TxDOT contract A00206631 bid tabulation
Hazard Elimination & Safety, FM 485 (1.99 Mi W of FM 979 to 1.86 Mi E of FM 979). Let by Texas DOT on November 4, 2026, Milam, Bryan District. 7 bids received; low bid $9,787,627 by Big Creek Construction, LTD., -7.2% against the engineer's estimate of $10,546,131.
- Owner
- Texas DOT
- Letting
- 04 NOV 2026
- Pay items
- 116
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Big Creek Construction, LTD. | $9,787,627 | Low | -7.0% |
| 2 | Larry Young Paving, Inc. | $10,182,780 | +4.0% | -3.0% |
| 3 | Knife River Corporation - South | $10,424,591 | +7.0% | -1.0% |
| 4 | Texas Materials Group, Inc. | $12,020,138 | +23% | +14% |
| 5 | A. L. Helmcamp, Inc. | $12,374,454 | +26% | +17% |
| 6 | Patin Construction LLC | $15,629,317 | +60% | +48% |
| 7 | Joe Bland Construction LLC | $18,492,861 | +89% | +75% |
Engineer's estimate: $10,546,131.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Big Creek Construction, LTD. | 2. Larry Young Paving, Inc. | 3. Knife River Corporation - South | 4. Texas Materials Group, Inc. | 5. A. L. Helmcamp, Inc. | 6. Patin Construction LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 275 | $625.00 | $750.00 | $1,230.00 | $145.00 | $204.63 | $600.00 | $630.00 |
| 2 | Removing concrete (riprap) (104-7006) | SY | 246 | $12.00 | $25.00 | $9.00 | $53.00 | $24.00 | $36.00 | $25.00 |
| 3 | Remove (10"-14") TRT/untrt base & asphalt pavement (105-7010) | SY | 2,767 | $12.00 | $15.00 | $12.00 | $6.50 | $14.00 | $15.00 | $25.00 |
| 4 | Remove (12") TRT/untrt base & asphalt pavement (105-7032) | SY | 6,363 | $8.00 | $5.00 | $3.00 | $3.00 | $6.95 | $15.00 | $20.00 |
| 5 | Remove (2"-8") TRT/untrt base & asphalt pavement (105-7053) | SY | 3,663 | $3.50 | $10.00 | $3.00 | $3.00 | $3.40 | $8.00 | $20.00 |
| 6 | Excavation (roadway) (110-7001) | CY | 21,027 | $12.00 | $15.00 | $16.00 | $6.00 | $10.30 | $17.00 | $30.00 |
| 7 | Embankment (final)(DC)(type C) (132-7006) | CY | 21,464 | $14.00 | $15.00 | $12.00 | $25.25 | $8.60 | $19.00 | $60.00 |
| 8 | Furn & place topsoil (4") (160-7002) | SY | 160,878 | $0.75 | $0.50 | $0.50 | $1.00 | $0.50 | $1.50 | $2.00 |
| 9 | Hydro mulch seed (permanent_rural_sandy) (164-7017) | SY | 160,878 | $0.60 | $0.50 | $0.50 | $0.48 | $0.47 | $0.49 | $2.00 |
| 10 | Hydro mulch seed (temporary_warm) (164-7021) | SY | 80,442 | $0.40 | $0.46 | $0.45 | $0.45 | $0.45 | $0.47 | $1.00 |
| 11 | Hydro mulch seed (temporary_cool) (164-7022) | SY | 80,442 | $0.50 | $0.46 | $0.45 | $0.45 | $0.45 | $0.47 | $1.00 |
| 12 | Vegetative watering (168-7001) | TGL | 1,609 | $14.00 | $15.00 | $42.00 | $46.00 | $43.00 | $15.00 | $10.00 |
| 13 | Soil ret BLKT(chan_permanent_2 PSF) (169-7031) | SY | 15,144 | $3.00 | $1.00 | $0.90 | $0.92 | $2.50 | $2.60 | $3.00 |
| 14 | Soil ret BLKT(chan_permanent_4 PSF) (169-7032) | SY | 1,078 | $2.00 | $1.00 | $1.45 | $6.00 | $6.50 | $3.00 | |
| 15 | Soil ret BLKT(chan_permanent_6 PSF) (169-7033) | SY | 250 | $4.00 | $5.00 | $3.50 | $6.00 | $6.50 | $3.00 | |
| 16 | FL BS (compacted in place)(tya GR1-2)(final pos) (247-7176) | CY | 41,907 | $74.00 | $65.00 | $68.00 | $82.00 | $114.00 | $80.00 | $85.00 |
| 17 | Rework BS metal (type C)(12")(ord comp) (251-7055) | SY | 88,281 | $2.50 | $1.50 | $2.00 | $0.75 | $1.20 | $1.50 | $6.00 |
| 18 | Lime (com or QK)(slurry) or QK(dry) (260-7001) | TON | 1,546 | $330.00 | $342.00 | $400.00 | $335.00 | $334.00 | $350.00 | $400.00 |
| 19 | Lime TRT (existing material)(10") (260-7008) | SY | 54,945 | $3.50 | $4.00 | $5.00 | $5.00 | $3.70 | $5.00 | $10.00 |
| 20 | Cement (275-7001) | TON | 3,559 | $215.00 | $210.00 | $200.00 | $183.50 | $210.00 | $230.00 | $260.00 |
| 21 | Cement TRT (existing material & new base)(10") (275-7008) | SY | 143,219 | $2.50 | $1.60 | $1.00 | $0.85 | $2.25 | $2.50 | $6.00 |
| 22 | Cement TRT (new base)(8") (275-7011) | SY | 137,231 | $2.50 | $2.25 | $1.00 | $0.75 | $2.25 | $2.50 | $6.00 |
| 23 | Asphalt (AC-20XP) (316-7006) | GAL | 104,296 | $3.10 | $3.50 | $3.75 | $2.80 | $4.00 | $4.00 | $5.00 |
| 24 | Asphalt (RC-250) (316-7016) | GAL | 31,927 | $4.00 | $5.00 | $5.75 | $4.25 | $5.60 | $5.00 | $6.50 |
| 25 | Aggregate (type-PB or PL, GR-4)(sac-A) (316-7241) | CY | 2,196 | $150.00 | $165.00 | $200.00 | $184.50 | $184.00 | $200.00 | $240.00 |
| 26 | Aggregate (type-B or L, GR-5) (316-7251) | CY | 1,075 | $105.00 | $110.00 | $119.95 | $136.80 | $181.20 | $200.00 | $225.00 |
| 27 | Cut & restore asphalt paving (400-7008) | SY | 138 | $140.00 | $240.00 | $94.00 | $73.00 | $240.00 | $15.00 | $100.00 |
| 28 | Cem stabil BKFL (400-7010) | CY | 103 | $116.00 | $250.00 | $130.00 | $142.50 | $250.00 | $270.00 | $300.00 |
| 29 | Trench excavation protection (402-7001) | LF | 175 | $10.00 | $15.00 | $1.00 | $35.00 | $10.00 | $9.50 | $5.00 |
| 30 | Riprap (concrete)(5 in) (432-7002) | CY | 9 | $550.00 | $900.00 | $780.00 | $928.00 | $631.00 | $770.00 | $700.00 |
| 31 | Riprap (stone common)(dry)(12 in) (432-7031) | CY | 5 | $500.00 | $85.00 | $344.00 | $450.00 | $460.00 | $250.00 | |
| 32 | RC pipe (CL III)(18 in) (464-7003) | LF | 1,060 | $72.00 | $55.00 | $71.00 | $49.00 | $50.00 | $72.00 | $75.00 |
| 33 | RC pipe (CL III)(24 in) (464-7005) | LF | 806 | $90.00 | $75.00 | $85.00 | $84.00 | $71.00 | $97.00 | $90.00 |
| 34 | RC pipe (CL III)(30 in) (464-7007) | LF | 928 | $125.00 | $120.00 | $110.00 | $111.00 | $112.50 | $162.00 | $120.00 |
| 35 | RC pipe (CL III)(36 in) (464-7009) | LF | 70 | $180.00 | $175.00 | $180.00 | $190.00 | $172.50 | $188.00 | $150.00 |
| 36 | RC pipe (CL III)(48 in) (464-7011) | LF | 54 | $250.00 | $270.00 | $522.00 | $224.00 | $320.00 | $300.00 | |
| 37 | RC pipe (CL IV)(18 in) (464-7019) | LF | 448 | $90.00 | $65.00 | $77.00 | $50.00 | $59.00 | $82.00 | $100.00 |
| 38 | RC pipe (CL IV)(24 in) (464-7021) | LF | 502 | $120.00 | $90.00 | $97.00 | $72.00 | $84.00 | $110.00 | $120.00 |
| 39 | Headwall (CH - PW - 0) (diameter= 30 in) (466-7103) | EACH | 2 | $7,500.00 | $9,900.00 | $22,045 | $7,250.00 | $12,000 | $5,000.00 | |
| 40 | Headwall (CH - PW - 0) (diameter= 36 in) (466-7105) | EACH | 1 | $10,000 | $10,000 | $11,000 | $22,614 | $9,500.00 | $13,000 | $5,500.00 |
| 41 | Headwall (CH - PW - 0) (diameter= 48 in) (466-7107) | EACH | 2 | $11,000 | $13,000 | $30,245 | $10,250 | $15,000 | $6,500.00 | |
| 42 | Set (pipe runner assembly) (467-7001) | EACH | 2 | $1,500.00 | $1,500.00 | $1,200.00 | $1,820.00 | $1,100.00 | $1,200.00 | $2,500.00 |
| 43 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 64 | $1,150.00 | $1,000.00 | $1,300.00 | $1,971.00 | $850.00 | $2,000.00 | $2,000.00 |
| 44 | Set (type II) (24 in) (RCP) (3: 1) (C) (467-7325) | EACH | 4 | $1,700.00 | $1,200.00 | $110.00 | $2,164.00 | $1,100.00 | $1,900.00 | $2,500.00 |
| 45 | Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326) | EACH | 7 | $1,725.00 | $1,250.00 | $1,700.00 | $2,600.00 | $1,150.00 | $2,400.00 | $2,500.00 |
| 46 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 46 | $1,500.00 | $1,275.00 | $1,500.00 | $2,645.00 | $1,225.00 | $2,200.00 | $2,500.00 |
| 47 | Set (type II) (30 in) (RCP) (3: 1) (C) (467-7345) | EACH | 13 | $3,500.00 | $1,500.00 | $2,300.00 | $3,348.00 | $1,385.00 | $2,700.00 | $3,000.00 |
| 48 | Set (type II) (30 in) (RCP) (4: 1) (C) (467-7346) | EACH | 8 | $1,600.00 | $2,400.00 | $4,199.00 | $1,510.00 | $2,700.00 | $3,000.00 | |
| 49 | Set (type II) (30 in) (RCP) (6: 1) (P) (467-7348) | EACH | 14 | $2,500.00 | $4,000.00 | $3,100.00 | $5,115.00 | $3,940.00 | $3,800.00 | $3,000.00 |
| 50 | Set (type II) (36 in) (RCP) (6: 1) (P) (467-7368) | EACH | 2 | $6,600.00 | $4,300.00 | $4,400.00 | $6,820.00 | $4,100.00 | $5,400.00 | $3,500.00 |
| 51 | Set (type II) (48 in) (RCP) (3: 1) (C) (467-7389) | EACH | 2 | $4,500.00 | $4,300.00 | $6,140.00 | $4,150.00 | $5,500.00 | $5,000.00 | |
| 52 | Clean existing culverts (480-7001) | EACH | 12 | $2,000.00 | $1,500.00 | $2,000.00 | $2,817.00 | $1,350.00 | $1,900.00 | $500.00 |
| 53 | Removing structure (inlet) (496-7002) | EACH | 1 | $2,000.00 | $500.00 | $808.00 | $1,800.00 | $1,800.00 | $500.00 | |
| 54 | Removing structure (set) (496-7004) | EACH | 124 | $480.00 | $250.00 | $260.00 | $525.00 | $100.00 | $690.00 | $500.00 |
| 55 | Removing structure (headwall) (496-7006) | EACH | 3 | $1,500.00 | $5,000.00 | $1,704.00 | $1,100.00 | $1,800.00 | $1,500.00 | |
| 56 | Removing structure (pipe) (496-7037) | EACH | 53 | $575.00 | $400.00 | $1,100.00 | $542.00 | $325.00 | $650.00 | $250.00 |
| 57 | Removing rock riprap (496-7040) | LF | 25 | $75.00 | $81.00 | $43.00 | $175.00 | $62.00 | $50.00 | |
| 58 | Mobilization (500-7001) | LS | 1 | $780,430 | $900,000 | $833,000 | $702,000 | $902,000 | $1,100,000 | $150,000 |
| 59 | Barricades, signs and traffic handling (502-7001) | MO | 32 | $6,000.00 | $3,500.00 | $5,200.00 | $9,500.00 | $4,000.00 | $12,000 | $5,000.00 |
| 60 | Portable changeable message sign (503-7002) | EACH | 8 | $7,000.00 | $11,500 | $11,000 | $3,370.00 | $12,600 | $7,500.00 | $10,000 |
| 61 | TMA (stationary) (505-7001) | DAY | 826 | $250.00 | $50.00 | $100.00 | $175.00 | $110.00 | $240.00 | $400.00 |
| 62 | TMA (mobile operation) (505-7003) | DAY | 21 | $225.00 | $550.00 | $730.00 | $972.00 | $640.00 | $240.00 | $500.00 |
| 63 | Rock filter dams (install) (type 1) (506-7001) | LF | 325 | $35.00 | $33.00 | $32.00 | $32.00 | $40.00 | $42.00 | $70.00 |
| 64 | Rock filter dams (install) (type 2) (506-7002) | LF | 2,275 | $35.00 | $35.00 | $37.00 | $37.00 | $43.00 | $45.00 | $70.00 |
| 65 | Rock filter dams (remove) (506-7011) | LF | 2,600 | $10.00 | $10.00 | $10.00 | $10.00 | $11.00 | $12.00 | $10.00 |
| 66 | Construction exits (install) (type 1) (506-7020) | SY | 278 | $32.00 | $20.00 | $38.00 | $38.00 | $43.00 | $45.00 | $10.00 |
| 67 | Construction exits (remove) (506-7024) | SY | 278 | $10.00 | $10.00 | $12.00 | $12.00 | $11.00 | $12.00 | $2.00 |
| 68 | Temporary sediment control fence (install) (506-7039) | LF | 19,375 | $4.20 | $3.00 | $4.00 | $3.50 | $4.00 | $4.20 | $4.00 |
| 69 | Temporary sediment control fence (remove) (506-7041) | LF | 19,375 | $1.10 | $1.00 | $1.00 | $1.00 | $0.44 | $0.40 | $1.00 |
| 70 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 2,340 | $5.50 | $5.50 | $5.00 | $5.20 | $6.00 | $6.30 | $5.00 |
| 71 | Biodegradable erosion control logs (remove) (506-7046) | LF | 2,340 | $1.50 | $1.00 | $1.00 | $1.00 | $1.25 | $1.30 | $1.00 |
| 72 | Intersections (ACP) (530-7002) | SY | 161 | $60.00 | $60.00 | $30.00 | $80.00 | $120.00 | $100.00 | $275.00 |
| 73 | Driveways (ACP) (530-7010) | SY | 1,866 | $50.00 | $55.00 | $53.00 | $68.00 | $100.00 | $100.00 | $50.00 |
| 74 | Driveways (surface treat) (530-7016) | SY | 4,033 | $25.00 | $28.00 | $36.00 | $45.00 | $67.00 | $41.00 | $8.00 |
| 75 | Turnouts (surface treat) (530-7019) | SY | 168 | $46.00 | $60.00 | $34.00 | $70.00 | $63.00 | $41.00 | $30.00 |
| 76 | Remove metal beam guard fence (542-7001) | LF | 400 | $5.00 | $32.00 | $3.00 | $5.00 | $11.00 | $20.00 | |
| 77 | Remove terminal anchor section (542-7002) | EACH | 1 | $500.00 | $3,500.00 | $250.00 | $500.00 | $1,100.00 | $1,500.00 | |
| 78 | Guardrail end treatment (remove) (544-7003) | EACH | 9 | $500.00 | $350.00 | $275.00 | $500.00 | $1,100.00 | $500.00 | |
| 79 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 8 | $300.00 | $360.00 | $230.00 | $225.00 | $355.00 | $230.00 | $300.00 |
| 80 | Mailbox install-D (TWW-post) type 4 (560-7009) | EACH | 5 | $350.00 | $450.00 | $250.00 | $250.00 | $445.00 | $250.00 | $400.00 |
| 81 | Mailbox install-M (TWW-post) type 4 (560-7010) | EACH | 2 | $400.00 | $850.00 | $650.00 | $650.00 | $850.00 | $690.00 | $400.00 |
| 82 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 43 | $750.00 | $600.00 | $670.00 | $670.00 | $565.00 | $790.00 | $1,500.00 |
| 83 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 3 | $840.00 | $700.00 | $780.00 | $780.00 | $685.00 | $950.00 | $1,500.00 |
| 84 | Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025) | EACH | 1 | $825.00 | $850.00 | $850.00 | $850.00 | $815.00 | $950.00 | $1,500.00 |
| 85 | Remove SM RD SN sup&AM (644-7073) | EACH | 37 | $120.00 | $150.00 | $100.00 | $100.00 | $150.00 | $110.00 | $200.00 |
| 86 | Install object marker assembly (OM-2Z)(WFLX)GND (658-7058) | EACH | 32 | $100.00 | $85.00 | $70.00 | $70.00 | $85.00 | $90.00 | $250.00 |
| 87 | Remove delin & object marker assms (658-7078) | EACH | 27 | $17.00 | $25.00 | $15.00 | $15.00 | $25.00 | $11.00 | $100.00 |
| 88 | Install OM SM RD sign (1-OM-PW)R (658-7318) | EACH | 9 | $35.00 | $30.00 | $13.00 | $13.00 | $85.00 | $11.00 | $100.00 |
| 89 | Work zone pavement marking non-removing (W)6"(broken) (662-7005) | LF | 4,250 | $0.50 | $0.23 | $0.20 | $0.22 | $0.22 | $0.23 | $1.00 |
| 90 | Work zone pavement marking non-removing (W)6"(DOT) (662-7006) | LF | 713 | $2.00 | $0.36 | $0.35 | $0.35 | $0.35 | $0.37 | $1.00 |
| 91 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 57,685 | $0.40 | $0.17 | $0.15 | $0.16 | $0.16 | $0.17 | $1.00 |
| 92 | Work zone pavement marking non-removing (W)8"(DOT) (662-7010) | LF | 40 | $2.25 | $0.66 | $0.65 | $0.65 | $0.65 | $0.68 | $1.00 |
| 93 | Work zone pavement marking non-removing (W)8"(solid) (662-7012) | LF | 805 | $0.80 | $0.45 | $0.40 | $0.40 | $0.40 | $0.42 | $1.00 |
| 94 | Work zone pavement marking non-removing (W)24"(solid) (662-7017) | LF | 150 | $5.00 | $3.15 | $3.00 | $3.10 | $3.10 | $3.26 | $5.00 |
| 95 | Work zone pavement marking non-removing (W)(arrow) (662-7018) | EACH | 8 | $78.00 | $70.00 | $65.00 | $65.00 | $65.00 | $68.25 | $250.00 |
| 96 | Work zone pavement marking non-removing(W)(word) (662-7030) | EACH | 2 | $92.00 | $85.00 | $80.00 | $80.00 | $80.00 | $84.00 | $250.00 |
| 97 | Work zone pavement marking non-removing (Y)6"(broken) (662-7036) | LF | 1,305 | $0.23 | $0.20 | $0.22 | $0.22 | $0.23 | $1.00 | |
| 98 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 61,406 | $0.40 | $0.23 | $0.20 | $0.22 | $0.22 | $0.23 | $1.00 |
| 99 | Work zone pavement marking non-removing (Y)24"(solid) (662-7042) | LF | 791 | $5.00 | $3.00 | $3.00 | $2.85 | $2.85 | $2.99 | $5.00 |
| 100 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 5,464 | $1.30 | $1.50 | $1.00 | $1.10 | $1.00 | $0.90 | $2.00 |
| 101 | Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009) | LF | 713 | $1.50 | $1.15 | $1.00 | $1.10 | $1.10 | $1.16 | $5.00 |
| 102 | Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018) | LF | 40 | $1.20 | $2.00 | $2.00 | $1.85 | $1.85 | $1.94 | $2.00 |
| 103 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 805 | $1.00 | $1.30 | $1.00 | $1.25 | $1.25 | $1.31 | $2.00 |
| 104 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 150 | $7.50 | $15.00 | $14.00 | $14.00 | $14.00 | $14.70 | $10.00 |
| 105 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 8 | $160.00 | $200.00 | $190.00 | $185.00 | $185.00 | $195.00 | $500.00 |
| 106 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 2 | $200.00 | $220.00 | $200.00 | $200.00 | $200.00 | $210.00 | $500.00 |
| 107 | Reflectorized pavement marking type I (Y)24"(solid)(100MIL) (666-7123) | LF | 791 | $7.50 | $14.00 | $13.00 | $12.50 | $12.50 | $13.00 | $10.00 |
| 108 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 4,250 | $0.60 | $0.75 | $0.70 | $0.71 | $0.71 | $0.75 | $1.00 |
| 109 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 57,685 | $0.60 | $0.70 | $0.70 | $0.68 | $0.68 | $0.71 | $1.00 |
| 110 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 1,305 | $0.72 | $0.70 | $0.71 | $0.71 | $0.75 | $1.00 | |
| 111 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 61,406 | $0.60 | $0.70 | $0.70 | $0.68 | $0.68 | $0.71 | $1.00 |
| 112 | PRFB rumble strip (BLK)(1')(centerline) (668-7002) | LF | 24,329 | $2.00 | $0.75 | $0.75 | $0.73 | $0.73 | $0.77 | $5.00 |
| 113 | PRFB rumble strip (BLK)(1')(edgeline) (668-7137) | LF | 55,688 | $2.00 | $0.75 | $0.70 | $0.71 | $0.71 | $0.75 | $5.00 |
| 114 | Reflectorized pavement marker type I-C (672-7002) | EACH | 319 | $4.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.30 | $10.00 |
| 115 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 2,566 | $4.00 | $5.00 | $5.00 | $4.75 | $4.75 | $5.00 | $10.00 |
| 116 | LED roadside sign (6066-7001) | EACH | 1 | $3,000.00 | $4,000.00 | $3,800.00 | $3,750.00 | $3,750.00 | $3,700.00 | $10,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of November 4, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.