TxDOT contract A00178897 bid tabulation
Hazard Elimination & Safety, FM 718 (Tarrant County line to US 287/81). Let by Texas DOT on April 3, 2025, Tarrant, Fort Worth District. 4 bids received; low bid $2,429,827 by Jagoe-Public Company, -15% against the engineer's estimate of $2,846,179.
- Owner
- Texas DOT
- Letting
- 03 APR 2025
- Pay items
- 50
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Jagoe-Public Company | $2,429,827 | Low | -15% |
| 2 | Ed Bell Construction Company | $2,447,588 | +1.0% | -14% |
| 3 | Texas Materials Group, Inc. | $2,495,182 | +3.0% | -12% |
| 4 | Grey Sky Construction LLC | $3,195,556 | +32% | +12% |
Engineer's estimate: $2,846,179.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Jagoe-Public Company | 2. Ed Bell Construction Company | 3. Texas Materials Group, Inc. | 4. Grey Sky Construction LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 145 | $4,000.00 | $1,750.00 | $675.00 | $100.00 | $2,000.00 |
| 2 | Remove (7"-13") TRT/untrt base & asphalt pavement (105-7058) | SY | 2,904 | $15.00 | $12.00 | $10.00 | $15.00 | $20.00 |
| 3 | Excavation (roadway) (110-7001) | CY | 2,255 | $40.00 | $40.00 | $10.00 | $24.00 | $20.00 |
| 4 | Embankment (final)(DC)(type B) (132-7004) | CY | 899 | $125.00 | $75.00 | $120.00 | $65.00 | $50.00 |
| 5 | Compost manuf topsoil (4") (161-7002) | SY | 5,682 | $4.00 | $12.00 | $10.00 | $9.01 | $10.00 |
| 6 | Straw or hay mulch (162-7003) | SY | 6,243 | $1.00 | $2.00 | $1.15 | $1.75 | $1.00 |
| 7 | Broadcast seed (permanent_rural_clay) (164-7002) | SY | 6,243 | $3.50 | $1.00 | $1.00 | $1.01 | $0.50 |
| 8 | Broadcast seed (temporary_warm) (164-7005) | SY | 3,121.50 | $1.00 | $0.25 | $0.75 | $0.89 | $0.50 |
| 9 | Broadcast seed (temporary_cool) (164-7006) | SY | 3,121.50 | $1.00 | $0.25 | $0.75 | $0.94 | $0.50 |
| 10 | Fertilizer (166-7001) | ACRE | 1.30 | $1,090.00 | $1,500.00 | $700.00 | $1,412.00 | $5,000.00 |
| 11 | Vegetative watering (168-7001) | TGL | 218.50 | $288.75 | $140.00 | $90.00 | $98.63 | $20.00 |
| 12 | Lime (com or QK)(slurry) (260-7005) | TON | 165 | $350.00 | $325.00 | $325.00 | $350.00 | $500.00 |
| 13 | Lime TRT (subgrade) (8") (260-7020) | SY | 9,347 | $10.00 | $18.00 | $15.00 | $15.00 | $20.00 |
| 14 | Prime coat (multi option) (310-7015) | GAL | 1,877 | $24.00 | $2.00 | $11.00 | $6.00 | $6.00 |
| 15 | D-GR HMA type-B PG64-22 (341-7001) | TON | 2,381 | $120.00 | $140.00 | $150.00 | $200.00 | $180.00 |
| 16 | Tack coat (341-7082) | GAL | 1,448 | $5.25 | $2.00 | $3.00 | $5.00 | $6.00 |
| 17 | SP mixes SP-C sac-B PG70-28 (344-7025) | TON | 835 | $150.00 | $210.00 | $225.00 | $270.00 | $200.00 |
| 18 | Mobilization (500-7001) | LS | 1 | $258,744 | $258,000 | $331,000 | $245,000 | $310,000 |
| 19 | Barricades, signs and traffic handling (502-7001) | MO | 7 | $10,500 | $30,000 | $42,000 | $55,000 | $12,500 |
| 20 | Portable changeable message sign (503-7002) | EACH | 2 | $11,000 | $25,000 | $15,000 | $12,750 | $20,000 |
| 21 | TMA (stationary) (505-7001) | DAY | 106 | $300.00 | $225.00 | $157.50 | $100.00 | $250.00 |
| 22 | TMA (mobile operation) (505-7003) | DAY | 10 | $220.00 | $225.00 | $1,155.00 | $250.00 | $550.00 |
| 23 | Construction exits (install) (type 1) (506-7020) | SY | 312 | $50.00 | $25.00 | $35.00 | $49.99 | $40.00 |
| 24 | Construction exits (remove) (506-7024) | SY | 312 | $20.00 | $10.00 | $11.00 | $19.50 | $20.00 |
| 25 | Temporary sediment control fence (install) (506-7039) | LF | 2,990 | $6.00 | $6.00 | $3.75 | $5.62 | $4.00 |
| 26 | Temporary sediment control fence (remove) (506-7041) | LF | 2,990 | $2.50 | $1.00 | $1.25 | $1.00 | $2.00 |
| 27 | Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001) | LF | 1,350 | $50.00 | $95.00 | $89.00 | $100.00 | $100.00 |
| 28 | Portable concrete traffic barrier (des source)(single slope)(type 1) (512-7013) | LF | 1,020 | $30.00 | $25.00 | $21.00 | $26.00 | $50.00 |
| 29 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 9,060 | $15.00 | $15.00 | $15.75 | $16.00 | $50.00 |
| 30 | Portable concrete traffic barrier (stockpile)(single slope)(type 1) (512-7037) | LF | 2,370 | $12.00 | $15.00 | $21.00 | $26.00 | $30.00 |
| 31 | Driveways (ACP) (530-7010) | SY | 137 | $100.00 | $65.00 | $200.00 | $250.00 | $50.00 |
| 32 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 32,205 | $0.75 | $0.15 | $0.13 | $0.25 | $0.50 |
| 33 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 16,459 | $0.80 | $0.15 | $0.25 | $0.25 | $0.50 |
| 34 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 30 | $2,200.00 | $750.00 | $1,000.00 | $1,500.00 | $6,500.00 |
| 35 | Crash cushion attenuator (remove) (545-7004) | EACH | 8 | $1,204.00 | $750.00 | $750.00 | $2,000.00 | $3,500.00 |
| 36 | Cca (install)(N)(TL3)(work zone) (545-7018) | EACH | 8 | $7,777.50 | $1,000.00 | $1,250.00 | $3,500.00 | $15,000 |
| 37 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 3 | $840.00 | $1,100.00 | $1,365.00 | $1,500.00 | $1,500.00 |
| 38 | Work zone pavement marking non-removing (W)4"(solid) (662-7004) | LF | 48,860 | $2.50 | $0.40 | $0.17 | $0.15 | $0.50 |
| 39 | Work zone pavement marking non-removing (Y)4"(solid) (662-7035) | LF | 48,216 | $2.50 | $0.40 | $0.17 | $0.15 | $0.50 |
| 40 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 2,372 | $1.00 | $2.50 | $6.30 | $0.50 | $5.00 |
| 41 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 2,341 | $1.00 | $2.50 | $6.30 | $0.50 | $5.00 |
| 42 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 400 | $1.75 | $1.50 | $2.00 | $1.00 | $6.00 |
| 43 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 2 | $210.00 | $280.00 | $175.00 | $140.00 | $500.00 |
| 44 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 2 | $215.00 | $330.00 | $200.00 | $170.00 | $500.00 |
| 45 | All-wther PM type I (W)6"(solid)(100MIL) (666-7309) | LF | 32,205 | $1.50 | $1.00 | $1.50 | $0.74 | $1.50 |
| 46 | All-wther PM type I (Y)6"(solid)(100MIL) (666-7315) | LF | 25,478 | $1.25 | $1.00 | $1.50 | $0.74 | $1.50 |
| 47 | All-wther PM type I (Y)6"(broken)(100MIL) (666-7316) | LF | 1,460 | $1.25 | $1.00 | $1.50 | $0.80 | $1.50 |
| 48 | Reflectorized pavement marker type I-C (672-7002) | EACH | 20 | $8.00 | $8.00 | $12.00 | $5.75 | $6.00 |
| 49 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 397 | $10.00 | $8.00 | $8.00 | $5.75 | $6.00 |
| 50 | Eliminating existing PM & markers (4") (677-7001) | LF | 59,236 | $1.00 | $0.90 | $0.99 | $0.45 | $0.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of April 3, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.