TxDOT contract A00193521 bid tabulation
Hazard Elimination & Safety, FM 665 (1600 FT W OF CR75 to 1600 FT E OF CR75). Let by Texas DOT on November 4, 2026, Nueces, Corpus Christi District. 5 bids received; low bid $3,833,265 by J E Construction Services, LLC, -20% against the engineer's estimate of $4,792,153.
- Owner
- Texas DOT
- Letting
- 04 NOV 2026
- Pay items
- 88
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | J E Construction Services, LLC | $3,833,265 | Low | -20% |
| 2 | Anderson Columbia Co., Inc. | $3,837,222 | 0.0% | -20% |
| 3 | CK Newberry, LLC | $4,616,801 | +20% | -4.0% |
| 4 | STX Civil | $4,817,402 | +26% | +1.0% |
| 5 | Texas Materials Group, Inc. | $4,943,316 | +29% | +3.0% |
Engineer's estimate: $4,792,153.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. J E Construction Services, LLC | 2. Anderson Columbia Co., Inc. | 3. CK Newberry, LLC | 4. STX Civil | 5. Texas Materials Group, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 28 | $3,500.00 | $1,160.00 | $430.00 | $500.00 | $697.50 | $969.00 |
| 2 | Removing concrete (riprap) (104-7007) | CY | 8 | $75.00 | $208.00 | $115.00 | $325.00 | $419.77 | $150.00 |
| 3 | Remove stab base and asphalt pavement (6"-20") (105-7123) | SY | 7,459 | $8.00 | $8.00 | $17.50 | $6.50 | $13.57 | $13.00 |
| 4 | Excavation (roadway) (110-7001) | CY | 8,898 | $9.00 | $8.00 | $7.75 | $15.00 | $9.02 | $17.50 |
| 5 | Embankment (final)(DC)(type C) (132-7006) | CY | 5,427 | $9.00 | $7.00 | $7.75 | $26.00 | $10.48 | $22.00 |
| 6 | Drill seed (permanent_rural_clay) (164-7042) | ACRE | 5.89 | $1,500.00 | $2,210.00 | $2,490.00 | $3,000.00 | $3,649.84 | $2,800.00 |
| 7 | Vegetative watering (168-7001) | TGL | 521 | $25.00 | $28.00 | $44.00 | $20.00 | $54.95 | $25.00 |
| 8 | FL BS (cip)(type A GR 1-2 or 5) final pos (247-7348) | CY | 5,473 | $75.00 | $54.00 | $86.00 | $115.00 | $135.76 | $120.00 |
| 9 | Lime (com or QK)(slurry) (260-7005) | TON | 400 | $350.00 | $314.00 | $395.00 | $350.00 | $405.82 | $410.00 |
| 10 | Lime TRT (subgrade) (8") (260-7020) | SY | 20,157 | $4.00 | $3.00 | $5.40 | $5.00 | $3.43 | $6.40 |
| 11 | Prime coat (MC-30) (310-7004) | GAL | 3,788 | $5.00 | $6.00 | $5.30 | $5.00 | $6.47 | $6.70 |
| 12 | Asphalt(AC-15P, HFRS-2P or CRS-2P) (316-7070) | GAL | 11,645 | $2.75 | $4.00 | $3.90 | $4.50 | $5.30 | $3.60 |
| 13 | Aggregate (type-PB, GR-4S or 4)(sac-B) (316-7212) | CY | 305 | $115.00 | $199.00 | $205.00 | $175.00 | $160.40 | $220.00 |
| 14 | D-GR HMA type-B sac-B PG64-22 (341-7002) | TON | 4,125 | $105.00 | $123.00 | $111.00 | $110.00 | $138.64 | $130.00 |
| 15 | D-GR HMA type D sac-B PG70-22 (341-7050) | TON | 3,622 | $115.00 | $132.00 | $122.00 | $126.00 | $126.50 | $140.00 |
| 16 | Tack coat (341-7082) | GAL | 2,615 | $4.00 | $5.00 | $3.40 | $4.00 | $3.95 | $4.70 |
| 17 | Planing asphalt concrete pavement(0" to 2") (354-7032) | SY | 14,332 | $1.50 | $2.00 | $2.80 | $2.00 | $2.85 | $2.10 |
| 18 | Cem stabil BKFL (400-7010) | CY | 57 | $75.00 | $60.00 | $128.00 | $250.00 | $190.23 | $150.00 |
| 19 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 80 | $300.00 | $234.00 | $266.00 | $250.00 | $317.05 | $280.00 |
| 20 | Riprap (concrete)(5 in) (432-7002) | CY | 5 | $600.00 | $724.00 | $798.00 | $1,000.00 | $602.64 | $1,500.00 |
| 21 | Riprap (concrete)(6 in) (432-7003) | CY | 6 | $600.00 | $732.00 | $706.00 | $1,100.00 | $602.64 | $1,300.00 |
| 22 | Riprap (concrete)(CL B) (432-7005) | CY | 2.80 | $800.00 | $717.00 | $1,220.00 | $1,200.00 | $777.15 | $2,500.00 |
| 23 | RC pipe (CL III)(18 in) (464-7003) | LF | 88 | $100.00 | $84.00 | $82.00 | $125.00 | $59.28 | $140.00 |
| 24 | RC pipe (CL III)(24 in) (464-7005) | LF | 56 | $105.00 | $98.00 | $121.00 | $150.00 | $69.50 | $93.00 |
| 25 | RC pipe (CL III)(30 in) (464-7007) | LF | 99 | $125.00 | $121.00 | $188.00 | $160.00 | $207.41 | $400.00 |
| 26 | Set (type II) (18 in) (RCP) (6: 1) (C) (467-7307) | EACH | 2 | $2,100.00 | $4,036.00 | $2,050.00 | $3,500.00 | $1,404.72 | $1,800.00 |
| 27 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 2 | $3,100.00 | $4,287.00 | $2,450.00 | $4,000.00 | $1,593.67 | $2,100.00 |
| 28 | Set (type II) (30 in) (RCP) (3: 1) (C) (467-7345) | EACH | 9 | $2,500.00 | $4,279.00 | $2,810.00 | $4,250.00 | $2,025.76 | $2,700.00 |
| 29 | Set (type II) (30 in) (RCP) (4: 1) (C) (467-7346) | EACH | 9 | $3,000.00 | $4,514.00 | $2,810.00 | $4,750.00 | $2,025.76 | $3,000.00 |
| 30 | Clean existing culverts (480-7001) | EACH | 1 | $1,500.00 | $2,146.00 | $2,720.00 | $10,000 | $1,902.28 | $3,400.00 |
| 31 | Removing structure (headwall) (496-7006) | EACH | 2 | $5,000.00 | $3,586.00 | $1,470.00 | $2,500.00 | $3,728.47 | $2,400.00 |
| 32 | Removing structure (pipe) (496-7007) | LF | 40 | $20.00 | $26.00 | $30.00 | $25.00 | $58.26 | $52.00 |
| 33 | Mobilization (500-7001) | LS | 1 | $325,000 | $327,944 | $236,600 | $400,000 | $246,612 | $435,000 |
| 34 | Barricades, signs and traffic handling (502-7001) | MO | 14 | $5,000.00 | $1,670.00 | $6,620.00 | $4,000.00 | $5,309.86 | $3,700.00 |
| 35 | Portable changeable message sign (503-7002) | EACH | 3 | $7,500.00 | $3,511.00 | $13,800 | $4,000.00 | $3,170.47 | $28,400 |
| 36 | TMA (stationary) (505-7001) | DAY | 18 | $150.00 | $301.00 | $578.00 | $250.00 | $296.82 | $950.00 |
| 37 | TMA (mobile operation) (505-7003) | DAY | 36 | $200.00 | $587.00 | $10.00 | $25.00 | $1,176.88 | $950.00 |
| 38 | Rock filter dams (install) (type 2) (506-7002) | LF | 58 | $30.00 | $76.00 | $85.00 | $75.00 | $93.08 | $96.00 |
| 39 | Rock filter dams (remove) (506-7011) | LF | 58 | $15.00 | $44.00 | $51.00 | $20.00 | $23.72 | $58.00 |
| 40 | Construction exits (install) (type 1) (506-7020) | SY | 112 | $35.00 | $62.00 | $17.00 | $15.00 | $56.94 | $120.00 |
| 41 | Construction exits (remove) (506-7024) | SY | 112 | $25.00 | $19.00 | $12.00 | $5.00 | $13.57 | $10.75 |
| 42 | Temporary sediment control fence (install) (506-7039) | LF | 203 | $5.00 | $4.00 | $5.65 | $10.00 | $9.45 | $6.50 |
| 43 | Temporary sediment control fence (remove) (506-7041) | LF | 203 | $2.00 | $3.00 | $3.40 | $2.00 | $1.27 | $3.90 |
| 44 | Constructing detours (508-7001) | SY | 14,413 | $125.00 | $59.00 | $49.00 | $70.00 | $71.78 | $65.00 |
| 45 | Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001) | LF | 3,570 | $20.00 | $31.00 | $28.00 | $45.00 | $92.58 | $26.00 |
| 46 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 2,790 | $12.00 | $15.00 | $15.00 | $17.00 | $6.34 | $16.00 |
| 47 | Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049) | LF | 3,570 | $15.00 | $11.00 | $17.00 | $35.00 | $5.07 | $28.00 |
| 48 | Driveways (ACP) (530-7010) | SY | 471 | $50.00 | $74.00 | $85.00 | $50.00 | $79.27 | $71.00 |
| 49 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 11,096 | $0.25 | $1.00 | $0.65 | $0.40 | $0.41 | $0.45 |
| 50 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 5,444 | $0.25 | $1.00 | $1.05 | $0.50 | $0.41 | $0.55 |
| 51 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 4 | $1,000.00 | $1,504.00 | $1,940.00 | $1,500.00 | $1,404.25 | $2,000.00 |
| 52 | Crash cushion attenuator (remove) (545-7004) | EACH | 6 | $700.00 | $1,244.00 | $1,690.00 | $1,500.00 | $1,145.47 | $1,300.00 |
| 53 | Cca (install)(N)(TL3)(work zone) (545-7018) | EACH | 6 | $8,000.00 | $8,661.00 | $2,360.00 | $8,500.00 | $12,418 | $11,000 |
| 54 | Remove RD IL asm (trans-base) (610-7009) | EACH | 6 | $1,000.00 | $551.00 | $622.00 | $550.00 | $767.25 | $640.00 |
| 55 | In RD IL (type SA) 50T-10 (400W EQ) LED (610-7198) | EACH | 8 | $12,000 | $5,766.00 | $6,500.00 | $5,750.00 | $8,528.56 | $6,700.00 |
| 56 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 1,640 | $22.00 | $10.00 | $11.00 | $10.00 | $16.49 | $11.75 |
| 57 | Electrical conductor (no.12) insulated (620-7004) | LF | 5,010 | $3.50 | $1.00 | $0.75 | $0.75 | $2.35 | $0.75 |
| 58 | Ground box type A (122311)W/apron (624-7002) | EACH | 1 | $750.00 | $1,103.00 | $1,240.00 | $1,100.00 | $1,528.17 | $1,300.00 |
| 59 | Elc SRV type A 240/480 060(NS)SS(E)GC(O) (628-7044) | EACH | 1 | $23,000 | $7,012.00 | $7,920.00 | $7,000.00 | $11,033 | $8,100.00 |
| 60 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 2 | $850.00 | $1,369.00 | $1,560.00 | $1,375.00 | $1,743.76 | $1,600.00 |
| 61 | Install small roadside sign support and assembly type 10BWG(1)SA(P-BM) (644-7002) | EACH | 1 | $750.00 | $1,505.00 | $1,810.00 | $1,600.00 | $2,029.10 | $1,900.00 |
| 62 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 1 | $850.00 | $1,405.00 | $1,700.00 | $1,500.00 | $1,902.28 | $1,800.00 |
| 63 | Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007) | EACH | 1 | $950.00 | $1,654.00 | $1,870.00 | $1,650.00 | $2,092.51 | $1,900.00 |
| 64 | Install small roadside sign support and assembly type 10BWG(2)SA(P) (644-7017) | EACH | 1 | $1,200.00 | $1,756.00 | $2,090.00 | $1,850.00 | $2,346.15 | $2,200.00 |
| 65 | Remove SM RD SN sup&AM (644-7073) | EACH | 4 | $150.00 | $75.00 | $85.00 | $75.00 | $285.34 | $87.00 |
| 66 | Install object marker assembly (OM-2Z)(WFLX)GND(BI) (658-7059) | EACH | 6 | $100.00 | $174.00 | $198.00 | $175.00 | $221.93 | $210.00 |
| 67 | Remove delin & object marker assms (658-7078) | EACH | 4 | $10.00 | $25.00 | $28.00 | $25.00 | $31.70 | $29.00 |
| 68 | Work zone pavement marking removing (reflectorized) type II-A-A (662-7051) | EACH | 1,375 | $2.00 | $3.00 | $3.95 | $3.50 | $4.44 | $4.10 |
| 69 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 30,375 | $0.40 | $1.00 | $0.40 | $0.40 | $0.46 | $0.43 |
| 70 | Work zone pavement marking removing (W)8"(DOT) (662-7070) | LF | 860 | $2.00 | $2.00 | $2.25 | $2.00 | $1.64 | $2.40 |
| 71 | Work zone pavement marking removing (W)8"(solid) (662-7072) | LF | 446 | $1.50 | $1.00 | $0.65 | $0.60 | $1.64 | $0.70 |
| 72 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 48 | $16.00 | $24.00 | $27.00 | $25.00 | $30.44 | $28.00 |
| 73 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 47,949 | $0.40 | $1.00 | $0.40 | $0.40 | $0.46 | $0.43 |
| 74 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 442 | $1.50 | $3.00 | $2.15 | $1.00 | $5.07 | $5.30 |
| 75 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 787 | $1.50 | $3.00 | $1.45 | $1.00 | $5.07 | $5.80 |
| 76 | Reflectorized pavement marking type I (W)8"(DOT)(125MIL) (666-7449) | LF | 935 | $1.30 | $2.00 | $2.00 | $1.75 | $2.22 | $2.10 |
| 77 | Reflectorized pavement marking type I (W)8"(solid)(125MIL) (666-7451) | LF | 446 | $1.05 | $2.00 | $2.00 | $1.75 | $2.22 | $2.10 |
| 78 | Reflectorized pavement marking type I (Y)12"(solid)(125MIL) (666-7482) | LF | 906 | $1.30 | $2.00 | $2.55 | $2.25 | $2.85 | $2.60 |
| 79 | Reflectorized pavement marking type I (W)6"(solid)(125MIL) (666-7519) | LF | 11,393 | $0.55 | $1.00 | $1.20 | $1.00 | $1.33 | $1.25 |
| 80 | Reflectorized pavement marking type I (Y)6"(solid)(125MIL) (666-7523) | LF | 16,492 | $0.55 | $1.00 | $1.20 | $1.00 | $1.33 | $1.25 |
| 81 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 36 | $10.00 | $24.00 | $27.00 | $24.00 | $30.44 | $28.00 |
| 82 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 2 | $150.00 | $149.00 | $170.00 | $150.00 | $327.61 | $180.00 |
| 83 | Prefabricated PM type C (W)(LN reduct arrow) (668-7100) | EACH | 2 | $500.00 | $366.00 | $424.00 | $375.00 | $327.61 | $440.00 |
| 84 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 2 | $250.00 | $240.00 | $283.00 | $250.00 | $327.61 | $290.00 |
| 85 | Reflectorized pavement marker type I-C (672-7002) | EACH | 21 | $4.00 | $7.00 | $8.50 | $7.50 | $9.51 | $8.70 |
| 86 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 670 | $4.00 | $7.00 | $8.50 | $7.50 | $9.51 | $8.70 |
| 87 | Eliminating existing PM & markers (6") (677-7002) | LF | 16,623 | $1.00 | $1.00 | $0.85 | $1.00 | $0.95 | $0.90 |
| 88 | Removing RDSD FLSH BCN AM (solar PWRD) (685-7006) | EACH | 1 | $1,000.00 | $612.00 | $803.00 | $750.00 | $558.00 | $820.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of November 4, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.