7052) | CY | 11.10 | $2,500.00 | $757.85 | $1,100.00 | $1,500.00 | $1,150.00 |
| 32 | Penetrating concrete surface treatment (428-7001) | SY | 16 | $60.00 | $29.50 | $250.00 | $75.00 | $100.00 |
| 33 | Riprap (concrete)(4 in) (432-7001) | CY | 295 | $550.00 | $645.74 | $600.00 | $650.00 | $710.00 |
| 34 | Riprap (concrete)(5 in) (432-7002) | CY | 461 | $600.00 | $645.74 | $550.00 | $650.00 | $718.00 |
| 35 | Riprap (mow strip)(4 in) (432-7013) | CY | 446 | $550.00 | $516.66 | $650.00 | $650.00 | $725.00 |
| 36 | Riprap (stone common)(dry)(18 in) (432-7033) | CY | 248 | $225.00 | $164.03 | $180.00 | $150.00 | $290.00 |
| 37 | Cleaning and sealing existing joints (CL3) (438-7004) | LF | 201 | $70.00 | $58.04 | $75.00 | $80.00 | $62.00 |
| 38 | Rail (type T221)(mod) (450-7067) | LF | 36.70 | $200.00 | $147.46 | $500.00 | $350.00 | $235.00 |
| 39 | Retrofit rail (type T631) (451-7020) | LF | 510 | $115.00 | $91.91 | $105.00 | $150.00 | $140.00 |
| 40 | Waterproofing (type 10) (458-7007) | SY | 95 | $189.00 | $108.14 | $60.00 | $75.00 | $200.00 |
| 41 | CMP (gal steel 24 in) (460-7005) | LF | 1,969 | $90.00 | $147.33 | $80.00 | $75.00 | $68.00 |
| 42 | Concrete box culvert (3 FT X 2 FT) (462-7001) | LF | 62 | $390.00 | $449.35 | $400.00 | $400.00 | $390.00 |
| 43 | Concrete box culvert (4 FT X 4 FT) (462-7005) | LF | 130 | $475.00 | $584.11 | $500.00 | $500.00 | $868.00 |
| 44 | Concrete box culvert (8 FT X 6 FT) (462-7023) | LF | 54 | $1,200.00 | $1,299.46 | $1,200.00 | $1,000.00 | $1,300.00 |
| 45 | Concrete box culvert (8 FT X 6 FT)(extend) (462-7078) | LF | 32 | $1,500.00 | $1,718.14 | $1,500.00 | $1,500.00 | $1,380.00 |
| 46 | Concrete box culvert (8 FT X 8 FT)(extend) (462-7080) | LF | 60 | $1,575.00 | $1,963.89 | $1,600.00 | $1,700.00 | $1,640.00 |
| 47 | Concrete box culvert (10 FT X 10 FT)(extend) (462-7093) | LF | 28 | $1,900.00 | $2,209.63 | $2,100.00 | $2,000.00 | $2,770.00 |
| 48 | RC pipe (CL III)(18 in) (464-7003) | LF | 82 | $140.00 | $215.38 | $120.00 | $100.00 | $82.00 |
| 49 | RC pipe (CL III)(24 in) (464-7005) | LF | 387 | $120.00 | $234.88 | $125.00 | $122.00 | $100.00 |
| 50 | Wingwall (PW - 1) (HW=10 FT) (466-7180) | EACH | 4 | $92,000 | $18,120 | $60,000 | $55,000 | $50,000 |
| 51 | Wingwall (PW - 1) (HW=14 FT) (466-7184) | EACH | 2 | $115,000 | $43,955 | $125,000 | $120,000 | $100,000 |
| 52 | Set (type I)(S= 3 FT)(HW= 3 FT)(3:1)(C) (467-7040) | EACH | 4 | $9,000.00 | $3,287.39 | $8,000.00 | $5,000.00 | $9,300.00 |
| 53 | Set (type I)(S= 4 FT)(HW= 4 FT)(3:1)(C) (467-7071) | EACH | 2 | $13,000 | $5,047.52 | $16,000 | $10,000 | $10,600 |
| 54 | Set (type I)(S= 4 FT)(HW= 5 FT)(3:1)(C) (467-7075) | EACH | 10 | $19,700 | $6,507.99 | $6,000.00 | $5,000.00 | $10,000 |
| 55 | Set (type II) (24 in) (CMP) (6: 1) (P) (467-7324) | EACH | 70 | $1,930.00 | $3,604.52 | $2,000.00 | $1,500.00 | $1,500.00 |
| 56 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 3 | $2,425.00 | $3,149.43 | $2,800.00 | $1,750.00 | $1,600.00 |
| 57 | Removing structure (pipe) (496-7007) | LF | 77 | $24.00 | $45.64 | $60.00 | $35.00 | $12.00 |
| 58 | Removing structure (pipe) (496-7037) | EACH | 10 | $800.00 | $702.82 | $2,500.00 | $650.00 | $200.00 |
| 59 | Mobilization (500-7001) | LS | 1 | $1,150,000 | $1,052,000 | $1,100,000 | $1,100,000 | $1,175,000 |
| 60 | Barricades, signs and traffic handling (502-7001) | MO | 24 | $10,000 | $10,115 | $5,000.00 | $5,000.00 | $2,300.00 |
| 61 | Portable changeable message sign (503-7001) | DAY | 180 | $170.00 | $104.46 | $100.00 | $150.00 | $118.00 |
| 62 | TMA (stationary) (505-7001) | DAY | 241 | $205.00 | $227.34 | $250.00 | $300.00 | $110.00 |
| 63 | TMA (mobile operation) (505-7003) | DAY | 62 | $250.00 | $727.64 | $200.00 | $550.00 | $110.00 |
| 64 | Rock filter dams (install) (type 3) (506-7003) | LF | 580 | $80.00 | $67.72 | $75.00 | $80.00 | $70.00 |
| 65 | Rock filter dams (remove) (506-7011) | LF | 1,480 | $16.00 | $14.52 | $16.00 | $12.00 | $15.00 |
| 66 | Construction exits (install) (type 1) (506-7020) | SY | 1,170 | $32.25 | $33.86 | $10.00 | $25.00 | $35.00 |
| 67 | Construction exits (remove) (506-7024) | SY | 1,170 | $11.00 | $9.67 | $5.00 | $10.00 | $10.00 |
| 68 | Backhoe work (erosion & sediment control) (506-7030) | HR | 68 | $182.00 | $156.61 | $125.00 | $150.00 | $222.00 |
| 69 | Temporary sediment control fence (install) (506-7039) | LF | 15,413 | $4.25 | $4.11 | $4.50 | $4.00 | $4.25 |
| 70 | Temporary sediment control fence (remove) (506-7041) | LF | 15,413 | $1.00 | $0.28 | $0.50 | $1.00 | $0.29 |
| 71 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 560 | $10.00 | $7.74 | $10.00 | $7.00 | $8.00 |
| 72 | Biodegradable erosion control logs (remove) (506-7046) | LF | 560 | $2.65 | $1.93 | $2.00 | $1.00 | $2.00 |
| 73 | Rock filter dams (install) (type 2) 6:1 (506-7048) | LF | 900 | $80.00 | $62.88 | $70.00 | $60.00 | $65.00 |
| 74 | Constructing detours (508-7001) | SY | 28,057 | $29.00 | $23.21 | $25.00 | $35.00 | $35.50 |
| 75 | One-way traffic control (port traffic signal) (510-7003) | MO | 9 | $6,000.00 | $4,102.96 | $7,500.00 | $5,000.00 | $8,160.00 |
| 76 | Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001) | LF | 390 | $70.00 | $107.54 | $125.00 | $50.00 | $112.00 |
| 77 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 1,470 | $25.00 | $18.51 | $50.00 | $15.00 | $23.00 |
| 78 | Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049) | LF | 390 | $30.00 | $23.26 | $100.00 | $45.00 | $59.00 |
| 79 | Driveways (concrete) (530-7006) | SY | 97 | $108.00 | $100.86 | $150.00 | $150.00 | $145.00 |
| 80 | Driveways (surface treat) (530-7016) | SY | 3,852 | $30.00 | $17.76 | $25.00 | $25.00 | $90.00 |
| 81 | Turnouts (ACP) (530-7018) | SY | 83 | $100.00 | $55.26 | $120.00 | $75.00 | $33.00 |
| 82 | Metal W-beam guard fence (steel post) (540-7002) | LF | 3,525 | $32.50 | $29.99 | $32.00 | $35.00 | $32.00 |
| 83 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 2 | $2,500.00 | $2,936.29 | $2,500.00 | $2,500.00 | $3,250.00 |
| 84 | Remove metal beam guard fence (542-7001) | LF | 2,200 | $3.25 | $2.42 | $2.75 | $10.00 | $2.00 |
| 85 | Guardrail end treatment (install) (544-7001) | EACH | 28 | $3,500.00 | $2,999.06 | $3,250.00 | $3,500.00 | $3,500.00 |
| 86 | Guardrail end treatment (remove) (544-7003) | EACH | 22 | $300.00 | $241.86 | $250.00 | $500.00 | $300.00 |
| 87 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 10 | $2,500.00 | $2,902.33 | $1,000.00 | $2,500.00 | $1.00 |
| 88 | Crash cushion attenuator (remove) (545-7004) | EACH | 2 | $2,000.00 | $1,451.17 | $1,000.00 | $1,250.00 | $1,200.00 |
| 89 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 2 | $12,000 | $10,158 | $10,000 | $9,000.00 | $12,000 |
| 90 | Wire fence (type C) (552-7003) | LF | 610 | $25.00 | $26.12 | $17.00 | $25.00 | $35.00 |
| 91 | Wire fence (type D) (552-7004) | LF | 650 | $27.00 | $26.12 | $18.00 | $25.00 | $30.00 |
| 92 | Gate (type 2) (552-7007) | EACH | 2 | $2,000.00 | $1,040.00 | $1,200.00 | $2,500.00 | $2,000.00 |
| 93 | Wire fence (water gap) (552-7010) | LF | 60 | $60.00 | $31.44 | $60.00 | $100.00 | $65.00 |
| 94 | Pipe underdrains (type 7) (6") (556-7007) | LF | 425 | $28.00 | $30.72 | $50.00 | $70.00 | $45.00 |
| 95 | Mailbox install-S (WC-post) type 3 (560-7004) | EACH | 8 | $300.00 | $237.02 | $250.00 | $350.00 | $400.00 |
| 96 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 35 | $750.00 | $606.59 | $650.00 | $550.00 | $700.00 |
| 97 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 4 | $900.00 | $794.27 | $825.00 | $700.00 | $850.00 |
| 98 | Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007) | EACH | 2 | $1,000.00 | $960.67 | $1,000.00 | $850.00 | $1,000.00 |
| 99 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 1 | $1,300.00 | $1,149.32 | $1,200.00 | $1,000.00 | $1,100.00 |
| 100 | Install delineator assembly (D-SW)SZ 1(WFLX)GND(BI) (658-7004) | EACH | 49 | $85.00 | $50.31 | $55.00 | $50.00 | $245.00 |
| 101 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 52 | $38.00 | $23.22 | $25.00 | $30.00 | $40.00 |
| 102 | Install OM SM RD sign (1-OM-con)Y (658-7079) | EACH | 18 | $40.00 | $29.99 | $32.00 | $20.00 | $200.00 |
| 103 | Install OM SM RD sign (1-OM-con)R (658-7080) | EACH | 7 | $40.00 | $29.99 | $32.00 | $30.00 | $200.00 |
| 104 | Install OM SM RD sign (1-OM-con)G (658-7084) | EACH | 14 | $40.00 | $29.99 | $32.00 | $20.00 | $200.00 |
| 105 | Install OM SM RD sign (1-OM-con)W (658-7086) | EACH | 3 | $40.00 | $29.99 | $32.00 | $50.00 | $200.00 |
| 106 | Install object marker assembly (OM-2Z)(yflx)GNDHH (658-7251) | EACH | 20 | $107.00 | $243.80 | $255.00 | $200.00 | $310.00 |
| 107 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 71,650 | $0.40 | $0.38 | $0.50 | $0.40 | $0.40 |
| 108 | Work zone pavement marking non-removing (W)24"(solid) (662-7017) | LF | 48 | $12.00 | $9.82 | $11.00 | $11.00 | $10.15 |
| 109 | Work zone pavement marking non-removing (Y)6"(broken) (662-7036) | LF | 2,720 | $0.42 | $0.42 | $0.50 | $0.45 | $0.43 |
| 110 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 53,535 | $0.42 | $0.38 | $0.50 | $0.40 | $0.40 |
| 111 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 81,537 | $0.92 | $0.38 | $0.50 | $0.40 | $0.40 |
| 112 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 432 | $15.00 | $9.82 | $10.00 | $11.00 | $10.15 |
| 113 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 84,788 | $1.00 | $0.38 | $0.50 | $0.40 | $0.40 |
| 114 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 1,272 | $1.35 | $3.59 | $1.00 | $1.50 | $1.00 |
| 115 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 2,600 | $1.60 | $2.66 | $1.00 | $1.50 | $1.00 |
| 116 | Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009) | LF | 1,146 | $1.50 | $0.63 | $0.73 | $1.00 | $0.65 |
| 117 | Reflectorized pavement marking type I(W)(lane drop arrow)(100MIL) (666-7060) | EACH | 4 | $400.00 | $686.88 | $725.00 | $750.00 | $710.00 |
| 118 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 20,070 | $0.26 | $0.47 | $0.50 | $0.50 | $0.49 |
| 119 | Reflectorized pavement marking type II (Y) 6" (broken) (666-7211) | LF | 1,890 | $0.38 | $0.47 | $0.50 | $0.50 | $0.49 |
| 120 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 32,082 | $0.20 | $0.47 | $0.50 | $0.50 | $0.49 |
| 121 | Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266) | LF | 48,195 | $1.00 | $0.95 | $1.00 | $1.00 | $0.98 |
| 122 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 4,240 | $1.00 | $0.65 | $0.70 | $0.70 | $0.67 |
| 123 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 5,040 | $0.55 | $0.58 | $0.60 | $0.60 | $0.60 |
| 124 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 40 | $1.15 | $0.65 | $0.70 | $0.70 | $0.67 |
| 125 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 53,315 | $0.55 | $0.58 | $0.60 | $0.60 | $0.60 |
| 126 | PRFB rumble strip (BLK)(1')(centerline) (668-7002) | LF | 5,290 | $4.60 | $3.19 | $3.50 | $4.00 | $3.30 |
| 127 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 1,305 | $5.00 | $5.08 | $5.50 | $6.00 | $5.25 |
| 128 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 213 | $5.00 | $6.53 | $7.00 | $7.00 | $6.75 |
| 129 | Eliminating existing PM & markers (6") (677-7002) | LF | 39,516 | $0.55 | $0.62 | $2.00 | $1.25 | $1.65 |
| 130 | Preformed in-lane (trans) rumble strip (6024-7001) | LF | 160 | $10.00 | $18.81 | $20.00 | $20.00 | $19.45 |
| 131 | Subsurface util locate (outside rdbed) (7019-7001) | EACH | 6 | $1,500.00 | $1,486.90 | $3,500.00 | $1,500.00 | $1,300.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of September 5, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.