TxDOT contract A00188510 bid tabulation
Intersection Improvements With Right And/Or Left Turn Lanes, US 180 (West of Cool Jct to East of Cool Jct). Let by Texas DOT on November 3, 2026, Parker, Fort Worth District. 8 bids received; low bid $494,986 by Jay Mills Contracting, Incorporated, -22% against the engineer's estimate of $632,887.
- Owner
- Texas DOT
- Letting
- 03 NOV 2026
- Pay items
- 44
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Jay Mills Contracting, Incorporated | $494,986 | Low | -22% |
| 2 | Texas Materials Group, Inc. | $495,404 | 0.0% | -22% |
| 3 | Jagoe-Public Company | $598,414 | +21% | -5.0% |
| 4 | Eurovia Atlantic Coast LLC | $614,549 | +24% | -3.0% |
| 5 | Overland Corporation | $616,693 | +25% | -3.0% |
| 6 | Foutsco Paving Company, LLC | $621,064 | +25% | -2.0% |
| 7 | A. L. Helmcamp, Inc. | $662,993 | +34% | +5.0% |
| 8 | Ed Bell Construction Company | $679,542 | +37% | +7.0% |
Engineer's estimate: $632,887.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Jay Mills Contracting, Incorporated | 2. Texas Materials Group, Inc. | 3. Jagoe-Public Company | 4. Eurovia Atlantic Coast LLC | 5. Overland Corporation | 6. Foutsco Paving Company, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Excavation (roadway) (110-7001) | CY | 182 | $60.00 | $26.00 | $50.00 | $110.00 | $40.00 | $34.00 | $90.00 |
| 2 | Embankment (final)(OC)(type B) (132-7003) | CY | 275 | $150.00 | $26.00 | $50.00 | $85.00 | $115.00 | $58.04 | $60.00 |
| 3 | Backfill (type A) (134-7001) | STA | 10 | $550.00 | $215.00 | $500.00 | $1,000.00 | $755.00 | $1,370.29 | $300.00 |
| 4 | Block sodding (162-7002) | SY | 2,175 | $5.00 | $6.05 | $7.74 | $5.50 | $5.40 | $5.40 | $1.00 |
| 5 | Vegetative watering (168-7001) | TGL | 76 | $30.00 | $21.00 | $1.00 | $115.00 | $108.00 | $95.00 | $1.00 |
| 6 | SLV, haul & stockpile reclaimed asphalt PV(8" to 14") (305-7049) | SY | 560 | $30.00 | $22.00 | $25.00 | $23.00 | $15.00 | $35.00 | $20.00 |
| 7 | Prime coat (AE-P) (310-7001) | GAL | 290 | $10.00 | $9.00 | $1.00 | $7.50 | $14.00 | $10.00 | $1.00 |
| 8 | Asphalt (CRS-2) (316-7011) | GAL | 2,224 | $5.00 | $8.00 | $4.00 | $6.00 | $5.85 | $5.90 | $5.00 |
| 9 | Aggregate (type-B, GR-4)(sac-B) (316-7173) | CY | 51 | $250.00 | $300.00 | $300.00 | $350.00 | $342.00 | $350.00 | $350.00 |
| 10 | D-GR HMA type-B PG64-22 (341-7001) | TON | 918 | $170.00 | $117.00 | $125.00 | $120.00 | $128.00 | $165.00 | $197.00 |
| 11 | D-GR HMA type D PG64-22 (level-UP) (341-7046) | TON | 112 | $170.00 | $275.00 | $200.00 | $200.00 | $200.00 | $200.00 | $270.00 |
| 12 | Tack coat (341-7082) | GAL | 290 | $5.00 | $0.01 | $0.01 | $2.00 | $3.25 | $4.50 | $1.00 |
| 13 | SP mixes SP-C sac-A PG70-28 (344-7024) | TON | 640 | $180.00 | $185.00 | $220.00 | $188.00 | $193.00 | $230.00 | $220.00 |
| 14 | Tack coat (344-7077) | GAL | 1,112 | $5.00 | $0.01 | $0.01 | $2.00 | $3.25 | $5.00 | $0.10 |
| 15 | Flexible pavement structure repair(8") (351-7007) | SY | 445 | $90.00 | $100.00 | $100.00 | $90.00 | $110.00 | $102.50 | $150.00 |
| 16 | Plane & text asphalt concrete pavement(0" to 2") (354-7002) | SY | 4,108 | $5.00 | $4.20 | $5.00 | $5.50 | $3.75 | $5.18 | $2.00 |
| 17 | Mobilization (500-7001) | LS | 1 | $57,535 | $49,000 | $43,000 | $66,000 | $55,000 | $60,010 | $30,000 |
| 18 | Barricades, signs and traffic handling (502-7001) | MO | 3 | $20,000 | $3,500.00 | $1,000.00 | $18,500 | $13,500 | $4,000.00 | $20,000 |
| 19 | Portable changeable message sign (503-7002) | EACH | 2 | $7,500.00 | $3,500.00 | $1,500.00 | $3,500.00 | $18,500 | $5,845.50 | $3,500.00 |
| 20 | TMA (stationary) (505-7001) | DAY | 46 | $250.00 | $170.00 | $1.00 | $200.00 | $325.00 | $296.51 | $1.00 |
| 21 | TMA (mobile operation) (505-7003) | DAY | 6 | $250.00 | $170.00 | $1.00 | $200.00 | $715.00 | $1.00 | $1.00 |
| 22 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 20 | $10.00 | $19.25 | $15.00 | $18.00 | $17.25 | $17.25 | $1.00 |
| 23 | Biodegradable erosion control logs (remove) (506-7046) | LF | 20 | $1.00 | $9.00 | $10.00 | $8.00 | $8.00 | $8.00 | $0.10 |
| 24 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 1,800 | $1.00 | $4.65 | $2.50 | $2.75 | $3.10 | $4.17 | $4.00 |
| 25 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 1 | $1,400.00 | $750.00 | $1,000.00 | $700.00 | $650.00 | $650.00 | $3,000.00 |
| 26 | Remove SM RD SN sup&AM (644-7073) | EACH | 1 | $115.00 | $110.00 | $100.00 | $110.00 | $100.00 | $100.00 | $400.00 |
| 27 | Install object marker assembly (OM-2Z)(WFLX)GND(BI) (658-7059) | EACH | 1 | $125.00 | $90.00 | $80.00 | $80.00 | $80.00 | $80.00 | $400.00 |
| 28 | Work zone pavement marking non-removing (W)6"(broken) (662-7005) | LF | 250 | $1.00 | $1.15 | $0.80 | $0.80 | $0.80 | $0.65 | $0.65 |
| 29 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 932 | $1.00 | $0.85 | $0.70 | $0.70 | $0.70 | $0.65 | $0.65 |
| 30 | Work zone pavement marking non-removing (W)8"(solid) (662-7012) | LF | 650 | $1.00 | $1.40 | $1.50 | $1.50 | $1.50 | $0.80 | $0.80 |
| 31 | Work zone pavement marking non-removing (W)24"(solid) (662-7017) | LF | 40 | $1.00 | $8.95 | $24.00 | $25.00 | $24.00 | $5.50 | $5.50 |
| 32 | Work zone pavement marking non-removing (W)(arrow) (662-7018) | EACH | 2 | $40.00 | $78.50 | $800.00 | $800.00 | $800.00 | $160.00 | $160.00 |
| 33 | Work zone pavement marking non-removing(W)(word) (662-7030) | EACH | 2 | $50.00 | $90.00 | $800.00 | $800.00 | $800.00 | $175.00 | $175.00 |
| 34 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 976 | $1.00 | $1.15 | $0.70 | $0.70 | $0.70 | $0.65 | $0.65 |
| 35 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 154 | $1.00 | $1.35 | $0.50 | $2.25 | $2.00 | $1.90 | $1.00 |
| 36 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 49 | $1.00 | $1.35 | $0.50 | $2.25 | $2.25 | $3.15 | $1.00 |
| 37 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 650 | $2.00 | $1.65 | $1.90 | $2.00 | $1.90 | $1.45 | $1.45 |
| 38 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 40 | $40.00 | $11.20 | $24.00 | $25.00 | $24.00 | $5.66 | $5.66 |
| 39 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 2 | $150.00 | $225.00 | $500.00 | $500.00 | $500.00 | $175.00 | $175.00 |
| 40 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 2 | $160.00 | $280.00 | $500.00 | $500.00 | $500.00 | $195.00 | $195.00 |
| 41 | All-wther PM type I (W)6"(solid)(100MIL) (666-7309) | LF | 932 | $2.00 | $3.35 | $1.00 | $1.00 | $1.00 | $0.93 | $0.93 |
| 42 | All-wther PM type I (W)6"(broken)(100MIL) (666-7310) | LF | 250 | $2.00 | $3.35 | $1.15 | $1.25 | $1.15 | $0.93 | $0.93 |
| 43 | All-wther PM type I (Y)6"(solid)(100MIL) (666-7315) | LF | 976 | $2.00 | $3.35 | $1.00 | $1.00 | $1.00 | $0.93 | $0.93 |
| 44 | Reflectorized pavement marker type I-C (672-7002) | EACH | 33 | $10.00 | $22.35 | $23.00 | $24.00 | $23.00 | $6.50 | $6.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of November 3, 2026. Compiled by Mirage Metrics.