TxDOT contract A00184285 bid tabulation
Hazard Elimination & Safety, US 83 (1300 FT N OF AMBLER to N 10TH ST). Let by Texas DOT on April 4, 2025, Taylor, Abilene District. 6 bids received; low bid $493,190 by Icos Management, LLC, -28% against the engineer's estimate of $680,583.
- Owner
- Texas DOT
- Letting
- 04 APR 2025
- Pay items
- 20
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Icos Management, LLC | $493,190 | Low | -28% |
| 2 | HJC Farms, Inc. | $734,197 | +49% | +8.0% |
| 3 | Built Right Construction of Oklahoma, LLC | $850,483 | +72% | +25% |
| 4 | Roadway Specialties, Inc. | $861,446 | +75% | +27% |
| 5 | SCR Civil Construction, LLC | $887,552 | +80% | +30% |
| 6 | O. Trevino Construction, LLC | $896,153 | +82% | +32% |
Engineer's estimate: $680,583.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Icos Management, LLC | 2. HJC Farms, Inc. | 3. Built Right Construction of Oklahoma, LLC | 4. Roadway Specialties, Inc. | 5. SCR Civil Construction, LLC | 6. O. Trevino Construction, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (mowstrip) (104-7005) | LF | 814 | $19.00 | $22.00 | $19.00 | $10.00 | $11.32 | $30.00 | $27.00 |
| 2 | Embankment (final)(OC)(type A) (132-7001) | CY | 385 | $50.00 | $44.00 | $200.00 | $100.00 | $57.98 | $85.00 | $145.00 |
| 3 | Backfill (type B) (134-7002) | STA | 69 | $350.00 | $132.00 | $250.00 | $100.00 | $45.46 | $315.00 | $641.00 |
| 4 | Class C concrete (rail foundation) (420-7052) | CY | 24.30 | $1,100.00 | $864.00 | $2,500.00 | $750.00 | $2,189.86 | $2,400.00 | $1,610.00 |
| 5 | Riprap (concrete)(4 in) (432-7001) | CY | 239 | $710.00 | $540.00 | $700.00 | $600.00 | $395.97 | $717.00 | $950.00 |
| 6 | Mobilization (500-7001) | LS | 1 | $63,210 | $10,000 | $100,000 | $80,000 | $239,729 | $88,700 | $89,615 |
| 7 | Barricades, signs and traffic handling (502-7001) | MO | 3 | $8,000.00 | $1.00 | $10,000 | $3,000.00 | $3,475.77 | $10,550 | $20,000 |
| 8 | TMA (stationary) (505-7001) | DAY | 120 | $350.00 | $1.00 | $325.00 | $270.00 | $571.93 | $200.00 | $197.00 |
| 9 | TMA (mobile operation) (505-7003) | DAY | 100 | $550.00 | $1.00 | $10.00 | $325.00 | $1,315.99 | $400.00 | $76.86 |
| 10 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 151 | $7.00 | $10.00 | $5.00 | $15.00 | $4.60 | $15.75 | $15.00 |
| 11 | Biodegradable erosion control logs (remove) (506-7046) | LF | 151 | $3.00 | $1.00 | $1.00 | $3.00 | $1.35 | $5.70 | $5.00 |
| 12 | Portable concrete traffic barrier (des source)(single slope)(type 1) (512-7013) | LF | 6,420 | $25.00 | $22.00 | $25.00 | $65.00 | $23.09 | $22.00 | $34.00 |
| 13 | Permanent CTB (tran SSCB to SSTR) (mod) (514-7038) | LF | 119 | $500.00 | $880.00 | $350.00 | $300.00 | $470.89 | $1,600.00 | $550.00 |
| 14 | Permanent CTB (single slope)(type 1)(transition) (514-7041) | LF | 27 | $410.00 | $1,100.00 | $350.00 | $300.00 | $497.86 | $1,000.00 | $675.00 |
| 15 | Remove metal beam guard fence (542-7001) | LF | 600 | $3.00 | $5.00 | $3.00 | $7.50 | $3.38 | $36.00 | $13.00 |
| 16 | Remove downstream anchor terminal (542-7003) | EACH | 3 | $300.00 | $550.00 | $300.00 | $650.00 | $112.61 | $400.00 | $990.00 |
| 17 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 2 | $330.00 | $550.00 | $300.00 | $2,500.00 | $224.86 | $800.00 | $1,485.00 |
| 18 | Guardrail end treatment (remove) (544-7003) | EACH | 2 | $300.00 | $550.00 | $300.00 | $650.00 | $337.82 | $1,000.00 | $1,485.00 |
| 19 | Crash cushion attenuator (remove) (545-7004) | EACH | 1 | $1,800.00 | $1,100.00 | $5,000.00 | $1,500.00 | $3,272.36 | $1,000.00 | $900.00 |
| 20 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (658-7031) | EACH | 67 | $41.00 | $55.00 | $75.00 | $50.00 | $47.11 | $80.00 | $66.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of April 4, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.