TxDOT contract A00186521 bid tabulation
Bridge Replacement, LA PALOMA (LA PALOMA AT GALLINA SLOUGH CREEK to .). Let by Texas DOT on April 7, 2026, Zavala, Laredo District. 5 bids received; low bid $1,523,016 by Acee Construction LLC., -6.7% against the engineer's estimate of $1,631,537.
- Owner
- Texas DOT
- Letting
- 07 APR 2026
- Pay items
- 72
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Acee Construction LLC. | $1,523,016 | Low | -7.0% |
| 2 | Presidio Contracting, LLC | $1,591,656 | +5.0% | -2.0% |
| 3 | J. Carroll Weaver, Inc. | $1,824,936 | +20% | +12% |
| 4 | Acme Bridge Company, Inc. | $1,857,167 | +22% | +14% |
| 5 | CK Newberry, LLC | $2,491,325 | +64% | +53% |
Engineer's estimate: $1,631,537.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Acee Construction LLC. | 2. Presidio Contracting, LLC | 3. J. Carroll Weaver, Inc. | 4. Acme Bridge Company, Inc. | 5. CK Newberry, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 7 | $3,500.00 | $2,250.00 | $9,615.00 | $1,761.13 | $3,310.00 | $5,000.00 |
| 2 | Tree protection (install) (100-7013) | EACH | 6 | $450.00 | $315.25 | $705.00 | $1,110.00 | $1,060.00 | $1,000.00 |
| 3 | Tree protection (remove) (100-7015) | EACH | 6 | $120.00 | $150.35 | $215.00 | $888.00 | $318.00 | $500.00 |
| 4 | Removing concrete (flume) (104-7041) | SY | 266 | $39.90 | $25.25 | $19.73 | $20.90 | $35.00 | |
| 5 | Excavation (roadway) (110-7001) | CY | 342.00 | $35.00 | $25.00 | $58.15 | $41.92 | $44.00 | $125.00 |
| 6 | Excavation (channel) (110-7002) | CY | 310.40 | $30.00 | $25.00 | $59.60 | $34.64 | $39.70 | $100.00 |
| 7 | Embankment (final)(OC)(type A) (132-7001) | CY | 484.40 | $45.00 | $35.00 | $26.60 | $14.64 | $60.00 | $60.00 |
| 8 | Backfill (type B) (134-7002) | STA | 4 | $264.60 | $1,500.00 | $1,218.64 | $332.00 | $2,000.00 | |
| 9 | Blading (150-7002) | HR | 24 | $100.00 | $55.00 | $65.00 | $101.55 | $100.00 | $200.00 |
| 10 | Drill seed (permanent_rural_clay) (164-7042) | ACRE | 0.85 | $1,500.00 | $5,061.00 | $5,230.00 | $5,350.20 | $5,114.48 | $6,000.00 |
| 11 | Drill seed (temporary_warm) (164-7045) | ACRE | 0.85 | $1,500.00 | $4,368.00 | $4,515.00 | $4,617.60 | $4,414.15 | $6,000.00 |
| 12 | Proof rolling (216-7001) | HR | 16 | $120.00 | $38.50 | $25.00 | $76.17 | $107.00 | $100.00 |
| 13 | FL BS (compacted in place)(tya GR1-2)(final pos) (247-7176) | CY | 337 | $160.00 | $125.00 | $125.60 | $115.42 | $127.00 | $200.00 |
| 14 | Prime coat (MC-30) (310-7004) | GAL | 404.37 | $18.00 | $21.15 | $13.00 | $11.31 | $12.30 | $20.00 |
| 15 | Lra pavement type-I GR-A (330-7002) | TON | 96 | $160.00 | $210.00 | $475.00 | $157.79 | $459.00 | $225.00 |
| 16 | D-GR HMA type-C sac-A PG76-22 (341-7031) | TON | 222.30 | $250.00 | $310.00 | $366.75 | $298.00 | $300.00 | |
| 17 | Cem stabil BKFL (400-7010) | CY | 28 | $250.00 | $145.00 | $300.00 | $330.25 | $436.00 | $400.00 |
| 18 | Flowable backfill (401-7001) | CY | 25 | $350.00 | $145.00 | $345.00 | $428.20 | $405.00 | $500.00 |
| 19 | Temporary special shoring (403-7001) | SF | 600 | $18.00 | $7.00 | $20.41 | $1.05 | $30.00 | |
| 20 | Drilled shaft (24 in) (416-7004) | LF | 742 | $240.00 | $285.00 | $301.10 | $428.82 | $295.00 | $500.00 |
| 21 | Class C concrete (abutment) (420-7012) | CY | 105.60 | $1,250.00 | $1,461.85 | $1,060.00 | $998.12 | $1,090.00 | $2,250.00 |
| 22 | Reinforced concrete slab (slab beam) (422-7007) | SF | 1,040 | $35.00 | $27.95 | $26.85 | $54.90 | $41.60 | $60.00 |
| 23 | Approach slab (422-7013) | CY | 38.50 | $665.00 | $1,195.80 | $932.00 | $943.26 | $1,090.00 | $1,500.00 |
| 24 | Prestressed concrete slab beam (5SB15) (425-7019) | LF | 197.50 | $325.00 | $429.05 | $322.00 | $361.13 | $439.00 | $325.00 |
| 25 | Riprap (concrete)(4 in) (432-7001) | CY | 20 | $580.00 | $670.00 | $760.26 | $873.00 | $800.00 | |
| 26 | Riprap (mow strip)(4 in) (432-7013) | CY | 46 | $650.00 | $580.00 | $690.00 | $832.49 | $921.00 | $900.00 |
| 27 | Riprap (stone protection)(12 in) (432-7041) | CY | 98 | $210.00 | $210.00 | $250.00 | $200.83 | $500.00 | $325.00 |
| 28 | Rail (type T631) (450-7020) | LF | 140 | $110.00 | $102.55 | $110.00 | $181.41 | $130.00 | $250.00 |
| 29 | Armor joint (sealed) (454-7003) | LF | 44 | $100.00 | $208.05 | $200.00 | $105.45 | $264.00 | $250.00 |
| 30 | Removing structure (pipe) (496-7007) | LF | 216 | $17.35 | $72.00 | $24.30 | $15.70 | $100.00 | |
| 31 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 1 | $25,000 | $12,500 | $25,750 | $73,515 | $10,000 | $75,000 |
| 32 | Remove STR (gabion) (496-7018) | LF | 80 | $11.75 | $60.00 | $65.62 | $34.00 | $100.00 | |
| 33 | Mobilization (500-7001) | LS | 1 | $125,230 | $152,000 | $154,785 | $173,034 | $168,000 | $225,000 |
| 34 | Barricades, signs and traffic handling (502-7001) | MO | 8 | $10,000 | $3,950.00 | $4,135.00 | $2,775.00 | $2,000.00 | $10,000 |
| 35 | Portable changeable message sign (503-7002) | EACH | 4 | $10,000 | $12,500 | $6,500.00 | $6,105.00 | $18,000 | $10,000 |
| 36 | Rock filter dams (install) (type 4) (506-7004) | LF | 200 | $50.00 | $67.20 | $69.45 | $67.00 | $67.90 | $25.00 |
| 37 | Rock filter dams (remove) (506-7011) | LF | 200 | $12.00 | $16.50 | $17.00 | $11.10 | $16.70 | $12.00 |
| 38 | Construction exits (install) (type 1) (506-7020) | SY | 233 | $30.00 | $30.80 | $32.00 | $22.20 | $31.10 | $30.00 |
| 39 | Construction exits (remove) (506-7024) | SY | 233 | $10.00 | $10.35 | $10.00 | $8.88 | $10.40 | $12.00 |
| 40 | Backhoe work (erosion & sediment control) (506-7030) | HR | 40 | $75.00 | $40.00 | $125.00 | $60.93 | $167.00 | $100.00 |
| 41 | Temporary sediment control fence (install) (506-7039) | LF | 800 | $3.50 | $6.30 | $6.50 | $7.64 | $6.40 | $12.00 |
| 42 | Temporary sediment control fence (remove) (506-7041) | LF | 800 | $1.50 | $2.10 | $2.15 | $4.26 | $2.10 | $6.00 |
| 43 | Constructing detours (type 1) (508-7003) | SY | 715 | $150.00 | $55.00 | $54.75 | $120.31 | $114.00 | $100.00 |
| 44 | Constructing detours (type 2) (508-7004) | SY | 949 | $70.00 | $44.25 | $95.32 | $138.00 | $80.00 | |
| 45 | One-way traffic control (flagger cont) (510-7001) | HR | 80 | $147.00 | $75.00 | $63.33 | $100.00 | $60.00 | |
| 46 | One-way traffic control (port traffic signal) (510-7003) | MO | 5 | $7,644.00 | $5,140.00 | $4,059.11 | $4,190.00 | $10,000 | |
| 47 | Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009) | LF | 360 | $35.00 | $33.60 | $31.40 | $30.29 | $37.10 | $60.00 |
| 48 | Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010) | LF | 160 | $40.00 | $31.65 | $31.40 | $30.29 | $30.60 | $110.00 |
| 49 | Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057) | LF | 360 | $20.00 | $25.30 | $17.55 | $30.29 | $37.00 | $60.00 |
| 50 | Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058) | LF | 160 | $25.00 | $21.95 | $17.55 | $30.29 | $31.60 | $100.00 |
| 51 | Concrete curb (type III) (529-7004) | LF | 36 | $13.50 | $265.00 | $84.44 | $96.50 | $200.00 | |
| 52 | Metal W-beam guard fence (timber post) (540-7001) | LF | 314 | $35.00 | $29.95 | $31.00 | $33.38 | $31.80 | $60.00 |
| 53 | Downstream anchor terminal section (540-7015) | EACH | 2 | $1,725.15 | $1,780.00 | $2,740.27 | $1,700.00 | $1,500.00 | |
| 54 | Guardrail end treatment (install) (544-7001) | EACH | 6 | $3,500.00 | $3,888.15 | $4,020.00 | $5,037.21 | $3,710.00 | $4,000.00 |
| 55 | Wire fence (type C) (552-7003) | LF | 520 | $15.00 | $58.80 | $30.00 | $27.75 | $15.90 | $40.00 |
| 56 | Wire fence (water gap) (552-7010) | LF | 40 | $50.00 | $269.50 | $105.00 | $333.00 | $37.10 | $120.00 |
| 57 | Wire fence (remove) (552-7011) | LF | 560 | $10.00 | $7.85 | $5.00 | $11.10 | $5.30 | $20.00 |
| 58 | Remove SM RD SN sup&AM (sign only) (644-7075) | EACH | 4 | $100.00 | $98.00 | $100.00 | $194.25 | $106.00 | $600.00 |
| 59 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 38 | $50.00 | $117.60 | $27.00 | $84.36 | $31.80 | $75.00 |
| 60 | Install object marker assembly (OM-2Z)(WFLX)(wap) (658-7062) | EACH | 6 | $150.00 | $352.80 | $163.00 | $138.75 | $79.60 | $75.00 |
| 61 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 6,000 | $1.95 | $0.90 | $0.72 | $0.45 | $2.00 | |
| 62 | Work zone pavement marking SHT terminal (tab)type Y (662-7113) | EACH | 150 | $2.65 | $5.30 | $2.22 | $1.85 | $1.00 | |
| 63 | Type I high perf PM (Y)6"(solid)(100MIL) (666-7305) | LF | 2,000 | $4.75 | $2.15 | $2.22 | $2.05 | $3.00 | |
| 64 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 50 | $15.70 | $27.50 | $8.88 | $26.50 | $30.00 | |
| 65 | Precast C-span culverts (4066-7001) | LF | 34 | $3,350.00 | $5,400.00 | $6,262.71 | $8,000.00 | $8,750.00 | |
| 66 | Asphalt (AC-15P) (316-7005) | GAL | 0 | $274.40 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| 67 | Lra pavement type-I GR-A (330-7002) | TON | 0 | $254.20 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| 68 | Drilled shaft (24 in) (416-7004) | LF | 0 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |
| 69 | Drilled shaft (30 in) (416-7005) | LF | 0 | $394.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| 70 | Class C concrete (abutment) (420-7012) | CY | 0 | $1,300.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| 71 | Prestressed concrete deck slab beam (6DS20) (425-7020) | LF | 0 | $318.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| 72 | Rail (type T631) (450-7020) | LF | 0 | $110.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of April 7, 2026. Compiled by Mirage Metrics.