TxDOT contract A00132314 bid tabulation
Install/Rehabilitate Its, Various (Various Locations in City of Bellaire to .). Let by Texas DOT on February 5, 2026, Harris, Houston District. 7 bids received; low bid $1,434,678 by Creacom, Inc., -31% against the engineer's estimate of $2,070,252.
- Owner
- Texas DOT
- Letting
- 05 FEB 2026
- Pay items
- 43
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Creacom, Inc. | $1,434,678 | Low | -31% |
| 2 | Traf-Tex, Inc. | $1,444,964 | +1.0% | -30% |
| 3 | Third Coast Services LLC | $1,574,922 | +10% | -24% |
| 4 | Florida Traffic Control Devices, Inc. | $1,628,000 | +13% | -21% |
| 5 | Econolite Systems, Inc. | $1,643,996 | +15% | -21% |
| 6 | Allstate Signal & Construction, LLC | $2,051,018 | +43% | -1.0% |
| 7 | The Levy Company, Inc. | $2,195,627 | +53% | +6.0% |
Engineer's estimate: $2,070,252.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Creacom, Inc. | 2. Traf-Tex, Inc. | 3. Third Coast Services LLC | 4. Florida Traffic Control Devices, Inc. | 5. Econolite Systems, Inc. | 6. Allstate Signal & Construction, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Spec excavation work (hyd excavator) (158-7002) | HR | 20 | $227.00 | $876.19 | $403.00 | $460.54 | $430.00 | $293.32 | $1,062.50 |
| 2 | Mobilization (500-7001) | LS | 1 | $135,437 | $100,428 | $68,553 | $157,492 | $150,000 | $158,243 | $150,000 |
| 3 | Barricades, signs and traffic handling (502-7001) | MO | 8 | $6,500.00 | $10,389 | $5,407.00 | $2,076.23 | $24,415 | $931.91 | $12,794 |
| 4 | TMA (stationary) (505-7001) | DAY | 80 | $221.23 | $660.19 | $110.00 | $399.68 | $162.00 | $373.82 | $525.00 |
| 5 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 165 | $16.34 | $12.22 | $17.70 | $12.76 | $16.10 | $36.88 | $32.56 |
| 6 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 1,180 | $22.28 | $15.85 | $27.80 | $17.56 | $19.00 | $36.83 | $52.65 |
| 7 | Conduit (prepare) (618-7090) | LF | 5,265 | $5.16 | $0.94 | $1.20 | $1.83 | $4.40 | $8.24 | $5.00 |
| 8 | Electrical conductor (no.14) insulated (620-7002) | LF | 1,345 | $1.25 | $1.02 | $1.05 | $2.30 | $1.80 | $3.74 | $2.35 |
| 9 | Install highway traffic signal (upgrade) (680-7011) | EACH | 16 | $17,590 | $8,745.84 | $12,384 | $23,439 | $9,910.00 | $9,274.33 | $19,750 |
| 10 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 16 | $349.00 | $307.11 | $238.00 | $255.96 | $282.00 | $409.02 | $655.00 |
| 11 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 32 | $342.00 | $307.11 | $238.00 | $255.96 | $282.00 | $298.97 | $655.00 |
| 12 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 16 | $285.00 | $307.11 | $238.00 | $255.96 | $282.00 | $409.02 | $655.00 |
| 13 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 124 | $1,012.00 | $665.74 | $644.00 | $568.42 | $620.00 | $648.68 | $1,065.00 |
| 14 | Backplate W/reflectorized border(4 sec) (682-7037) | EACH | 16 | $221.00 | $212.66 | $221.00 | $224.81 | $345.00 | $233.15 | $250.00 |
| 15 | Pedestrian pole assembly (687-7001) | EACH | 1 | $3,197.00 | $1,890.16 | $2,937.00 | $3,207.38 | $2,439.50 | $799.47 | $1,765.00 |
| 16 | Pedestrian detect push button (APS) (688-7001) | EACH | 36 | $900.00 | $918.46 | $744.00 | $899.25 | $1,000.00 | $977.38 | $976.00 |
| 17 | Pedestrian detector controller unit (688-7003) | EACH | 4 | $3,200.00 | $3,539.25 | $3,570.00 | $3,699.88 | $4,400.00 | $3,170.09 | $3,965.00 |
| 18 | Removal of cables (690-7009) | LF | 990 | $1.58 | $1.49 | $0.90 | $0.97 | $12.85 | $11.81 | $4.00 |
| 19 | Removal of signal head assembly (690-7024) | EACH | 140 | $90.75 | $102.35 | $142.40 | $101.38 | $171.00 | $152.25 | $250.00 |
| 20 | Removal of signal related signs (690-7027) | EACH | 14 | $120.00 | $182.35 | $197.00 | $67.60 | $205.00 | $152.25 | $200.00 |
| 21 | Removal of pedestrian push buttons (690-7030) | EACH | 36 | $119.00 | $71.60 | $38.25 | $84.49 | $47.00 | $152.25 | $75.00 |
| 22 | Removal of control cabinet(GRND MNT) (690-7038) | EACH | 1 | $2,071.00 | $1,197.70 | $896.00 | $608.27 | $1,545.00 | $462.59 | $225.00 |
| 23 | Removal of signal pole assembly (690-7051) | EACH | 1 | $1,840.00 | $927.17 | $977.00 | $728.58 | $307.00 | $264.73 | $2,220.00 |
| 24 | Remove vid image vehicle det sys (VIVDS) (690-7086) | EACH | 62 | $1,280.00 | $176.47 | $596.00 | $67.59 | $415.00 | $304.50 | $250.00 |
| 25 | Replace bbu batteries (6007-7003) | EACH | 4 | $1,000.00 | $1,797.44 | $1,970.00 | $398.93 | $950.00 | $398.30 | $885.00 |
| 26 | Ground box (prepare) (6013-7006) | EACH | 80 | $440.00 | $226.89 | $100.00 | $528.89 | $322.00 | $609.01 | $235.00 |
| 27 | Video imaging and radar detector (6017-7015) | EACH | 65 | $8,915.00 | $6,239.43 | $3,124.00 | $5,759.94 | $6,032.00 | $6,601.65 | $6,330.00 |
| 28 | Video imaging and radar set-UP sys (6017-7016) | EACH | 16 | $1,120.00 | $518.47 | $11,523 | $536.31 | $641.00 | $502.42 | $1,695.00 |
| 29 | Vid image and radar com cable (coax) (6017-7017) | LF | 12,215 | $3.00 | $1.71 | $3.22 | $1.73 | $2.05 | $10.79 | $4.48 |
| 30 | Vid image and radar det processor sys (6017-7018) | EACH | 16 | $19,450 | $12,222 | $14,300 | $11,056 | $11,430 | $11,222 | $11,740 |
| 31 | CCTV field equipment (digital) (6018-7002) | EACH | 16 | $8,433.00 | $7,246.32 | $7,612.45 | $6,188.27 | $7,110.00 | $7,358.65 | $8,892.00 |
| 32 | CCTV mount (pole) (6018-7003) | EACH | 16 | $1,495.00 | $453.54 | $872.46 | $326.19 | $378.00 | $446.35 | $159.00 |
| 33 | Fiber optic fusion splice (6027-7004) | EACH | 576 | $63.98 | $12.42 | $37.00 | $17.81 | $38.00 | $12.35 | $138.10 |
| 34 | Fiber optic CBL(single-mode)(144 fiber) (6027-7006) | LF | 1,345 | $3.01 | $5.55 | $5.15 | $4.42 | $4.50 | $8.30 | $8.75 |
| 35 | Fiber optic patch panel (36 positions) (6027-7007) | EACH | 1 | $3,300.00 | $1,526.59 | $2,172.00 | $3,593.96 | $1,278.00 | $2,135.98 | $4,472.00 |
| 36 | FO splice enclosure (type 1) (6027-7009) | EACH | 1 | $2,040.00 | $2,129.50 | $2,051.00 | $3,303.77 | $1,225.00 | $1,192.93 | $5,505.00 |
| 37 | Fiber optic CBL (SNGL-mode)(48 fiber) (6027-7013) | LF | 420 | $5.00 | $4.74 | $6.00 | $4.38 | $4.10 | $4.95 | $25.91 |
| 38 | Fiber optic CBL (sing-mode)(24 fiber) (6027-7019) | LF | 925 | $1.58 | $3.89 | $3.40 | $2.45 | $3.90 | $2.72 | $25.71 |
| 39 | FO CBL (12 SMF)(pigtail) (6027-7020) | LF | 600 | $10.00 | $7.45 | $5.70 | $16.74 | $8.40 | $7.58 | $44.45 |
| 40 | Spread spectrum radio (6043-7001) | EACH | 4 | $2,968.00 | $2,977.10 | $3,511.00 | $2,929.91 | $5,388.00 | $3,706.56 | $2,843.00 |
| 41 | Coaxial cable (6043-7002) | LF | 415 | $3.97 | $4.74 | $5.80 | $4.99 | $4.25 | $15.81 | $5.30 |
| 42 | Antenna (uni-directional) (6043-7003) | EACH | 2 | $910.00 | $1,099.53 | $920.00 | $913.56 | $800.00 | $1,236.72 | $1,265.00 |
| 43 | Antenna(omni-directional) (6043-7004) | EACH | 2 | $2,428.90 | $932.42 | $624.00 | $768.46 | $625.00 | $1,079.48 | $1,136.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of February 5, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.