TxDOT contract A00193132 bid tabulation

Rehabilitate Existing Roadway, SH 16 (Mills County Line to .4 Miles S. of CR 140). Let by Texas DOT on September 5, 2025, San Saba, Brownwood District. 4 bids received; low bid $11,074,629 by Allen Keller Company, -21% against the engineer's estimate of $13,990,091.

Owner
Texas DOT
Letting
05 SEP 2025
Pay items
131
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Allen Keller Company$11,074,629Low-21%
2CK Newberry, LLC$11,885,997+7.0%-15%
3Big Creek Construction, LTD.$12,387,672+12%-11%
4Texas Materials Group, Inc.$13,973,452+26%0.0%
TxDOT contract A00193132: bids by rank

Engineer's estimate: $13,990,091.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Allen Keller Company2. CK Newberry, LLC3. Big Creek Construction, LTD.4. Texas Materials Group, Inc.
1Preparing row (100-7002)STA240$1,100.00$502.07$500.00$2,000.00$797.00
2Removing concrete (driveways) (104-7011)SY25$30.00$73.64$50.00$50.00$71.00
3Excavation (roadway) (110-7001)CY20,497$16.25$5.77$15.00$17.00$12.75
4Embankment (final)(DC)(type C) (132-7006)CY24,553$18.00$3.32$18.00$17.00$10.30
5Blading (150-7002)HR40$170.00$468.68$175.00$150.00$155.00
6Broadcast seed (temporary_warm) (164-7005)SY26,295$0.20$0.17$0.20$0.20$0.18
7Broadcast seed (temporary_cool) (164-7006)SY26,295$0.20$0.17$0.20$0.20$0.18
8Drill seed (permanent_rural_sand) (164-7009)SY52,589$0.20$0.17$0.20$0.20$0.18
9Vegetative watering (168-7001)TGL578.50$25.00$46.50$25.00$15.00$70.25
10Proof rolling (216-7001)HR40$111.00$147.42$100.00$150.00$143.25
11FL BS (compacted in place)(type A GR 1-2) (10") (247-7090)SY120,269$22.00$17.44$16.00$17.00$21.75
12FL BS (compacted in place)(tya GR1-2)(final pos) (247-7176)CY11,151$83.00$43.47$50.00$50.00$64.50
13FL BS (compacted in place)(type D GR 4)(final pos) (247-7190)CY2,500$75.00$55.27$95.00$125.00$87.40
14Rework BS metal (type C)(8")(density control) (251-7052)SY121,502$2.75$0.56$1.00$1.00$1.85
15Cement (275-7001)TON882$245.00$243.11$235.00$250.00$275.00
16Cement TRT (existing material)(8") (275-7003)SY104,249$4.00$1.75$2.00$2.50$1.75
17Prime coat (MC-30) (310-7004)GAL18,597$6.00$5.15$5.00$5.50$8.15
18Asphalt (RC-250) (316-7016)GAL23,556$5.00$5.15$4.00$5.00$6.80
19Asphalt (AC-20-5TR or CRS-2P) (316-7086)GAL66,453$4.75$4.68$4.25$4.00$5.05
20Aggregate (type-B, GR-4)(sac-B) (316-7173)CY563$110.00$154.92$140.00$150.00$235.00
21Aggregate (type-PB, GR-4)(sac-B) (316-7211)CY1,476$130.00$160.60$175.00$130.00$215.25
22D-GR HMA type-B PG64-22 (341-7001)TON6,524$125.00$107.70$130.00$102.00$159.00
23SP mixes SP-D sac-B PG76-22 (344-7065)TON535$140.00$126.47$165.00$150.00$245.00
24Plane & text asphalt concrete pavement(0" to 10") (354-7008)SY8,813$7.50$8.99$5.00$12.00$17.70
25Planing asphalt concrete pavement(0" to 3") (354-7033)SY802$3.00$5.39$5.00$7.00$26.50
26Planing asphalt concrete pavement(0" to 4") (354-7034)SY802$3.50$5.60$5.00$8.00$26.00
27Cem stabil BKFL (400-7010)CY400$220.00$199.43$250.00$180.00$275.00
28Flowable backfill (401-7001)CY113$280.00$234.70$375.00$220.00$290.00
29Trench excavation protection (402-7001)LF111$31.00$251.85$35.00$30.00$1.00
30Temporary special shoring (403-7001)SF8,335$25.00$38.30$22.00$15.00$28.00
31Class C concrete (rail foundation) (420-7052)CY11.10$2,500.00$757.85$1,100.00$1,500.00$1,150.00
32Penetrating concrete surface treatment (428-7001)SY16$60.00$29.50$250.00$75.00$100.00
33Riprap (concrete)(4 in) (432-7001)CY295$550.00$645.74$600.00$650.00$710.00
34Riprap (concrete)(5 in) (432-7002)CY461$600.00$645.74$550.00$650.00$718.00
35Riprap (mow strip)(4 in) (432-7013)CY446$550.00$516.66$650.00$650.00$725.00
36Riprap (stone common)(dry)(18 in) (432-7033)CY248$225.00$164.03$180.00$150.00$290.00
37Cleaning and sealing existing joints (CL3) (438-7004)LF201$70.00$58.04$75.00$80.00$62.00
38Rail (type T221)(mod) (450-7067)LF36.70$200.00$147.46$500.00$350.00$235.00
39Retrofit rail (type T631) (451-7020)LF510$115.00$91.91$105.00$150.00$140.00
40Waterproofing (type 10) (458-7007)SY95$189.00$108.14$60.00$75.00$200.00
41CMP (gal steel 24 in) (460-7005)LF1,969$90.00$147.33$80.00$75.00$68.00
42Concrete box culvert (3 FT X 2 FT) (462-7001)LF62$390.00$449.35$400.00$400.00$390.00
43Concrete box culvert (4 FT X 4 FT) (462-7005)LF130$475.00$584.11$500.00$500.00$868.00
44Concrete box culvert (8 FT X 6 FT) (462-7023)LF54$1,200.00$1,299.46$1,200.00$1,000.00$1,300.00
45Concrete box culvert (8 FT X 6 FT)(extend) (462-7078)LF32$1,500.00$1,718.14$1,500.00$1,500.00$1,380.00
46Concrete box culvert (8 FT X 8 FT)(extend) (462-7080)LF60$1,575.00$1,963.89$1,600.00$1,700.00$1,640.00
47Concrete box culvert (10 FT X 10 FT)(extend) (462-7093)LF28$1,900.00$2,209.63$2,100.00$2,000.00$2,770.00
48RC pipe (CL III)(18 in) (464-7003)LF82$140.00$215.38$120.00$100.00$82.00
49RC pipe (CL III)(24 in) (464-7005)LF387$120.00$234.88$125.00$122.00$100.00
50Wingwall (PW - 1) (HW=10 FT) (466-7180)EACH4$92,000$18,120$60,000$55,000$50,000
51Wingwall (PW - 1) (HW=14 FT) (466-7184)EACH2$115,000$43,955$125,000$120,000$100,000
52Set (type I)(S= 3 FT)(HW= 3 FT)(3:1)(C) (467-7040)EACH4$9,000.00$3,287.39$8,000.00$5,000.00$9,300.00
53Set (type I)(S= 4 FT)(HW= 4 FT)(3:1)(C) (467-7071)EACH2$13,000$5,047.52$16,000$10,000$10,600
54Set (type I)(S= 4 FT)(HW= 5 FT)(3:1)(C) (467-7075)EACH10$19,700$6,507.99$6,000.00$5,000.00$10,000
55Set (type II) (24 in) (CMP) (6: 1) (P) (467-7324)EACH70$1,930.00$3,604.52$2,000.00$1,500.00$1,500.00
56Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH3$2,425.00$3,149.43$2,800.00$1,750.00$1,600.00
57Removing structure (pipe) (496-7007)LF77$24.00$45.64$60.00$35.00$12.00
58Removing structure (pipe) (496-7037)EACH10$800.00$702.82$2,500.00$650.00$200.00
59Mobilization (500-7001)LS1$1,150,000$1,052,000$1,100,000$1,100,000$1,175,000
60Barricades, signs and traffic handling (502-7001)MO24$10,000$10,115$5,000.00$5,000.00$2,300.00
61Portable changeable message sign (503-7001)DAY180$170.00$104.46$100.00$150.00$118.00
62TMA (stationary) (505-7001)DAY241$205.00$227.34$250.00$300.00$110.00
63TMA (mobile operation) (505-7003)DAY62$250.00$727.64$200.00$550.00$110.00
64Rock filter dams (install) (type 3) (506-7003)LF580$80.00$67.72$75.00$80.00$70.00
65Rock filter dams (remove) (506-7011)LF1,480$16.00$14.52$16.00$12.00$15.00
66Construction exits (install) (type 1) (506-7020)SY1,170$32.25$33.86$10.00$25.00$35.00
67Construction exits (remove) (506-7024)SY1,170$11.00$9.67$5.00$10.00$10.00
68Backhoe work (erosion & sediment control) (506-7030)HR68$182.00$156.61$125.00$150.00$222.00
69Temporary sediment control fence (install) (506-7039)LF15,413$4.25$4.11$4.50$4.00$4.25
70Temporary sediment control fence (remove) (506-7041)LF15,413$1.00$0.28$0.50$1.00$0.29
71Biodegradable erosion control logs (install) (18") (506-7045)LF560$10.00$7.74$10.00$7.00$8.00
72Biodegradable erosion control logs (remove) (506-7046)LF560$2.65$1.93$2.00$1.00$2.00
73Rock filter dams (install) (type 2) 6:1 (506-7048)LF900$80.00$62.88$70.00$60.00$65.00
74Constructing detours (508-7001)SY28,057$29.00$23.21$25.00$35.00$35.50
75One-way traffic control (port traffic signal) (510-7003)MO9$6,000.00$4,102.96$7,500.00$5,000.00$8,160.00
76Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001)LF390$70.00$107.54$125.00$50.00$112.00
77Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025)LF1,470$25.00$18.51$50.00$15.00$23.00
78Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049)LF390$30.00$23.26$100.00$45.00$59.00
79Driveways (concrete) (530-7006)SY97$108.00$100.86$150.00$150.00$145.00
80Driveways (surface treat) (530-7016)SY3,852$30.00$17.76$25.00$25.00$90.00
81Turnouts (ACP) (530-7018)SY83$100.00$55.26$120.00$75.00$33.00
82Metal W-beam guard fence (steel post) (540-7002)LF3,525$32.50$29.99$32.00$35.00$32.00
83Metal beam guard fence trans (thrie-beam) (540-7005)EACH2$2,500.00$2,936.29$2,500.00$2,500.00$3,250.00
84Remove metal beam guard fence (542-7001)LF2,200$3.25$2.42$2.75$10.00$2.00
85Guardrail end treatment (install) (544-7001)EACH28$3,500.00$2,999.06$3,250.00$3,500.00$3,500.00
86Guardrail end treatment (remove) (544-7003)EACH22$300.00$241.86$250.00$500.00$300.00
87Crash cushion attenuator (move & reset) (545-7002)EACH10$2,500.00$2,902.33$1,000.00$2,500.00$1.00
88Crash cushion attenuator (remove) (545-7004)EACH2$2,000.00$1,451.17$1,000.00$1,250.00$1,200.00
89Crash cushion attenuator (install)(S)(N)(TL3) (545-7014)EACH2$12,000$10,158$10,000$9,000.00$12,000
90Wire fence (type C) (552-7003)LF610$25.00$26.12$17.00$25.00$35.00
91Wire fence (type D) (552-7004)LF650$27.00$26.12$18.00$25.00$30.00
92Gate (type 2) (552-7007)EACH2$2,000.00$1,040.00$1,200.00$2,500.00$2,000.00
93Wire fence (water gap) (552-7010)LF60$60.00$31.44$60.00$100.00$65.00
94Pipe underdrains (type 7) (6") (556-7007)LF425$28.00$30.72$50.00$70.00$45.00
95Mailbox install-S (WC-post) type 3 (560-7004)EACH8$300.00$237.02$250.00$350.00$400.00
96Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH35$750.00$606.59$650.00$550.00$700.00
97Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH4$900.00$794.27$825.00$700.00$850.00
98Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007)EACH2$1,000.00$960.67$1,000.00$850.00$1,000.00
99Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031)EACH1$1,300.00$1,149.32$1,200.00$1,000.00$1,100.00
100Install delineator assembly (D-SW)SZ 1(WFLX)GND(BI) (658-7004)EACH49$85.00$50.31$55.00$50.00$245.00
101Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019)EACH52$38.00$23.22$25.00$30.00$40.00
102Install OM SM RD sign (1-OM-con)Y (658-7079)EACH18$40.00$29.99$32.00$20.00$200.00
103Install OM SM RD sign (1-OM-con)R (658-7080)EACH7$40.00$29.99$32.00$30.00$200.00
104Install OM SM RD sign (1-OM-con)G (658-7084)EACH14$40.00$29.99$32.00$20.00$200.00
105Install OM SM RD sign (1-OM-con)W (658-7086)EACH3$40.00$29.99$32.00$50.00$200.00
106Install object marker assembly (OM-2Z)(yflx)GNDHH (658-7251)EACH20$107.00$243.80$255.00$200.00$310.00
107Work zone pavement marking non-removing (W)6"(solid) (662-7008)LF71,650$0.40$0.38$0.50$0.40$0.40
108Work zone pavement marking non-removing (W)24"(solid) (662-7017)LF48$12.00$9.82$11.00$11.00$10.15
109Work zone pavement marking non-removing (Y)6"(broken) (662-7036)LF2,720$0.42$0.42$0.50$0.45$0.43
110Work zone pavement marking non-removing (Y)6"(solid) (662-7038)LF53,535$0.42$0.38$0.50$0.40$0.40
111Work zone pavement marking removing (W)6"(solid) (662-7068)LF81,537$0.92$0.38$0.50$0.40$0.40
112Work zone pavement marking removing (W)24"(solid) (662-7077)LF432$15.00$9.82$10.00$11.00$10.15
113Work zone pavement marking removing (Y)6"(solid) (662-7100)LF84,788$1.00$0.38$0.50$0.40$0.40
114Work zone pavement marking SHT terminal (tab)type W (662-7112)EACH1,272$1.35$3.59$1.00$1.50$1.00
115Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114)EACH2,600$1.60$2.66$1.00$1.50$1.00
116Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009)LF1,146$1.50$0.63$0.73$1.00$0.65
117Reflectorized pavement marking type I(W)(lane drop arrow)(100MIL) (666-7060)EACH4$400.00$686.88$725.00$750.00$710.00
118Reflectorized pavement marking type II (W) 6" (solid) (666-7175)LF20,070$0.26$0.47$0.50$0.50$0.49
119Reflectorized pavement marking type II (Y) 6" (broken) (666-7211)LF1,890$0.38$0.47$0.50$0.50$0.49
120Reflectorized pavement marking type II (Y) 6" (solid) (666-7213)LF32,082$0.20$0.47$0.50$0.50$0.49
121Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266)LF48,195$1.00$0.95$1.00$1.00$0.98
122Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408)LF4,240$1.00$0.65$0.70$0.70$0.67
123Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF5,040$0.55$0.58$0.60$0.60$0.60
124Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420)LF40$1.15$0.65$0.70$0.70$0.67
125Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF53,315$0.55$0.58$0.60$0.60$0.60
126PRFB rumble strip (BLK)(1')(centerline) (668-7002)LF5,290$4.60$3.19$3.50$4.00$3.30
127Reflectorized pavement marker type II-A-A (672-7004)EACH1,305$5.00$5.08$5.50$6.00$5.25
128Reflectorized pavement marker type II-C-R (672-7006)EACH213$5.00$6.53$7.00$7.00$6.75
129Eliminating existing PM & markers (6") (677-7002)LF39,516$0.55$0.62$2.00$1.25$1.65
130Preformed in-lane (trans) rumble strip (6024-7001)LF160$10.00$18.81$20.00$20.00$19.45
131Subsurface util locate (outside rdbed) (7019-7001)EACH6$1,500.00$1,486.90$3,500.00$1,500.00$1,300.00
TxDOT contract A00193132: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of September 5, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy