TxDOT contract A00222905 bid tabulation
Widen Road - Add Lanes And Shoulders, SH 114 (At Alliance Blvd to .). Let by Texas DOT on November 4, 2026, Wise, Fort Worth District. 7 bids received; low bid $482,224 by Xit Paving and Construction Inc., -22% against the engineer's estimate of $620,363.
- Owner
- Texas DOT
- Letting
- 04 NOV 2026
- Pay items
- 45
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Xit Paving and Construction Inc. | $482,224 | Low | -22% |
| 2 | Ed Bell Construction Company | $583,959 | +21% | -6.0% |
| 3 | O. Trevino Construction, LLC | $594,655 | +23% | -4.0% |
| 4 | Jay Mills Contracting, Incorporated | $607,976 | +26% | -2.0% |
| 5 | Silver Creek Construction, Inc. | $649,060 | +35% | +5.0% |
| 6 | Jagoe-Public Company | $701,946 | +46% | +13% |
| 7 | Overland Corporation | $771,411 | +60% | +24% |
Engineer's estimate: $620,363.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Xit Paving and Construction Inc. | 2. Ed Bell Construction Company | 3. O. Trevino Construction, LLC | 4. Jay Mills Contracting, Incorporated | 5. Silver Creek Construction, Inc. | 6. Jagoe-Public Company |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 13 | $5,067.00 | $2,100.00 | $3,000.00 | $3,846.00 | $2,500.00 | $2,000.00 | $390.00 |
| 2 | Excavation (roadway) (110-7001) | CY | 455 | $31.00 | $30.00 | $5.25 | $32.00 | $40.00 | $40.00 | $60.00 |
| 3 | Embankment (final)(DC)(type B) (132-7004) | CY | 1,260 | $30.00 | $35.00 | $42.00 | $50.00 | $45.00 | $50.00 | $70.00 |
| 4 | Hydro mulch seed (permanent_rural_sandy) (164-7017) | SY | 3,612 | $5.00 | $0.75 | $6.30 | $0.75 | $1.25 | $1.10 | $1.75 |
| 5 | Hydro mulch seed (temporary_warm) (164-7021) | SY | 1,806 | $1.20 | $0.50 | $0.01 | $0.55 | $1.62 | $1.45 | $2.50 |
| 6 | Hydro mulch seed (temporary_cool) (164-7022) | SY | 1,806 | $1.20 | $0.50 | $0.01 | $0.56 | $1.62 | $1.45 | $2.50 |
| 7 | Vegetative watering (168-7001) | TGL | 127 | $5.00 | $130.00 | $10.00 | $44.00 | $25.00 | $100.00 | $45.00 |
| 8 | Lime (commercial lime slurry) (260-7004) | TON | 7.50 | $380.00 | $450.00 | $630.00 | $712.50 | $365.00 | $1,000.00 | $440.00 |
| 9 | Lime TRT (subgrade) (8") (260-7020) | SY | 1,470 | $15.00 | $14.00 | $10.00 | $26.50 | $10.00 | $25.00 | $20.00 |
| 10 | Prime coat(MC-30 or AE-P) (310-7013) | GAL | 184 | $16.00 | $6.00 | $18.00 | $20.00 | $20.00 | $35.00 | $12.00 |
| 11 | D-GR HMA type-B sac-B PG64-22 (341-7002) | TON | 286 | $135.00 | $200.00 | $220.00 | $205.00 | $250.00 | $230.00 | $170.00 |
| 12 | Tack coat (344-7077) | GAL | 262 | $10.00 | $6.00 | $9.00 | $9.50 | $0.01 | $1.00 | $3.00 |
| 13 | Concrete pavement (CRCP) (11") (360-7005) | SY | 960 | $160.00 | $130.00 | $150.00 | $121.35 | $130.00 | $175.00 | $230.00 |
| 14 | Concrete pavement (CRCP)(hes) (8") (360-7047) | SY | 17 | $200.00 | $200.00 | $300.00 | $525.00 | $250.00 | $1,000.00 | $700.00 |
| 15 | Cut & restoring pavement (400-7006) | SY | 17 | $300.00 | $109.00 | $150.00 | $525.00 | $135.00 | $40.00 | $210.00 |
| 16 | Flowable backfill (401-7001) | CY | 16 | $440.00 | $300.00 | $250.00 | $525.00 | $200.00 | $350.00 | $380.00 |
| 17 | RC pipe (CL V)(18 in) (464-7032) | LF | 25 | $225.00 | $180.00 | $80.00 | $265.00 | $108.00 | $100.00 | $140.00 |
| 18 | RC pipe (CL V)(24 in) (464-7034) | LF | 191 | $180.00 | $183.00 | $85.00 | $96.00 | $250.00 | $125.00 | $122.00 |
| 19 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 1 | $3,100.00 | $2,105.00 | $2,000.00 | $2,800.00 | $1,800.00 | $3,500.00 | $2,100.00 |
| 20 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 3 | $2,600.00 | $2,386.00 | $3,500.00 | $5,000.00 | $3,000.00 | $3,750.00 | $2,400.00 |
| 21 | Removing structure (set) (496-7004) | EACH | 3 | $1,440.00 | $850.00 | $300.00 | $340.00 | $450.00 | $400.00 | $460.00 |
| 22 | Removing structure (pipe) (496-7007) | LF | 37 | $49.00 | $40.00 | $30.00 | $53.00 | $30.00 | $20.00 | $110.00 |
| 23 | Mobilization (500-7001) | LS | 1 | $49,928 | $23,000 | $57,500 | $55,000 | $60,000 | $64,500 | $77,000 |
| 24 | Barricades, signs and traffic handling (502-7001) | MO | 3 | $18,321 | $4,945.00 | $31,500 | $9,375.00 | $21,000 | $7,500.00 | $19,000 |
| 25 | Portable changeable message sign (503-7001) | DAY | 176 | $90.00 | $100.00 | $25.00 | $159.00 | $100.00 | $75.00 | $50.00 |
| 26 | TMA (stationary) (505-7001) | DAY | 92 | $235.00 | $140.00 | $1.00 | $159.00 | $115.00 | $400.00 | $150.00 |
| 27 | Temporary sediment control fence (install) (506-7039) | LF | 2,060 | $4.20 | $4.00 | $3.38 | $3.50 | $3.70 | $3.00 | $3.25 |
| 28 | Temporary sediment control fence (remove) (506-7041) | LF | 2,060 | $3.00 | $0.50 | $1.82 | $0.50 | $1.65 | $1.00 | $1.00 |
| 29 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 200 | $6.00 | $5.00 | $5.72 | $4.50 | $8.10 | $4.85 | $5.00 |
| 30 | Biodegradable erosion control logs (remove) (506-7046) | LF | 200 | $6.00 | $0.50 | $2.34 | $0.56 | $4.00 | $1.00 | $1.00 |
| 31 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 1,300 | $2.50 | $6.00 | $0.01 | $3.25 | $6.45 | $3.00 | $3.25 |
| 32 | Aluminum signs (type A) (636-7001) | SF | 2 | $85.00 | $58.00 | $52.00 | $83.00 | $112.00 | $70.00 | $50.00 |
| 33 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 2 | $1,050.00 | $1,105.00 | $988.00 | $1,600.00 | $1,675.00 | $70.00 | $1,000.00 |
| 34 | Remove SM RD SN sup&AM (644-7073) | EACH | 2 | $175.00 | $174.00 | $156.00 | $250.00 | $335.00 | $400.00 | $160.00 |
| 35 | Reflectorized pavement marking type III (W)(8")(solid) (666-7239) | LF | 1,400 | $1.50 | $3.00 | $2.76 | $2.55 | $3.80 | $2.50 | $2.50 |
| 36 | Reflectorized pavement marking type III (W)(24")(solid) (666-7244) | LF | 36 | $10.50 | $17.00 | $15.60 | $33.00 | $22.35 | $32.00 | $34.00 |
| 37 | Reflectorized pavement marking type III (W)(arrow) (666-7254) | EACH | 4 | $300.00 | $291.00 | $260.00 | $620.00 | $391.00 | $600.00 | $600.00 |
| 38 | Reflectorized pavement marking type III (W)(word) (666-7257) | EACH | 4 | $300.00 | $378.00 | $338.00 | $620.00 | $447.00 | $600.00 | $600.00 |
| 39 | Reflectorized pavement marker type II-C-C (672-7005) | EACH | 140 | $10.00 | $8.00 | $7.28 | $12.50 | $7.85 | $12.00 | $13.00 |
| 40 | Pavement surface preparation for marking (8") (678-7004) | LF | 1,400 | $1.00 | $1.00 | $1.04 | $0.55 | $1.40 | $0.50 | $0.50 |
| 41 | Pavement surface preparation for marking (24") (678-7008) | LF | 36 | $1.20 | $3.00 | $3.12 | $1.05 | $3.35 | $1.00 | $1.00 |
| 42 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 4 | $20.00 | $116.00 | $104.00 | $105.00 | $112.00 | $100.00 | $100.00 |
| 43 | Pavement surface preparation for marking (word) (678-7016) | EACH | 4 | $40.00 | $140.00 | $124.80 | $105.00 | $134.00 | $100.00 | $100.00 |
| 44 | Pavement surface preparation for marking (RPM) (678-7033) | EACH | 140 | $3.50 | $3.00 | $3.12 | $0.10 | $3.35 | $0.10 | $0.10 |
| 45 | Ditch cleaning and reshaping (foot) (760-7001) | LF | 400 | $26.00 | $10.00 | $18.00 | $7.50 | $12.00 | $12.00 | $15.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of November 4, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.